Professional Documents
Culture Documents
This module will provide the necessary information, skills and attitudes
in putting up a hatchery facility. It also covers the knowledge and skills in
layouting, evaluating a site for fish tank, and constructing fish tanks.
106
Quarter 3
Introduction
The lesson deals with designing and layouting of tanks. This includes
the area and depth of a tank, site selection, number and size of
compartments, the materials to be used, and life support units for the tank
system.
Specific Objectives
1. select the area and depth of tanks which conforms to the available
site and determine the species of fish to be cultured based on
specifications.
2. determine the number and size of compartments based on the area
of the land.
3. determine the materials to be used based on available capital.
4. emphasize the essentials for life support on tank design.
5. stipulate other life supports in the layout and plan.
107
Quarter 3
Pre-assessment
Multiple Choice: Read and answer the following items carefully. Encircle the
letter of the best answer.
108
Quarter 3
109
Quarter 3
Ø = 3.4 m
9 m2
There are several shapes of tanks that may be used. The most
common shapes are the rectangular, square, and circular tanks. The volume
of water they carry may range from 100m3 to 400m3. Different compartments
are also included in the layout depending on the fish species to be cultured
and on the aquaculturist’s prescription on the layout, and design of the
hatchery tank.
110
Quarter 3
SCALING
Scale is the ratio of the distance on the map or drawing and distance
on the ground. It is widely used by engineers and architects.
Formula:
Problem Solving
1m (map) = X map
1000m (ground) 125m (ground)
a. 1 x 125 m
1000
0.001 x 125 m = 0.125 m or 12.5 cm
111
Quarter 3
Hatchery is a facility for the production of fish eggs, larvae, and /or fish
fry. In practical terms, a hatchery is a structure that houses tanks and
equipment for egg cultivation and rearing of larvae. It has a life-support
system for fish eggs and larvae.
The hatchery tanks should be designed for easy operation and safety
to consider future expansion, such as spaces for extra tanks and facilities for
water, air supply, electricity, etc.
112
Quarter 3
Pump
Larval Larval
/ Fry Sand / Fry
tank filter tank
Microalgal
Rotifer tanks
Tanks
113
Quarter 3
The drain hole fitted with 3 in PVC pipe is situated at the rear end of
the tank (Figure 9). The tank floor should slightly slope (5° - 15°) towards the
drain hole for easy draining, cleaning, and maintenance.
114
Quarter 3
The outlet hole (Figure 9) drains water from the tank and the drainage
canal (Figure 10) drains water from the tank site.
For circular and hexagonal tanks, the drain hole should be in the
middle of the tank (Fig. 12). The tank bottom slightly slopes (5° - 15°) towards
the center where the drain outlet is constructed.
115
Quarter 3
the production units, where true production activities take place and this
includes hatching, larval, and natural food tanks.
116
Quarter 3
117
Quarter 3
The life-support units, which includes water filter, water pumps, aerators and
blowers.
Filter Tank. A set up with layers of different filter media. The filter medium is
generally composed of layers of fine sand, coarse sand, gravel or coarse
stones interpersed with charcoal, and shell. Water is pumped in at the top
of the tank and flows through various substrates and flows out at the bottom.
Figure 17. Elevated seawater with cut-out diagram of gravity sand filter
tank.
118
Quarter 3
119
Quarter 3
1. Find the equivalent unit (in cm) using the given scale.
4m
3.5 m
b.
2.5 m
c.
4m
120
Quarter 3
Directions: Given the following data below and the knowledge you gained in
this lesson, design your own hatchery facility.
I. Materials:
-tracing paper
-pencil
-ruler
- eraser
II. Specific Instructions
1. Using a tracing paper, ruler, pencil and your own scale, illustrate
the floor plan of your hatchery facility.
2. Your hatchery facility must have the following units:
121
Quarter 3
122
Quarter 3
Post-assessment
Multiple Choice: Read carefully and answer the following items. Encircle the
letter of the best answer.
123
Quarter 3
124
Quarter 3
Glossary
Fish tank. A fish or water holding structures, usually above ground, typically
with a high water turnover rate
Fry. A term to describe a fish at the post - larval stage. All stages from
hatching to fingerling stage can potentially be termed as fry
Hatchery. Place for artificial breeding, hatching and rearing through the early
life stages of fish. Generally, in fish culture, hatchery and nursery are closely
associated
Larva. The outcome of a newly hatched egg of fish and other animals
Wean. To accustom (as a young child or animal) to take food otherwise than
by nursing
125
Quarter 3
Resources
126
Quarter 3
Introduction
This lesson will provide you knowledge and skills in evaluating suitable
site for fish tanks, assessing water quality parameters and additional
information with regard to fish tanks.
