Professional Documents
Culture Documents
Inst 343 Cap DS Ele 002 R3
Inst 343 Cap DS Ele 002 R3
Contract: C-343-CAP-DS
Document Ref JMH: INST-343-CAP-DS-ELE-002
Version: English
Revision: 3
Date: February 2023
Author: Steven Lee
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
Contents
2. Introduction ................................................................................................................................. 8
6. Safety ......................................................................................................................................... 35
2
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
7.2. Disassembly..................................................................................................................................................... 36
8. Scope of Work & Supply (Installation) ......................................................................................... 37
3
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
4
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
5
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
6
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
1. Revision History
Created Approved
Revision Description By Created Date Approved Date
First Issue –
0 For Client Information to support S.L. 27.02.2023 A.D. 06.04.2023
installation works
Second Issue –
Sections 2.1.2., 2.1.4. updated.
1 Section 8.2.3.5.109 added. S.L. 16.05.2023 A.D. 16.05.2023
Notes added to sections under
sub-section 8.2.3.1 regarding JB
assembly
Third Issue –
2 Additional table added to section S.L. 17.05.2023 A.D. 17.05.2023
2.1.4. following customer request
for additional information
Fourth Issue –
Section 2.1.2 updated to
reference cable TX01.
Additional drawing (343-ELE-
A613-S1) added to section 2.1.3.
Additional installation note for
JB30 added to section 8.1.3.1.
3
Section 8.2.1 updated to S.L. 25.05.2023 A.D. 30.05.2023
reference cable TX01.
Section 8.2.3.5.97 updated to
reference cable F29 not F20.
Additional section added to
section 8.2.3.5 (8.2.3.5.110)
Additional installation notes for
PE40 to PE49 were added to
section 8.2.3.6.
7
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
2. Introduction
This specification covers the installation, testing and commissioning of the Electrical equipment in the following
areas at CAP Acero/Talcahuano Works, Chile.
The Mechanical, Hydraulic and Water installation work is identified in separate documents.
The Electrical work shall be coordinated with the Mechanical, Hydraulic and Water work to provide a complete
and operational system.
Wherever conflict exists between manufacturer’s instructions/drawings, this specification, other specification, or
codes, the JMHM Site Supervisor shall be notified and shall provide a final resolution.
John M Henderson Machines were awarded a contract by CAP Acero/Huachipato, Talcahuano Works to provide a
new emission system that incorporated a new Coke Guide Cage and replace with new the existing control system
on the Door Machines using the Best Available Technology (BAT).
The project will develop a new Coke Guide Cage c/w Hood System using BAT and a new 3rd rail structure to support
the new Hood System.
The Control System equipment will be manufactured by sub-contractors, which has been selected by JMHM. These
items will be delivered to CAP Acero/Huachipato, Talcahuano Works, where it will then be installed by a CAP
Acero/Huachipato selected sub-contractor.
8
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
2.1.1. Abbreviations
The following is presented to help understand the information presented within this document.
Abbreviation Definition
A Ampere
AC Alternating Current
BAT Best Available Technology
BS British Standard
CE Conformité Européene
CPU Central Processing Unit
CSS Control Systems Services
DC Direct Current
DM Door Machine
EC European Community
EN Euronorm
E-Stop Emergency Stop
GA General Arrangement Drawings
HMI Human Machine Interface
HS Hood System
Hz Hertz
I/O Input / Output
IEC International Electrotechnical Commission
ISO International Standards Organization
JMHM John M Henderson Machines
kW Kilo Watt
LT Long Travel
LAN Local Area Network
PLC Programmable Logic Controller
PSU Power Supply Unit
RA Risk Assessment
SCADA Supervisory Control and Data Acquisition
TBT Toolbox Talk
Vac Voltage Alternating Current
Vdc Voltage Direct Current
VSD Variable Speed Drive
W Watt
°C Degrees Celsius
°F Degrees Fahrenheit
Ω Ohms
9
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
NOTE – Please ensure that the latest revision of drawings are used at all times.
10
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
NOTE – Please ensure that the latest revision of drawings are used at all times.
12
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
14
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
NOTE – Please ensure that the latest revision of drawings are used at all times.
The control system will have been configured/assembled in accordance with the following CSS drawings:
The following table is to provide a cross-reference between the JMH drawing numbers noted in the table
above and the CSS drawing numbers.
