You are on page 1of 9

Scholarly Paper

Impacts of Change Orders on Cost and


Schedule Performance and the Correlation with
Project Size of DB Building Projects
Pramen P. Shrestha, Ph.D., P.E., M.ASCE 1; and Medya Fathi, S.M.ASCE 2
Downloaded from ascelibrary.org by Nottingham Trent University on 08/07/19. Copyright ASCE. For personal use only; all rights reserved.

Abstract: Few studies have been conducted to evaluate change orders in design-build (DB) projects, examining their impacts on cost and
schedule performance, and their relationship with project size. This study analyzed cost, schedule, and change order data for 125 DB building
projects to check whether the number of change orders for DB projects was higher than for design-bid-build (DBB) projects. All of the DB
projects considered in this study had fixed their final guaranteed maximum price (GMP) before the design was 100% completed. One of the
advantages of the DB delivery method is constructability, in which the designer can solicit feedback from construction personnel during the
design phase; this can reduce the number of change orders. Results indicated that there were fewer change orders during DB building projects
compared with DBB building projects. In addition, the percentage of projects that had cost overruns (21%) was significantly lower than that
for projects that had cost underruns or were completed on budget (79%). In addition, the percentage of change orders in projects that had
schedule overruns was not significantly higher than that in projects that had no schedule overruns; among other findings, the number of
change orders increased as the size of the project increased (r ¼ 0.59). DOI: 10.1061/(ASCE)LA.1943-4170.0000311. © 2019 American
Society of Civil Engineers.
Author keywords: Design-build; Building projects; Change orders; Cost overrun; Schedule overrun.

Introduction item in the contract document (Scott 1999; Jackson 2004; Günhan
et al. 2007; Jawad et al. 2009; Ibbs 2012). Some studies define
The construction industry’s contribution to the development of change orders according to their specific case of examination, type
countries and its effect on economies (Mahamid et al. 2012) are of contract, or type of project delivery. For instance, a change order
undeniable. The performance of a construction project is a deter- in a design-bid-build (DBB) building project might be related to a
mining factor in this regard, and can be affected by change orders. variation after the detailed design (Shrestha and Zeleke 2018).
Stakeholders in the construction industry commonly acknowledge It is challenging to maintain the success of a project when facing
that change orders are inevitable (Günhan et al. 2007). In a complex a change. Neither the owner nor the contractor is inclined to con-
environment including many tasks, a limited schedule and budget, tend with problems that preclude the project from meeting original
and unforeseen conditions, accurate planning and prediction can goals and expectations (Thomas and Napolitan 1995; Günhan et al.
hardly be obtained (Wysocki and McGary 2003; Frame 2003; 2007; Ibbs 2012). It is implied that a change order’s impact on
Andersen et al. 2004; Stare 2010). Change orders occur regularly. a project refers to its negative effects on unchanged activities as
In other words, no matter how excellent the project plan is, there is a result of a change in the contract (Hanna and Gunduz 2004).
always a “surprise” during design and construction (Young 2000). Many studies have concluded that cost overrun is among
Several scholars have provided definitions for the term change the detrimental effects (Nassar et al. 2005; Serag et al. 2010;
order and its concepts. In one of the initial attempts, Civitello Anastasopoulos et al. 2010), leading to additional costs
(1987) defined it as an unplanned change accompanied by extra (Ndihokubwayo and Haupt 2008; Günhan et al. 2007). However,
work—and subsequently cost and time—beyond expectations Ssegawa et al. (2002) claimed that not all types of change orders are
(Civitello 1987). According to Barrie and Paulson (1992), any coupled with increased cost. In addition, indirect effects have been
alteration in the contract made by the owner is a change order. recognized to increase costs, such as increased disputes, failure
A more holistic description considers a change order to be the ad- in coordination of the project, reduced productivity, limited cash
dition of a new item, a deletion, and/or a modification of an existing flow, low morale, and float (Sun and Meng 2009). By means of
a “ripple effect” or “cumulative impact” (Lee et al. 2004), loss
1
Professor, Dept. of Civil and Environmental Engineering, and in labor productivity has been considered an inevitable conse-
Construction, Howard R. Hughes College of Engineering, Univ. of Nevada, quence of change orders (Leonard 1988; Hanna et al. 1999a, b,
Las Vegas, NV 89154 (corresponding author). ORCID: https://orcid.org 2002; Thomas and Napolitan 1995; Ibbs 2005; Moselhi et al.
/0000-0001-6362-2315. Email: pramen.shrestha@unlv.edu 2005; Halligan et al. 1994; Han et al. 2011).
2
Ph.D. Candidate, Dept. of Civil and Environmental Engineering and The timing of a change order is also of great significance.
Construction, Howard R. Hughes College of Engineering, Univ. of Nevada, In general, more delays in a project cause more fatigue among
Las Vegas, NV 89154. Email: medya.fathi@unlv.edu
workers, which in turn can lead to impairment of productivity and
Note. This manuscript was submitted on August 29, 2018; approved on
January 15, 2019; published online on May 28, 2019. Discussion period
morale (Oglesby et al. 1989; Lee et al. 2005; Hanna et al. 2002;
open until October 28, 2019; separate discussions must be submitted for Han et al. 2011). Change orders occurring later in the project
individual papers. This paper is part of the Journal of Legal Affairs have more negative effects, and their level of severity can nullify
and Dispute Resolution in Engineering and Construction, © ASCE, previous efforts (Han et al. 2011). Early recognition and action
ISSN 1943-4162. regarding potential changes can provide opportunities to suggest

© ASCE 04519010-1 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2019, 11(3): 04519010


remedies for potential problems and maintain adequate project In order to assess the degradation of productivity and cost after
performance. the occurrence of a change order, Ibbs developed a comprehensive
Design Build (DB) is a project delivery method to design and questionnaire survey with the help of other academic researchers
construct a facility to be delivered by owners. It allows starting con- as well as members of the change management task force of the
struction before completion of the design. In recent studies, the au- Construction Industry Institute (CII), which included over 30 or-
thors have compared the output and advantages of saving time and ganizations and 104 projects having a total installed cost of greater
cost by the use of two project delivery methods, DB DBB. DBB is than $8 billion. The types of project included in the sample were
the traditional method, in which construction begins only after the refinery, manufacturing, petroleum or natural gas, and chemicals
completion of a detailed design. Reviewing the literature revealed and were built mostly using DBB and DB, although they were not
that no study has been conducted to investigate whether change limited to those methods. The various types of contract used in-
orders lead to an escalation in the expenses and duration of projects cluded lump sum, cost plus fixed fee, and cost plus percent fee.
built using DB project delivery. In the end, it was concluded that, as a higher number of change
The study of change orders is critical because it has implications
Downloaded from ascelibrary.org by Nottingham Trent University on 08/07/19. Copyright ASCE. For personal use only; all rights reserved.

