Document Submittal Form

Document
Contractor Rawabi Specialized Contracting Company 05-126000-4800000631-RSC-PCO-WPR-000025
submittal no.

Contract no. 4800000631/000 Date 26-July-2023

To PMC NEOM/AECOM

Rev
Document no. Type Description Action required
no.
Approval Comments
4800000631/000–Weekly Progress
05-126000-4800000631-RSC-PCO-WPR- Weekly Report for Piled Jetty to Ras Gasbah
01
000025 Report Up To 26-July-2023 Other
Information

Contractor authorized signatory


Name Ahmed Abdelfattah Date 26-July-2023

Signature

PMC’s comments

Exception as noted revise


No exception taken Revise and resubmit
Status code and resubmit for record
Rejected Review not required Issued for Construction

Engineer’s name Date

Signature

Received by Contractor
Name Date

Signature

Document No.05-126000-4800000631-RSC-PCO-WPR-000025 Rev.01 Page 1 of 20


WEEKLY REPORT

4800000631/000- Weekly Progress Report for Piled Jetty to Ras Gasbah


Up To 26-July-2023

0 5 – 1 2 6 0 0 0 – 4 8 0 0 0 0 0 6 3 1 – R S C – P C O – W P R – 0 0 0 0 2 5 " R e v. 0 1”, J u l y. 2 0 2 3

Document No.05-126000-4800000631-RSC-PCO-WPR-000025 Rev.01 Page 2 of 20


DOCUMENT HISTORY

Revision code Description of changes Purpose of issue Date

01 First Issue Issue for Information 26-July-2023

DOCUMENT APPROVAL

Prepared by Reviewed by Approved by


Name: Youssef Hesham Ahmed Abdelfattah Khaled Ahmed

Job Title: Project Control Engineer Project Manager Project Director


Signature

Document No.05-126000-4800000631-RSC-PCO-WPR-000025 Rev.01 Page 3 of 20


PILED JETTY TO RAS GASABAH

Activity ID Activity Name Original BL Project BL Project Last F'Cast Last F'Cast Current F'Cast Current F'Cast Total Variance - Variance - Schedule % Performance 2 2023
Duration Start Finish Start Finish Start Finish Float BL Finish LF Finish December
Complete % Complete January February March April May June July August September October November
21 28 04 11 18 25 01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08
PILED JETTY TO RAS GASABAH REV 02 - Update 26 Jul 2023 323 24-Dec-22 30-Sep-23 24-Dec-22 30-Sep-23 24-Dec-22 A 12-Nov-23 0 -43 -43 69.05% 43.49%
Milestones 323 24-Dec-22 30-Sep-23 24-Dec-22 30-Sep-23 24-Dec-22 A 12-Nov-23 0 -43 -43 0% 0%
Contractual Milestones 323 24-Dec-22 30-Sep-23 24-Dec-22 30-Sep-23 24-Dec-22 A 12-Nov-23 0 -43 -43 0% 0%
13.03-1-2-4-1000Project Commencement Date 0 24-Dec-22 24-Dec-22 24-Dec-22 A 0 0 100% 100%
13.03-1-2-4-1160Completion IFC Piles Design 0 22-Feb-23 22-Feb-23 23-Feb-23 A -1 -1 100% 100%
13.03-1-2-4-1730Completion IFC Full Design Package 0 24-Mar-23 24-Mar-23 23-Mar-23 A 1 1 100% 100%
13.03-1-2-4-1790Completion Construction Mobilization 0 23-Apr-23 23-Apr-23 05-May-23 A -12 -12 100% 100%
13.03-1-2-4-3190Completion and Handover 0 30-Sep-23 30-Sep-23 12-Nov-23 0 -43 -43 0% 0%
Non-contractual Milestones 24 29-Jan-23 07-Feb-23 29-Jan-23 07-Feb-23 01-Feb-23 A 28-Feb-23 A -21 -21 0% 0%
13.03-1-2-4-1940NCEC / Coast Guard Permits 0 29-Jan-23 29-Jan-23 01-Feb-23 A -3 -3 100% 100%
13.03-1-2-4-1100Land use Permits 0 07-Feb-23 07-Feb-23 22-Feb-23 A -15 -15 100% 100%
13.03-1-2-4-1660Receiving Final Geotechnical Report 0 02-Feb-23 02-Feb-23 28-Feb-23 A -26 -26 100% 100%
Mobilization 92 23-Jan-23 23-Apr-23 23-Jan-23 23-Apr-23 23-Jan-23 A 05-May-23 A -12 -12 100% 100%
13.03-1-2-4-3230 Issue PO to The Supplier 15 23-Jan-23 07-Feb-23 23-Jan-23 07-Feb-23 23-Jan-23 A 07-Feb-23 A 0 0 100% 100%
13.03-1-2-4-3240 Supply Site Temporary Facilities 30 07-Feb-23 09-Mar-23 07-Feb-23 09-Mar-23 07-Feb-23 A 14-Apr-23 A -36 -36 100% 100%
13.03-1-2-4-1150 Constrcut Site Temporary Facilities 30 09-Mar-23 08-Apr-23 09-Mar-23 08-Apr-23 11-Mar-23 A 02-May-23 A -24 -24 100% 100%
13.03-1-2-4-1800 Mobilization of Driving barge 30 24-Mar-23 23-Apr-23 24-Mar-23 23-Apr-23 26-Mar-23 A 05-May-23 A -12 -12 100% 100%
13.03-1-2-4-1810 Mobilization of Supply barge 30 24-Mar-23 23-Apr-23 24-Mar-23 23-Apr-23 26-Mar-23 A 05-May-23 A -12 -12 100% 100%
Engineering 97 24-Dec-22 24-Mar-23 24-Dec-22 24-Mar-23 24-Dec-22 A 23-Mar-23 A 1 1 100% 100%
Deliverables Submittal 97 24-Dec-22 24-Mar-23 24-Dec-22 24-Mar-23 24-Dec-22 A 23-Mar-23 A 1 1 100% 100%
Project Plans 36 24-Dec-22 29-Jan-23 24-Dec-22 29-Jan-23 24-Dec-22 A 04-Feb-23 A -6 -6 100% 100%
13.03-1-2-4-1030Preparing & Submittal Mobilization Plan 18 24-Dec-22 11-Jan-23 24-Dec-22 11-Jan-23 24-Dec-22 A 25-Jan-23 A -14 -14 100% 100%
13.03-1-2-4-1050Preparing & Submittal Quality Plan 18 27-Dec-22 14-Jan-23 27-Dec-22 14-Jan-23 27-Dec-22 A 25-Jan-23 A -11 -11 100% 100%
13.03-1-2-4-1090Preparing & Submittal Project Execution Plan 15 14-Jan-23 29-Jan-23 14-Jan-23 29-Jan-23 28-Dec-22 A 28-Jan-23 A 1 1 100% 100%
13.03-1-2-4-1020Preparing & Submittal HSE Plan 18 27-Dec-22 14-Jan-23 27-Dec-22 14-Jan-23 27-Dec-22 A 30-Jan-23 A -16 -16 100% 100%
13.03-1-2-4-1010Preparing & Submittal Environmental Plan 18 24-Dec-22 11-Jan-23 24-Dec-22 11-Jan-23 24-Dec-22 A 04-Feb-23 A -24 -24 100% 100%
Pre-Design 17 23-Jan-23 09-Feb-23 23-Jan-23 09-Feb-23 23-Jan-23 A 16-Feb-23 A -7 -7 100% 100%
13.03-1-2-4-1120Review and Analysis the Design Information Provided by Employer 10 23-Jan-23 02-Feb-23 23-Jan-23 02-Feb-23 23-Jan-23 A 02-Feb-23 A 0 0 100% 100%
13.03-1-2-4-1140Design Basis Report 7 02-Feb-23 09-Feb-23 02-Feb-23 09-Feb-23 02-Feb-23 A 16-Feb-23 A -7 -7 100% 100%
Development Design Stage 3B 36 09-Feb-23 17-Mar-23 09-Feb-23 17-Mar-23 06-Feb-23 A 25-Feb-23 A 20 20 100% 100%
13.03-1-2-4-1130Develop 3B- Jetty Piles Design 8 09-Feb-23 17-Feb-23 09-Feb-23 17-Feb-23 06-Feb-23 A 17-Feb-23 A 0 0 100% 100%
