Power and Blowing Station

Bhilai Steel Plant

Approved by

CGM (CO & CCD) CGM (POWER FACILITIES)


Protocol for capital repair of Boiler –1 (CG-667) of CDCP of Coke Oven Battery#11

Date : 15.07.2023 to 16.08.2023


Location: CDCP Boiler #1 of Coke Oven Battery#11

A protocol job is under taken for annual capital repair of CDCP Chamber-Boiler# 1. During the capital repair
jobs to be carried out are servicing, repair, replacement and overhauling of pressure parts, valves & boiler
drum internals. During the execution of above jobs workmen will be exposed to the hazard of entering
confined space, welding, cutting, working at height, material handling, and energy isolation. Responsibility
for execution of job during the capital repair are tabulated bellow.

Overall job Coordinator: SHEIKH ZAKIR, GM (B), PBS


S. No. Job Description Responsibility

Preparatory/Actual Jobs :
1 CHAMBER & BOILER SHUTDOWN PBS & CO CCD
2 CHAMBER EMPTYING CHAMBER & BOILER COOLING PBS & CO CCD
2 MAN HOLE OPENING ,ISOLATION & BLANKING PBS
3 ERRECTION OF APPROACH & ACCESSIBILITY OF WORK AREA PBS/PEM
4 INITIAL HT AND DEFECT IDENTIFICATION PBS &PEM
5 AREA SAMPLING & ISSUE OF FORM#3 BEFORE START OF JOB (EVERY DAY) EMD
5 CLEANING OF BOILER PLATFORM, DRUM LEVEL etc PBS
6 ELECTRICAL SHUT DOWN & SCHEME DISCONNECTION OF DRIVES CO CCD(E)
7 REFRACTORY REPAIR WORK IN BOILER AREA PEM &COCCD(REF)
8 LIQUIDATION OF DEFECTS OBSERVED IN INITIAL HT PEM
9 OPENING,COOLING AND CLEANING OF DRUM INTERNALS PEM
10 CLEANING/REPLACEMENT OF DEMISTER PADS PEM
11 REPAIR OF DRUM INTERNALS, IF ANY PEM
12 DRUM BOX UP PEM
13 CHECKING OF HEADERS, CLEANING & BOX-UP PEM
14 OVER HOULING OF SAFETY VALVES PEM
15 REPAIR / OVERHOULING OF GAUGE GLASS ASSEMBLIES, IF ANY PEM
16 REPLACEMENT OF VALVES WHEREVER REQUIRED PEM
17 SCAFFOLDING WORK , WHEREVER REQUIRED PEM
18 FABRICATION & ERECTION OF MODIFIED DUCT MANHOLE AT BOILER INLET PEM
Safety precautions:

The following safety precautions to be followed by the working group and to be monitored by DSO (PBS)
1 All IBR related welding jobs shall be carried out by experienced IBR welders only. Welding should be done
very carefully as the area is gas hazard prone area.
2 ISI approved safety harness and other safety appliances such as helmet, safety shoe, hand gloves etc.
should be used by the working group.
3 Jobs are to be carried out round the clock basis, if required.
4 Welding transformer shall be properly earthed. Welding machines must have RCCB/ELCBs.
5 No smoldering objects shall be left at the work spot after the stoppage of work.
6 Oxygen and D.A. /LPG cylinders shall be kept away so that while cutting/welding spark should not fall on
them. Cutting sets must have flash back arrestor.
7 Confined space standards shall be followed while working in confined space
8 Working at height standards shall be followed while working at height
9 Energy isolation standards shall be followed while carrying out energy isolation
10 Persons having valid gate pass for the said job shall be deputed for the work.

MOHIT PRABHAKAR SWARAJ ZODEY NISHANT KAMDE NIMESH KUMAR


Mgr (PBS) Mgr (PBS) SM (CO&CCD) SR. Mgr (CO&CCD)

CHETAN FUTANE S.K.SAMAL P.SASHIKANTA RAHUL NIGAM P.K.THAKRE


Mgr (CO&CCD) AGM (PBS) GM (CO&CCD) GM(PEM) AGM(PEM)

SHEIKH ZAKIR V.S.DEWANGAN T.K.MUKHERJEE SANJAY NIKHAR


GM (PBS) GM (PBS) GM (CO&CCD) GM (PBS)

S. DESHPANDEY S.K. MAHTO H.K.SAHU


GM (EMD) AGM(SED) GM(SED) GM I/C(PBS& PEM)

P.M.RAJENDRA KUMAR T K DUTTA


DSO (CO&CCD) DSO (PBS)

ENCL:-( 1) Schedule of CDCP Boiler #1 capital repair activities ( 2) HIRA document