TATA CONSULTING ENGINEERS LIMITED SECTION:

TCE.M7-ME-ER-F-096 FORMAT
FINAL ACCEPTANCE OF PUMPS / SHEET 1 OF 1
COMPRESSORS
Project System / Plant
Client / Job No. Reference No.
Contractor Reference Document No.
Size & Weight Equipment No.

The Contractor hereby declares that the Pump / Compressor Unit as described below
is completed in accordance with the latest revision of Approved for Construction
drawings and Project Specifications. The acceptance report does not relieve the
Contractor of his obligations as laid down in the contractual conditions. All
documents to support this statement are completed, approved & form part of this
acceptance certificate as applicable.

Sr. Description QCR Document No.


Remarks
No.
01 Location of Pumps / compressors as per
drawing
02 Pump / compressor Unit Alignment TCE.M7-ME-ER-F-030/031
03 Grouting Release / Acceptance for Equipment TCE.M7-ME-ER-F-082
and Main Structures
04 Pump / compressor Unit Alignment (with gear) TCE.M7-ME-ER-F-030
05 Pump / compressor Unit Alignment (without TCE.M7-ME-ER-F-031
gear)
06 Pump / compressor Unit Alignment with out TCE.M7-ME-ER-F-030/031
piping
07 Pump / compressor Unit Alignment with Piping TCE.M7-ME-ER-F-030/031
08 Installation of sealing system for pumps
09 Check list for rotating equipment TCE.M7-ME-ER-F-067
10 Punch list TCE.M7-ME-ER-F-057
11 Punch list TCE-M7-FO-EL-01-14
12 Punch list TCE-M7-FO-I&C-01-20
13 Trial run report (commissioning)
14 Vibration report (commissioning)

Final remarks for entire system:

-----------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------- ISSUE
----------------------------------------------------------------------------------------------------------------- R-5
-----------------------------------------------------------------------------------------------------------------
Contactor TCE Client
Name
designation
Signature & Date
FILE NAME: M7-ME-096.R5.doc. TCE FORM NO. 120 R3