13.03-1-2-4-1180Develop 3B- Jetty Deck Superstructure Design 10 17-Feb-23 27-Feb-23 17-Feb-23 27-Feb-23 17-Feb-23 A 25-Feb-23 A 2 2 100% 100%
13.03-1-2-4-1670Develop 3B- Design Report 18 27-Feb-23 17-Mar-23 27-Feb-23 17-Mar-23 23-Feb-23 A 25-Feb-23 A 20 20 100% 100%
Detailed Design Stage 3C 42 17-Feb-23 24-Mar-23 17-Feb-23 24-Mar-23 17-Feb-23 A 23-Mar-23 A 1 1 100% 100%
13.03-1-2-4-1170Develop 3C- Jetty Piles Design 5 17-Feb-23 22-Feb-23 17-Feb-23 22-Feb-23 17-Feb-23 A 23-Feb-23 A -1 -1 100% 100%
13.03-1-2-4-1240Develop 3C- Deck Superstructure Design 6 27-Feb-23 05-Mar-23 27-Feb-23 05-Mar-23 27-Feb-23 A 06-Mar-23 A -1 -1 100% 100%
13.03-1-2-4-1370Develop 3C- Electrical network Design 6 05-Mar-23 11-Mar-23 05-Mar-23 11-Mar-23 11-Mar-23 A 23-Mar-23 A -12 -12 100% 100%
13.03-1-2-4-1470Develop 3C- Firefighting network Design 6 11-Mar-23 17-Mar-23 11-Mar-23 17-Mar-23 11-Mar-23 A 23-Mar-23 A -6 -6 100% 100%
13.03-1-2-4-1740Develop 3C- Design Report 7 17-Mar-23 24-Mar-23 17-Mar-23 24-Mar-23 11-Mar-23 A 23-Mar-23 A 1 1 100% 100%
Deliverables Approval 30 11-Jan-23 15-Feb-23 11-Jan-23 15-Feb-23 26-Jan-23 A 11-Feb-23 A 3 3 100% 100%
Project Plans 30 11-Jan-23 15-Feb-23 11-Jan-23 15-Feb-23 26-Jan-23 A 11-Feb-23 A 3 3 100% 100%
13.03-1-2-4-1080Quality Plan Approval 10 14-Jan-23 25-Jan-23 14-Jan-23 25-Jan-23 26-Jan-23 A 30-Jan-23 A -4 -4 100% 100%
13.03-1-2-4-1110Project Execution Plan Approval 10 04-Feb-23 15-Feb-23 04-Feb-23 15-Feb-23 29-Jan-23 A 31-Jan-23 A 13 13 100% 100%
13.03-1-2-4-1070Mobilization Plan Approval 10 11-Jan-23 23-Jan-23 11-Jan-23 23-Jan-23 26-Jan-23 A 11-Feb-23 A -16 -16 100% 100%
13.03-1-2-4-1040Environmental Plan Approval 10 11-Jan-23 23-Jan-23 11-Jan-23 23-Jan-23 05-Feb-23 A 11-Feb-23 A -17 -17 100% 100%
13.03-1-2-4-1060HSE Plan Approval 10 23-Jan-23 03-Feb-23 23-Jan-23 03-Feb-23 26-Jan-23 A 11-Feb-23 A -7 -7 100% 100%
Preliminary Works 28 29-Jan-23 02-Feb-23 29-Jan-23 02-Feb-23 01-Feb-23 A 26-Feb-23 A -24 -24 100% 100%
Bathymetric Survey 4 29-Jan-23 02-Feb-23 29-Jan-23 02-Feb-23 23-Feb-23 A 26-Feb-23 A -24 -24 100% 100%
13.03-1-2-4-1220Perform Bathymetric Survey 1 29-Jan-23 30-Jan-23 29-Jan-23 30-Jan-23 23-Feb-23 A 25-Feb-23 A -26 -26 100% 100%
13.03-1-2-4-1340Issue Bathymetric Survey Report 3 30-Jan-23 02-Feb-23 30-Jan-23 02-Feb-23 23-Feb-23 A 26-Feb-23 A -24 -24 100% 100%
Diving Inspection 4 29-Jan-23 02-Feb-23 29-Jan-23 02-Feb-23 01-Feb-23 A 08-Feb-23 A -6 -6 100% 100%
13.03-1-2-4-1450Preform Diving Inspection 1 29-Jan-23 30-Jan-23 29-Jan-23 30-Jan-23 01-Feb-23 A 02-Feb-23 A -3 -3 100% 100%
13.03-1-2-4-1520Issue Diving Inspection Report 3 30-Jan-23 02-Feb-23 30-Jan-23 02-Feb-23 04-Feb-23 A 08-Feb-23 A -6 -6 100% 100%
Procurement 246 17-Feb-23 19-Jul-23 17-Feb-23 19-Jul-23 17-Feb-23 A 21-Oct-23 7 -94 -94 100% 85.27%
Concrete 77 27-Feb-23 28-Apr-23 27-Feb-23 28-Apr-23 27-Feb-23 A 06-May-23 A -7 -7 100% 100%
13.03-1-2-4-1310Request For Quotation for concrete 10 27-Feb-23 09-Mar-23 27-Feb-23 09-Mar-23 27-Feb-23 A 04-Mar-23 A 5 5 100% 100%
13.03-1-2-4-1440Select and Approval of Supplier for concrete 10 09-Mar-23 19-Mar-23 09-Mar-23 19-Mar-23 05-Mar-23 A 07-Mar-23 A 12 12 100% 100%
13.03-1-2-4-1650Issue PO to The Supplier for concrete 10 29-Mar-23 08-Apr-23 29-Mar-23 08-Apr-23 02-Apr-23 A 10-Apr-23 A -1 -1 100% 100%
13.03-1-2-4-1570Approval of Material Submittal for concrete 10 19-Mar-23 29-Mar-23 19-Mar-23 29-Mar-23 13-Apr-23 A 02-May-23 A -28 -28 100% 100%
13.03-1-2-4-1890Delivery Materials to the Site for concrete 20 08-Apr-23 28-Apr-23 08-Apr-23 28-Apr-23 13-Apr-23 A 06-May-23 A -7 -7 100% 100%
Steel Reinforcment 77 27-Feb-23 28-Apr-23 27-Feb-23 28-Apr-23 27-Feb-23 A 02-May-23 A -3 -3 100% 100%
13.03-1-2-4-1290Request For Quotation for steel reinforcement 10 27-Feb-23 09-Mar-23 27-Feb-23 09-Mar-23 27-Feb-23 A 04-Mar-23 A 5 5 100% 100%
13.03-1-2-4-1420Select and Approval of Supplier for steel reinforcement 10 09-Mar-23 19-Mar-23 09-Mar-23 19-Mar-23 05-Mar-23 A 07-Mar-23 A 12 12 100% 100%
13.03-1-2-4-1630Issue PO to The Supplier for steel reinforcement 10 29-Mar-23 08-Apr-23 29-Mar-23 08-Apr-23 02-Apr-23 A 10-Apr-23 A -1 -1 100% 100%
13.03-1-2-4-1550Approval of Material Submittal for steel reinforcement 10 19-Mar-23 29-Mar-23 19-Mar-23 29-Mar-23 13-Apr-23 A 01-May-23 A -27 -27 100% 100%
13.03-1-2-4-1870Delivery Materials to the Site for steel reinforcement 20 08-Apr-23 28-Apr-23 08-Apr-23 28-Apr-23 13-Apr-23 A 02-May-23 A -3 -3 100% 100%
Grouting Materials 81 27-Feb-23 28-Apr-23 27-Feb-23 28-Apr-23 27-Feb-23 A 02-May-23 A -3 -3 100% 100%
13.03-1-2-4-1300Request For Quotation for grouting materials 10 27-Feb-23 09-Mar-23 27-Feb-23 09-Mar-23 27-Feb-23 A 04-Mar-23 A 5 5 100% 100%
13.03-1-2-4-1430Select and Approval of Supplier for grouting materials 10 09-Mar-23 19-Mar-23 09-Mar-23 19-Mar-23 05-Mar-23 A 07-Mar-23 A 12 12 100% 100%
13.03-1-2-4-1640Issue PO to The Supplier for grouting materials 10 29-Mar-23 08-Apr-23 29-Mar-23 08-Apr-23 11-Apr-23 A 17-Apr-23 A -8 -8 100% 100%
13.03-1-2-4-1560Approval of Material Submittal for grouting materials 10 19-Mar-23 29-Mar-23 19-Mar-23 29-Mar-23 13-Apr-23 A 01-May-23 A -27 -27 100% 100%
13.03-1-2-4-1880Delivery Materials to the Site for grouting materials 20 08-Apr-23 28-Apr-23 08-Apr-23 28-Apr-23 17-Apr-23 A 02-May-23 A -3 -3 100% 100%
Geotextile Material 81 22-Feb-23 07-Apr-23 22-Feb-23 07-Apr-23 23-Feb-23 A 02-May-23 A -24 -24 100% 100%
13.03-1-2-4-1210Request For Quotation for geotextile 5 22-Feb-23 27-Feb-23 22-Feb-23 27-Feb-23 23-Feb-23 A 04-Mar-23 A -5 -5 100% 100%
13.03-1-2-4-1260Select and Approval of Supplier for geotextile 5 27-Feb-23 04-Mar-23 27-Feb-23 04-Mar-23 04-Mar-23 A 07-Mar-23 A -3 -3 100% 100%