order occur, the worse the effect is on cost growth and productivity.
for legal issues as well as disputes on any project. If there are no About three decades ago, scholars turned their attention to de-
changes or few changes on a project, legal issues and disputes re- creased labor efficiency. A study by Leonard (1988), considered the
lated to delay claims are reduced. On most projects, disputes occur first research effort in this field, formed the basis of many other
after the owners deviate from the original contract in terms of design studies (Ibbs 2008, 2012). Another ground-breaking article by
change, quantity variations, owner-initiated changes, or changes Thomas and Napolitan (1995) related to daily productivity in three
due to unforeseen conditions. Sometimes these changes become industrial projects that occurred between 1989 and 1992. Based on
disputes and can go to litigation if the change orders are not man- the output of variance tests and regression analyses for 522 work-
aged efficiently and appropriately (DeVries 2018). Therefore, it is days, a 30% loss was observed as the average effect of all changes.
necessary to determine whether the project delivery method has any Nevertheless, individual changes did not necessarily correlate with
impact on change orders in order to reduce disputes and litigations lower labor efficiency.
between owners and contractors. Hanna et al. (1999a) addressed the issue of lowered labor effi-
This study conducted a statistical analysis of change orders in ciency in the mechanical construction industry. For this study, 61
DB building projects and compared them with change orders in projects were selected, consisting of commercial, institutional, in-
DBB projects. In addition, analysis was conducted to determine dustrial, residential, and the like. Most projects were DBB but some
whether change orders have a detrimental effect on the schedules were DB having lump-sum fixed-price contracts. For data collec-
for DB building projects, as was found for DBB building projects. tion, 26 contractors participated in questionnaire surveys and inter-
Finally, this study assessed whether there is any relationship be- views. The input variables were the initial estimated labor hours
tween change orders and the size of a project in terms of project and measures for change orders, including estimated hours, num-
costs for DB building projects. The main objectives of this study ber, timing, and effects. The findings showed that change orders
were to
lowered labor efficiency, particularly when they were issued later
• Determine the percentage of change orders in DB projects and
in the projects.
compare that with DBB projects;
In addition, Hanna et al. (1999b) investigated labor efficiency in
• Assess whether change orders significantly affect projects with
the electrical construction industry. Focusing on macroeffects, this
regard to cost overruns;
research measured the effects of several factors on labor efficiency
• Assess the relationship between change orders and the size of
at the project level instead of the activity level. A questionnaire was
DB building projects; and
developed; after a revision based on feedback by experts, it was
• Determine whether change orders in projects that have schedule
overruns are significantly higher than change orders in projects distributed randomly to 200 contractors in 10 states. Follow-up in-
that have no schedule overruns. terviews were conducted to validate the collected data. In total, 61
projects of various types were used for hypothesis testing and re-
gression analysis by means of independent variables, such as esti-
mated period of time for each change order. This model was later
Literature Review
validated by an additional questionnaire. The projects were fixed-
The authors mainly reviewed the literature related to the impact of price or lump-sum and, as in Hanna et al. (1999a), they used mainly
change orders on productivity and loss of efficiency because it was DBB and some DB delivery. The results demonstrated direct links
necessary to determine whether change orders are detrimental to among schedule compression, sequencing of activities, and change
projects and can cause legal issues and disputes to arise between orders.
owners and contractors. If the changes have a negative impact on The increasing need for school buildings and the substantial
labor efficiency, then there is a higher probability that this can cre- number of change orders they involve has become a challenge
ate disputes between owners and the contractors, and sometimes in major school districts throughout the United States. Dealing with
the disputes can move to court for litigation. Therefore, the impact this issue, Günhan et al. (2007) investigated the causes and mag-
of change orders on labor efficiency needs to be explored in detail. nitude of change orders during the construction and renovation of
The authors also reviewed the literature related to the number of school buildings during the period 1999–2004. Over 6,500 change
change orders in various project delivery methods and contract orders were evaluated based on the amount of the contract award,
types, in order to determine which delivery methods and contract cost of the changes, and project completion. The changes were cat-
types yield fewer change orders, so that disputes and litigations egorized into five groups, such as owner-directed changes and
between project parties can be reduced. errors/omissions in the contract documents. The study emphasized
About two decades ago, among initial attempts to study change that it was possible to limit the costs related to change orders to 5%
orders in construction projects, Ibbs (1997) pinpointed a negative of the contract value by taking some precautionary measures—for
correlation between the number of change orders (i.e., size) and example, presenting an early definite scope and having effective
their effects, using standard statistical tests on quantitative data. management prior to the contract.

© ASCE 04519010-2 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2019, 11(3): 04519010


Adverse effects of change orders have been studied by many difference between the summation of the estimated base, change
researchers. Ndihokubwayo and Haupt (2008) discussed how cost, orders hours, and actual hours. In the final model, the principal var-
time, quality, health and safety, and professional relations costs iables leading to disruptions and loss of labor efficiency included
can affect project performance. However, their main focus was percentage of design-related and owner-related changes, ratio of
the effect on waste, as indicated by cost. They studied two residen- actual to estimated peak labor, project duration, and percentage of
tial and shopping apartment complexes in Cape Town, South work hours of the project manager.
Africa, and found that some unnecessary costs could not be com- Focusing on large buildings, Jawad et al. (2009) carried out a
pletely mitigated, such as resource waste, as well as the contribu- questionnaire survey to determine the causes and effects of change
tion of unnecessary costs to the final delivery cost. Another study orders, as well as to identify control measures for managing change
reviewed methods for quantifying lost productivity and assessed orders. In this investigation, 34 contractors and consultants, each
the relationship among changes, productivity losses, contributing with over 15 years’ experience, responded to questions on general
parties, and disruptions. Ibbs et al. (2007) observed that a single market characteristics and trends, causes and effects of change or-
factor could hardly cause a decline in productivity; instead, a num- ders, and management control tools. The common contract format
Downloaded from ascelibrary.org by Nottingham Trent University on 08/07/19. Copyright ASCE. For personal use only; all rights reserved.

