Sediment Pond - MW-6 should be relocated towards to North to have
100m distance from dry stack footprint and tagged as
WM-PZ-3 GWM Piezometer-3 - Relocate MW-1 with distance 100m from dry stack footprint and tagged as WM-PZ-2 (Relocated GWM well-6) - Relocate MW-10 next to the haul road to have 500m distance from south dry stack footprint and tagged as WM-PZ-1 - Update WM wells tags and coordinates table - Install 2 No’s Sediment ponds discharge point of run off water discharge points at North and South