15
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
16
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
17
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
18
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
19
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
20
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
21
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
NOTE – The following drawings relate to the existing installation configuration and in a number of instances
have been superseded by the drawings (referred to in Section 2.1.3 and 2.1.4 above) as part of scope of work
in this project.
2.1.5.1. General
22
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
23
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
24
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
25
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
26
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
27
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
28
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
29
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
3. Standards
The design and supply of all equipment within this Agreement shall be compliant with CAP Acero Standards,
British, European and ISO Engineering Standards as listed. JMHM design Coke Oven Machines based on
considerable experience. The system and associated equipment will be compliant to the following standards.
Standard Description
NO-90-019_13222-1-Anexo 7.1 ESP 1-5, Index Index
NO-90-019_13222-2-Anexo 7.2 ESP 1-5
General Electrical Specification
Resumen
NO-90-019_13222-3-Anexo 7.3 ESP 1-5
General Electrical Specification
Summary
NO-90-019_13222-4-Anexo 7.4 ESP 1-5-A General Electrical Specification
NO-90-019_13222-5-Anexo 7.5 ESP 1-5-B Equipment and Installation
NO-90-019_13222-6-Anexo 7.6 ESP 1-5-C Tests and Checks
NO-90-019_13222-7-Anexo 7.7 ESP 1-5-D Automation and Process Control
NO-90-019_13222-8-Anexo 7.8 ESP 1-5-E Electrical Construction Engineering I Design Guidelines
NO-90-019_13222-9-Anexo 7.9 ESP 1-5-F Electrical Construction Engineering II Specific Requirements
NO-90-019_N1@13222 Especificaciones
Electrical Technical Specifications
Tecnicas Electricas
NO-90-019_N1@13222 Electrical Technical Specifications
30
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
All equipment designed, manufactured, tested, installed, and commissioned shall comply with UK
Legislation and shall be in accordance with all relevant British, European and International Standards that
are applicable and including those that are specifically listed below. The standards shall be the latest issue,
including all parts, revisions, and addenda current at the date of contract.
Standard Description
Directive 2006/42/EC Machinery Directive
Directive 2014/30/EU EMC Directive
Directive 2014/35/EU Low Voltage Directive (LVD)
EN 614 Safety of machinery - Ergonomic design principles - Part 1: Terminology and general principles
Mechanical vibration and shock. Vibration isolation of Machines. Information for the
EN 1299
application of source isolation
Hydraulic fluid power — General rules and safety requirements for systems and their
ISO 4413
components
Pneumatic fluid power — General rules and safety requirements for systems and their
ISO 4414
components
BS 5424-3 Specification for Control Gear – contactors
BS 7671 IEE 18th Edition Requirements for Electrical Installations.
Ergonomic requirements for the design of displays and control actuators — Part 1: Human
ISO 9355-1
interactions with displays and control actuators
Ergonomic requirements for the design of displays and control actuators — Part 3: Control
ISO 9355-3
actuators
Ergonomic principles related to mental workload – Part 1: General issues and concepts, terms,
ISO 10075-1
and definitions
ISO 10075-2 Ergonomic principles related to mental workload – Part 2: Design Principles
ISO 12100 Safety of machinery. General principles for design. Risk assessment and risk reduction.
Ergonomics of the thermal environment. Methods for the assessment of human responses to
ISO 13732-1
contact with surfaces – Hot surfaces.
ISO 13849 Safety of machinery. Safety related parts of control systems. General principles for design
ISO 13850 Safety of Machinery. Emergency stop. Principles for design
ISO 14118 Safety of machinery – Prevention of unexpected start-up
Safety of machinery. Interlocking devices associated with guards. Principles for design and
ISO 14119
selection
Safety of machinery. Guards. General requirements for the design and construction of fixed
ISO 14120
and movable guards
ISO 14163 Acoustics — Guidelines for noise control by silencers
ISO 15667 Acoustics — Guidelines for noise control by enclosures and cabins
IEC 60038 IEC Standard Voltages
IEC 60059 IEC standard current ratings
IEC 60076 Power Transformers
IEC 60085 Electrical Insulation – Thermal evaluation and designation
IEC 60196 IEC standard frequencies
IEC 60204 Safety of machinery. Electrical equipment of machines – ALL PARTS
IEC 60228 Conductors of insulated cables.
