Doc. No.

: : 0-WD800-CZ250-00003
PULAU INDAH COMBINED CYCLE POWER PLANT
Rev. No.: Rev. 0
FIELD INSPECTION AND TEST PLAN Rev. Date: 9-Nov-21
FOR SURVEY WORKS (ON-SHORE AND OFFSHORE) Page: 2 / 17

REVISION HISTORY
REV. DESCRIPTIONS AND/OR REVISED SHEETS REFERENCE REV. DATE
A First Issue 6 Oct. 2021
Revised as per Owner’s comments
0 9 Nov. 2021
(DRS-WD800-CZ250-00003-A)
Doc. No.: : 0-WD800-CZ250-00003
PULAU INDAH COMBINED CYCLE POWER PLANT
Rev. No.: Rev. 0
FIELD INSPECTION AND TEST PLAN Rev. Date: 9-Nov-21
FOR SURVEY WORKS (ON-SHORE AND OFFSHORE) Page: 3 / 17

TABLE OF CONTENTS
1. INTRODUCTION 4 page

2. PURPOSE 4 page

3. DEFINITIONS/ABBREVIATIONS 4 page

4. REFERENCE STANDARDS & CODES 5 page

5. REFERENCE DOCUMENTS 5 page

6. INSPECTION MODES 5 page

7. INSPECTION AND TEST PLAN 6 page

8. ATTACHMENTS
Attachment 1: Field Inspection and Test Plan 12 page
Attachment 2: Survey Field Sheet Record 13 page
Attachment 3: Level Survey Field Sheet Record 15 page
Attachment 4: Field Inspection Notification ( FIN ) 16 page
Attachment 5: Survey Field Sheet Register Logs 17 page
Doc. No.: : 0-WD800-CZ250-00003
PULAU INDAH COMBINED CYCLE POWER PLANT
Rev. No.: Rev. 0
FIELD INSPECTION AND TEST PLAN Rev. Date: 9-Nov-21
FOR SURVEY WORKS (ON-SHORE AND OFFSHORE) Page: 4 / 17

1. INTRODUCTION

Pulau Indah 1200MW Combined Cycle Power Plant (CCPP) Project is a project developed by Pulau Indah Power Plant
Sdn. Bhd. and located in Pulau Indah, Klang Selangor. It is gas fired with 1200MW electrical supply capacity which is
enough to supply 500,000 households in the Klang Valley, Malaysia.

2. PURPOSE
This document is established to provide a standard guideline of Contractor/Owner’s involvement on inspection of related
site activities and testing in order to ensure compliance against design and project specification requirement for good
quality of finished products and acceptance by Owner

3. DEFINITIONS/ABBREVIATIONS

MPI CCPP PROJECT : Pulau Indah Combined Cycle Power Plant Project
OWNER : Pulau Indah Power Plant Sdn. Bhd.
OWNER’S ENGINEER (OE) : Jacobs Engineering Malaysia Sdn. Bhd.
The OWNER and OWNER’S ENGINEER personnel working as an
OWNER’S TEAM (OT) :
integrated team in delivery of the project
CONTRACTOR : PEC Powercon Sdn. Bhd.
Minconsult Sdn. Bhd.An Engineering Consultancy Practise (ECP)
Company which Professional Engineer with Practising Certificate
CONTRACTOR'S CONSULTANT : (PEPC) is working for or attach to. PEPC is appointed to perform roles
and responsibilities as Submitting Person (SP) to Authorities under
BEM’s Regulations
PEPC SITE TEAM :
Site quality supervision team assigned by PEPC to carry out inspection
to ensure works constructed as per design, quality plan & specification.

PEPC REVIEWER : Reviewer for Method Statement on behalf of Contractor's Consultant

CONTRACTOR'S GEO-CONSULTANT : Fugro Malaysia Land Sdn. Bhd.


SUBCONTRACTOR : Contractors appointed by EPC to conduct the construction work

The area within the boundary of Pulau Indah Combined Cycle Power
SITE :
Plant Project
Jabatan Ukur dan Pemetaan Malaysia
JUPEM : (Department of Survey and Mapping Malaysia) is the nation’s survey,
mapping services and geospatial data management.
Tentera Laut DiRaja Malaysia (The Royal Malaysian Navy) is the naval
RMN : arm of the Malaysian Armed Forces.who oversees the ship navigations,
sea activities and etc.
TBM : Temporary Benchmark
MS : Method Statements
FIN : Field Inspection Notice
LNTP : Limited Notice to Proceed
Doc. No.: : 0-WD800-CZ250-00003
PULAU INDAH COMBINED CYCLE POWER PLANT
Rev. No.: Rev. 0
FIELD INSPECTION AND TEST PLAN Rev. Date: 9-Nov-21
FOR SURVEY WORKS (ON-SHORE AND OFFSHORE) Page: 5 / 17

