ANGGARAN BIAYA PEMBORAN PT.TRIAS JAYA MANDIRI KEC.

BATU AMPAR
KAB.TANAH LAUT PROP. KALIMANTAN SELATAN

unit Qtt/days Tot/Qtt Biaya /unit/meter Total


A SURVEY DAN MARKING TITIK BOR
1 geologist 1 4 4 500,000 2,000,000
2 helper 2 4 8 125,000 1,000,000
3 Konsumsi 9 4 36 25,000 900,000
sub total 3,900,000

B DRILLING ( Tipe mesin power Rig. Total kedalaman 400 M)


1 Open Hole 400 130,000 52,000,000
2 Coring 100 200,000 20,000,000
3 Mobilisasi/Demobilisasi unit bor 1 7,000,000 7,000,000
4 Well Site Geologist 1 20 20 400,000 8,000,000
5 Konsumsi geologis dan wellsite geologist 1 20 20 60,000 1,200,000
6 Perlengkapan 1 1 1 2,500,000 2,500,000
7 Laporan Drilling Log 1 1 1 4,500,000 4,500,000
sub total 95,200,000
GRAND TOTAL 99,100,000