Professional Documents
Culture Documents
Capital Budgeting
Capital Budgeting
Budgeting
What is Capital Budgeting?
• The process of planning and evaluating
expenditures on assets whose cash flows are
expected to extend beyond one year
– Analysis of potential additions to fixed assets
– Long-term decisions which involve large
expenditures
– Analysis of replacement of existing equipment
or processes
– Very important to firm’s future
Generating Ideas for Capital Projects
0 1 2 3
Project L
CFt -100 10 60 80
0 1 2 3
Project S
CFt -100 70 50 20
Calculating Regular payback
0 1 2 2.4 3
Project L
CFt -100 10 60 100 80
Cumulative -100 -90 -30 0 50
PaybackL == 2 + 30 / 80 = 2.375 years
0 1 1.6 2 3
Project S
CFt -100 70 100 50 20
Cumulative -100 -30 0 20 40
.
0 10% 1 2 2.7 3
CFt -100 10 60 80
PV of CFt -100 9.09 49.59 60.11
Cumulative -100 -90.91 -41.32 18.79
0 1 2 3
Project S
CFt -100 70 50 20
.
0 10% 1 1.88 2 3
CFt -100 70 50 20
PV of CFt -100 63.64 41.32 15.03
Cumulative -100 -36.36 4.96 19.09
0 1 2 3
Project S
CFt -100 70 50 20
NPV = 0
100 10 /(1 IRR) 60 /(1 IRR) 80 /(1 IRR)
2 3
33
Trial and Error Method: IRR
34
Trial and Error Method: IRR
50.00
40.00
30.00
NPV
20.00
10.00
-
0% 5% 10% 15% 18% 19% 25%
(10.00)
37
Linear Interpolation Method: IRR
Where:
L = Lower discount rate
H = Higher discount rate
NL = NPV at lower discount rate
NH= NPV at higher discount rate
38
Linear Interpolation Method: IRR
= 18.13%
39
Linear Interpolation Method: IRR
0 1 2 3
Project S
CFt -100 70 50 20
Project S: IRR
If we try a rate of 10% our NPV is P19.99
NPV 70 /(1.1) 50 /(1.1) 2 20 /(1.1) 3 100 P19.99
We can try a number of rates and then have a table
as shown below.
41
Linear Interpolation Method: IRR
Project S: IRR
0.71
IRR 0.23 x(0.24 0.23)
0.71 (0.54)
IRR 0.2356
= 23.56%
42
IRR Acceptance Criteria
• If IRR > Weighted Average Cost of Capital (WACC),
the project’s rate of return is greater than its costs.
There is some return left over to boost
stockholders’ returns.
• If IRR > k, accept project & If IRR < k, reject project.
• IRRL = 18.13% and IRRS=23.56%
• If projects are independent, accept both projects,
as both IRR > k = 10%.
• If projects are mutually exclusive, accept S, because
IRRs > IRRL.
43
NPV Profiles
• Project NPVs at various different costs of capital.
k NPVL NPVS
0% $50 $40
5% 33 29
10% 19 20
15% 7 12
20% (4) 5
44
Drawing NPV profiles
NPV 60
($)
50 .
40 .
. Crossover Point = 8.7%
30 .
20 . IRRL = 18.1%
10 .. S IRRS = 23.6%
L . .
0 . Discount Rate (%)
5 10 15 20 23.6
-10
45
Comparing the NPV and IRR methods
47
Reinvestment rate assumptions
48
Since managers prefer the IRR to the NPV
method, is there a better IRR measure?
• Yes, MIRR is the discount rate that causes the
PV of a project’s terminal value (TV) to equal
the PV of costs. TV is found by compounding
inflows at Weighted Average Cost of Capital
(WACC) i.e. sum of FV of inflows.
• MIRR assumes cash flows are reinvested at the
WACC.
49
Calculating MIRR
TV inflows
• PV cash outflows
= (1 + MIRR)n
• TV inflows =
t n
COFt
• PV outflows =
t 0 (1 k )
t
50
Calculating MIRR
0 10% 1 2 3
51
Why use MIRR versus IRR?
52
Find Project P’s NPV and IRR.
0 1 2
k = 10%
IRR2 = 400%
450
0 k
100 400
IRR1 = 25%
-800
54
Why are there multiple IRRs?
55
When to use the MIRR instead of the IRR?
Accept Project P?
56
EXERCISE
58
EXERCISE
• Year Profit
• 1 P6 000
• 2 P18 000
• 3 P100 000
• 4 P66 000
• 5 P112 000
Additional information
The company has a cut-off payback period policy of 4
years on all its new capital investment projects.
59
EXERCISE
Required
i. Compute the annual cash flows for the new
machine.
ii. Calculate the regular payback period and
advise management whether or not the
project is acceptable
iii. Calculate the Net Present Value (NPV) of the
project. Should management accept the
project based on the NPV calculations?
60
EXERCISE
• The Costa Rican Coffee Company is evaluating the within-
plant distribution system for its new roasting, grinding,
and packing plant.
• The two alternatives are (1) a conveyor system with a
high initial cost but low annual operating costs and (2)
several forklift trucks, which cost less but have
considerably higher operating costs.
• The decision to construct the plant has already been
made, and the choice here will have no effect on the
overall revenues of the project. The cost of capital for the
plant is 8 percent, and the projects’ expected net costs
are listed below: 61
EXERCISE