4. REFERENCE CODES AND STANDARDS

1) BS5964-1: 1990 : Building Setting Out and Measurement Part 1


2) BS 5964-2: 1996 : Building Setting Out and Measurement Part 2

5. REFERENCE DOCUMENTS

1) 0-WD010-MZ711-00001 : Project Quality Plan


2) 0-WD010-MZ711-00005 : Calibration & Control of Measuring and Testing Equipment
3) 0-WD010-MZ711-00007 : Field Inspection and Test Procedure
4) 0-WD800-CC290-00005 : Method Statement for Survey Works
5) IFC Drawings : Latest
6) JUPEM 18/7/2.148 (86) : Standard-Guidelines-For-Underground Mapping
7) JUPEM 18/7/2.148 Jld. 3 (17) : Standard Guidelines for Malaysian RTK GPS
Network (MyRTKnet)

Notes: Contractor is to refer to the latest IFC revision of the relevant documents/drawings
during execution of works

6. INSPECTION MODES

The method of inspection and test shall be classified by following terms;

H: Hold point, inspection notification is required. During hold point inspection, the witness will be performed.
Subcontractor / Contractor shall not proceed with the work until presence of the inspector or written consent of
Owner’s inspector.

` W: Inspection activities performed by Subcontractor / Contractor and witnessed by Owner’s inspector. Inspection
notification is required. If the Owner’s inspector is not present, Subcontractor / Contractor may perform the
inspection/tests as scheduled unless otherwise requested
SW : Witness, but spot check basis, Inspection notification is required. Initial operation will be witnessed and
subsequent operation will be witnessed at discretion of the Owner’s inspector considering the results of previous
inspection unless otherwise sampling percentage is specified.
M : Monitoring, Contractor / Owner’s Inspector will have all the right to enter fabrication areas of Subcontractor at his
convenient time for the monitoring of Fabrication / Erection activities. Subcontractor is responsible for supporting
his expectations.
R : Review of inspection records and/or specified document.

A : Approval (for Document)


Doc. No.: : 0-WD800-CZ250-00003
PULAU INDAH COMBINED CYCLE POWER PLANT
Rev. No.: Rev. 0
FIELD INSPECTION AND TEST PLAN Rev. Date: 9-Nov-21
FOR SURVEY WORKS (ON-SHORE AND OFFSHORE) Page: 6 / 17

7. INSPECTION AND TEST PLAN


- Field Inspection and Test Plan shall be referred to Attachment 1.0 Field Inspection and Test Plan

8. ATTACHMENTS
Attachment 1. Field Inspection and Test Plan (FITP) for Survey Works (Onshore and Offshore)
Attachment 2. Survey Field Sheet
Attachment 3. Level Survey Field Sheet
Attachment 4. Field Inspection Notification (FIN)
Attachment 5: Survey Field Sheet Register Logs (For Information )
ATTACHMENT 1.0: FIELD INSPECTION AND TEST REPORT
Doc. No.: : 0-WD800-CZ250-00003
PULAU INDAH COMBINED CYCLE POWER PLANT Rev. No.: Rev. 0
FIELD INSPECTION AND TEST PLAN Rev. Date: 9-Nov-21
FOR SURVEY WORKS (ON-SHORE AND OFFSHORE) Page: 7 / 17

Stage/ Inspection Mode


Acceptance Record/
No. Description Ref. Doc. No. Type of Frequency Remarks
Criteria Evidence Contract Con- Owner
Inspection & Test Sub-Con
or sultant Team

1 Pre-construction Survey

IFC Drawings Prior to start survey Each revision/ As per Project Transmittal
/Specification, PQP, HSE works/Visual submission Specification/ PQP/ (Approval
Procedure, MFS, BS EN IFC Drawings/ HSE Status)
12699:2015 Procedure
Submission of Method
1.1 H H H R&A
Statement

0-WD010-MZ711- Prior to Once or when Calibrated and within


00005_Rev.0_ Calibration mobilization/ Visual change of the calibration M&TE
& Control of Measuring instrument certificate period Calibration
Instrument Mobilization and Testing Equipment, Record
(Submission of Survey Equipment Calibration (MTCR)
1.2 H R&A R R
Instruments Calibration Certificates
Certificates)