Actual Level of Effort Project Baseline Remaining Work Page 1 of 4 Date Revision Checked Approved
Revision #0 A. Kwesi M. Shaban
Primary Baseline Actual Work Critical Remaining Work Piled Jetty to Ras Gasabah
PILED JETTY TO RAS GASABAH

Activity ID Activity Name Original BL Project BL Project Last F'Cast Last F'Cast Current F'Cast Current F'Cast Total Variance - Variance - Schedule % Performance 2 2023
Duration Start Finish Start Finish Start Finish Float BL Finish LF Finish December
Complete % Complete January February March April May June July August September October November
21 28 04 11 18 25 01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08
13.03-1-2-4-1490Issue PO to The Supplier for geotextile 10 08-Mar-23 18-Mar-23 08-Mar-23 18-Mar-23 06-Apr-23 A 10-Apr-23 A -22 -22 100% 100%
13.03-1-2-4-1330Approval of Material Submittal for geotextile 5 04-Mar-23 08-Mar-23 04-Mar-23 08-Mar-23 13-Apr-23 A 01-May-23 A -45 -45 100% 100%
13.03-1-2-4-1680Delivery Materials to the Site for geotextile 20 18-Mar-23 07-Apr-23 18-Mar-23 07-Apr-23 13-Apr-23 A 02-May-23 A -24 -24 100% 100%
Pilles Dia. 1219 Thk. 25 mm 127 17-Feb-23 13-Jun-23 17-Feb-23 13-Jun-23 17-Feb-23 A 23-Jul-23 A -40 -40 100% 100%
13.03-1-2-4-1190Request For Quotation for Piles 1219 Thk. 25 mm 10 17-Feb-23 27-Feb-23 17-Feb-23 27-Feb-23 17-Feb-23 A 27-Feb-23 A 0 0 100% 100%
13.03-1-2-4-1230Select and Approval of Supplier for Piles 1219 Thk. 25 mm 7 27-Feb-23 06-Mar-23 27-Feb-23 06-Mar-23 27-Feb-23 A 20-Mar-23 A -14 -14 100% 100%
13.03-1-2-4-1390Issue PO to The Supplier for Piles 1219 Thk. 25 mm 5 14-Mar-23 19-Mar-23 14-Mar-23 19-Mar-23 19-Mar-23 A 23-Mar-23 A -4 -4 100% 100%
13.03-1-2-4-1350Approval of Material Submittal for Piles 1219 Thk. 25 mm 7 06-Mar-23 14-Mar-23 06-Mar-23 14-Mar-23 22-Mar-23 A 02-May-23 A -43 -43 100% 100%
13.03-1-2-4-2310Delivery Materials to the Site for Piles 1219 Thk. 25 mm 86 19-Mar-23 13-Jun-23 19-Mar-23 13-Jun-23 24-Mar-23 A 23-Jul-23 A -40 -40 100% 100%
Pilles Dia. 1219 Thk. 22 mm 129 17-Feb-23 15-Jun-23 17-Feb-23 15-Jun-23 17-Feb-23 A 23-Jul-23 A -38 -38 100% 100%
13.03-1-2-4-1200Request For Quotation for Piles 1219 Thk. 22 mm 10 17-Feb-23 27-Feb-23 17-Feb-23 27-Feb-23 17-Feb-23 A 27-Feb-23 A 0 0 100% 100%
13.03-1-2-4-1250Select and Approval of Supplier for Piles 1219 Thk. 22 mm 7 27-Feb-23 06-Mar-23 27-Feb-23 06-Mar-23 27-Feb-23 A 20-Mar-23 A -14 -14 100% 100%
13.03-1-2-4-1400Issue PO to The Supplier for Piles 1219 Thk. 22 mm 5 14-Mar-23 19-Mar-23 14-Mar-23 19-Mar-23 19-Mar-23 A 23-Mar-23 A -4 -4 100% 100%
13.03-1-2-4-1360Approval of Material Submittal for Piles 1219 Thk. 22 mm 7 06-Mar-23 14-Mar-23 06-Mar-23 14-Mar-23 22-Mar-23 A 02-May-23 A -43 -43 100% 100%
13.03-1-2-4-2320Delivery Materials to the Site for Piles 1219 Thk. 22 mm 88 19-Mar-23 15-Jun-23 19-Mar-23 15-Jun-23 24-Mar-23 A 23-Jul-23 A -38 -38 100% 100%
Trestle Steel Longitudinal Beams 105 27-Feb-23 17-Jun-23 27-Feb-23 17-Jun-23 09-Mar-23 A 04-Aug-23 6 -47 -47 100% 98.4%
13.03-1-2-4-1280Request For Quotation for trestle steel longitudinal beams 10 27-Feb-23 09-Mar-23 27-Feb-23 09-Mar-23 09-Mar-23 A 12-Mar-23 A -3 -3 100% 100%
13.03-1-2-4-1410Select and Approval of Supplier for trestle steel longitudinal beams 10 09-Mar-23 19-Mar-23 09-Mar-23 19-Mar-23 16-Mar-23 A 03-Apr-23 A -15 -15 100% 100%
13.03-1-2-4-1620Issue PO to The Supplier for trestle steel longitudinal beams 10 29-Mar-23 08-Apr-23 29-Mar-23 08-Apr-23 04-Apr-23 A 10-Apr-23 A -1 -1 100% 100%
13.03-1-2-4-1540Approval of Material Submittal for trestle steel longitudinal beams 10 19-Mar-23 29-Mar-23 19-Mar-23 29-Mar-23 13-May-23 A 30-May-23 A -52 -52 100% 100%
13.03-1-2-4-2330Delivery Materials to the Site for trestle steel longitudinal beams 70 08-Apr-23 17-Jun-23 08-Apr-23 17-Jun-23 11-Apr-23 A 04-Aug-23 6 -47 -47 100% 98%
Trestle Steel Cap Beams 105 27-Feb-23 07-Jun-23 27-Feb-23 07-Jun-23 09-Mar-23 A 04-Aug-23 3 -58 -58 100% 98.4%
13.03-1-2-4-1270Request For Quotation for trestle steel Cap beams 10 27-Feb-23 09-Mar-23 27-Feb-23 09-Mar-23 09-Mar-23 A 12-Mar-23 A -3 -3 100% 100%
13.03-1-2-4-1380Select and Approval of Supplier for trestle steel Cap beams 7 09-Mar-23 16-Mar-23 09-Mar-23 16-Mar-23 16-Mar-23 A 03-Apr-23 A -18 -18 100% 100%
13.03-1-2-4-1530Issue PO to The Supplier for trestle steel Cap beams 5 24-Mar-23 29-Mar-23 24-Mar-23 29-Mar-23 04-Apr-23 A 10-Apr-23 A -12 -12 100% 100%
13.03-1-2-4-1480Approval of Material Submittal for trestle steel Cap beams 7 16-Mar-23 24-Mar-23 16-Mar-23 24-Mar-23 13-May-23 A 30-May-23 A -58 -58 100% 100%
13.03-1-2-4-2280Delivery Materials to the Site for trestle steel Cap beams 70 29-Mar-23 07-Jun-23 29-Mar-23 07-Jun-23 11-Apr-23 A 04-Aug-23 3 -58 -58 100% 98%
Electrical network 163 11-Mar-23 21-Jun-23 11-Mar-23 21-Jun-23 20-Apr-23 A 06-Oct-23 22 -107 -107 100% 15.02%
13.03-1-2-4-1510Request For Quotation for Electrical network 10 11-Mar-23 21-Mar-23 11-Mar-23 21-Mar-23 20-Apr-23 A 06-May-23 A -46 -46 100% 100%
13.03-1-2-4-1610Select and Approval of Supplier for Electrical network 10 21-Mar-23 31-Mar-23 21-Mar-23 31-Mar-23 07-May-23 A 30-May-23 A -60 -60 100% 100%
13.03-1-2-4-1780Issue PO to The Supplier for Electrical network 10 12-Apr-23 22-Apr-23 12-Apr-23 22-Apr-23 17-Jun-23 A 26-Jul-23 A -95 -95 100% 100%
13.03-1-2-4-1720Approval of Material Submittal for Electrical network 10 01-Apr-23 12-Apr-23 01-Apr-23 12-Apr-23 26-Jul-23 07-Aug-23 19 -100 -100 100% 0%
13.03-1-2-4-2390Delivery Materials to the Site for Electrical network 60 22-Apr-23 21-Jun-23 22-Apr-23 21-Jun-23 07-Aug-23 06-Oct-23 22 -107 -107 100% 0%
lighting Masts 169 11-Mar-23 21-Jun-23 11-Mar-23 21-Jun-23 30-Mar-23 A 28-Sep-23 28 -99 -99 100% 15.02%
13.03-1-2-4-1500Request For Quotation for lighting Masts 10 11-Mar-23 21-Mar-23 11-Mar-23 21-Mar-23 06-Apr-23 A 10-Apr-23 A -20 -20 100% 100%
13.03-1-2-4-1590Select and Approval of Supplier for lighting Masts 10 21-Mar-23 31-Mar-23 21-Mar-23 31-Mar-23 30-Mar-23 A 30-May-23 A -60 -60 100% 100%
13.03-1-2-4-1750Issue PO to The Supplier for lighting Masts 10 12-Apr-23 22-Apr-23 12-Apr-23 22-Apr-23 04-Jun-23 A 27-Jun-23 A -66 -66 100% 100%
13.03-1-2-4-1690Approval of Material Submittal for lighting Masts 10 01-Apr-23 12-Apr-23 01-Apr-23 12-Apr-23 15-Jun-23 A 30-Jul-23 24 -93 -93 100% 92%
13.03-1-2-4-2370Delivery Materials to the Site for lighting Masts 60 22-Apr-23 21-Jun-23 22-Apr-23 21-Jun-23 30-Jul-23 28-Sep-23 28 -99 -99 100% 0%
Drainage gutters 163 21-Mar-23 30-Jun-23 21-Mar-23 30-Jun-23 20-Apr-23 A 06-Oct-23 16 -98 -98 100% 15.02%
13.03-1-2-4-1600Request For Quotation for drainage gutters 10 21-Mar-23 31-Mar-23 21-Mar-23 31-Mar-23 20-Apr-23 A 06-May-23 A -36 -36 100% 100%
13.03-1-2-4-1700Select and Approval of Supplier for drainage gutters 10 31-Mar-23 10-Apr-23 31-Mar-23 10-Apr-23 07-May-23 A 19-Jun-23 A -70 -70 100% 100%
13.03-1-2-4-1920Issue PO to The Supplier for drainage gutters 10 21-Apr-23 01-May-23 21-Apr-23 01-May-23 20-Jun-23 A 26-Jul-23 A -86 -86 100% 100%
13.03-1-2-4-1760Approval of Material Submittal for drainage gutters 10 10-Apr-23 21-Apr-23 10-Apr-23 21-Apr-23 26-Jul-23 07-Aug-23 14 -92 -92 100% 0%
13.03-1-2-4-2470Delivery Materials to the Site for drainage gutters 60 01-May-23 30-Jun-23 01-May-23 30-Jun-23 07-Aug-23 06-Oct-23 16 -98 -98 100% 0%
Firefighting Network 170 31-Mar-23 11-Jul-23 31-Mar-23 11-Jul-23 06-Apr-23 A 06-Oct-23 19 -87 -87 100% 15.01%
13.03-1-2-4-1710Request For Quotation for firefighting network 10 31-Mar-23 10-Apr-23 31-Mar-23 10-Apr-23 06-Apr-23 A 10-Apr-23 A 0 0 100% 100%
13.03-1-2-4-1770Select and Approval of Supplier for firefighting network 10 10-Apr-23 20-Apr-23 10-Apr-23 20-Apr-23 12-Apr-23 A 30-May-23 A -40 -40 100% 100%
13.03-1-2-4-2050Issue PO to The Supplier for firefighting network 10 02-May-23 12-May-23 02-May-23 12-May-23 10-Jun-23 A 26-Jul-23 A -75 -75 100% 100%
13.03-1-2-4-1930Approval of Material Submittal for firefighting network 10 20-Apr-23 02-May-23 20-Apr-23 02-May-23 26-Jul-23 07-Aug-23 16 -83 -83 100% 0%
13.03-1-2-4-2540Delivery Materials to the Site for firefighting network 60 12-May-23 11-Jul-23 12-May-23 11-Jul-23 07-Aug-23 06-Oct-23 19 -87 -87 100% 0%
Bollards 151 24-Mar-23 19-Jul-23 24-Mar-23 19-Jul-23 23-Mar-23 A 13-Aug-23 74 -25 -25 100% 89.85%
13.03-1-2-4-1900Request For Quotation for bollards 10 24-Mar-23 03-Apr-23 24-Mar-23 03-Apr-23 23-Mar-23 A 28-Mar-23 A 6 6 100% 100%
13.03-1-2-4-1960Select and Approval of Supplier for bollards 10 03-Apr-23 13-Apr-23 03-Apr-23 13-Apr-23 28-Mar-23 A 10-Apr-23 A 3 3 100% 100%
13.03-1-2-4-2070Approval of Material Submittal for bollards 10 13-Apr-23 25-Apr-23 13-Apr-23 25-Apr-23 13-Apr-23 A 02-May-23 A -6 -6 100% 100%
13.03-1-2-4-2170Issue PO to The Supplier for bollards 10 25-Apr-23 05-May-23 25-Apr-23 05-May-23 25-Apr-23 A 06-Jun-23 A -32 -32 100% 100%
13.03-1-2-4-2750Delivery Materials to the Site for bollards 75 05-May-23 19-Jul-23 05-May-23 19-Jul-23 06-Jun-23 A 13-Aug-23 74 -25 -25 100% 88%
Fenders 160 24-Mar-23 19-Jul-23 24-Mar-23 19-Jul-23 23-Mar-23 A 13-Aug-23 74 -25 -25 100% 89.8%
13.03-1-2-4-1820Request For Quotation for fenders 10 24-Mar-23 03-Apr-23 24-Mar-23 03-Apr-23 23-Mar-23 A 28-Mar-23 A 6 6 100% 100%
13.03-1-2-4-1970Select and Approval of Supplier for fenders 8 03-Apr-23 13-Apr-23 03-Apr-23 13-Apr-23 28-Mar-23 A 10-Apr-23 A 3 3 100% 100%
13.03-1-2-4-2180Issue PO to The Supplier for fenders 10 25-Apr-23 05-May-23 25-Apr-23 05-May-23 25-Apr-23 A 06-Jun-23 A -32 -32 100% 100%
13.03-1-2-4-2080Approval of Material Submittal for fenders 10 13-Apr-23 25-Apr-23 13-Apr-23 25-Apr-23 07-May-23 A 12-Jul-23 A -68 -68 100% 100%
13.03-1-2-4-2760Delivery Materials to the Site for fenders 75 05-May-23 19-Jul-23 05-May-23 19-Jul-23 06-Jun-23 A 13-Aug-23 74 -25 -25 100% 88%
Navegation Aids 185 24-Mar-23 19-Jul-23 24-Mar-23 19-Jul-23 19-Apr-23 A 21-Oct-23 5 -94 -94 100% 12.77%
13.03-1-2-4-1830Request For Quotation for navigation aids 10 24-Mar-23 03-Apr-23 24-Mar-23 03-Apr-23 19-Apr-23 A 06-May-23 A -33 -33 100% 100%
13.03-1-2-4-1980Select and Approval of Supplier for navigation aids 10 03-Apr-23 13-Apr-23 03-Apr-23 13-Apr-23 07-May-23 A 02-Jul-23 A -80 -80 100% 100%
13.03-1-2-4-2090Approval of Material Submittal for navigation aids 10 13-Apr-23 25-Apr-23 13-Apr-23 25-Apr-23 26-Jul-23 07-Aug-23 4 -89 -89 100% 0%
13.03-1-2-4-2190Issue PO to The Supplier for navigation aids 10 25-Apr-23 05-May-23 25-Apr-23 05-May-23 03-Jul-23 A 07-Aug-23 5 -94 -94 100% 85%
13.03-1-2-4-2770Delivery Materials to the Site for navigation aids 75 05-May-23 19-Jul-23 05-May-23 19-Jul-23 07-Aug-23 21-Oct-23 5 -94 -94 100% 0%
Mooring Buoy 185 24-Mar-23 19-Jul-23 24-Mar-23 19-Jul-23 19-Apr-23 A 21-Oct-23 5 -94 -94 100% 11.34%
13.03-1-2-4-1840Request For Quotation for mooring buoy 10 24-Mar-23 03-Apr-23 24-Mar-23 03-Apr-23 19-Apr-23 A 06-May-23 A -33 -33 100% 100%
13.03-1-2-4-1990Select and Approval of Supplier for mooring buoy 10 03-Apr-23 13-Apr-23 03-Apr-23 13-Apr-23 07-May-23 A 03-Jul-23 A -81 -81 100% 100%
13.03-1-2-4-2100Approval of Material Submittal for mooring buoy 10 13-Apr-23 25-Apr-23 13-Apr-23 25-Apr-23 26-Jul-23 07-Aug-23 4 -89 -89 100% 0%