Specific Objectives
Pre-Assessment
I. MULTIPLE CHOICE
Directions: Choose the letter of your answer. Write your answer in your test
notebook.
127
Quarter 3
128
Quarter 3
Site Selection
129
Quarter 3
Water Temperature
Water temperature is important because it affects the rates of
biological and chemical processes. Temperature is measured in Celsius or
Fahrenheit.
The health of aquatic organisms from microbes to fish depends on
temperature. If temperature is outside the optimal range for a prolonged
period, organisms are stressed and can die. For fish, the reproductive stage
(including spawning and embryo development) is the most temperature-
sensitive period.
130
Quarter 3
131
Quarter 3
132
Quarter 3
133
Quarter 3
Flow Chart
Directions: Illustrate the factors that have to be considered in selecting a
suitable site for hatchery facility using the flow chart below. Add possible
details for each factor.
FACILITY
134
Quarter 3
Now that you have gained the required knowledge to assess a site for a
hatchery facility, try to do the activity below.
I. Materials
-digital camera/cellphone camera
-notebook
-ballpen
135
Quarter 3
Assessment Sheet
136
Quarter 3
Post-assessment
I. MULTIPLE CHOICE
Directions: Choose the letter of your answer. Write your answer in your test
notebook.
1. What is the ideal pH for the growth of fish?
a. 0 – 6.4
b. 6.5 – 9.0
c. 9.1 – 12.0
d. 12.1 – 14.0
2. Below are some of the heavy metals considered harmful to fish except;
a. Zinc
b. Lead
c. Mercury
d. Chloride
3. Which of the following is the foremost factor to be considered in selecting
an ideal site for hatchery facility?
a. Accessibility
b. Availability of man power
c. Security to power supply
d. Availability of good quality water
4. What instrument measures the availability of water coming from the water
source?
a. pH meter
b. refractometer
c. thermometer
d. flow rate meter
137
Quarter 3
5. What is the ideal pH level of a brackish water with 12 -16 ppt salinity?
a. 6.5 – 6.9
b. 7.0 – 8.5
c. 8.6 – 9.0
d. 9.1 – 14.0
138
Quarter 3
Glossary
Resources
139
Quarter 3
Introduction
Specific Objectives
140
Quarter 3
Pre-Assessment
Multiple Choice: Choose the letter of the best answer. Write them in your test
notebook.
1. Which of the following is NOT a typical type of a hatchery tank?
a. plastic tank
b. concrete tank
c. fiber glass tank
d. polyethylene tank
2. You will need five trucks of sand for the construction of hatchery tanks.
How much will 5 trucks cost if one truck is Php 1,500.00?
a. Php 2,500.00
b. Php 3,500.00
c. Php 6,500.00
d. Php 7,500.00
3. Which of the following reduces the presence of ammonia in hatchery
tanks?
a. biofilter
b. egg collector
c. recirculation system
d. water treatment system
4. What is the usual size range of a spawning tank?
a. 1 – 15 m3
b. 2 – 20 m3
c. 4 – 20 m3
d. 5 – 40 m3
141
Quarter 3
5. How many kilograms of breeders can be stock per cubic meter (m3) of
conditioning tank/facility?
a. 15 kg/m3
b. 20 kg/m3
c. 25 kg/m3
d. 30 kg/m3
6. Which tank is intended for culture of natural food such as phytoplankton?
a. rotifer tank
b. sand filter tank
c. microalgal tank
d. larval rearing tank
7. How many feet are in 1 meter?
a. 1.5 ft
b. 2.5 ft
c. 3.0 ft
d. 3.28 ft
8. It is a type of water outlet where in the inner tube is shorter than the
external one.
a. drain outlet
b. sink outlet
c. main outlet
d. telescope outlet
9. What is the aggregate area of a 4m x 2m x 1m fish tank in square feet?
a. 107.78 ft2
b. 117.58 ft2
c. 127.58 ft2
d. 137.58 ft2
142
Quarter 3
10. What is the area of a 4” x 8” x 16” concrete hollow block in square feet?
a. 0.578 ft2
b. 0.678 ft2
c. 0.778 ft2
d. 0.878 ft2
- gravel - sand
- steel - bars
- cement - faucet
- GI wire - shovel
143
Quarter 3
Figure 24. pipe wrench Figure 25. GI Wire Figure 26. PVC pipe
144
Quarter 3
II. Resources:
calculator
ball pen
paper
III. Procedures:
Example: If you are to construct a tank 5 meters long, 1.5 meters wide and 1
meter high. How many hollow blocks are needed to finish the job?