Plot Plan, Benchmark LNTP Stage/Visual, Once/or as - Drawings has to be Endorsed


Details from JUPEM, Measurment deemed endorsed by Licensed Drawing by
JUPEM 18/7/2.148 (86) - required by Surveyor Licensed
Malaysian RTK GPS Contractor to Surveyor
Selection of JUPEM's Network, improve
1.3 JUPEM 18/7/2.148 Jld. 3 survey control H R R R
Benchmark
(17) - Technical Guide to
the Coordinates Reference
System

H: Hold, R: Review Spec./Record, W: Witness


SW: Spot Witness, M: Monitoring, A: Approval
Doc. No.: : 0-WD800-CZ250-00003
PULAU INDAH COMBINED CYCLE POWER PLANT Rev. No.: Rev. 0
Rev. Date: 9-Nov-21
0
Page: 8 / 17

Stage/ Inspection Mode


Acceptance Record/
No. Description Ref. Doc. No. Type of Frequency Remarks
Criteria Evidence Contract Con- Owner
Inspection & Test Sub-Con
or sultant Team
Benchmark Details from LNTP Stage/Visual, Once - Drawings has to be Endorsed
JUPEM, Measurment endorsed by Licensed Drawing by
JUPEM 18/7/2.148 (86) - Surveyor Licensed
Malaysian RTK GPS Surveyor
Network
1.4 Boundary Survey JUPEM 18/7/2.148 Jld. 3 H H R R
(17) - Technical Guide to
the Coordinates Reference
System

Plot Plan, Benchmark LNTP Stage/Visual, Once/or as - Drawings has to be Endorsed


Details from JUPEM, Measurment deemed endorsed by Licensed Drawing by
JUPEM 18/7/2.148 (86) - required by Surveyor Licensed
Malaysian RTK GPS Contractor to Surveyor
Establishment and Checking Network, improve
1.5 JUPEM 18/7/2.148 Jld. 3 survey control H H R R
of Project Site TBM
(17) - Technical Guide to
the Coordinates Reference
System

Benchmark Details from LNTP Stage/Visual, Once - Drawings has to be Endorsed


JUPEM, Measurment endorsed by Licensed Drawing by
JUPEM 18/7/2.148 (86) - Surveyor Licensed
Malaysian RTK GPS Surveyor
Network
1.6 Topography (OGL) Survey JUPEM 18/7/2.148 Jld. 3 H H R R
(17) - Technical Guide to
the Coordinates Reference
System

H: Hold, R: Review Spec./Record, W: Witness


SW: Spot Witness, M: Monitoring, A: Approval
Doc. No.: : 0-WD800-CZ250-00003
PULAU INDAH COMBINED CYCLE POWER PLANT Rev. No.: Rev. 0
FIELD INSPECTION AND TEST PLAN Rev. Date: 9-Nov-21
FOR SURVEY WORKS (ON-SHORE AND OFFSHORE) Page: 9 / 17
Stage/ Inspection Mode
Acceptance Record/
No. Description Ref. Doc. No. Type of Frequency Con- Con- Owner Remarks
Criteria Evidence Sub-Con
Inspection & Test tractor sultant Team
Benchmark Details from LNTP Stage/Visual, Once - Drawings has to be Endorsed
RMN, Measurment endorsed by Licensed Drawing by
JUPEM 18/7/2.148 (86) - Surveyor Licensed
Malaysian RTK GPS Surveyor
1.7 Bathymetry Survey Network H H R R
JUPEM 18/7/2.148 Jld. 3
( 17 ) - Technical Guide to
the Coordinates Reference
System

Standard Guidelines for LNTP Stage/Visual, Once - Drawings has to be Underground


Underground Utility Measurment endorsed by Licensed Utilities
Mapping by JUPEM Surveyor Mapping - by
JUPEM 18/7/2.148 Jld. 3 Contractor's
Underground ( 17 ) - Technical Guide to Licensed
1.8 H H R R
Service/Utilities Mapping the Coordinates Reference Surveyor
System (Endorsed) or
by Asset
Owner

H: Hold, R: Review Spec./Record, W: Witness


SW: Spot Witness, M: Monitoring, A: Approval
Doc. No.: : 0-WD800-CZ250-00003
PULAU INDAH COMBINED CYCLE POWER PLANT Rev. No.: Rev. 0
FIELD INSPECTION AND TEST PLAN Rev. Date: 9-Nov-21
FOR SURVEY WORKS (ON-SHORE AND OFFSHORE) Page: 10 / 17
Stage/ Inspection Mode
Acceptance Record/
No. Description Ref. Doc. No. Type of Frequency Con- Con- Owner Remarks
Criteria Evidence Sub-Con
Inspection & Test tractor sultant Team