Actual Level of Effort Project Baseline Remaining Work Page 2 of 4 Date Revision Checked Approved
Revision #0 A. Kwesi M. Shaban
Primary Baseline Actual Work Critical Remaining Work Piled Jetty to Ras Gasabah
PILED JETTY TO RAS GASABAH

Activity ID Activity Name Original BL Project BL Project Last F'Cast Last F'Cast Current F'Cast Current F'Cast Total Variance - Variance - Schedule % Performance 2 2023
Duration Start Finish Start Finish Start Finish Float BL Finish LF Finish December
Complete % Complete January February March April May June July August September October November
21 28 04 11 18 25 01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08
13.03-1-2-4-2200Issue PO to The Supplier for mooring buoy 10 25-Apr-23 05-May-23 25-Apr-23 05-May-23 04-Jul-23 A 07-Aug-23 5 -94 -94 100% 75%
13.03-1-2-4-2780Delivery Materials to the Site for mooring buoy 75 05-May-23 19-Jul-23 05-May-23 19-Jul-23 07-Aug-23 21-Oct-23 5 -94 -94 100% 0%
Ladders 185 24-Mar-23 19-Jul-23 24-Mar-23 19-Jul-23 19-Apr-23 A 21-Oct-23 5 -94 -94 100% 11.32%
13.03-1-2-4-1850Request For Quotation for ladders 10 24-Mar-23 03-Apr-23 24-Mar-23 03-Apr-23 19-Apr-23 A 06-May-23 A -33 -33 100% 100%
13.03-1-2-4-2000Select and Approval of Supplier for ladders 10 03-Apr-23 13-Apr-23 03-Apr-23 13-Apr-23 07-May-23 A 03-Jul-23 A -81 -81 100% 100%
13.03-1-2-4-2110Approval of Material Submittal for ladders 10 13-Apr-23 25-Apr-23 13-Apr-23 25-Apr-23 26-Jul-23 07-Aug-23 4 -89 -89 100% 0%
13.03-1-2-4-2210Issue PO to The Supplier for ladders 10 25-Apr-23 05-May-23 25-Apr-23 05-May-23 02-Jul-23 A 07-Aug-23 5 -94 -94 100% 75%
13.03-1-2-4-2790Delivery Materials to the Site for ladders 75 05-May-23 19-Jul-23 05-May-23 19-Jul-23 07-Aug-23 21-Oct-23 5 -94 -94 100% 0%
Crash barriers 163 24-Mar-23 04-Jul-23 24-Mar-23 04-Jul-23 20-Apr-23 A 06-Oct-23 20 -94 -94 100% 9.04%
13.03-1-2-4-1860Request For Quotation for Crash barriers 10 24-Mar-23 03-Apr-23 24-Mar-23 03-Apr-23 20-Apr-23 A 06-May-23 A -33 -33 100% 100%
13.03-1-2-4-2010Select and Approval of Supplier for Crash barriers 10 03-Apr-23 13-Apr-23 03-Apr-23 13-Apr-23 07-May-23 A 13-Jul-23 A -91 -91 100% 100%
13.03-1-2-4-2220Issue PO to The Supplier for Crash barriers 10 25-Apr-23 05-May-23 25-Apr-23 05-May-23 16-Jul-23 A 30-Jul-23 28 -86 -86 100% 60%
13.03-1-2-4-2120Approval of Material Submittal for Crash barriers 10 13-Apr-23 25-Apr-23 13-Apr-23 25-Apr-23 26-Jul-23 07-Aug-23 17 -89 -89 100% 0%
13.03-1-2-4-2600Delivery Materials to the Site for Crash barriers 60 05-May-23 04-Jul-23 05-May-23 04-Jul-23 07-Aug-23 06-Oct-23 20 -94 -94 100% 0%
Pavement Joint 173 24-Mar-23 04-Jul-23 24-Mar-23 04-Jul-23 20-Apr-23 A 16-Oct-23 10 -104 -104 100% 0.02%
13.03-1-2-4-1910Request For Quotation for pavement joint 10 24-Mar-23 03-Apr-23 24-Mar-23 03-Apr-23 20-Apr-23 A 06-May-23 A -33 -33 100% 100%
13.03-1-2-4-2020Select and Approval of Supplier for pavement joint 10 03-Apr-23 13-Apr-23 03-Apr-23 13-Apr-23 07-May-23 A 18-Jul-23 A -96 -96 100% 100%
13.03-1-2-4-2130Approval of Material Submittal for pavement joint 10 13-Apr-23 25-Apr-23 13-Apr-23 25-Apr-23 26-Jul-23 07-Aug-23 9 -89 -89 100% 0%
13.03-1-2-4-2240Issue PO to The Supplier for pavement joint 10 25-Apr-23 05-May-23 25-Apr-23 05-May-23 07-Aug-23 17-Aug-23 10 -104 -104 100% 0%
13.03-1-2-4-2620Delivery Materials to the Site for pavement joint 60 05-May-23 04-Jul-23 05-May-23 04-Jul-23 17-Aug-23 16-Oct-23 10 -104 -104 100% 0%
Construction 174 23-Apr-23 25-Sep-23 23-Apr-23 25-Sep-23 15-May-23 A 07-Nov-23 0 -43 -43 47.9% 6.58%
Fabrication Activities 115 28-Apr-23 07-Aug-23 28-Apr-23 07-Aug-23 15-May-23 A 09-Sep-23 37 -32 -32 92.07% 59.24%
Fabrication of Acess Trestle Pre-Cast Slab 39 28-Apr-23 30-May-23 28-Apr-23 30-May-23 15-Jun-23 A 01-Aug-23 76 -62 -62 100% 85%
13.03-1-2-4-1950Fabrication of Trestle Pre-Cast Slab 1-4 8 28-Apr-23 06-May-23 28-Apr-23 06-May-23 15-Jun-23 A 30-Jun-23 A -54 -54 100% 100%
13.03-1-2-4-2040Fabrication of Trestle Pre-Cast Slab 2-4 8 06-May-23 14-May-23 06-May-23 14-May-23 02-Jul-23 A 10-Jul-23 A -56 -56 100% 100%
13.03-1-2-4-2150Fabrication of Trestle Pre-Cast Slab 3-4 8 14-May-23 22-May-23 14-May-23 22-May-23 11-Jul-23 A 22-Jul-23 A -60 -60 100% 100%
13.03-1-2-4-2250Fabrication of Trestle Pre-Cast Slab 4-4 8 22-May-23 30-May-23 22-May-23 30-May-23 22-Jul-23 A 01-Aug-23 76 -62 -62 100% 40%
Fabrication Jetty Head Pre-Cast Pile Cap 69 30-May-23 29-Jun-23 30-May-23 29-Jun-23 15-May-23 A 31-Jul-23 58 -31 -31 100% 87%
13.03-1-2-4-2260Fabrication of Jetty Precast Pile Cap 1-2 6 30-May-23 05-Jun-23 30-May-23 05-Jun-23 15-May-23 A 25-May-23 A 12 12 100% 100%
13.03-1-2-4-2270Fabrication of Jetty Precast Pile Cap 3-4 6 05-Jun-23 11-Jun-23 05-Jun-23 11-Jun-23 24-May-23 A 30-May-23 A 13 13 100% 100%
13.03-1-2-4-2300Fabrication of Jetty Precast Pile Cap 5-6 6 11-Jun-23 17-Jun-23 11-Jun-23 17-Jun-23 30-May-23 A 06-Jun-23 A 12 12 100% 100%
13.03-1-2-4-2380Fabrication of Jetty Precast Pile Cap 7-8 6 17-Jun-23 23-Jun-23 17-Jun-23 23-Jun-23 06-Jun-23 A 17-Jul-23 A -23 -23 100% 100%
13.03-1-2-4-2430Fabrication of Jetty Precast Pile Cap 9-10 6 23-Jun-23 29-Jun-23 23-Jun-23 29-Jun-23 23-Jul-23 A 31-Jul-23 58 -31 -31 100% 35%
Fabrication Jetty Head Pre-Cast Slabs 45 23-Jun-23 07-Aug-23 23-Jun-23 07-Aug-23 26-Jul-23 09-Sep-23 30 -32 -32 74.09% 0%