Safety of machinery - Indication, marking and actuation - Part 1: Requirements for visual,
IEC 61310-1
acoustic, and tactile signals
Safety of machinery - Indication, marking and actuation - Part 3: Requirements for the
IEC 61310-3
location and operation of actuators
IEC 60331 Tests for electric cables under fire conditions – Circuit integrity
IEC 60332 Tests on electric and optical fibre cables under fire conditions - ALL PARTS
IEC 60364 Low-voltage electrical installations
31
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
Standard Description
Basic and safety principles for man-machine interface, marking and identification -
IEC 60445
Identification of equipment terminals and conductor terminations.
Basic and safety principles for man-machine interface, marking and identification – Actuating
IEC 60447
principles
IEC 60529 Degrees of protection provided by enclosures (IP Code).
IEC 60947-1 Low-voltage switchgear and control gear
BS EN 60947-2 Low-voltage switchgear and control gear – Circuit-breakers
Low-voltage switchgear and control gear – Switches, disconnectors, switch-disconnectors, and
BS EN 60947-3
fuse-combination units
Low-voltage switchgear and control gear – Contactors and motor-starters. Electromechanical
BS EN IEC 60947-4-1
contactors and motor-starters
Low-voltage switchgear and control gear – Contactors and motor-starters. AC semiconductor
BS EN 60947-4-2
motor controllers and starters.
Low-voltage switchgear and control gear – Control circuit devices and switching elements.
BS EN 60947-5-1
Electromechanical control circuit devices
Low-voltage switchgear and control gear – Multiple function equipment. Transfer switching
BS EN 60947-6-1
equipment
Low-voltage switchgear and control gear - Multiple function equipment. Control and
BS EN 60947-6-2
protective switching devices (or equipment) (CPS)
BS EN 60950-22 Information technology equipment. Safety – Equipment to be installed outdoors
IEC 61000 Electromagnetic Compatibility
IEC 61131 Industrial-process measurement and control – Programmable controllers
IEC 61158 Industrial communication networks – Fieldbus specifications
IEC 61310 Safety of machinery – Indication, marking and actuation
IEC 61347 Lamp control gear
IEC 61439 Low-voltage switchgear and control gear assemblies
IEC 61508 Functional safety of electrical/electronic/programmable electronic safety-related systems
IEC 61511 Functional safety – safety instrumented systems for the process industry sector
IEC 61537 Cable management. Cable tray systems and cable ladder systems.
IEC 61558 Safety of power transformers, power supplies, reactors, and similar products
IEC 61643 Low-voltage surge protective devices
IEC 61926 Design automation
IEC 62040 Uninterruptible power systems (UPS)
IEC 62041 Transformers, power supplies, reactors, and similar products – EMC requirements
Safety of machinery: Functional safety of electrical, electronic, and programmable electronic
IEC 62061
control systems
ISO 7010 Graphical symbols. Safety colours and safety signs. Registered safety signs
PD 5304 Guidance on safe use of machinery
32
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
4. General Requirements
The Contractor shall provide labour, equipment, materials, tools, and supplies unless specifically noted as being
provided by others, to perform the work described herein in accordance with this document and the referenced
specification, drawings, and related documents. Work not specifically shown on the drawings or enumerated herein,
but that is reasonably necessary for the proper completion of the contract shall be provided by the Contractor the
same as if shown on the drawings or enumerated herein.
The electrical equipment shall be installed in accordance with all the applicable codes, standards, rules, regulations,
and laws including, but not limited to, the codes and standards referenced in Section 3 of this specification.
The Contractor shall provide means of unloading equipment and materials when they arrive On-site.
The Contractor will be responsible for the storage of all equipment and materials ‘free issued’ by JMHM / CAP.
The Contractor will be responsible for loading and transporting equipment and materials from the storage area to
the installation location.
Install all the equipment shown on the drawings or as noted in other contract documents.
All materials and equipment furnished by the Contractor shall be in accordance with the specifications. Substitution
of any materials deviating from the specifications and drawings shall be approved in writing by JMHM. A description
of Contractor supplied substituted material shall be submitted to JMHM for approval.