2 During Construction

MS For Survey Works, Prior to start setting A) Every Mis-closure within Survey Field
Licensed Surveyor's BM out of Control Points minimum accuracy Sheet
Survey Drawing, setting location/visual, need to check requirement as per
Site Control Points out plan for critical measurement everytime specified in Method
Establishment and Routine dimension of each facility prior to use
sue. Statement for Survey
2.1 H H & W SW & R R
Checking Against TBM Works (Onshore and
Offshore).
Survey equipment with
valid calibration
certificates
MS For Survey Works, Prior to start setting Once in 3 Mis-closure within Survey Field
Licensed Surveyor's BM out of months/or minimum accuracy Sheet
Survey Drawing, setting location/visual, when requirement as per
out plan for critical measurement observed specified in Method
Site TBM Routine Checking dimension of each facility disturbance Statement for Survey
2.2 H H & W SW & R R
Against BM Works (Onshore and
Offshore).
Survey equipment with
valid calibration
MS For Survey Works, During start of Every pile, certificates
- As per design Survey Field
Related MS work/visual, Every corner coordinate in IFC Sheet
IFC Drawings measurement of structures, Drawings.
or centerlines - Tolerance to be
Setting out and positining by whichever specified in related MS
marking/pegging of lines and deemed -Survey equipment with
2.3 elevations of related required, valid calibration H W SW R
structures, equipment, and every anchor certificates
etc.(Onshore and Offshore) bolts - Survey Field Sheet to
be reviewed/approved
by Consultant

H: Hold, R: Review Spec./Record, W: Witness


SW: Spot Witness, M: Monitoring, A: Approval
Doc. No.: : 0-WD800-CZ250-00003
PULAU INDAH COMBINED CYCLE POWER PLANT Rev. No.: Rev. 0
FIELD INSPECTION AND TEST PLAN Rev. Date: 9-Nov-21
FOR SURVEY WORKS (ON-SHORE AND OFFSHORE) Page: 11 / 17
Stage/
Acceptance Record/
No. Description Ref. Doc. No. Type of Frequency Contract Con- Owner Remarks
Criteria Evidence Sub-Con
Inspection & Test or sultant Team
Related MS, IFC Prior to concrete Every vertical - As per design coordinate Survey Field
Drawings pouring, bolt elements in IFC Drawings Sheet
Vertical Element (Pile,
tightening/ - Tolerance to be specified
Columns, Wall, Anchor Bolts,
Measurement in related MS
Embedments, Steel Structures,
2.4 - Survey equipment with H H W SW
Equipments and etc.)
valid calibration
- Verticality check
certificates
- Position check

H: Hold, R: Review Spec./Record, W: Witness


SW: Spot Witness, M: Monitoring, A: Approval
Doc. No.: : 0-WD800-CZ250-00003
PULAU INDAH COMBINED CYCLE POWER PLANT Rev. No.: Rev. 0
FIELD INSPECTION AND TEST PLAN Rev. Date: 9-Nov-21
FOR SURVEY WORKS (ON-SHORE AND OFFSHORE) Page: 12 / 17
Stage/
Acceptance Record/
No. Description Ref. Doc. No. Type of Frequency Contract Con- Owner Remarks
Criteria Evidence Sub-Con
Inspection & Test or sultant Team

3 Post-construction Survey

- IFC Drawings After completed Every stage of Comply to tolerance as Survey Field
- MS For Survey Works and structure installation of element specified as per related Sheet
other related MS or construction each construction, Project Specification (if
- Project Specification (if of element elevation,/ e.g: top of soil, any), International
As-built Survey prior to related) Visual, Measurement top of leanco, Standards, Vendor
Handover of Completed Scope - related Codes and top of Specification, as specified
of Works to Other Trade Standards foundation, top in related MS (if any), and
3.1 H H&R R A
Subcontractor - MFS (B0.1-B14) of pedestal, etc.
-Measure position and elevation embedment Valid survey instruments
-- Measure verticality exposed surface, calibration certificates
and etc.