13.03-1-2-4-2420Fabrication of Jetty Head Precast Slabs 1-16 5 23-Jun-23 28-Jun-23 23-Jun-23 28-Jun-23 26-Jul-23 31-Jul-23 30 -32 -32 100% 0%
13.03-1-2-4-2450Fabrication of Jetty Head Precast Slabs 17-32 5 28-Jun-23 03-Jul-23 28-Jun-23 03-Jul-23 31-Jul-23 05-Aug-23 30 -32 -32 100% 0%
13.03-1-2-4-2490Fabrication of Jetty Head Precast Slabs 33-48 5 03-Jul-23 08-Jul-23 03-Jul-23 08-Jul-23 05-Aug-23 10-Aug-23 30 -32 -32 100% 0%
13.03-1-2-4-2530Fabrication of Jetty Head Precast Slabs 49-64 5 08-Jul-23 13-Jul-23 08-Jul-23 13-Jul-23 10-Aug-23 15-Aug-23 30 -32 -32 100% 0%
13.03-1-2-4-2560Fabrication of Jetty Head Precast Slabs 65-80 5 13-Jul-23 18-Jul-23 13-Jul-23 18-Jul-23 15-Aug-23 20-Aug-23 30 -32 -32 100% 0%
13.03-1-2-4-2590Fabrication of Jetty Head Precast Slabs 81-96 5 18-Jul-23 23-Jul-23 18-Jul-23 23-Jul-23 20-Aug-23 25-Aug-23 30 -32 -32 100% 0%
13.03-1-2-4-2640Fabrication of Jetty Head Precast Slabs 97-112 5 23-Jul-23 28-Jul-23 23-Jul-23 28-Jul-23 25-Aug-23 30-Aug-23 30 -32 -32 40.91% 0%
13.03-1-2-4-2670Fabrication of Jetty Head Precast Slabs 113-128 5 28-Jul-23 02-Aug-23 28-Jul-23 02-Aug-23 30-Aug-23 04-Sep-23 30 -32 -32 0% 0%
13.03-1-2-4-2700Fabrication of Jetty Head Precast Slabs 129-144 5 02-Aug-23 07-Aug-23 02-Aug-23 07-Aug-23 04-Sep-23 09-Sep-23 30 -32 -32 0% 0%
Installation Activities 98 23-Apr-23 12-Sep-23 23-Apr-23 12-Sep-23 23-Jul-23 A 25-Oct-23 13 -43 -43 46.82% 0.76%
Abutment Structure (Access way) 44 23-Apr-23 06-Jun-23 23-Apr-23 06-Jun-23 26-Jul-23 08-Sep-23 60 -94 -94 100% 0%
13.03-1-2-4-2030Excavation and Compaction 15 23-Apr-23 08-May-23 23-Apr-23 08-May-23 26-Jul-23 10-Aug-23 60 -94 -94 100% 0%
13.03-1-2-4-2060Geotextile Installation 3 08-May-23 11-May-23 08-May-23 11-May-23 10-Aug-23 13-Aug-23 60 -94 -94 100% 0%
13.03-1-2-4-2160Blocks Installation 10 11-May-23 21-May-23 11-May-23 21-May-23 13-Aug-23 23-Aug-23 60 -94 -94 100% 0%
13.03-1-2-4-2140Natural stone / Rocks Installation 10 21-May-23 31-May-23 21-May-23 31-May-23 23-Aug-23 02-Sep-23 60 -94 -94 100% 0%
13.03-1-2-4-2230Levelling & Compaction for Abutment 6 31-May-23 06-Jun-23 31-May-23 06-Jun-23 02-Sep-23 08-Sep-23 60 -94 -94 100% 0%
Trestle Road 92 15-Jun-23 08-Sep-23 15-Jun-23 08-Sep-23 23-Jul-23 A 19-Oct-23 3 -41 -41 51.23% 1.42%
Trestle Road Foundations 79 15-Jun-23 26-Aug-23 15-Jun-23 26-Aug-23 23-Jul-23 A 06-Oct-23 3 -41 -41 55.52% 2.79%
Pile Guides Installation 71 15-Jun-23 18-Aug-23 15-Jun-23 18-Aug-23 23-Jul-23 A 28-Sep-23 3 -41 -41 66.67% 3.75%
13.03-1-2-4-2290
Install Pile Guides 1-19 6 15-Jun-23 21-Jun-23 15-Jun-23 21-Jun-23 23-Jul-23 A 31-Jul-23 5 -40 -40 100% 15%
13.03-1-2-4-2480
Install Pile Guides 20-38 6 01-Jul-23 07-Jul-23 01-Jul-23 07-Jul-23 11-Aug-23 17-Aug-23 3 -41 -41 100% 0%
13.03-1-2-4-2630
Install Pile Guides 39-57 6 22-Jul-23 28-Jul-23 22-Jul-23 28-Jul-23 01-Sep-23 07-Sep-23 3 -41 -41 66.67% 0%
13.03-1-2-4-2880
Install Pile Guides 58-76 6 12-Aug-23 18-Aug-23 12-Aug-23 18-Aug-23 22-Sep-23 28-Sep-23 3 -41 -41 0% 0%
Piles Installation 77 16-Jun-23 25-Aug-23 16-Jun-23 25-Aug-23 23-Jul-23 A 05-Oct-23 3 -41 -41 50% 3.75%
13.03-1-2-4-2340
Driving Piles 1-19 7 16-Jun-23 23-Jun-23 16-Jun-23 23-Jun-23 23-Jul-23 A 01-Aug-23 5 -39 -39 100% 15%
13.03-1-2-4-2510
Driving Piles 20-38 7 07-Jul-23 14-Jul-23 07-Jul-23 14-Jul-23 17-Aug-23 24-Aug-23 3 -41 -41 100% 0%
13.03-1-2-4-2680
Driving Piles 39-57 7 28-Jul-23 04-Aug-23 28-Jul-23 04-Aug-23 07-Sep-23 14-Sep-23 3 -41 -41 0% 0%
13.03-1-2-4-2950
Driving Piles 58-76 7 18-Aug-23 25-Aug-23 18-Aug-23 25-Aug-23 28-Sep-23 05-Oct-23 3 -41 -41 0% 0%
Top Cutting of Piles 69 20-Jun-23 26-Aug-23 20-Jun-23 26-Aug-23 29-Jul-23 06-Oct-23 3 -41 -41 50% 0%
13.03-1-2-4-2350
Cutting Top Piles 1-19 4 20-Jun-23 24-Jun-23 20-Jun-23 24-Jun-23 29-Jul-23 02-Aug-23 5 -39 -39 100% 0%
13.03-1-2-4-2520
Cutting Top Piles 20-38 4 11-Jul-23 15-Jul-23 11-Jul-23 15-Jul-23 21-Aug-23 25-Aug-23 3 -41 -41 100% 0%
13.03-1-2-4-2690
Cutting Top Piles 39-57 4 01-Aug-23 05-Aug-23 01-Aug-23 05-Aug-23 11-Sep-23 15-Sep-23 3 -41 -41 0% 0%
13.03-1-2-4-2960
Cutting Top Piles 58-76 4 22-Aug-23 26-Aug-23 22-Aug-23 26-Aug-23 02-Oct-23 06-Oct-23 3 -41 -41 0% 0%
Trestle Road Superstructure 76 24-Jun-23 08-Sep-23 24-Jun-23 08-Sep-23 04-Aug-23 19-Oct-23 3 -41 -41 46.74% 0%
Trestle SteelCap Beams 66 24-Jun-23 29-Aug-23 24-Jun-23 29-Aug-23 04-Aug-23 09-Oct-23 3 -41 -41 50% 0%
13.03-1-2-4-2360
Install Trestle Cap Beam 1-10 3 24-Jun-23 27-Jun-23 24-Jun-23 27-Jun-23 04-Aug-23 07-Aug-23 3 -41 -41 100% 0%
13.03-1-2-4-2550
Install Trestle Cap Beam 11-20 3 15-Jul-23 18-Jul-23 15-Jul-23 18-Jul-23 25-Aug-23 28-Aug-23 3 -41 -41 100% 0%
13.03-1-2-4-2730
Install Trestle Cap Beam 21-30 3 05-Aug-23 08-Aug-23 05-Aug-23 08-Aug-23 15-Sep-23 18-Sep-23 3 -41 -41 0% 0%
13.03-1-2-4-2990
Install Trestle Cap Beam 31-38 3 26-Aug-23 29-Aug-23 26-Aug-23 29-Aug-23 06-Oct-23 09-Oct-23 3 -41 -41 0% 0%
Trestle SteelLongitudinal Beams 67 27-Jun-23 02-Sep-23 27-Jun-23 02-Sep-23 07-Aug-23 13-Oct-23 3 -41 -41 50% 0%
13.03-1-2-4-2410
Install Trestle Longitudinal Beams 1-34 4 27-Jun-23 01-Jul-23 27-Jun-23 01-Jul-23 07-Aug-23 11-Aug-23 3 -41 -41 100% 0%
13.03-1-2-4-2570
Install Trestle Longitudinal Beams 35-68 4 18-Jul-23 22-Jul-23 18-Jul-23 22-Jul-23 28-Aug-23 01-Sep-23 3 -41 -41 100% 0%