All materials and equipment ‘free issued’ by JMHM / CAP shall be handled with care.
The Contractor will be responsible for any material or equipment that is ‘free issued’ by JMHM that is subsequently
lost or damaged.
The Contractor will be responsible for completing site Risk Assessments in compliance with CAP working practices
prior to commencing any work.
33
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
5. Installation Requirements
The Contractor shall read and understand the manufacturers installation requirements prior to beginning the
installation of the equipment.
Before installation, area should be blown down with compressed air to rid of excess coke dust.
Bolts and screws shall be tightened uniformly without overstressing the threads.
On-site alterations to equipment to facilitate installation shall not be made without written approval from JMHM.
Sub-assemblies shall be dismantled only to the extent necessary to verify clearances and equipment condition. Total
dismantle of the sub-assemblies, if necessary, shall be carried out only with written approval from JMHM.
Welding shall not be performed in the proximity of bearings. Grounding for welding shall not be through the shaft
or bearing.
It will be the Contractors responsibility to do touch up painting on all finished surfaces damaged or abraded during
installation or left unpainted for on-site welding. Contractor shall prepare the surface by removing all oil, dirt, scale,
rust, and damaged paint and shall feather edge breaks in existing paint. Contractor shall furnish and apply the
materials including primer and paint needed to properly restore the damaged surface coating.
34
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
6. Safety
Prior to the Installation work commencing, a Risk Assessment should have been conducted in accordance with
BS EN ISO 12100 and where hazards have been identified appropriate measures have been implemented to
allow the testing to be carried out in a safe environment.
It is important that the workforce involved has the required skills and training to competently perform their
tasks in a healthy, safe, and environmentally sound manner.
Toolbox talks are an effective means of increasing the knowledge of workers on the HSE risks they face, and
the precautions required, when carrying out the installation work. They also encourage and reinforce safe,
healthy, and environmentally sound behaviours.
35
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
7.1. Pre-Work
As part of the scope of the project, the existing Toshiba control systems that are currently installed on the
South Door Machine is being replaced with a completely new Siemens control system.
Before removal of the existing enclosures, and to assist with a smoother installation it is highly recommended
that the existing cable installation on both machines is traced and marked up accordingly (especially at the
control panel end). It is recommended that this work is carried out in advance of the Disassembly/Assembly
work commencing to avoid any potential delays during this period.
The following reference file should be used during this process as it relates to the original installation:
However, to align with the new configuration that will be installed the following reference file should be used
to identify the cables ready for the installation of the new control system enclosures:
NOTE: Please ensure the latest revision of the new Cable Schedule (343-ELE-A503) is used during this process
to avoid any potential issues at a later stage.
7.2. Disassembly
All field cables shall be disconnected and suitably protected to avoid damage during the removal of the
control system enclosures.
Once all field cables are disconnected, any interconnections between the control panel sections should be
removed to assist with the removal process. Once confirmed that any interconnections have been removed
the process of removing each enclosure section can begin.
Due to the weight of the panels, it would be recommended to remove the back plates of all the enclosures to
reduce the weight of the enclosures.
Once the back plates have been removed all the enclosures can now be removed but ensure that any
equipment not being removed in the surrounding area within the cabins is not damaged during the removal
process.
NOTE: Please ensure suitable lifting equipment is used during to removal process and ensure that everyone
knows where the old equipment is being removed to.
36
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
To install the new control system enclosures, the following drawings are to be used: -
NOTE – Please ensure that the latest revision of drawings are used at all times.
37
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
NOTE – Please ensure that the latest revision of drawings are used at all times.
The control system will have been configured/assembled in accordance with the following CSS drawings:
38
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
8.1.3. Installation
8.1.3.1. Enclosures
1. Install each enclosure section for the electrical cabin in accordance with drawing 343-ELE-A403-S1
2. Install each enclosure section & operators’ desk for the operator cabin in accordance with drawing 343-ELE-
A443-S1.
3. Install JB30 enclosure labelled ‘Estación de control Local’ into the area behind the door located outside the
lower hydraulic cabin (see photo for reference).
4. Once each of the enclosure sections are installed into the respective cabins, all the cabling that was removed
during the process noted in Section 7.2 should be installed into the panels. The drawings referenced in Sections
8.1.1. & 8.1.2. should be utilised for this stage of the installation.
