I Pek. Persiapan
1 Pek. Bowplank 33.100 m'
Kaso Borneo 5/7 6.951 btg
Reng Borneo 3/4 8.275 btg
Total I
II Pek. Pondasi
Total II
Total III
IV Pek. Dinding
Total IV
V Pek. Lantai
Total V
VI Pek. Plafond
Total VI
2 Listplank 16.180 m1
Listplank GRC 8.090 lbr
Paku 0.809 kg
3 Rangka Atap 6.930 m2
Baja Canal C 5.000 btg
sekerub 131.670 bh
Atap Alderon Upvc Gelombang 6.930 m2
Single Layer Trimdeck 11.000 lbr
Total VII
1 Pintu
Kunci Pintu 4.000 set
Engsel 4" 4.000 set
2 Jendela
Grendel 3.000 bh
Engsel 3" 3.000 set
Hak angin 3.000 set
Total VIII
3 Bak Kontrol
batako 5.000 bh
Semen 0.250 zak
Pasir 0.100 m3
4 Septic Tank
Buis Beton dia. 100 cm 1.000 bh
Total IX
Total X
1 Carport 0.550 m3
Semen 1.925 zak
Pasir 0.374 m3
Split 0.572 m3
2 Deuker 0.300 m3
Besi O 10 3.300 btg
Semen 1.050 zak
Pasir 0.204 m3
Split 0.312 m3
Total XI
Total XII
TOTAL