ELECTRICAL REQUIREMENT IN ROOM OF SUBSTATION # 1

6 2

4
3
5

1.- It is required to install the ground system cable inside the trench to be able to ground the
substation equipment, it is suggested to place it with clamps.

2.- It is required to install the ground bar in the transformer room.

3.- It is required to install the perimeter ground system cable and join it with the ground system
inside the trench.

At this point, it is necessary to make some steps in the walls that divide the transformer room with the distribution
room and service room in order to be able to join the ground system.

4.- The placement of the ground cable is required to join the Substation Room with the
Mold warehouse as indicated in the project.

5.- It is required, prior to the casting of the road, placement of canalization and construction of
records for electrical supply from the Substation Room to the Mold Warehouse, in the Mold
Warehouse leave the passages in the wall for wiring.

6. The placement of pipes inside the transformer room is required (2 tubes of 50mmØ and 2 tubes of
160mmØ)
Machine Translated by Google

ELECTRICAL REQUIREMENT IN SUBSTATION ROOM # 2 AND 3

3
4

1
2

1.- It is required to install the ground system cable inside the trench to be able to ground the
substation equipment, it is suggested to place it with clamps.

2.- It is required to install ground bars in transformer rooms.

3.- It is required to install the perimeter ground system cable and join it with the ground system
inside the trench.

At this point, it is necessary to make some steps in the walls that divide the transformer rooms with the
distribution room in order to be able to join the ground system.

4. The placement of pipes is required inside the transformer room 2 (2 tubes of 50mmØ and 2 tubes
of 160mmØ)

5. The placement of pipes is required inside the transformer room 3 (2 tubes of 50mmØ and 4 tubes
of 160mmØ)

6. The placement of pipes inside the distribution room is required (4 pipes of 100mmØ and 1 pipe of 50mmØ)
Machine Translated by Google

ELECTRICAL REQUIREMENT IN ROOM OF SUBSTATION # 4

4 2

3
5

1.- It is required to install the ground system cable inside the trench to be able to ground the
substation equipment, it is suggested to place it with clamps.

2.- It is required to install the ground bar in the transformer room.

3.- It is required to install the perimeter ground system cable and join it with the ground system
inside the trench.

At this point, it is necessary to make some steps in the walls that divide the transformer rooms with the
distribution room in order to be able to join the ground system.

4. The placement of pipes inside the transformer room is required (1 tube of 100mmØ, 2 tubes of 50mmØ and
2 tubes of 160mmØ)

5. The placement of pipes inside the distribution room is required (4 pipes of 80mmØ)
Machine Translated by Google

ELECTRICAL REQUIREMENT IN ROOM OF SUBSTATION # 5

1 2

1.- It is required to install the ground system cable inside the trench to be able to ground the
substation equipment, it is suggested to place it with clamps.

2.- It is required to install the ground bar in the transformer room.

3.- It is required to install the perimeter ground system cable and join it with the ground system
inside the trench.

At this point, it is necessary to make some steps in the walls that divide the transformer rooms with the
distribution room in order to be able to join the ground system.

4. The placement of pipes inside the transformer room is required (2 tubes of 150mmØ, 2 tubes of 160mmØ
and 2 tubes of 250mmØ)