1 m = 100 cm
1 in = 2.54 cm
1 ft = 12 inches
W=1.0 m
= 16.40 ft × 3.28 ft
= 53.79 ft2 x 2
145
Quarter 3
= 4.92 ft × 3.28 ft
= 16.14 ft2
Total area of wall = 107.58 ft2 + 32.28 ft2 =139.86 ft2 or 13.0 m2
= 0.66 ft x 1.33 ft
= 0.878 ft2
No. of CHB
146
Quarter 3
Table 2. CHB LAID PER BAG CEMENT Table 3. VOLUME OF CEMENT PER
CHB
4”x 8” x 16” 55 to 60 Pieces
6”x 8” x 16” 30 to 36 Pieces 4”x 8” x 16” 0.001 m3
8”x 8” x 16” 25 to 30 Pieces 6”x 8” x 16” 0.003 m3
8”x 8” x 16” 0.004 m3
147
Quarter 3
148
Quarter 3
Step 4. Compute the amount of cement, sand and gravel needed for the
flooring
V = 4 in x 5 m x 1.5 m
V = 0.10 m x 5 m x 1.5 m
V = 0.75 m3
Step 5. Compute for the amount of cement needed for laying the CHB
(Refer to Table 2)
Number of bags
= 2.91 or 3 bags
Step 6. Compute for the amount of cement and sand for mortar
P = 2 (length + width)
= 2 (5 m + 1.5 m)
149
Quarter 3
= 2 (6.5 m)
= 13 meter
A = 13 m x 1 m
= 13 m2
Amount of cement:
= 13 m2 x 0.36 bags/m2
= 4.68 bags
Amount of sand:
= 13 m2 x 0.019m3/m2
= 0.247 m3
Step 7. Compute for the amount of cement and sand for CHB plaster finish
using the following formula:
(Refer to Table 4)
= 13.00 m2 x ¼ bags / 1 m2
= 3.25 bags
= 0.28 m3 x 2
150
Quarter 3
= 0.28 m3
= o.56 m3
Step 8. Compute for the amount of cement for plain cement floor finish (Refer
to Table 5)
Step 9. Compute for the needed number of steel bars (Refer to Table 6)
Area = 13 m2
= 5.75 bar
Area = 13 m2
= 39 m x 1 bar / 6.096 m
= 6.4 bars
151
Quarter 3
Flooring:
Area = 7.5 m2
No. of Bars = 7.5 m2 x 3 m / m2
= 22.5 m
= 22.5 m x 1 bar/ 6.096 m
= 3.7 bars
Total amount of Bars= 5.75 + 6.4 + 3.7 = 15.85pcs or 16 pcs.
Bill of Materials and Cost Estimates
Unit Cost Total
Materials Quantity
(Php) (Php)
1. Gravel 1 Elf Load 1, 400.00 1, 400.00
2. Sand 1 Elf Load 1, 000.00 1, 000.00
3. CHB 4” x 8” x 16” 160 pcs 5.50 880.00
4. Portland Cement 23 bags 182.00 4,186.00
5. Steel Bar(10mm.) 16 pcs. 175.00 2,800.00
6. Sahara Cement 9 bags 30.00 270.00
7. PVC ¾” 5 pcs. 100.00 500.00
8. PVC Elbow ¾” 6 pcs. 15.00 90.00
9. PVC 4” 1 pc. 220.00 220.00
10. PVC Solvent Cement 1 small can 35.00 35.00
11. Faucet 1 pc. 130.00 130.00
12. G.I. Wire # 16 1 kg. 65.00 65.00
13. Hose 5 mm 10 m 8.00 80.00
Grand Total : Php. 11,656.00
Note:
*For every bag of cement for Plaster Finish, 1 bag of Sahara cement is added
for water proofing purpose
*The cost of the materials is subject to change based on the prevailing price
at a certain period.
152
Quarter 3
Program of Work
The water outlet is usually constructed at the rear end of the tank.
The drain outlet ( see Figure 9 p.99) must be fitted with 4 in PVC pipe
to prevent the drain hole ( see Figure 8 p.99) from enlarging due to constant
flow of water. This is where the water from the tank flows out to the drainage
canal. The drainage canal ( see Figure 10) is 0.5 m wide and 0.3 m deep.
153
Quarter 3
constructed at the middle of the tank. The tank floor must have a moderate
slope towards the center. The construction of outlet may vary in types with or
without particle traps. Particle trap can be installed for outlet cleaning or for
the water to be reused.
1. Sink outlet. Horizontal grid outlets are common in smaller tanks. The
outlet is a sink with a grid as described below.
2. Telescope outlet. The telescope outlet with inner level control is shown in
Figure 13. The inner tube of the tank is a shorter pipe than the external
one, with a slightly wider tube at the top which can be moved up and
down to control the level of water in the tank.
