Equipment Code TA150SB-2-220 Location Practical Work area Operation Procedure: 1. Connect the vacuum pump, gauge manifold and air conditioner as per the [Connection example] shown below. 2. Confirm with the gauge that it is not under any pressure. * If any CFC (chlorofluorocarbon) or nitrogen gas enters the vacuum pump, oil may be blown off from the muffler or damage may be caused thereby. 3. Confirm that the manifold valve on the high-pressure side is closed and then switch ON the power of the vacuum pump and open the vacuum pump valve and the manifold vale on the low- pressure side. 4. Perform vacuuming for a specified time in accordance with the instruction manual of the air conditioner manufacturer. 5. Close the low-pressure valve of the manifold, close the vacuum pump valve and, thereafter, switch OFF the power of the vacuum pump. 6. Confirm the gauge pressure, leave it for a few minutes and if the gauge pressure as reconfirmed then shows the same value as confirmed before, there has been no leakage in the system and the vacuum operation can be confirmed as having been completed.