5. Work Complete.
39
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
To install the equipment on the new machine, the following drawings are to be used: -
NOTE – Please ensure that the latest revision of drawings are used at all times.
40
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
NOTE – Please ensure that the latest revision of drawings are used at all times.
42
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
44
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
1. Assemble (free issued) components for JB20 (North End Machine Devices JB) in accordance with drawings 343-
ELE-A653-S1 to 343-ELE-A653-S5.
2. Attach enclosure label to enclosure lid (Refer to drawing 343-ELE-A693-S1 for specific label).
3. Prepare gland entries for JB in accordance with drawing 343-ELE-A653-S3.
4. Work Complete.
1. Assemble (free issued) components for JB21 (South End Machine Devices JB) in accordance with drawings 343-
ELE-A653-S6 to 343-ELE-A653-S10.
2. Attach enclosure label to enclosure lid (Refer to drawing 343-ELE-A693-S1 for specific label).
3. Prepare gland entries for JB in accordance with drawing 343-ELE-A653-S8.
4. Work Complete.
1. Assemble (free issued) components for JB22 (Long Travel No.3 JB) in accordance with drawings 343-ELE-A653-
S11 to 343-ELE-A653-S15.
2. Attach enclosure label to enclosure lid (Refer to drawing 343-ELE-A693-S1 for specific label).
3. Prepare gland entries for JB in accordance with drawing 343-ELE-A653-S13.
4. Work Complete.
NOTE: Points 1 to 3 have been completed in the UK but point 4 is required to be completed on site.
1. Assemble (free issued) components for JB23 (Long Travel No.3 Encoder JB) in accordance with drawings 343-
ELE-A653-S16 to 343-ELE-A653-S20.
2. Attach enclosure label to enclosure lid (Refer to drawing 343-ELE-A693-S1 for specific label).
3. Prepare gland entries for JB in accordance with drawing 343-ELE-A653-S18.
4. Mount enclosure into SSTB Junction Box Cover (Refer to drawing 343-ELE-A683-S1) in preparation for mounting
onto the machine.
5. Work Complete.
45
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
1. Assemble (free issued) components for JB24 (Long Travel No.4 JB) in accordance with drawings 343-ELE-A653-
S21 to 343-ELE-A653-S25.
2. Attach enclosure label to enclosure lid (Refer to drawing 343-ELE-A693-S1 for specific label).
3. Prepare gland entries for JB in accordance with drawing 343-ELE-A653-S23.
4. Work Complete.
NOTE: Points 1 to 3 have been completed in the UK but point 4 is required to be completed on site.
1. Assemble (free issued) components for JB25 (Long Travel No.4 Encoder JB) in accordance with drawings 343-
ELE-A653-S26 to 343-ELE-A653-S30.
2. Attach enclosure label to enclosure lid (Refer to drawing 343-ELE-A693-S2 for specific label).
3. Prepare gland entries for JB in accordance with drawing 343-ELE-A653-S28.
4. Mount enclosure into SSTB Junction Box Cover (Refer to drawing 343-ELE-A683-S1) in preparation for mounting
onto the machine.
5. Work Complete.
1. Assemble (free issued) components for JB27 (Water Sprayer System Water Tank JB) in accordance with drawings
343-ELE-A653-S31 to 343-ELE-A653-S35.
2. Attach enclosure label to enclosure lid (Refer to drawing 343-ELE-A693-S2 for specific label).
3. Prepare gland entries for JB in accordance with drawing 343-ELE-A653-S33.
4. Work Complete.
NOTE: Points 1 to 3 have been completed in the UK but point 4 is required to be completed on site.
1. Assemble (free issued) components for JB31 (Machine Lighting – LF16 JB) in accordance with drawings 343-ELE-
A653-S36 to 343-ELE-A653-S40.
2. Attach enclosure label to enclosure lid (Refer to drawing 343-ELE-A693-S2 for specific label).
3. Prepare gland entries for JB in accordance with drawing 343-ELE-A653-S38.
4. Mount enclosure into SSTB Junction Box Cover (Refer to drawing 343-ELE-A683-S1) in preparation for mounting
onto the machine.
5. Work Complete.
46
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
NOTE: Points 1 to 3 have been completed in the UK but point 4 is required to be completed on site.
