1.) A physical condition or a release of a hazardous material that could
result from component failure and result in human injury or death, loss
or damage, or environ- mental degradation.
VA. Hazard
B. Loss
C. Failure
2.) Limitation of any negative consequence or reduction in probability of a
particular event.
A. Mitigation
B. Reduction
C. Residual
3.) Methods that use engineering judgment and experience as the bases for
the analysis of probabilities and consequences of failure.
A. Qualitative risk assessment
B. Relative risk
C. Nominal risk
4.) An analysis that identifies and delineates the combinations of events
estimates the frequency of occurrence for each combination and
estimates the consequences.
A. Quantitative risk analysis
B, Qualitative risk analysis
C. Process hazard analysis
5.) uses logic models depicting combinations of events
~ Quantitative risk analysis
\B. Qualitative risk analysis
C. Process hazard analysis
6.) Quantitative risk analysis logic models generally consist of.
and.
A, Event tees and fault trees
B. Product trees and loss trees
C. Likelihood trees and consequence trees7.)
8.)
9.)
____delineate initiating events and combinations of system
successes and failures
A. Event trees
B. Fault trees
C. Logic trees
Depict ways in which the system failures rep- resented
in the event trees can occur.
A. Event trees
B. Fault trees
C. Logic trees
The comparative risk of a facility, process unit, system, equipment
item or component to other facilities
A. Relative risk
B. Absolute risk
C. No risk
10.) Combination of the probability of an event and its consequence.
A. Risk
B. Failure
C. Loss
D. Reduction
11.) Systematic use of information to identify sources and to estimate the
12)
13)
risk.
A. Risk
B. Risk analysis
C. Hazard analysis
Provides a basis for risk evaluation, risk mitigation and risk acceptance.
A. Risk
B. Risk analysis
C. Hazard analysis
Process used to assign values to the probability and consequence of a
cisk.
A. Risk evaluation
-B. Risk estimation
C. Risk identification14.) Process used to compare the estimated risk against given risk criteria
to determine the significance of the risk.
_A. Risk evaluation
B. Risk estimation
C. Risk identification
15.) Process to find, list, and characterize elements of risk.
A. Risk estimation
B. Risk evaluation
« C. Risk identification
16.) Coordinated activities to direct and control an organization with regard
to risk.
A. Risk management
B. Risk evaluation
C. Risk control
17.) Thing or activity with a potential for con- sequence.
A. Source
in a safety context is a hazard.
19.) The risk prior to mitigation activities
A. Unmitigated risk
B. Known risk
C. Mitigated risk
20) is the combination of the probability of some event
occurring during a time period of interest and the consequences,
associated with the event.
A. Risk
B. Loss
C. Mitigated risk21.) Act of mitigating a known risk to a lower level of risk.
A. Risk reduction
B. Risk mitigation
C. Risk evaluation
22.) A process to assess risks, to determine if risk reduction is required and
to develop a plan to maintain risks at an acceptable level.
A. Risk management
B. Risk mitigation
C. Risk control
23.) When some risk identified as acceptable then one of the following is
not required.
WA. Risk reduction
B. Risk evaluation
C. Risk mitigation
D. Risk control
24.) In process plants are established to detect and evaluate deterioration
due to in service operation.
A. Inspection and testing programs
B. Condition monitoring programs
C. Preventive maintenance programs
D. Inservice inspection programs
25.) When equipment has low deterioration rates as an inspector what you
decide in lieu of internal inspection.
\ A. On-stream inspection
B. Out of service inspection
C. External inspection
26.) _____ represents the next generation of inspection approaches
and interval setting, recognizing that the ultimate goal of inspection is
the safety and reliability of operating facilities.
Ac Rbi
B. Pha
C. Hazop
B. Rem27.) For a typical inspection program, if excessive inspection is applied
28.)
29.)
30.)
31.)