ber of causes played simultaneous roles. This group reviewed a va- among the projects was lump-sum turnkey. The output indicated
riety of estimating methods for lost productivity, such as project that the cost overrun was 5%–10% of the original contract value,
practice–based methods (e.g., baseline productivity and earned while the schedule overrun was less than 10% of the original
value analysis) and industry-based or cost-based methods, since contract duration. According to this study, the owner was the chief
specific circumstances required the most suitable analysis method source of change orders and the primary cause was plan changes
to resolve the problem. by the owner.
Combining individual sets of projects presented by Leonard Communication among the parties involved in the occurrence of
(1988) and Ibbs (2005, 2008), Ibbs (2012) followed the same ob- change orders in various phases of a project can be problematic;
jectives and examined the effects on labor productivity, supporting this is true even for reasonable change orders if they cause the
the previous conclusions regarding productivity. Using a larger data project to exceed contract expectations. Among attempts to quan-
set [i.e., combining the databases of Leonard (1988) and Ibbs tify the possible effects of change orders on project performance,
(2005, 2008)], Ibbs (2012) quantified the likelihood, number, Yitmen and Soujeri (2010) used an artificial neural network (ANN)
and effect of change orders on project cost, schedule, and produc- to determine potential dispute resolutions between a client and
tivity. This study included a series of statistical tests not addressed a contractor. Using certain factors, ANN identified the negative
before, and detected an analogous relationship between productiv- effects and the probability of a dispute occurring. The selected proj-
ity, cost and schedule overruns, and the likelihood and severity of ects were 29 buildings and 6 infrastructures constructed in North
changes. The results showed that a greater number of changes Cyprus, with an original total value above $90 million. One of the
deteriorated productivity and its predictability. Compared with pre- drawbacks of this study is that the authors selected various types of
vious reports, the study found a greater ratio of final to estimated projects from buildings to roads to water/wastewater.
project costs and more frequent cumulative effects. Also, with less Effective change management can help a project meet its origi-
than a 5% change, more than half of the projects experienced a nal goals with no disputes or waste of time and money. The pre-
higher productivity rate than had been planned; however, when vention of change orders and the reduction in their effects on
change orders increased fourfold, the planned productivity rate project performance by means of comprehensive management
could not be achieved. was the subject of close scrutiny by Stare (2010). The model de-
Subjective assessments to identify a project affected by change veloped in this study took advantage of combining risk manage-
orders underlie the need for a clear and quantitative definition of ment and project control with change management to detect
their effects. To fulfill this need, Hanna et al. (2002) proposed a changes early, have suitable reactions, lower the potential effects
classified measurement to determine whether electrical or mechani- of change, and implement changes properly. By means of a web
cal projects, as labor-intensive environments, were affected or un- survey of about 1,000 construction professionals in Slovenia,
affected by change orders. In this study, CII members contributed to 137 respondents indicated that change orders in 90% of projects
the development of a questionnaire. For 116 projects, 35 electrical caused them to exceed their estimated time and costs.
contractors and 33 mechanical contractors responded that 59 and Alnuaimi et al. (2010) found that change orders and disputes
57 projects, respectively, were successful in meeting the limits of increased the cost and duration of projects. This group analyzed
the model. The project types were commercial, industrial, institu- four public construction projects in Oman and showed that the par-
tional, manufacturing, residential, power plant, and wastewater. ties that benefited the most from change orders were the contrac-
The collected data were analyzed by logistic regression, and cross- tors. However, consultants were also beneficiaries because of low
validation was used to validate the developed model. The researchers risks and guaranteed payment from change orders.
claimed that the model could be considered a forecasting tool to Shrestha and Zeleke (2018) examined the effects of change or-
predict whether or not a project was affected by change orders ders in school building renovation projects in the Las Vegas Valley
based on eight primary factors, including percent change, estimated in southern Nevada. In this study, 161 projects were analyzed to
and actual peak manpower, change timing, and overtime. quantify change orders and evaluate their effects on project perfor-
Hanna and Gunduz (2004) believed that small projects in gen- mance. The researchers determined the change orders that affected
eral were more likely to be affected by changes due to the lack of cost and time overruns to a greater extent and correlated the number
accurate planning for labor and costs during the design and con- of change orders with project size. Most change orders were due to
struction phases. That being said, small electrical and mechanical unforeseen conditions and design rather than owners. Regarding
projects were selected to investigate the detrimental effects of the detrimental effects on project performance, the projects expe-
change orders on overall productivity. A CII committee took part rienced 75% cost overruns and 40% schedule overruns.
in developing the questionnaire and conducting data collection, A number of studies have been conducted to compare construc-
which was based on causative factors. In total, 34 projects having tion cost change in various project delivery methods (e.g., DBB,
less than 5,000 estimated work hours were selected and used in a DB) and construction manager at risk (CMAR) in building projects
linear regression equation to reach the value of delta, which was the (Konchar and Sanvido 1998; DBIA 2018; Shrestha and Fernane

© ASCE 04519010-3 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2019, 11(3): 04519010


2017). However, the study most relevant to the work described in of previous studies on the percentage of change orders in DBB
this paper is the one conducted by Rojas and Kell (2008) on school building projects to compare with the percentage of change orders
building projects. This study’s findings on the cost performance of in DB building projects from the data collected in this study.
CMAR compared with DBB in building projects were exactly the
opposite of what most other studies found. Roja and Kell collected Null Hypotheses
297 school building projects from Washington and Oregon and
found no significant difference in the construction change order To test the second research hypothesis, it was converted to a null
costs of CMAR and DBB projects. They also showed that the cost hypothesis. The null hypothesis stated that there is no significant
growth of CMAR projects was significantly higher than that of difference between the percentage of projects with positive change
DBB projects during buyout (Rojas and Kell 2008). orders compared with projects that have no or negative change
Reviewing the literature revealed that, although many attempts orders. This would show whether there are a significantly higher
have been made to determine the effects of change orders on cost, number of DB projects that have cost overruns than the number
schedule, and productivity, previous studies investigated these of projects that have cost underruns.
Downloaded from ascelibrary.org by Nottingham Trent University on 08/07/19. Copyright ASCE. For personal use only; all rights reserved.