1. Assemble (free issued) components for JB32 (Machine Lighting – LF17 & LF18 JB) in accordance with drawings
343-ELE-A653-S41 to 343-ELE-A653-S45.
2. Attach enclosure label to enclosure lid (Refer to drawing 343-ELE-A693-S2 for specific label).
3. Prepare gland entries for JB in accordance with drawing 343-ELE-A653-S43.
4. Mount enclosure into SSTB Junction Box Cover (Refer to drawing 343-ELE-A683-S1) in preparation for mounting
onto the machine.
5. Work Complete.
NOTE: Points 1 to 3 have been completed in the UK but point 4 is required to be completed on site.
1. Assemble (free issued) components for JB33 (Machine Lighting – LF19 & LF20 JB) in accordance with drawings
343-ELE-A653-S46 to 343-ELE-A653-S50.
2. Attach enclosure label to enclosure lid (Refer to drawing 343-ELE-A693-S3 for specific label).
3. Prepare gland entries for JB in accordance with drawing 343-ELE-A653-S48.
4. Mount enclosure into SSTB Junction Box Cover (Refer to drawing 343-ELE-A683-S1) in preparation for mounting
onto the machine.
5. Work Complete.
NOTE: Points 1 to 3 have been completed in the UK but point 4 is required to be completed on site.
1. Assemble (free issued) components for JB34 (Machine Lighting – LF21 JB) in accordance with drawings 343-ELE-
A653-S51 to 343-ELE-A653-S55.
2. Attach enclosure label to enclosure lid (Refer to drawing 343-ELE-A693-S3 for specific label).
3. Prepare gland entries for JB in accordance with drawing 343-ELE-A653-S53.
4. Mount enclosure into SSTB Junction Box Cover (Refer to drawing 343-ELE-A683-S1) in preparation for mounting
onto the machine.
5. Work Complete.
1. Assemble (free issued) components for JB35 (Coke Guide Cage JB) in accordance with drawings 343-ELE-A653-
S56 to 343-ELE-A653-S60.
2. Attach enclosure label to enclosure lid (Refer to drawing 343-ELE-A693-S3 for specific label).
3. Prepare gland entries for JB in accordance with drawing 343-ELE-A653-S58.
4. Work Complete.
47
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
NOTE: Points 1 to 3 have been completed in the UK but point 4 is required to be completed on site.
1. Assemble (free issued) components for JB40 (Hood Interface JB) in accordance with drawings 343-ELE-A653-
S61 to 343-ELE-A653-S65.
2. Attach enclosure label to enclosure lid (Refer to drawing 343-ELE-A693-S3 for specific label).
3. Prepare gland entries for JB in accordance with drawing 343-ELE-A653-S63.
4. Mount enclosure into Junction Box Cover for JB40 (Refer to drawing 343-ELE-A683-S3) in preparation for
mounting onto the machine.
5. Work Complete.
NOTE: Points 1 to 3 have been completed in the UK but point 4 is required to be completed on site.
1. Assemble (free issued) components for JB50 (Long Travel No.1 Encoder JB) in accordance with drawings 343-
ELE-A653-S66 to 343-ELE-A653-S70.
2. Attach enclosure label to enclosure lid (Refer to drawing 343-ELE-A693-S3 for specific label).
3. Prepare gland entries for JB in accordance with drawing 343-ELE-A653-S68.
4. Mount enclosure into SSTB Junction Box Cover (Refer to drawing 343-ELE-A683-S1) in preparation for mounting
onto the machine.
5. Work Complete.
NOTE: Points 1 to 3 have been completed in the UK but point 4 is required to be completed on site.
1. Assemble (free issued) components for JB51 (Long Travel No.2 Encoder JB) in accordance with drawings 343-
ELE-A653-S71 to 343-ELE-A653-S75.
2. Attach enclosure label to enclosure lid (Refer to drawing 343-ELE-A693-S3 for specific label).
3. Prepare gland entries for JB in accordance with drawing 343-ELE-A653-S73.
4. Mount enclosure into SSTB Junction Box Cover (Refer to drawing 343-ELE-A683-S1) in preparation for mounting
onto the machine.
