BATU AMPAR KAB.TANAH LAUT PROP. KALIMANTAN SELATAN
unit Qtt/days Tot/Qtt Biaya /unit/meter Total
A SURVEY DAN MARKING TITIK BOR 1 geologist 1 4 4 500,000 2,000,000 2 helper 2 4 8 125,000 1,000,000 3 Konsumsi 9 4 36 25,000 900,000 sub total 3,900,000
B DRILLING ( Tipe mesin power Rig. Total kedalaman 400 M)
1 Open Hole 400 130,000 52,000,000 2 Coring 100 200,000 20,000,000 3 Mobilisasi/Demobilisasi unit bor 1 7,000,000 7,000,000 4 Well Site Geologist 1 20 20 400,000 8,000,000 5 Konsumsi geologis dan wellsite geologist 1 20 20 60,000 1,200,000 6 Perlengkapan 1 1 1 2,500,000 2,500,000 7 Laporan Drilling Log 1 1 1 4,500,000 4,500,000 sub total 95,200,000 GRAND TOTAL 99,100,000