issues only in DBB building projects Recently the authors found The null hypothesis for the third research hypothesis stated that
that the owners received significantly higher schedule advantage there is no significant difference between change order percentages
than cost advantage in DB building projects (Fathi and Shrestha in the projects that have schedule overruns compared with projects
2018). The current study focused on DB building projects, a meth- that have no schedule overruns. It can be mathematically expressed
odology used to increase collaboration between owners and build- as follows: the difference in the population means of change order
ers in order to reduce the number of change orders and their effects percentages of the two project groups is not significantly different
on productivity and schedules. Additionally, most previous studies from zero as expressed as shown in Eq. (1)
focused on contributing factors as well as improving strategies and
management styles. Therefore, to fill the knowledge gap, this study μchange orders in DB projects with schedule overruns
quantified change orders in DB building projects and analyzed their
¼ μchange orders in of DB projects with no schedule overruns ð1Þ
relationships with schedules and project sizes. The objective was to
determine whether the DB delivery method yields fewer change
orders when compared with DBB, which is one of the premises The fourth null hypothesis stated that there is no significant cor-
for using the DB delivery method when designing and constructing relation between the number of change orders and contract costs of
projects. DB building projects. Alternatively, it can be stated that the corre-
lation coefficient between the number of change orders and the size
of a DB building project is not significantly different from zero.
Research Methodology It can be expressed as shown in Eq. (2)

The authors collected DB building project change order, cost, and ρchange orders and project contract cost ¼ 0 ð2Þ
schedule data . The projects were categorized as schools and cam-
puses, offices and commercial buildings, and clinics and hospitals.
Data Collection
School and campus buildings generally consist of classrooms, labs,
libraries, and the like, constructed for school districts or for univer- For this study, the data from 125 DB buildings were collected from
sities and community colleges. These data were collected from the the DBIA database from September 2017 to May 2018. The sample
database of the Design Build Institute of America (DBIA). contains three groups: schools and campuses (57%), offices and
After collection, the data were verified and checked for consis- commercial buildings (22%), and clinics and hospitals (21%).
tency. The data were screened, and general descriptive statistics The following information from the projects was gathered:
were analyzed. The data were used for statistical analysis to deter- • Project’s location, size, procurement/selection criteria (mostly
mine the correlation coefficient, as well as to determine whether best value), and design-build contract terms (mainly lump sum
change orders were significantly different in two types of project, and guaranteed maximum price);
categorized based on schedule overrun and project size. Chi-square, • Change order data: total number of change orders in the project;
Pearson’s correlation coefficient and t-tests were used to confirm • Cost data: contracted project costs and actual total project
the research hypothesis. The research and null hypotheses and the costs; and
statistical analyses conducted in this study are described next. • Schedule data: notice to proceed (NTP), bid/contracted con-
struction start and completion dates, actual construction start
Research Hypothesis and completion dates, contract bid duration, and actual duration.
These data were used to developed two major metrics: one re-
Four research hypotheses were created in this study. The first stated lated to change orders and the other related to schedule growth.
that there is a lower percentage of change orders in DB building Eqs. (3) and (4) show how these metrics were calculated. The au-
projects compared with DBB projects. The second was related thors did not use the cost growth metric in this study because total
to the effects of change orders on cost overruns in DB projects, project completion cost was not available. However, for consis-
stating that the number of DB projects that have positive change tency, the author show the cost growth metric generally used in
orders is higher than the number of projects that have negative research in Eq. (5)
or no change orders. The third research hypothesis stated that
change orders have detrimental effects on the schedule growth Total change order cost
of these projects. The final research hypothesis stated that the num- Change order ð%Þ ¼ × 100 ð3Þ
Total contract cost
ber of change orders has a significant positive correlation with the
contract costs of DB projects, similar to that found in DBB projects.
Schedule growth ð%Þ
All of these research hypotheses, except the first one, were con-
verted to null hypotheses to conduct statistical tests for validation. Total actual duration − total contract bid duration
¼ ð4Þ
To prove the first research hypothesis, the authors used the findings Total contract bid duration

© ASCE 04519010-4 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2019, 11(3): 04519010


Total completion cost − total contract cost assumption, related to equal variances in both groups, was tested by
Cost Growth ð%Þ ¼ conducting Levene’s test. If this test failed, it would show that
Total contract cost
ð5Þ the variances were unequal in these two groups. Then a t-test with
unequal variances would be conducted to determine whether the
change order percentages in these two groups of projects were sig-
Statistical Tests nificantly different.
Before analyzing the data, boxplots of change order numbers and Pearson’s Correlation Test
percentages were prepared to determine whether there were outliers Pearson’s correlation test was conducted to determine the correla-
in the data. If so, they were removed. An outlier is generally defined tion of change order numbers with project contract costs. To con-
as a data point “which falls more than 1.5 times the interquartile duct this test, four major assumptions had to be verified: (1) the data
range above the third quartile or below the first quartile” (Wolfram would be in interval or ratio scale; (2) no significant outliers would
MathWorld 2018). be present in the data set; (3) the data would be normally distrib-
Downloaded from ascelibrary.org by Nottingham Trent University on 08/07/19. Copyright ASCE. For personal use only; all rights reserved.

