NAME OF CONTRACTOR: FREE AIR ENG'G SERVICES & CONSULTANCY CO.

PROJECT NAME: SCIC - SOLID LF


SUBJECT: PROJECT SCHEDULE

Number of Days:
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41

Months AUG

This chart isn't available in your version of Excel.


Date:
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10
Editing this shape or saving this workbook into a different file format will permanently break the chart.
Electrical Works Inbound Dock Area-2FLR

1 Submittal of Materials, Shop Drawings and Approval 2 2 2 2 2 2 2

2 Procurement and Delivery of Materials (Consumables Items) 2 2 2

3 Rough ins (Piping Works) Lighting Lay out 6 6 6 6 5 5 5 5 5 5 5 5 5 5 5 5

5 Installation of Hangers and Support 6 6 6 6 6 6 6 6

6 Installation of Wire's for Lightings including Home run 8 8 8 8 8 8 8 8 8

7 Fabrications of Cable Ladder -Provided by Sta.Clara International

8 Installation of Cable Ladder -Terminations 5 5 5 5 5 5 5 5

9 Installation of Lighting Fixtures -(Devices Provided by Sta.Clara International)

10 Lay out for Box Settings for Power Lay out 7 7 7 7

12 Rough ins (Piping Works) Power Lay out 4 4 4 4 4 4 4 4

13 Installation of Hangers and Support 3 3 3 3 3 3

14 Installation of Wire's for Power Outlet including Home run

15 Installation of Panel Boards 7 7 7 7 7

16 Installation of Power Outlet Devices

17 Tagging of Wires for Lightings and Outlets Provisions


Manpower: 2 2 2 2 2 6 15 15 25 22 15 15 15 26 26 26 16 16 16 13 18 13 5 5 5 5 5 5 0 0 0 2 2 0 0 0 7 7 7 7 7

Number of Days:
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41

Months AUG SEPT

Date: This chart isn't available in your version of Excel.


27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6
Editing this shape or saving this workbook into a different file format will permanently break the chart.
Electrical Works Out Bound-3F Dock Area

1 Submittal of Materials, Shop Drawings and Approval 2 2 2 2 2 2 2 2 2

2 Procurement and Delivery of Materials (Consumables Items) 2 2 2

3 Rough ins (Piping Works) Lighting Lay out 6 6 6 6 5 5 5 5 5 5 5 5 5 5 5 5

5 Installation of Hangers and Support 6 6 6 6 6 6 6 6

6 Installation of Wire's for Lightings including Home run 8 8 8 8 8 8 8 8 8

7 Fabrications of Cable Ladder -Provided by Sta.Clara International

8 Installation of Cable Ladder -Terminations 5 5 5 5 5 5 5 5

9 Installation of Lighting Fixtures -(Devices Provided by Sta.Clara International) 8 8 8 8 8 8 8

10 Lay out for Box Settings for Power Lay out 7 7 7 7

12 Rough ins (Piping Works) Power Lay out 4 4 4 4 4 4 4 4

13 Installation of Hangers and Support 3 3 3 3 3 3

14 Installation of Wire's for Power Outlet including Home run

15 Installation of Panel Boards 7 7 7 7 7

16 Installation of Power Outlet Devices

17 Tagging of Wires for Lightings and Outlets Provisions


Manpower: 2 2 2 2 2 6 15 15 25 22 15 15 15 26 26 26 16 16 18 15 18 13 5 5 5 5 5 5 8 8 8 10 10 8 8 0 7 7 7 7 7

Number of Days:
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41

Months AUG SEPT

Date:
This chart isn't available in your version of Excel.
27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6
Editing this shape or saving this workbook into a different file format will permanently break the chart.
Electrical Works Out Bound-3F Dock Area

1 Submittal of Materials, Shop Drawings and Approval 2 2 2 2 2 2 2 2 2

2 Procurement and Delivery of Materials (Consumables Items) 2 2 2

3 Rough ins (Piping Works) Lighting Lay out 6 6 6 6 5 5 5 5 5 5 5 5 5 5 5 5

5 Installation of Hangers and Support 6 6 6 6 6 6 6 6

6 Installation of Wire's for Lightings including Home run 8 8 8 8 8 8 8 8 8

7 Fabrications of Cable Ladder -Provided by Sta.Clara International

8 Installation of Cable Ladder -Terminations 5 5 5 5 5 5 5 5

9 Installation of Lighting Fixtures -(Devices Provided by Sta.Clara International) 8 8 8 8 8 8 8

10 Lay out for Box Settings for Power Lay out 7 7 7 7

12 Rough ins (Piping Works) Power Lay out 4 4 4 4 4 4 4 4

13 Installation of Hangers and Support 3 3 3 3 3 3

14 Installation of Wire's for Power Outlet including Home run

15 Installation of Panel Boards 7 7 7 7 7

16 Installation of Power Outlet Devices


17 Tagging of Wires for Lightings and Outlets Provisions

Manpower: 2 2 2 2 2 6 15 15 25 22 15 15 15 26 26 26 16 16 18 15 18 13 5 5 5 5 5 5 8 8 8 10 10 8 8 0 7 7 7 7 7

Prepared By: Approved By:


Engr Rizal Timagos Arch.Ronie Magno
PIC-Electrical Engr Free Air Eng’g Services & Consultancy Co. PM -Free Air Eng’g Services & Consultancy Co.