Actual Level of Effort Project Baseline Remaining Work Page 3 of 4 Date Revision Checked Approved
Revision #0 A. Kwesi M. Shaban
Primary Baseline Actual Work Critical Remaining Work Piled Jetty to Ras Gasabah
PILED JETTY TO RAS GASABAH

Activity ID Activity Name Original BL Project BL Project Last F'Cast Last F'Cast Current F'Cast Current F'Cast Total Variance - Variance - Schedule % Performance 2 2023
Duration Start Finish Start Finish Start Finish Float BL Finish LF Finish December
Complete % Complete January February March April May June July August September October November
21 28 04 11 18 25 01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08
13.03-1-2-4-2810
Install Trestle Longitudinal Beams 69-102 4 08-Aug-23 12-Aug-23 08-Aug-23 12-Aug-23 18-Sep-23 22-Sep-23 3 -41 -41 0% 0%
13.03-1-2-4-3020
Install Trestle Longitudinal Beams 103-136 4 29-Aug-23 02-Sep-23 29-Aug-23 02-Sep-23 09-Oct-23 13-Oct-23 3 -41 -41 0% 0%
Installation of Trestle Pre-Cast Slab 69 01-Jul-23 08-Sep-23 01-Jul-23 08-Sep-23 11-Aug-23 19-Oct-23 3 -41 -41 41.67% 0%
13.03-1-2-4-2460
Install Trestle Pre-Cast Slab 1-4 6 01-Jul-23 07-Jul-23 01-Jul-23 07-Jul-23 11-Aug-23 17-Aug-23 3 -41 -41 100% 0%
13.03-1-2-4-2610
Install Trestle Pre-Cast Slab 2-4 6 22-Jul-23 28-Jul-23 22-Jul-23 28-Jul-23 01-Sep-23 07-Sep-23 3 -41 -41 66.67% 0%
13.03-1-2-4-2870
Install Trestle Pre-Cast Slab 3-4 6 12-Aug-23 18-Aug-23 12-Aug-23 18-Aug-23 22-Sep-23 28-Sep-23 3 -41 -41 0% 0%
13.03-1-2-4-3050
Install Trestle Pre-Cast Slab 4-4 6 02-Sep-23 08-Sep-23 02-Sep-23 08-Sep-23 13-Oct-23 19-Oct-23 3 -41 -41 0% 0%
Jetty Head 91 13-Jun-23 12-Sep-23 13-Jun-23 12-Sep-23 26-Jul-23 25-Oct-23 0 -43 -43 36.6% 0%
Jetty Head Foundations 47 13-Jun-23 30-Jul-23 13-Jun-23 30-Jul-23 26-Jul-23 11-Sep-23 10 -43 -43 93.72% 0%
Pile Guides Installation 14 13-Jun-23 27-Jun-23 13-Jun-23 27-Jun-23 26-Jul-23 09-Aug-23 0 -43 -43 100% 0%
13.03-1-2-4-2400
Install Pile Guides 77-96 7 13-Jun-23 20-Jun-23 13-Jun-23 20-Jun-23 26-Jul-23 02-Aug-23 0 -43 -43 100% 0%
13.03-1-2-4-2440
Install Pile Guides 97-116 7 20-Jun-23 27-Jun-23 20-Jun-23 27-Jun-23 02-Aug-23 09-Aug-23 0 -43 -43 100% 0%
Piles Installation 16 27-Jun-23 13-Jul-23 27-Jun-23 13-Jul-23 09-Aug-23 25-Aug-23 0 -43 -43 100% 0%
13.03-1-2-4-2500
Driving Piles 77-96 8 27-Jun-23 05-Jul-23 27-Jun-23 05-Jul-23 09-Aug-23 17-Aug-23 0 -43 -43 100% 0%
13.03-1-2-4-2580
Driving Piles 97-116 8 05-Jul-23 13-Jul-23 05-Jul-23 13-Jul-23 17-Aug-23 25-Aug-23 0 -43 -43 100% 0%
Top Cutting of Piles 14 13-Jul-23 27-Jul-23 13-Jul-23 27-Jul-23 25-Aug-23 08-Sep-23 10 -43 -43 92.86% 0%
13.03-1-2-4-2650
Cutting Top Piles 77-96 7 13-Jul-23 20-Jul-23 13-Jul-23 20-Jul-23 25-Aug-23 01-Sep-23 0 -43 -43 100% 0%
13.03-1-2-4-2720
Cutting Top Piles 97-116 7 20-Jul-23 27-Jul-23 20-Jul-23 27-Jul-23 01-Sep-23 08-Sep-23 10 -43 -43 85.71% 0%
Pouring R.C Of Piles 10 20-Jul-23 30-Jul-23 20-Jul-23 30-Jul-23 01-Sep-23 11-Sep-23 10 -43 -43 50% 0%
13.03-1-2-4-2660
Installing Pile Plug & Pouring RC Of Piles 77-96 2 20-Jul-23 22-Jul-23 20-Jul-23 22-Jul-23 01-Sep-23 03-Sep-23 0 -43 -43 100% 0%
13.03-1-2-4-2800
Installing Pile Plug & Pouring RC Of Piles 97-116 3 27-Jul-23 30-Jul-23 27-Jul-23 30-Jul-23 08-Sep-23 11-Sep-23 10 -43 -43 0% 0%
Jetty Head Superstructure 52 22-Jul-23 12-Sep-23 22-Jul-23 12-Sep-23 03-Sep-23 25-Oct-23 0 -43 -43 1.22% 0%
Installation Jetty Head Pre-Cast Pile Cap 30 22-Jul-23 21-Aug-23 22-Jul-23 21-Aug-23 03-Sep-23 03-Oct-23 0 -43 -43 13.34% 0%
13.03-1-2-4-2710
Install Jetty Precast Pile Cap 1-2 6 22-Jul-23 28-Jul-23 22-Jul-23 28-Jul-23 03-Sep-23 09-Sep-23 0 -43 -43 66.67% 0%
13.03-1-2-4-2820
Install Jetty Precast Pile Cap 3-4 6 28-Jul-23 03-Aug-23 28-Jul-23 03-Aug-23 09-Sep-23 15-Sep-23 0 -43 -43 0% 0%
13.03-1-2-4-2850
Install of Jetty Precast Pile Cap 5-6 6 03-Aug-23 09-Aug-23 03-Aug-23 09-Aug-23 15-Sep-23 21-Sep-23 0 -43 -43 0% 0%
13.03-1-2-4-2910
Install of Jetty Precast Pile Cap 7-8 6 09-Aug-23 15-Aug-23 09-Aug-23 15-Aug-23 21-Sep-23 27-Sep-23 0 -43 -43 0% 0%
13.03-1-2-4-2970
Install of Jetty Precast Pile Cap 9-10 6 15-Aug-23 21-Aug-23 15-Aug-23 21-Aug-23 27-Sep-23 03-Oct-23 0 -43 -43 0% 0%
Pouring RC In Jetty Head Pre-Cast Pile Cap 27 28-Jul-23 24-Aug-23 28-Jul-23 24-Aug-23 09-Sep-23 06-Oct-23 0 -43 -43 0% 0%
13.03-1-2-4-2740
Pouring RC In Jetty Precast Pile Cap 1-2 3 28-Jul-23 31-Jul-23 28-Jul-23 31-Jul-23 09-Sep-23 12-Sep-23 3 -43 -43 0% 0%
13.03-1-2-4-2840
Pouring RC In Jetty Precast Pile Cap 3-4 3 03-Aug-23 06-Aug-23 03-Aug-23 06-Aug-23 15-Sep-23 18-Sep-23 0 -43 -43 0% 0%
13.03-1-2-4-2900
Pouring RC In Jetty Precast Pile Cap 5-6 3 09-Aug-23 12-Aug-23 09-Aug-23 12-Aug-23 21-Sep-23 24-Sep-23 0 -43 -43 0% 0%
13.03-1-2-4-2940
Pouring RC In Jetty Precast Pile Cap 7-8 3 15-Aug-23 18-Aug-23 15-Aug-23 18-Aug-23 27-Sep-23 30-Sep-23 0 -43 -43 0% 0%
13.03-1-2-4-3010
Pouring RC In Jetty Precast Pile Cap 9-10 3 21-Aug-23 24-Aug-23 21-Aug-23 24-Aug-23 03-Oct-23 06-Oct-23 0 -43 -43 0% 0%
Installation Jetty Head Pre-Cast Slab 30 31-Jul-23 30-Aug-23 31-Jul-23 30-Aug-23 12-Sep-23 12-Oct-23 0 -43 -43 0% 0%
13.03-1-2-4-2830
Install of Jetty Precast Slab 1-16 3 31-Jul-23 03-Aug-23 31-Jul-23 03-Aug-23 12-Sep-23 15-Sep-23 3 -43 -43 0% 0%
13.03-1-2-4-2860
Install of Jetty Precast Slab 17-32 3 06-Aug-23 09-Aug-23 06-Aug-23 09-Aug-23 18-Sep-23 21-Sep-23 0 -43 -43 0% 0%
13.03-1-2-4-2890
Install of Jetty Precast Slab 33-48 3 09-Aug-23 12-Aug-23 09-Aug-23 12-Aug-23 21-Sep-23 24-Sep-23 0 -43 -43 0% 0%
13.03-1-2-4-2920
Install of Jetty Precast Slab 49-64 3 12-Aug-23 15-Aug-23 12-Aug-23 15-Aug-23 24-Sep-23 27-Sep-23 0 -43 -43 0% 0%
13.03-1-2-4-2930
Install of Jetty Precast Slab 65-80 3 15-Aug-23 18-Aug-23 15-Aug-23 18-Aug-23 27-Sep-23 30-Sep-23 0 -43 -43 0% 0%
13.03-1-2-4-2980
Install of Jetty Precast Slab 81-96 3 18-Aug-23 21-Aug-23 18-Aug-23 21-Aug-23 30-Sep-23 03-Oct-23 0 -43 -43 0% 0%
13.03-1-2-4-3000
Install of Jetty Precast Slab 97-112 3 21-Aug-23 24-Aug-23 21-Aug-23 24-Aug-23 03-Oct-23 06-Oct-23 0 -43 -43 0% 0%
13.03-1-2-4-3030
Install of Jetty Precast Slab 113-128 3 24-Aug-23 27-Aug-23 24-Aug-23 27-Aug-23 06-Oct-23 09-Oct-23 0 -43 -43 0% 0%
13.03-1-2-4-3040
Install of Jetty Precast Slab 129-144 3 27-Aug-23 30-Aug-23 27-Aug-23 30-Aug-23 09-Oct-23 12-Oct-23 0 -43 -43 0% 0%
Jetty Head Cast In-Situ Concrete 13 30-Aug-23 12-Sep-23 30-Aug-23 12-Sep-23 12-Oct-23 25-Oct-23 0 -43 -43 0% 0%
13.03-1-2-4-3060
Install Formwork 10 30-Aug-23 09-Sep-23 30-Aug-23 09-Sep-23 12-Oct-23 22-Oct-23 0 -43 -43 0% 0%
13.03-1-2-4-3070
Fixing Steel Reinforcement 10 31-Aug-23 10-Sep-23 31-Aug-23 10-Sep-23 13-Oct-23 23-Oct-23 0 -43 -43 0% 0%
13.03-1-2-4-3080
Pouring of Concrete 2 10-Sep-23 12-Sep-23 10-Sep-23 12-Sep-23 23-Oct-23 25-Oct-23 0 -43 -43 0% 0%
Finishing Activities 19 08-Sep-23 25-Sep-23 08-Sep-23 25-Sep-23 19-Oct-23 07-Nov-23 0 -43 -43 0% 0%
Networks 19 08-Sep-23 25-Sep-23 08-Sep-23 25-Sep-23 19-Oct-23 07-Nov-23 0 -43 -43 0% 0%
13.03-1-2-4-3090Install Drainage gutters 10 08-Sep-23 18-Sep-23 08-Sep-23 18-Sep-23 19-Oct-23 29-Oct-23 3 -41 -41 0% 0%
13.03-1-2-4-3100Install Firefighting network 10 12-Sep-23 22-Sep-23 12-Sep-23 22-Sep-23 25-Oct-23 04-Nov-23 0 -43 -43 0% 0%
13.03-1-2-4-3110Install Electrical network 10 15-Sep-23 25-Sep-23 15-Sep-23 25-Sep-23 28-Oct-23 07-Nov-23 0 -43 -43 0% 0%
Furniture 12 12-Sep-23 24-Sep-23 12-Sep-23 24-Sep-23 25-Oct-23 06-Nov-23 1 -43 -43 0% 0%
13.03-1-2-4-3120Install Bollards 12 12-Sep-23 24-Sep-23 12-Sep-23 24-Sep-23 25-Oct-23 06-Nov-23 1 -43 -43 0% 0%
13.03-1-2-4-3130Install Fenders 12 12-Sep-23 24-Sep-23 12-Sep-23 24-Sep-23 25-Oct-23 06-Nov-23 1 -43 -43 0% 0%
13.03-1-2-4-3140Install Mooring Buoys 12 12-Sep-23 24-Sep-23 12-Sep-23 24-Sep-23 25-Oct-23 06-Nov-23 1 -43 -43 0% 0%
13.03-1-2-4-3150Install lighting masts 12 12-Sep-23 24-Sep-23 12-Sep-23 24-Sep-23 25-Oct-23 06-Nov-23 1 -43 -43 0% 0%
13.03-1-2-4-3160Install Nav Aids 12 12-Sep-23 24-Sep-23 12-Sep-23 24-Sep-23 25-Oct-23 06-Nov-23 1 -43 -43 0% 0%
13.03-1-2-4-3170Install Ladders 12 12-Sep-23 24-Sep-23 12-Sep-23 24-Sep-23 25-Oct-23 06-Nov-23 1 -43 -43 0% 0%
13.03-1-2-4-3180Install Crash Barriers 12 12-Sep-23 24-Sep-23 12-Sep-23 24-Sep-23 25-Oct-23 06-Nov-23 1 -43 -43 0% 0%
Handing Over 8 22-Sep-23 30-Sep-23 22-Sep-23 30-Sep-23 04-Nov-23 12-Nov-23 0 -43 -43 0% 0%
Testing and Commissioning 8 22-Sep-23 30-Sep-23 22-Sep-23 30-Sep-23 04-Nov-23 12-Nov-23 0 -43 -43 0% 0%
13.03-1-2-4-3210Testing and Commisionning 5 25-Sep-23 30-Sep-23 25-Sep-23 30-Sep-23 07-Nov-23 12-Nov-23 0 -43 -43 0% 0%
13.03-1-2-4-3220Prepare and Submit As-built drawings 8 22-Sep-23 30-Sep-23 22-Sep-23 30-Sep-23 04-Nov-23 12-Nov-23 0 -43 -43 0% 0%
Demobilization 7 23-Sep-23 30-Sep-23 23-Sep-23 30-Sep-23 05-Nov-23 12-Nov-23 0 -43 -43 0% 0%
13.03-1-2-4-3200Demobilization From Site 7 23-Sep-23 30-Sep-23 23-Sep-23 30-Sep-23 05-Nov-23 12-Nov-23 0 -43 -43 0% 0%