Chi-square, Pearson’s correlation, and t-tests were conducted to uted; and (4) the data set would have a linear correlation (Laerd
test whether the null hypotheses were true. Chi-square tests were Statistics 2018b). The first assumption was true because both
conducted to determine whether the percentage of projects that had the change order percentages and project contract cost data were
positive change orders was significantly higher than the percentage on ratio scales. The outliers were identified and removed before
of projects that had no/negative change orders. Pearson’s correla- the data were analyzed. Normality was tested by Pearson’s corre-
tion tests were conducted to check for a significant correlation be- lation test. The final assumption related to linearity was tested by a
tween change order percentages and schedule growth. To determine scatterplot of change order numbers and project contract costs. The
whether the size of projects that had no/negative change orders plot showed whether these two variables had linear relationships.
were significantly larger than projects that had positive change or-
ders, t-tests were conducted. These tests and their assumptions are
described next. Results

Chi-Square Test In order to determine whether the data had any outliers, a boxplot of
The chi-square test was conducted to determine if there was any change order percentages was prepared using SPSS, as shown in
significant difference between the percentage of projects that Fig. 1. From the boxplot, it can be seen that 10 data points were
had no/ negative change orders and the percentage of projects that considered outliers. Therefore, before analyzing the data, these 10
had positive change orders (Statistics Solutions 2018). In this study, data points were removed. The remaining 115 data sets were used
the authors investigated whether change orders have significant det- to determine the descriptive statistics and to conduct statistical
rimental effects on DB building projects in terms of cost overruns. analyses to prove the research hypotheses. These are described in
There were three assumptions to be met: (1) the data would be ran- detail in the following subsections.
domly selected; (2) the variable under study would be a categorical
variable; and (3) the expected value of the number of sample ob- Descriptive Statistics
servations in each level of the variable would be at least 5 (Star Trek
2018). Based on the randomly selected projects collected from the Descriptive statistics were calculated for the number of change
DBIA database, the first assumption held true. Similarly, the var- orders, percentage of change orders, schedule growth, and contract
iable used in this study to test was percentage of projects, which costs of DB building projects. The project data collected in this sam-
was a categorical variable. Also, the sample size of each of these ple were taken from different time periods; therefore, change order
two groups was more than 5. Therefore, all three assumptions were costs and contract project costs were normalized using the cost
true in this sample and so this test was conducted to determine indices from the RS Mean Cost Guide (2018). All cost data were
whether the second null hypothesis would hold true. The test was converted to January 2018 equivalent costs using these indices.
conducted at alpha level 0.05. If the p-value was found to be less
than 0.05, then the null hypothesis would be rejected, confirming
that change orders significantly affect DB building projects in cost
overrun.

t-Test
The t-tests were conducted to determine whether the change order
numbers and percentages in DB building projects completed on
time or ahead of time were significantly lower than those in projects
that took more than the contracted time to complete. To conduct
this test, six assumptions had to be verified: (1) dependent variables
would be in continuous scale; (2) there would be two independent
groups; (3) the data would be randomly selected; (4) there would
not be any significant outliers present in the data set; (5) the de-
pendent variables would be normally distributed; and (6) the homo-
geneity of variances in these two groups would be equal (Laerd
Statistics 2018a). The first three assumptions held true in this sam-
ple. The fourth assumption had already been tested and verified
before the data were analyzed. For testing normality, “the residual
of regression should follow a normal distribution” (Laerd Statistics
Fig. 1. Boxplot of the percentage of change orders in DB building
2018a). Therefore, a normal predicted probability (P-P) plot was
projects.
checked to see whether the data were normally distributed. The last

© ASCE 04519010-5 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2019, 11(3): 04519010


Downloaded from ascelibrary.org by Nottingham Trent University on 08/07/19. Copyright ASCE. For personal use only; all rights reserved.

Fig. 2. Mean and median values of the percentage of change orders and schedule growth in DB projects.

Table 1. Results of chi-square test


Percentage of Chi-square
DB project types based on cost growth No. of projects projects value p-value
With cost underrun or completed on budget 91 79 39.03 0.000a
With cost overrun 24 21 — —
Total 115 100 — —
a
Significant at alpha level 0.05.

Fig. 2 shows the mean and median values of the percentage of had no schedule overruns, the assumptions of data normality
change orders and schedule growth. It can be seen that the average and equal variances in these two groups of projects needed to
percentage in change orders for DB building projects was 4.04% be tested. The normality assumption of the data was tested by pre-
and the median value was similar to the mean value. About 50% of paring a P-P plot using SPSS. Fig. 3 shows the P-P plot of regres-
the projects had no schedule growth, and the average value of sion standardized residual for change order costs of sample DB
schedule growth was −1.4%. The average size of the DB building building projects. The normal P-P plot did not show that the data
projects was $84.4 million, equivalent to a 2018 base cost. were normally distributed. However, based on the central limit
The analysis showed that the mean value of change order costs theorem, the data were considered normally distributed if the
was about $3.04 million and the median value was $4.29 million. sample size exceeded 30. In this case, the sample size was 115;
The average DB project size considered in this study was about
$84.42 million. A statistical test was conducted to determine
whether the number of projects having cost overruns was signifi-
cantly higher than the number of projects having no cost overruns.
The results of this test are described in the following section.

Chi-Square Test Results


The chi-square test showed whether the percentage of projects that
had cost overruns was significantly higher than the percentage of
projects that had cost underruns or no cost overruns. The data
analysis indicated that there were 91 (79%) projects that had no
cost overruns or cost underruns. The remaining 24 projects (21%)
had cost overruns. The chi-Square test results showed that, in the
population, the number of cost-overrun DB projects was signifi-
cantly lower than the number of cost-underrun or no-cost-overrun
projects because the p-value found in the test was less than 0.05
(Table 1). Therefore, it can be stated that, the use of DB project
delivery in designing and constructing building projects reduces
cost overruns in terms of number of projects.

t-test Results
Before conducting a T-test to determine whether the change order
percentages of projects that had schedule overruns were signifi-
Fig. 3. Normal P-P plot of change order costs in DB building projects.
cantly higher than the change order percentages of projects that

© ASCE 04519010-6 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2019, 11(3): 04519010


Table 2. Results of Levene’s test Table 4. Results of Pearson’s correlation test
Sample Levene’s Independent Sample Correlation
Group size Variances statistic p-value Dependent variable variable size coefficient p-value
Projects with schedule overrun 91 48.57 0.05 0.83 Change order cost Total contract cost 115 0.59 0.001a
Projects with no schedule overrun 24 36.0 — — a
Significant at alpha level 0.05.

Table 3. Results of t-test with equal variances are random and that schedule overruns have no correlation with
Mean change order percentages.
Sample change
Group size order (%) t-statistic p-value Pearson’s Correlation Test Results
Downloaded from ascelibrary.org by Nottingham Trent University on 08/07/19. Copyright ASCE. For personal use only; all rights reserved.