5. Work Complete.
1. Mount Emergency stop stations (free issued) into Emergency Stop covers (Refer to drawing 343-ELE-A683-S2)
in preparation for mounting onto the machine.
2. Work Complete.
48
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
1. Assemble (free issued) components for Light Support Brackets (4 off) in accordance with drawings 343-ELE-
A363-S2. NOTE: The brackets shall be supplied from CAP as part of the manufacture supply.
2. Assemble (free issued) components for Light Support Brackets (1 off) in accordance with drawings 343-ELE-
A363-S3. NOTE: The brackets shall be supplied from CAP as part of the manufacture supply.
3. Attach Floodlight (5 off) assembly (reference on drawing 343-ELE-A363-S1) to the support assemblies that were
assembled in points 1 & 2.
4. Attach JB31 Assembly (referenced in section 8.2.3.1.8) to one of the Light Support Assembly referenced in point
1, in preparation for mounting onto the machine.
5. Attach JB32 Assembly (referenced in section 8.2.3.1.9) to one of the Light Support Assembly referenced in point
1, in preparation for mounting onto the machine.
6. Attach JB33 Assembly (referenced in section 8.2.3.1.10) to one of the Light Support Assembly referenced in
point 1, in preparation for mounting onto the machine.
7. Attach JB34 Assembly (referenced in section 8.2.3.1.11) to one of the Light Support Assembly referenced in
point 1, in preparation for mounting onto the machine.
8. Work Complete.
49
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
Note: The following details are in accordance with drawings 343-ELE-A353-S1, 343-ELE-A363-S1, 343-ELE-A393-S2,
343-ELE-A603-S1 to S7, 343-ELE-A623-S1 & 343-ELE-A643-S1 along with 343-ELE-A503.
NOTE: The following steps should only be carried out if the devices haven’t already been installed by others and
should only be carried out when safe to do so.
NOTE: The following steps should only be carried out if the devices haven’t already been installed by others and
should only be carried out when safe to do so.
50
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
NOTE: The following steps should only be carried out when safe to do so.
51
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
21. Utilising drawings 343-ELE-A353-S1 & 343-ELE-A603-S1, install the Junction Box Assembly for JB20 that was
prepared in Section 8.2.3.1.1., using 4 off M8 channel nut with 4 off M8 x 30mm bolts, flat washers, and spring
washers.
22. Utilising drawings 343-ELE-A353-S1 & 343-ELE-A603-S1, install the Junction Box Assembly for JB21 that was
prepared in Section 8.2.3.1.2., using 4 off M8 channel nut with 4 off M8 x 30mm bolts, flat washers, and spring
washers.
23. Utilising drawings 343-ELE-A353-S1 & 343-ELE-A603-S1, install the Junction Box Assembly for JB22 that was
prepared in Section 8.2.3.1.3., using 4 off M8 channel nut with 4 off M8 x 30mm bolts, flat washers, and spring
washers.
24. Utilising drawings 343-ELE-A353-S1 & 343-ELE-A603-S1, install the Junction Box Assembly for JB23 that was
prepared in Section 8.2.3.1.4., using 4 off M8 channel nut with 4 off M8 x 30mm bolts, flat washers, and spring
washers.
25. Utilising drawings 343-ELE-A353-S1 & 343-ELE-A603-S1, install the Junction Box Assembly for JB24 that was
prepared in Section 8.2.3.1.5., using 4 off M8 channel nut with 4 off M8 x 30mm bolts, flat washers, and spring
washers.
26. Utilising drawings 343-ELE-A353-S1 & 343-ELE-A603-S1, install the Junction Box Assembly for JB25 that was
prepared in Section 8.2.3.1.6., using 4 off M8 channel nut with 4 off M8 x 30mm bolts, flat washers, and spring
washers.
27. Utilising drawings 343-ELE-A353-S1 & 343-ELE-A603-S1, install the Junction Box Assembly for JB27 that was
prepared in Section 8.2.3.1.7., using 4 off M8 channel nut with 4 off M8 x 30mm bolts, flat washers, and spring
washers.
28. Utilising drawings 343-ELE-A353-S1 & 343-ELE-A603-S1, install the Junction Box Assembly for JB35 that was
prepared in Section 8.2.3.1.12., using 4 off M8 channel nut with 4 off M8 x 30mm bolts, flat washers, and spring
washers.