Actual Level of Effort Project Baseline Remaining Work Page 4 of 4 Date Revision Checked Approved
Revision #0 A. Kwesi M. Shaban
Primary Baseline Actual Work Critical Remaining Work Piled Jetty to Ras Gasabah
Piled Jetty to Ras Gasabah
Contract No. 4800000631
WEEKLY PROGRESS REPORT
Reporting Period up to 26 Jul 2023

(Week 31)
Document history

Revision code Description of changes Purpose of issue Date


01 - Issued for info 27 - Jul - 2023

Document approval

Prepared by Approved by
Name Youssef Hesham

Job Title Senior Planning


Engineer

D O C U M E N T CODECODE : R EVI SIO N C ODE: 00 PAG E 2 OF 15


1. Executive Summary
This weekly progress report covers the period from 20 Jul 2023 to 26 Jul 2023.
The table below shows the status of the current project.

Anticipated
Item Short Description Comments
Date
1 Project Commencement Date 24-Dec-22 Completed

2 Completion IFC Piles Design 22-Feb-23 Completed

3 Completion IFC Full Design Package 23-Mar-23 Completed

4 Completion Construction Mobilization 23-Apr-23 Completed

5 Completion and Handover 30-Sep-23

Short Description Planned % Actual % Variance

Manhours Progress 62.64% 37.57% -25.07%

1.1 Key Activities in Progress

 Delivery Materials to the Site for trestle steel longitudinal beams


 Delivery Materials to the Site for trestle steel Cap beams
 Manufacturing for bollards
 Manufacturing for Fenders
 Purchasing order for Lighting Masts
 Purchasing order for Mooring buoys
 Purchasing order for Lighting Ladders
 Purchasing order for Electrical Network
 Purchasing order for Drainage Gutters
 Purchasing order for firefighting works
 Fabrication of Trestle Pre-Cast Slab
 Fabrication of Jetty Precast Pile Cap
 Driving piles
 Install pile guides.