32.)
then,
A. Level of risk may go up
B. Level of risk may go down ‘7
C. Level of risk remain the same
provides a consistent methodology for assessing the
optimum combination of methods and frequencies.
A. Rbi
B. Rem
C. Pha
D. Hazop
Through , inspection activities are focused on
higher risk items and away from lower risk items.
A. Rbi
B. Pha
C. Rem
D. Hazop
Following are not the residual risk factors for loss of containment.
A. Human error
B. Natural disasters
C. Fundamental limitations of inspection method
D. Toxic fluid containment
Rbi is focused on a systematic determination of
A. Relative risks
B. Absolute risks
C. Comparable risks
D. Total risks
Act of mitigating a known risk to a lower level of risk.
A. Risk reduction
33.)
B. Risk management
C. Risk mitigation
Some failures have potentially serious consequences, but if the
probability of the incident is low, then
‘A. The risk may not warrant immediate action
B. The risk may warrant immediate action
C. The risk may warrant appropriate mitigation action34.) If the probability and consequence combination (risk) is high enough to
be unacceptable, then
A. A mitigation action to predict or prevent the event is
recommended.
B. A mitigation action to predict or prevent the event is not
recommended ,
C. Warrant to analyze risks involved
35.) __ refers to a prescriptive methodology that has resulted
from the application of risk analysis techniques at many different types
of facilities.
A. Quantitative risk assessment (qra)
B. Qualitative risk assessment
C. Semi quantitative risk assessment
36.)A Rbi analysis shares many of the techniques and data requirements
witha -
A. Qra:
B. Pha
C. Hazop
D. Event tree
37.)If a qra has been prepared for a process unit, the analysis can borrow
extensively from this effort.
‘A. Rbi consequence
B. Rbi likelihood
C. Rbi probability
38.) Hazard identification in a rbi analysis generally focuses on identifiable
failure mechanisms in the equipment (inspectable causes) but does not
explicitly deal with
‘A. Other potential failure scenarios resulting from events such as power
“” failures or human errors
B. Other potential failure resulting from events such as flammable fire
due to leak from equipment
C. Environmental impact caused due to toxic release39.) deals with total risk than with risk involve only with the
equipment.
A. Qra
B. Rbi
C. Pha
D. Fta
40.) Risk presented in quantitative risk analysis as a
A. Precise numeric value
B. Form of risk matrix
C. Form of event tree and fault tree
41.) Risk presented in qualitative risk analysis as
D. Precise numeric value
E. Form of risk matrix
F. Form of event tree and fault tree
42.) Results from quantitative analysis logic models are validated by
_A. Expert judgment
B. Inspection engineer
C. Maintenance engineer
D. Operations personnel
43.) The suitability and current condition of the equipment within the
current operating envelope will determine the ___of the
equipment from one or more deterioration mechanisms.
A. Probability of failure (pot)
B. Consequence of failure
C. Total risk
D. Relative risk
44.) The probability of failure, when coupled with the associated
consequence of failure (cof) (see section 11) will determine
associated with the equipment item,
Operating risk
B. Ranking
C. Residual risk
45.) Isa risk management activity that may lead to risk reduction?
A. Inspection
B. Evaluation
C. Analysis46.) The primary product of a rbi effort should be
A. An inspection plan for each equipment item evaluated
B. Mitigation plan for each equipment item evaluated
C. Residual risk assessment plan for each equipment item evaluated
47.) Following are some of the recognized risks which cannot be managed
by inspection alone except one
A. Equipment nearing retirement
B. Failure mechanisms (such as brittle fracture, fatigue) where
avoidance of failure primarily depends on operating within a
defined pressure/ temperature envelope
C. Consequence-dominated risks
D. The suitability and current condition of the equipment within the
current operating envelope will determine the probability of failure
{pof) of the equipment from one or more deterioration mechanisms
48.) Following are the non-inspection mitigation actions except one
‘A. Replacement or upgrade
B. Equipment redesign
C. Maintenance of strict controls on operating conditions