- IFC Drawings Completion of the - Once, when All related documents has Survey Field
- MS For Survey Works and overall works of the the structure is been verified and Sheet, As-built
other related MS structure/equipment/ completed. endorsed by relevant Drawings
- Project Specification (if instrument/ cables/ - All Structures parties including licensed (Buildings and
related) pipes surveyor as per Structures As-
- Project final project/regulation built shall be
As-built Survey for As-built documentation/handover requirement endorsed by
3.2 Drawings Preparation procedure Licensed H H&R R A
(Completion of Works) - related Codes and Surveyor -
Standards whichever
- MFS (B0.1-B14) deemed
necessary by
local regulations)

H: Hold, R: Review Spec./Record, W: Witness


SW: Spot Witness, M: Monitoring, A: Approval
ATTACHMENT 2
PULAU INDAH CCPP
Survey Field Sheet Record

Report No. Date

Ref. Drawing FIN No.

Structure/Location Page No. /

Description of Survey
▶ Datum
Bearing Horizontal Coordinates
Station To Remarks
Degree Minutes Seconds Distance N E

▶ Survey Record
Design Actual Deviation
No. Items Coordinate Level Coordinate Level Horizontal (mm) Vertical (mm) Remark
N E Z N E Z N E Z

REMARKS:

PREPARED BY CHECKED BY WITNESSED BY ACKNOWLEDGED BY


(Sub-Contractor) (Contractor: QAQC/Surveyor) (Contractor's Consultant) (Owner's Team)

Name : Name : Name : Name :

Signature : Signature : Signature : Signature :

Date: Date: Date: Date:

NOTES: Survey record shall be attached with relevant latest IFC Drawings Form No. : PI-PEC-FORM-001 / Rev. A / date : 06.Oct.2021
Attachment 2
PULAU INDAH CCPP
Survey Report - ref. DWGs

Form No. C-SI-002


ATTACHMENT 3
PULAU INDAH CCPP
Level Survey Field Sheet Record

Report No. Date

Ref. Drawing FIN No.

Structure/Location Page No. /

Description of Survey
▶ Survey Record

No. Items BS IS FS RL DESIGN RL Remark

REMARKS:

PREPARED BY CHECKED BY WITNESSED BY ACKNOWLEDGED BY


(Sub-Contractor) (Contractor: QAQC/Surveyor) (Contractor's Consultant) (Owner's Team)

Name : Name : Name : Name :

Signature : Signature : Signature : Signature :

Date: Date: Date: Date:

NOTES: Survey record shall be attached with relevant latest IFC Drawings Form No. : PI-PEC-FORM-002 / Rev. A / date : 31.Oct.2021
Attachment 4

PULAU INDAH CCPP


Field Inspection Notification ( FIN )

Activity Sub-Contractor

FIN No. Issued Date

Rev. No. Discipline

Please be invited to attend the following inspection according to the following schedules:

Inspection Details

No. Inspection / Testing Description Location Date / Time

Reference Documents

FITP No. Drawing No.

Spec. No. Others

Contractor/QAQC Hold Point Witness Spot Witness


Inspection
Contractor's Consultant Hold Point Witness Spot Witness
Mode
Owner's Team Hold Point Witness Spot Witness

Contractor's QAQC Owner's Team

Name : Name :
ACKNOWLEDGEMENT OF RECEIVED
Signature : Signature :

Date : Date :

INSPECTION STATUS (To be completed after the inspection)

Inspection Item

□ Inspection Passed. The Testing / Inspection is satisfactory and works may proceed to the next stage
□ Remedial works listed below to be completed and inspection is required after remedial works
□ Remedial works listed below to be completed but no further inspection required
□ Rejected
※ New FIN raised? ☐Yes ☐ No New FIN No.:
REMARKS:

ACKNOWLEDGEMENT OF INSPECTION
PREPARED BY CHECKED BY WITNESSED BY ACKNOWLEDGED BY
(Sub-Contractor) (Contractor/QAQC) (Contractor's Consultant) (Owner's Team)

Name : Name : Name : Name :

Signature : Signature : Signature : Signature :

Date : Date : Date : Date :

Form No. : 5PG-0701-012-F1 / Rev.0 / Date : 04.Oct.2021


ATTACHMENT 5
PULAU INDAH CCPP
Survey Field Sheets Register Logs

No. Date Discipline Subcontractor Structure Type of Survey Report No. Remark

REMARKS:

NOTES: No. System Sample: PI-SR-D-SUB-YY-XXXX ; D = Disciplines (A: Architecture C: Civil M: Mechanical P:Piping E:Electrical I: Instrument) SUB = Subcontractors (3 Letters Shortform) YY = Year XXXX = No. Sequence