Time Entry Description / Remarks


08:15 a.m. -Punchcard at the guard house.

09:00 a.m. -Cleaning die head at machine A-4. the


machine did not working because no
order of product that produce by this
machine. So we need to service the
machine like cleaning and maintaining.

12.30 p.m -Lunch

Figure 1: Die Head


.

-Follow Technician to maintaing the


2.00 p.m contactor that control the heater.
This need to be done once per week
to make sure the contactor is in a
good condition.for example tighten
the screw and make sure the cable is
really tight so that when current
flow there is no spark occur.

6.00 p.m -Punchout.


Figure 2: Contactor

Note: Please include attachment whenever necessary

AFIQ AIMAN

Student Signature
Date: 11/08/2023
Date: 1 2 /09/2023 Day: 3 2 Training Week: WEEK 7
(Please specify training information by descriptive statement, tables, sketches, figures etc.)

Time Entry Description / Remarks


08:30 a.m. -Punchcard at the guard house.

09:00 a.m. -cleaning an air-ring from grease that


attached at the air-ring.

Figure 3: Air-ring
12:30 p.m -Lunch

2.00 p.m -Cleaning die head Machine A-3. this


cleaning need to be done due to defect
to the product.

Figure 4: Die Head


4.00p.m
-follow technician to site visit.

6.00 p.m -Punchout

Note: Please include attachment whenever necessary

AFIQ AIMAN

Student Signature
Date: 12/09/2023
Date: 1 3 /09/2023 Day: 3 3 Training Week: WEEK 7
(Please specify training information by descriptive statement, tables, sketches, figures etc.)

Time Entry Description / Remarks


08:30 a.m. -Punchcard at the guard house.
09.00 a.m -follow technician to plant 3 to check
roller condition, because it cannot roll
smoothly. Then we decide to change
the bearing.

Figure 5: Change bearing

10.30 a.m -install the die head for machine A-4

Figure 6: Die Head


12.30 p.m -Lunch

2.00 p.m -clean up the inverter from dust using


air blower. Then troubleshoot the
inverter to ensure the inverter is still in a
good condition

6.00 p.m -Punchout


Figure 7: Motor Inverter

Note: Please include attachment whenever necessary

AFIQ AIMAN

Student Signature
Date: 13/09/2023
Date: 1 4 /09/2023 Day: 3 4 Training Week: WEEK 7
(Please specify training information by descriptive statement, tables, sketches, figures etc.)

Time Entry Description / Remarks


08:30 a.m. Punchcard at the guard house.

09:00 a.m. -Help technician clean up the power


supply. They found out that machine
they have troubleshoot got problem
from tht power supply.

12.30 p.m -Lunch. Figure 8: Power supply

3.00 p.m -fixing the roller. The operator has


smash the shaft that make the tighten
the bearing so that the bearing cannot
roll smoothly.

Figure 9: Grinder the Roller


6.00 p.m -Punchout

Note: Please include attachment whenever necessary

AFIQ AIMAN

Student Signature
Date: 14/09/2023
Date: 1 5 /09/2023 Day: 3 5 Training Week: WEEK 7
(Please specify training information by descriptive statement, tables, sketches, figures etc.)

Time Entry Description / Remarks


08:30 a.m. Punchcard at the guard house.

09:00 a.m. -follow technician to separate the screw


barrel at machine B-5 to clean up from
carbon.

Figure 10: Take out the screw barrel

Figure 11: Clean up the material.


12.30 p.m -Lunch.

2.00 p.m -clean up the screw barrel from carbon.

Figure 12: Clean up the screw barrel


using air gun
Figure 13: screw barrel

6.00 p.m -Punchout