29. Utilising drawings 343-ELE-A353-S1 & 343-ELE-A603-S1, install the Junction Box Assembly for JB40 that was
prepared in Section 8.2.3.1.13., using 4 off M10 channel nut with 4 off M10 x 30mm bolts, flat washers, and
spring washers.
30. Utilising drawings 343-ELE-A353-S1 & 343-ELE-A603-S1, install the Junction Box Assembly for JB50 that was
prepared in Section 8.2.3.1.14., using 4 off M8 channel nut with 4 off M8 x 30mm bolts, flat washers, and spring
washers.
31. Utilising drawings 343-ELE-A353-S1 & 343-ELE-A603-S1, install the Junction Box Assembly for JB51 that was
prepared in Section 8.2.3.1.15., using 4 off M8 channel nut with 4 off M8 x 30mm bolts, flat washers, and spring
washers.
32. Utilising drawing 343-ELE-A623-S1, prepare and install the cable tray lengths in accordance with the drawings,
using M6 x 16mm roofing bolt & nut.
33. Utilising drawing 343-ELE-A643-S1, prepare and install the cable tray lengths in accordance with the drawings,
using M6 x 16mm roofing bolt & nut.
34. Utilising drawings 343-ELE-A603-S1, 343-ELE-A603-S2 & 343-ELE-A603-S7, prepare the cable tray lengths in
accordance with the drawings.
35. Mount cable tray to suit cable routing as shown on drawings 343-ELE-A603-S1 & 343-ELE-A603-S2 using M6 x
16mm roofing bolt & nut (referenced on drawing 343-ELE-A603-S7).
36. Couplers should be used to join each section of cable tray to create one full structure.
37. For cable separation within the cable tray, dividers should be installed throughout the installation.
38. Earth braids shall be installed at each join of cable tray.
39. Any Bracketry and support clamps that are not stated within the reference drawings or any other relevant
documentation are in the supplier’s scope of supply.
40. Work Complete.
52
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
Note: The following details are in accordance with drawings 343-ELE-A703-S1 to 343-ELE-A703-A703-S110.
53
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
54
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
55
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
56
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
57
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
58
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
59
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
60
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
61
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
62
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
63
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
64
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
65
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
66
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
67
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
68
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
69
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
70
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
71
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
72
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
73
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
74
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
75
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
17. Run new cable PE44 (1 core 70mm²) around the external edge of the cable tray installation. Ensure it is securely
clipped onto the cable tray. NOTE: This requirement is outlined in CAP standard NO-90-019_13222-9-Anexo 7.9
ESP 1-5-F, Section 1.11 Grounding.
18. Run new cable PE45 (1 core 70mm²) around the external edge of the cable tray installation. Ensure it is securely
clipped onto the cable tray. NOTE: This requirement is outlined in CAP standard NO-90-019_13222-9-Anexo 7.9
ESP 1-5-F, Section 1.11 Grounding.
19. Run new cable PE46 (1 core 70mm²) around the external edge of the cable tray installation. Ensure it is securely
clipped onto the cable tray. NOTE: This requirement is outlined in CAP standard NO-90-019_13222-9-Anexo 7.9
ESP 1-5-F, Section 1.11 Grounding.
20. Run new cable PE47 (1 core 70mm²) around the external edge of the cable tray installation. Ensure it is securely
clipped onto the cable tray. NOTE: This requirement is outlined in CAP standard NO-90-019_13222-9-Anexo 7.9
ESP 1-5-F, Section 1.11 Grounding.
21. Run new cable PE48 (1 core 70mm²) around the external edge of the cable tray installation. Ensure it is securely
clipped onto the cable tray. NOTE: This requirement is outlined in CAP standard NO-90-019_13222-9-Anexo 7.9
ESP 1-5-F, Section 1.11 Grounding.
22. Run new cable PE49 (1 core 70mm²) around the external edge of the cable tray installation. Ensure it is securely
clipped onto the cable tray. NOTE: This requirement is outlined in CAP standard NO-90-019_13222-9-Anexo 7.9
ESP 1-5-F, Section 1.11 Grounding.
23. Work Complete.
76
Cokeside Extraction for Battery Discharge
Electrical Installation Specification (South)
INST-343-CAP-DS-ELE-002
77