154
Quarter 3
155
Quarter 3
For a large circular tank, there are three ways of fitting the inlet pipe.
1. Vertical pipe with rounded holes gives weight to the bottom of the
circular tank.
2. Horizontal pipe with rounded holes makes the fitting of the inlet pipe
durable. The length is 1/3 of the diameter of the tank.
3. Install the combined vertical and horizontal inlet properly. The length of
the horizontal inlet is ¼ of the radius of the tank.
Figure 32. Air blower Figure 33. Pipe lines are installed to
the blower with plastic tube and air
stone.
156
Quarter 3
Figure 34. Fitting the plastic tube to Figure 35. Fitting the sinker stone
the to the hose
PVC pipe line
Regardless of shape and size, the spawning tanks should fulfil the
following conditions:
157
Quarter 3
Lights
Aeration system
Conditioning facilities
The area is also subdivided into several zones, isolated from each
other, where different light/temperature regimes can be adopted. This
requires independent systems for light and water temperature regulation. The
heating system is often coupled with a cooling system, usually a heat pump,
to provide out of season winter conditions.
158
Quarter 3
Each sub-unit is housed in a room of variable size with tiled floor and walls
and is provided with air conditioning, treated seawater supply, freshwater
supply, air distribution system, working lights, safe plugs, and a drain system.
Adaptations to the needs of each sub-unit are specified below.
Program of Activities
159
Quarter 3
4. Laying out by erecting pegs, tying strings, and putting up marks for the
dimension of the tank to be constructed
5. Excavating of the tank area to a depth based on specifications.
6. Preparing the mixture for footing, 1:2.5:5 ( cement- sand- gravel)
7. Preparing the horizontal and vertical bars based on the dimension of
the tank to be constructed.
8. Preparing a class A mixture for the mortar which is 1:2:4.
9. Piling the hollow blocks (CHB 4”x 8” x 16”) layer by layer until the
required height is reached.
10. Cementing the tank floor with class A mixture.
11. Plaster finishing. The walls of the tank (in and out) to a mixture of 1:2.
Add one bag of Sahara cement per mixture
160
Quarter 3
Event 1: Event 2:
Event 4:
Event 3:
161
Quarter 3
Directions: Group the class with 3 – 4 members per group. Present a video
clip (from internet or recorded) about hatchery facility construction. Note the
points from the video for a class discussion.
162
Quarter 3
Post-Assessment
Multiple Choice: Read and understand each item below. Encircle the letter of
the best answer.
1. Which of the following is NOT a typical type of a hatchery tank?
a. plastic tank
b. concrete tank
c. fiber glass tank
d. polyethylene tank
2. It refers to a rectangular, square, hexagonal, octagonal or circular in shape
and a concrete structure used as aquaculture facility.
a. fish tank
b. plastic tank
c. canvass tank
d. fiber glass tank
3. Which of the following supplies dissolved oxygen into the tank?
a. aerator
b. drain hole
c. water inlet
d. water pump
4. Fish hatcheries are important in aquaculture industry because ______.
a. they prevent flooding in the area
b. they serve as water reservoir
c. they serve as an artificial hatching area of fish
d. they serve as storage area of feeds and other equipment
6. The following are the commonly used materials in the construction of a
fish tank except for;
a. GI wire
b. PVC pipe
163
Quarter 3
c. air stone
d. corrugated steel bars
6. It is a tank intended for culture of natural food such as phytoplankton.
a. rotifer tank
b. sand filter tank
c. microalgal tank
d. larval rearing tank
7. How many feet are there in 1 meter?
a. 1.5 ft
b. 2.5 ft
c. 3.0 ft
d. 3.28 ft
8. It is a type of water outlet wherein inner tube is shorter than the external
one.
a. drain outlet
b. sink outlet
c. main outlet
d. telescope outlet
9. What is the aggregate area of a 4m x 2m x 1m fish tank in square feet?
e. 107.78 ft2
f. 117.58 ft2
g. 127.58 ft2
h. 137.58 ft2
10. What is the area of a 4” x 8” x 16” concrete hollow block in square feet?
a. 0.578 ft2
b. 0.678 ft2
c. 0.778 ft2
d. 0.878 ft2
164
Quarter 3
Glossary
165
Quarter 3
Resources
Gapasin, R., & Marte, C. (1990, May 1). Milkfish hatchery operations.
Retrieved October 29, 2014, from
http://repository.seafdec.org.ph/bitstream/handle/10862/172/aem17.pdf;jsessi
onid=7C75D199125F593201BF81F4B69432AA.jvm1?sequence=1
166