D O C U M E N T CODECODE : R EVI SIO N C ODE: 00 PAG E 3 OF 15


1.2 Two weeks Lookahead Activities
Planned
BL Progress
WBS Activity Name OD Actual Start Forecasted %
Finish %
Finish
Delivery Materials to the Site for trestle steel 70 11-Apr-23 A 04-Aug-23 17-Jun-23 100% 98%
Procurement
longitudinal beams
Delivery Materials to the Site for trestle steel Cap 70 11-Apr-23 A 04-Aug-23 07-Jun-23 100% 98%
Procurement
beams
Procurement Delivery Materials to the Site for Electrical network 60 07-Aug-23 06-Oct-23 21-Jun-23 100% 0%

Procurement Approval of Material Submittal for Electrical network 10 26-Jul-23 07-Aug-23 12-Apr-23 100% 0%

Procurement Delivery Materials to the Site for lighting Masts 60 30-Jul-23 28-Sep-23 21-Jun-23 100% 0%

Procurement Approval of Material Submittal for lighting Masts 10 15-Jun-23 A 30-Jul-23 12-Apr-23 100% 92%

Procurement Delivery Materials to the Site for drainage gutters 60 07-Aug-23 06-Oct-23 30-Jun-23 100% 0%

Procurement Approval of Material Submittal for drainage gutters 10 26-Jul-23 07-Aug-23 21-Apr-23 100% 0%

Procurement Delivery Materials to the Site for firefighting network 60 07-Aug-23 06-Oct-23 11-Jul-23 100% 0%
Approval of Material Submittal for firefighting network 10 26-Jul-23 07-Aug-23 02-May- 100% 0%
Procurement
23
Procurement Delivery Materials to the Site for bollards 75 06-Jun-23 A 13-Aug-23 19-Jul-23 100% 88%

Procurement Delivery Materials to the Site for fenders 75 06-Jun-23 A 13-Aug-23 19-Jul-23 100% 88%
Issue PO to The Supplier for navigation aids 10 03-Jul-23 A 07-Aug-23 05-May- 100% 85%
Procurement
23
Procurement Delivery Materials to the Site for navigation aids 75 07-Aug-23 21-Oct-23 19-Jul-23 100% 0.00%

Procurement Approval of Material Submittal for navigation aids 10 26-Jul-23 07-Aug-23 25-Apr-23 100% 0%

D O C U M E N T CODECODE : RE VI SIO N COD E: 00 PAGE 4 OF 15


Issue PO to The Supplier for mooring buoy 10 04-Jul-23 A 07-Aug-23 05-May- 100% 75.00%
Procurement
23
Procurement Delivery Materials to the Site for mooring buoy 75 07-Aug-23 21-Oct-23 19-Jul-23 100% 0%

Procurement Approval of Material Submittal for mooring buoy 10 26-Jul-23 07-Aug-23 25-Apr-23 100% 0%

Issue PO to The Supplier for ladders 10 02-Jul-23 A 07-Aug-23 05-May- 100% 75%
Procurement
23
Procurement Delivery Materials to the Site for ladders 75 07-Aug-23 21-Oct-23 19-Jul-23 100% 0%

Procurement Approval of Material Submittal for ladders 10 26-Jul-23 07-Aug-23 25-Apr-23 100% 0%
Issue PO to The Supplier for Crash barriers 10 16-Jul-23 A 30-Jul-23 05-May- 100% 60%
Procurement
23
Procurement Delivery Materials to the Site for Crash barriers 60 07-Aug-23 06-Oct-23 04-Jul-23 100% 0%

Procurement Approval of Material Submittal for Crash barriers 10 26-Jul-23 07-Aug-23 25-Apr-23 100% 0%
Issue PO to The Supplier for pavement joint 10 07-Aug-23 17-Aug-23 05-May- 100% 0%
Procurement
23
Procurement Delivery Materials to the Site for pavement joint 60 17-Aug-23 16-Oct-23 04-Jul-23 100% 0%

Procurement Approval of Material Submittal for pavement joint 10 26-Jul-23 07-Aug-23 25-Apr-23 100% 0%

Fabrication of Trestle Pre-Cast Slab 4-4 8 22-Jul-23 A 01-Aug-23 30-May- 100% 40%
Procurement
23
Procurement Fabrication of Jetty Precast Pile Cap 9-10 6 23-Jul-23 A 31-Jul-23 29-Jun-23 100% 35.00%

Procurement Fabrication of Jetty Head Precast Slabs 97-112 5 25-Aug-23 30-Aug-23 28-Jul-23 41% 0%

Procurement Fabrication of Jetty Head Precast Slabs 81-96 5 20-Aug-23 25-Aug-23 23-Jul-23 100% 0%

Procurement Fabrication of Jetty Head Precast Slabs 65-80 5 15-Aug-23 20-Aug-23 18-Jul-23 100% 0.00%

Procurement Fabrication of Jetty Head Precast Slabs 49-64 5 10-Aug-23 15-Aug-23 13-Jul-23 100% 0%

D O C U M E N T CODECODE : RE VI SIO N COD E: 00 PAGE 5 OF 15


Procurement Fabrication of Jetty Head Precast Slabs 33-48 5 05-Aug-23 10-Aug-23 08-Jul-23 100% 0%
Procurement Fabrication of Jetty Head Precast Slabs 17-32 5 31-Jul-23 05-Aug-23 03-Jul-23 100% 0%
Procurement Fabrication of Jetty Head Precast Slabs 129-144 5 04-Sep-23 09-Sep-23 07-Aug-23 0% 0%
Construction Fabrication of Jetty Head Precast Slabs 113-128 5 30-Aug-23 04-Sep-23 02-Aug-23 0% 0%
Construction Fabrication of Jetty Head Precast Slabs 1-16 5 26-Jul-23 31-Jul-23 28-Jun-23 100% 0%
Construction Natural stone / Rocks Installation 10 23-Aug-23 02-Sep-23 31-May- 100% 0%
23
Construction Levelling & Compaction for Abutment 6 02-Sep-23 08-Sep-23 06-Jun-23 100.00% 0%
Construction Geotextile Installation 3 10-Aug-23 13-Aug-23 11-May- 100% 0%
23
Construction Excavation and Compaction 15 26-Jul-23 10-Aug-23 08-May- 100% 0%
23
Construction Blocks Installation 10 13-Aug-23 23-Aug-23 21-May- 100% 0%
23
Construction Install Pile Guides 39-57 6 01-Sep-23 07-Sep-23 28-Jul-23 67% 0%

Construction Install Pile Guides 20-38 6 11-Aug-23 17-Aug-23 07-Jul-23 100% 0%

Construction Install Pile Guides 1-19 6 23-Jul-23 A 31-Jul-23 21-Jun-23 100% 15%

Construction Driving Piles 39-57 7 07-Sep-23 14-Sep-23 04-Aug-23 0% 0%

Construction Driving Piles 20-38 7 17-Aug-23 24-Aug-23 14-Jul-23 100% 0%

Construction Driving Piles 1-19 7 23-Jul-23 A 01-Aug-23 23-Jun-23 100% 15%

Construction Cutting Top Piles 39-57 4 11-Sep-23 15-Sep-23 05-Aug-23 0% 0%

Construction Cutting Top Piles 20-38 4 21-Aug-23 25-Aug-23 15-Jul-23 100% 0%

D O C U M E N T CODECODE : RE VI SIO N COD E: 00 PAGE 6 OF 15


Construction Cutting Top Piles 1-19 4 29-Jul-23 02-Aug-23 24-Jun-23 100% 0%

Construction Install Trestle Cap Beam 21-30 3 15-Sep-23 18-Sep-23 08-Aug-23 0% 0%


Construction Install Trestle Cap Beam 11-20 3 25-Aug-23 28-Aug-23 18-Jul-23 100.00% 0%
Construction Install Trestle Cap Beam 1-10 3 04-Aug-23 07-Aug-23 27-Jun-23 100.00% 0%
Construction Install Trestle Longitudinal Beams 35-68 4 28-Aug-23 01-Sep-23 22-Jul-23 100.00% 0%
Construction Install Trestle Longitudinal Beams 1-34 4 07-Aug-23 11-Aug-23 01-Jul-23 100% 0%
Construction Install Trestle Pre-Cast Slab 1-4 6 11-Aug-23 17-Aug-23 07-Jul-23 100.00% 0%
Construction Install Trestle Pre-Cast Slab 2-4 6 01-Sep-23 07-Sep-23 28-Jul-23 66.67% 0%
Construction Install Pile Guides 97-116 7 02-Aug-23 09-Aug-23 27-Jun-23 100% 0%
Construction Install Pile Guides 77-96 7 26-Jul-23 02-Aug-23 20-Jun-23 100.00% 0%
Construction Driving Piles 97-116 8 17-Aug-23 25-Aug-23 13-Jul-23 100% 0%
Construction Driving Piles 77-96 8 09-Aug-23 17-Aug-23 05-Jul-23 100% 0%
Construction Cutting Top Piles 97-116 7 01-Sep-23 08-Sep-23 27-Jul-23 86% 0%
Construction Cutting Top Piles 77-96 7 25-Aug-23 01-Sep-23 20-Jul-23 100% 0%
Construction Installing Pile Plug & Pouring RC Of Piles 97-116 3 08-Sep-23 11-Sep-23 30-Jul-23 0% 0%
Construction Installing Pile Plug & Pouring RC Of Piles 77-96 2 01-Sep-23 03-Sep-23 22-Jul-23 100% 0%
Construction Install Jetty Precast Pile Cap 3-4 6 09-Sep-23 15-Sep-23 03-Aug-23 0% 0%
Construction Install Jetty Precast Pile Cap 1-2 6 03-Sep-23 09-Sep-23 28-Jul-23 67% 0%
Construction Pouring RC In Jetty Precast Pile Cap 3-4 3 15-Sep-23 18-Sep-23 06-Aug-23 0% 0%

D O C U M E N T CODECODE : RE VI SIO N COD E: 00 PAGE 7 OF 15


2. Project Contracts Management
2.1 Progress S-Curve by Manhours

2.2 Progress S-Curve by BOQ Items

D O C U M E N T CODECODE : R EVI SIO N C ODE: 00 PAG E 8 OF 15


1.1 Manpower Histogram

4.4 Equipment Histogram

D O C U M E N T CODECODE : R EVI SIO N C ODE: 00 PAG E 9 OF 15


1.2 Project Schedule
The project schedule will be attached along with the .xer file.

2. Progress Photos

Fabrication and Casting for pre-cast slab

D O C U M E N T CODECODE : R EVI SIO N C ODE: 00 PAG E 10 OF 15


D O C U M E N T CODECODE : R EVI SIO N C ODE: 00 PAG E 11 OF 15
D O C U M E N T CODECODE : R EVI SIO N C ODE: 00 PAG E 12 OF 15
D O C U M E N T CODECODE : R EVI SIO N C ODE: 00 PAG E 13 OF 15
D O C U M E N T CODECODE : R EVI SIO N C ODE: 00 PAG E 14 OF 15
D O C U M E N T CODECODE : R EVI SIO N C ODE: 00 PAG E 15 OF 15