Projects with schedule overrun 91 3.5 −1.66 0.10 Pearson’s correlation test was conducted on change order percent-
Projects with no schedule overrun 24 6.0 — — ages and total contract costs of DB projects to see whether they
were linearly correlated. Before conducting this test, the assump-
tions related to linearity and normality were checked. First, a scat-
therefore, it could be considered that the data were normally dis- terplot was created to see whether there was a linear correlation
tributed. According to Bartlett (2018), “as the sample size in the between these two variables, as shown in Fig. 4. From the plot,
two groups gets large, the t-test is valid (i.e., the type 1 error rate it can be seen there was indeed linearity.
is controlled at 5%) even when data doesn’t follow normal The result of Pearson’s correlation test is provided in Table 4.
distribution.” It shows that there was good positive linear correlation (0.59)
The final assumption of the t-test was that the variances of the between the two variables and that the correlation was significant
two groups were equal. In this test, the two groups considered were at alpha level 0.05. Therefore, it can be stated that, as the total
projects that had schedule overruns and the projects that had no contact cost of DB project increases, the change order cost
increases.
schedule overruns. Levene’s test was conducted to verify this
assumption; the results are provided in Table 2. The null hypothesis
of the test was that the two groups had equal variances. If the Discussion
p-value was less than 0.05, then the null hypothesis was rejected,
showing that the groups had unequal variances. The results showed The study results show that the average value of change orders in
that these two groups had equal variances because the p-value was DB building projects was 4.04%. In this study, the majority of the
greater than 0.05 and failed to reject the null hypothesis. data collected were from school and campus buildings. When the
A t-test with equal variances was conducted to determine the change orders of this DB data sample were compared with those for
difference in change order percentages between the two project DB campus buildings studied previously by the authors, they were
groups. The results of this test are provided in Table 3, which found to be fewer (16%) (Shrestha and Fernane 2017). In addition,
indicates that the change order percentages were not significantly the change orders for this set of DB building projects were found to
different. This proved that change orders in DB building projects be fewer than the change orders for DBB campus (11.5%) and

Fig. 4. Scatterplot of change order cost and total contract cost in DB building projects.

© ASCE 04519010-7 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2019, 11(3): 04519010


school building (5.9%) projects reported by Shrestha and Fernane DB projects are similar to DBB projects. However, findings related
(2017) and Shrestha et al. (2018). Therefore, it can be concluded to the impact of change orders on cost and schedule performance
that the number of change orders in DB building projects is fewer indicate that DB and DBB projects are diametrically opposed. This
than that in DBB building projects. A study conducted by Perkins study found that change orders have a significantly lower effect on
(2010) on Military Construction (MILICON) projects supports this DB project cost performance and no effect on DB schedule perfor-
conclusion, showing that DB family housing projects also had mance, which is not the case with DBB projects. Also, in terms of
fewer change orders than DBB family housing projects. These con- change order performance, it was found that DB building projects
clusions were derived based on the numbers without conducting have fewer change orders when compared with DBB building proj-
the statistical test. ects. Therefore, it can be stated that DB is a better project delivery
Another important finding of this study was that change orders method than DBB in terms of generation of change orders and im-
caused a significantly fewer number of projects to have cost over- pact on cost and schedule overruns.
runs. It was found that change orders increased costs in only 21% of The major contribution of this study to the body of knowledge is
the building projects. This was significantly lower compared with the light it sheds on change order performance and its impact on
Downloaded from ascelibrary.org by Nottingham Trent University on 08/07/19. Copyright ASCE. For personal use only; all rights reserved.

the percentages of projects that were completed on budget or under cost and schedule performance in DB building projects. The prac-
budget (79%). This finding shows that DB delivery has less impact tical implications of this study’s findings are that owners should
on building projects in terms of cost overruns. It differs from DBB consider the advantages of DB delivery in terms of fewer change
building project findings, in which a higher number of projects orders and no impact on schedule when developing new projects.
(42%) have cost overruns due to change orders (Ibbs 2012). However, it should be noted that change orders need to be con-
The third major finding of this study was that change orders do trolled on large DB building projects so that they have no effect
not have a significant impact on schedule overruns in DB building on cost and schedule performance. It was found that large DB proj-
projects. Average schedule overruns for the entire data set of ects tend to have more change orders when compared with small
DB building projects were found to be a negative 1.4%, which DB projects. The authors recommend conducting a similar study on
is impressive. Additionally, when change orders in projects with highway and infrastructure projects. Further, the authors recom-
schedule overruns were compared with those in projects with no mend conducting studies to determine the various types of change
schedule overruns, no significant difference was found. This shows orders in DB building projects, as well as to determine which major
that change orders have no impact on schedule performance in DB change orders affect DB cost and schedule performance.
building projects, which is exactly opposite to what was found for
DBB building projects in the studies by Shrestha et al. (2018) and
Shrestha and Zeleke (2018). The authors found that, in DBB ren- References
ovation and new school building projects, change orders have sig-
nificantly detrimental effects on schedule overruns. However, in
DB building projects, this is not the case. Therefore, it can be as- Works Cited
sumed that, even when there are change orders in DB projects, the Alnuaimi, A. S., R. A. Taha, M. Al Mohsin, and A. S. Al-Harthi. 2010.
design-builders manage the changes as they phase from design to “Causes, effects, benefits, and remedies of change orders on public con-
construction. Because in the DB delivery method design and con- struction projects in Oman.” J. Constr. Eng. Manage. 136 (5): 615–622.
struction are carried out by one entity, there is flexibility in man- https://doi.org/10.1061/(ASCE)CO.1943-7862.0000154.
aging changes in such a way that they have no effect on project Anastasopoulos, P. C., S. Labi, A. Bhargava, C. Bordat, and F. L.
completion time. Mannering. 2010. “Frequency of change orders in highway construc-
The final finding of this study was a strong and significant pos- tion using alternate count-data modeling methods.” J. Constr. Eng.
Manage. 136 (8): 886–893. https://doi.org/10.1061/(ASCE)CO.1943
itive correlation between change order numbers and total contract
-7862.0000198.
costs in DB building projects. The results show that change orders
Andersen, E. S., K. V. Grude, and T. Haug. 2004. Goal directed project
increase as project size increases. Therefore, a large DB building management: Selective techniques and strategies. 3rd ed. London:
project owner and design-builder must consider an appropriate Konan Page.
change order management system in order to reduce impacts on Barrie, D. S., and B. C. Paulson. 1992. Professional construction manage-
costs and schedules. This finding is similar to what was found ment: Including CM, design-consruct, and general contracting.
in DBB building renovation projects (Shrestha and Haileab 2018) New York: McGraw Hill.
and transportation projects (Hinze et al. 1992; Anastasopoulos et al. Bartlett, J. 2018. “The t-test and robustness to non-normality.” Accessed
2010). It shows that the change management process is very im- June 10, 2018. https://thestatsgeek.com/2013/09/28/the-t-test-and
portant in large DB and DBB projects because both have high num- -robustness-to-non-normality/.
bers of change orders. Contract administrators of large DB and Civitello, A. M. 1987. Contractor’s guide to change orders. Englewood
DBB projects need to be vigilant during the change management Cliffs, CA: Prentice-Hall.
process so that change orders will not have ripple effects, creating DBIA (Design Build Institute of America). 2018. “Delivery system study:
disputes and litigation between project participants. Construction Industry Institute (CEE)/Penn State.” Accessed November
14, 2018. https://dbia.org/wp-content/uploads/2018/05/Research-Cii
-Penn-State-Study.pdf.
Devries, M. J. 2018. “How to deal with the ‘ripple effect’ or ‘cumulative
Conclusions impact’ of change orders: Best practices construction laws.” Accessed
December 27, 2018. https://www.bestpracticesconstructionlaw.com
Change orders, their impact on cost and schedule performance, and /articles/project-management/page/3/.
their correlation with project size, especially in DB building proj- Fathi, M., and P. P. Shrestha. 2018. “Performance comparison of design-
ects, were examined comprehensively in this study. Due to a lack of build projects for highways and buildings.” In Proc., Construction
literature on change orders in DB building projects, the findings Research Congress 2018, 139–149. Reston, VA: ASCE.
here have immense importance for owners and design-builders Frame, J. D. 2003. Managing projects in organizations: How to make
who have recently started using DB delivery . One finding related the best use of time, techniques, and people. 3rd ed. San Francisco:
to the relationship between change orders and project size is that Jossey-Bass.

© ASCE 04519010-8 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2019, 11(3): 04519010


Günhan, S., D. Arditi, and J. Doyle. 2007. “Avoiding change orders in Mahamid, I., A. Bruland, and N. Dmaidi. 2012. “Causes of delay in road
public school construction.” J. Prof. Issues Eng. Educ. Pract. 133 (1): construction projects.” J. Manage. Eng. 28 (3): 300–310. https://doi.org
67–73. https://doi.org/10.1061/(ASCE)1052-3928(2007)133:1(67). /10.1061/(ASCE)ME.1943-5479.0000096.
Halligan, D. W., L. A. Demsetz, J. D. Brown, and C. B. Pace. 1994. “Ac- Moselhi, O., I. Assem, and K. El-Rayes. 2005. “Change order impact on
tion-response model and loss of productivity in construction.” J. Constr. labor productivity.” J. Constr. Eng. Manage. 131 (3): 354–359. https://
Engineer. Manage. 120 (1): 47–64. https://doi.org/10.1061/(ASCE) doi.org/10.1061/(ASCE)0733-9364(2005)131:3(354).
0733-9364(1994)120:1(47). Nassar, K. M., W. M. Nassar, and M. Y. Hegab. 2005. “Evaluating cost
Han, S., S. Lee, and F. Pena-Mora. 2012. “Identification and quantification overruns of asphalt paving project using statistical process control
of non-value-adding effort from errors and changes in design and con- methods.” J. Constr. Engineer. Manage. 131 (11): 1173–1178.
struction projects.” J. Constr. Engineer. Manage. 138 (1): 98–109. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:11(1173).
https://doi.org/10.1061/(ASCE)CO.1943-7862.0000406. Ndihokubwayo, R., and T. C. Haupt. 2008. “Uncovering the origins of
Hanna, A. S., R. Camlic, P. A. Peterson, and E. V. Nordheim. 2002. variation orders.” In Proc., 5th Post Graduate Conf. on Construction
“Quantitative definition of projects impacted by change orders.” Industry Development. Port Louis, Mauritius: Construction Industry
J. Constr. Eng. Manage. 128 (1): 57–64. https://doi.org/10.1061 Development Board.
Downloaded from ascelibrary.org by Nottingham Trent University on 08/07/19. Copyright ASCE. For personal use only; all rights reserved.

/(ASCE)0733-9364(2002)128:1(57). Oglesby, C. H., H. W. Parker, and G. A. Howell. 1989. Productivity im-


Hanna, A. S., and M. Gunduz. 2004. “Impact of change orders on small provement in construction. New York: McGraw Hill.
labor-intensive projects.” J. Constr. Eng. Manage. 130 (5): 726–733. Perkins, R. A. 2010. “Sources of changes in design-build contracts for
https://doi.org/10.1061/(ASCE)0733-9364(2004)130:5(726). a governmental owner.” J. Constr. Eng. Manage. 135 (7): 588–593.
Hanna, A. S., J. S. Russell, T. W. Gotzion, and E. V. Nordheim. 1999a. https://doi.org/10.1061/(ASCE)0733-9364(2009)135:7(588).
“Impact of change orders on labor efficiency for mechanical construc- Rojas, E. M., and I. Kell. 2008. “Comparative analysis of project delivery
tion.” J. Constr. Eng. Manage. 125 (3): 176–184. https://doi.org/10 systems cost performance in Pacific Northwest public schools.”
.1061/(ASCE)0733-9364(1999)125:3(176). J. Constr. Eng. Manage. 134 (6): 387–397. https://doi.org/10.1061
Hanna, A. S., J. S. Russell, E. V. Nordheim, and M. J. Bruggink. 1999b. /(ASCE)0733-9364(2008)134:6(387).
“Impact of change orders on labor efficiency for electrical construc- RS Mean Cost Guide. 2018. “Historical cost indexes.” Accessed March 15,
tion.” J. Constr. Eng. Manage. 125 (4): 224–232. https://doi.org/10 2018. https://www.rsmeansonline.com/references/unit/refpdf/hci.pdf.
.1061/(ASCE)0733-9364(1999)125:4(224). Scott, R. D. 1999. “Change order protection.” Reeves J. 79 (3): 38.
Hinze, J., G. Selstead, and J. P. Mahoney. 1992. “Cost overruns on State of Serag, E., A. Oloufa, L. Malone, and E. Radwan. 2010. “Model for quan-
Washington construction Contracts.” Transp. Res. Rec. 1351: 87–93. tifying the impact of change orders on project cost for U.S. roadwork
Ibbs, W. 1997. “Quantitative impacts of project change: Size issues.” construction.” J. Constr. Eng. Manage. 136 (9): 1015–1027. https://doi
J. Constr. Eng. Manage. 123 (3): 308–311. https://doi.org/10.1061 .org/10.1061/(ASCE)CO.1943-7862.0000206.
/(ASCE)0733-9364(1997)123:3(308). Shrestha, P. P., and J. Fernane. 2017. “Performance of design-build and
design-bid-build projects for public universities.” J. Constr. Eng. Man-
Ibbs, W. 2005. “Impact of change’s timing on labor productivity.” J. Constr.
age. 143 (3): 0401610. https://doi.org/10.1061/(ASCE)CO.1943-7862
Eng. Manage. 131 (11): 1219–1223. https://doi.org/10.1061/(ASCE)
.0001241.
0733-9364(2005)131:11(1219).
Shrestha, P. P., K. K. Shrestha, and H. Zeleke. 2018. “Probability of change
Ibbs, W. 2008. “Impact of change’s timing on labor productivity.” J. Constr.
orders and the effect on cost and schedule for new public school build-
Eng. Manage. 131 (11): 1219–1223. https://doi.org/10.1061/(ASCE)
ings.” J. Constr. Archit. Manage. https://doi.org/10.1108/ECAM-01
0733-9364(2005)131:11(1219).
-2018-0017.
Ibbs, W. 2012. “Construction change: Likelihood, severity, and impact on
Shrestha, P. P., and H. Zeleke. 2018. “Effect of change orders on cost and
productivity.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 4 (3): 67–73.
schedule overruns of school building renovation projects.” J. Leg. Aff.
https://doi.org/10.1061/(ASCE)LA.1943-4170.0000089.
Dispute Resolut. Des. Constr. 10 (4): 04518018. https://doi.org/10.1061
Ibbs, W., L. D. Nguyen, and S. Lee. 2007. “Quantified impacts of project /(ASCE)LA.1943-4170.0000271.
change.” J. Prof. Issues Eng. Educ. Pract. 133 (1): 45–52. https://doi Ssegawa, J. K., K. M. Mfolwe, B. Makuke, and B. Kutua. 2002. “Construc-
.org/10.1061/(ASCE)1052-3928(2007)133:1(45). tion variations: A scourge or a necessity?” In Proc., 1st Int. Conf. of CIB
Jackson, B. J. 2004. Construction management JumpStart. 2nd ed. W107, 87–96. Cape Town.
San Francisco: SYBEX. Stare, A. 2010. “Comprehensive management of project changes.” Econ.
Jawad, R. S., R. Abdulkader, and A. A. A. Ali. 2009. “Variation orders in Bus. Rev. Cent. South-East. Eur. 12 (3): 195.
construction projects.” J. Eng. Appl. Sci. 4 (3): 170–176. Statistics Solutions. 2018. “Using chi-square statistic in research.” Ac-
Konchar, M., and V. Sanvido. 1998. “Comparison of U.S. project delivery cessed November 5, 2018. https://www.statisticssolutions.com/using
systems.” J. Constr. Eng. Manage. 124 (6): 435–444. https://doi.org/10 -chi-square-statistic-in-research/.
.1061/(ASCE)0733-9364(1998)124:6(435). Stat Trek. 2018. “Chi-square goodness of fit test.” Accessed June 6, 2018.
Laerd Statistics. 2018a. “Independent t-test using SPSS statistics.” http://stattrek.com/chi-square-test/goodness-of-fit.aspx?Tutorial=AP.
Accessed June 8, 2018. https://statistics.laerd.com/spss-tutorials Sun, M., and X. Meng. 2009. “Taxonomy for change causes and effects in
/independent-t-test-using-spss-statistics.php. construction projects.” Int. J. Pro. Manage. 27 (6): 560–572. https://doi
Laerd Statistics. 2018b. “Pearson’s product-moment correlation using .org/10.1016/j.ijproman.2008.10.005.
SPSS statistics.” Accessed June 8, 2018. https://statistics.laerd.com/spss Thomas, H. R., and C. L. Napolitan. 1995. “Quantitative effects of
-tutorials/pearsons-product-moment-correlation-using-spss-statistics.php. construction changes on labor productivity.” J. Constr. Eng. Manage.
Lee, M. J., A. S. Hanna, and W. Y. Loh. 2004. “Decision tree approach 121 (3): 290–296. https://doi.org/10.1061/(ASCE)0733-9364(1995)
to classify and quantify cumulative impact of change orders on produc- 121:3(290).
tivity.” J. Comput. Civ. Eng. 18 (2): 132–144. https://doi.org/10.1061 Wolfram MathWorld. 2018. “Outlier.” Accessed June 6, 2018. http://
/(ASCE)0887-3801(2004)18:2(132). mathworld.wolfram.com/Outlier.html.
Lee, S., F. Peña-Mora, and M. Park. 2005. “Quality and change manage- Wysocki, R. K., and R. McGary. 2003. Effective project management:
ment model for large scale concurrent design and construction projects.” Traditional, adaptive, extreme. 3rd ed. New York: Wiley.
J. Constr. Eng. Manage. 131 (8): 890–902. https://doi.org/10.1061 Yitmen, I., and E. Soujeri. 2010. “An artificial neural network model for
/(ASCE)0733-9364(2005)131:8(890). estimating the influence of change orders on project performance and
Leonard, C. A. 1988. “The effects of change orders on productivity.” dispute resolution.” In Proc., Int. Conf. on Computing in Civil and
Master’s thesis, Building, Civil and Environmental Engineering, Building Engineer. Nottingham, UK: Nottingham University Press.
Concordia Univ. Young, T. L. 2000. Successful project management. London: Kogan Page.

© ASCE 04519010-9 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2019, 11(3): 04519010

You might also like