PRESUPUESTO DE OBRA

PROYECTO : EDIFICIO MULTIFAMILIAR DE 5 NIVELES "GRUPO 1" - AREQUIPA, AREQUIPA AREQUIPA


ETAPA 1.0 : PRESUPUESTO: EDIFICIO MULTIFAMILIAR G1
PROPIETARIO : CONSTRUCTORA G1
UBICACION : DPTO:AREQUIPA PROV:AREQUIPA DIST:AREQUIPA
FECHA PROYECTO : 18/09/2023
Item Descripción Unid. Cant. Precio Parcial Sub Total
1.0 PRESUPUESTO: EDIFICIO MULTIFAMILIAR G1 1,470,630.97
OE.2 ESTRUCTURAS. 1,470,630.97
OE.2.2 OBRAS DE CONCRETO SIMPLE 53,010.54
OE.2.2.1 SUBZAPATAS Y SUBCIMIENTOS 32,676.07
OE.2.2.1.1 SUBCIMIENTO CONCRETO f'c=100 kg/cm2 + 30% PIEDRA und 97.43 335.38 32,676.07
MEDIANA
OE.2.2.2 CIMIENTOS CORRIDOS 10,758.99
OE.2.2.2.1 CIMIENTOS CORRIDOS CONCRETO f'c=140 kg/cm2 1.10 + m³ 32.08 335.38 10,758.99
30% Piedra Mediana
OE.2.2.3 FALSO PISO 9,575.48
OE.2.2.3.1 FALSO PISO DE 2" F'C=210 KG/CM2 m² 28.14 340.28 9,575.48
OE.2.3 OBRAS DE CONCRETO ARMADO 1,417,620.43
OE.2.3.2 ZAPATAS 63,523.02
OE.2.3.2.1 CONCRETO PREMEZCLADO f´c=210kg/cm2 ZAPATAS m³ 70.91 380.05 26,949.35
OE.2.3.2.2 ENCOFRADO Y DESENCOFRADO NORMAL ZAPATAS m² 122.42 65.02 7,959.75
OE.2.3.2.3 ACERO CORR. ZAPATAS F'Y 4200 KG/CM2 G-60 kg 4,195.59 6.82 28,613.92
OE.2.3.3 VIGAS DE CIMENTACIÓN 22,583.49
OE.2.3.3.1 CONCRETO PREMEZCLADO f'c=210 kg/cm2 EN VIGAS DE m³ 9.10 385.58 3,508.78
CIMENTACION
OE.2.3.3.2 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE m² 87.19 75.27 6,562.79
CIMENTACION
OE.2.3.3.3 ACERO CORR. EN VIGAS DE CIMENTACION F'Y 4200 kg 1,795.11 6.97 12,511.92
KG/CM2 G-60
OE.2.3.4 LOSAS DE CIMENTACIÓN 2,319.97
OE.2.3.4.1 CONCRETO PREMEZCLADO f'c=210 kg/cm2 EN LOSA DE m³ 2.08 375.17 780.35
CIMENTACION
OE.2.3.4.2 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSA DE m² 4.74 70.00 331.80
CIMENTACION
OE.2.3.4.3 ACERO CORR. EN LOSA DE CIMENTACION F'Y 4200 kg 177.10 6.82 1,207.82
KG/CM2 G-60
OE.2.3.6 MUROS REFORZADOS 258,721.65
OE.2.3.6.1 MUROS DE CONCRETO F'C=210 KG/CM2 91,062.25
OE.2.3.6.1.1 CONCRETO PREMEZCLADO f'c=210 kg/cm2 EN MUROS m³ 48.34 413.97 20,011.31
OE.2.3.6.1.2 ENCOFRADO Y DESENCOFRADO NORMAL EN MUROS m² 424.14 68.34 28,985.73
OE.2.3.6.1.3 ACERO CORR. MUROS F'Y 4200 KG/CM2 G-60 kg 6,167.92 6.82 42,065.21
OE.2.3.6.2 PLACAS REFORZADOS F'C=210KG/CM2 167,659.40
OE.2.3.6.2.1 CONCRETO PREMEZCLADO f'c=210 kg/cm2 PLACAS m³ 82.48 414.20 34,163.22
OE.2.3.6.2.2 ENCOFRADO Y DESENCOFRADO NORMAL PLACAS m² 820.26 75.24 61,716.36
OE.2.3.6.2.3 ACERO CORR. PLACAS F'Y 4200 KG/CM2 G-60 kg 10,524.90 6.82 71,779.82
OE.2.3.7 COLUMNAS 181,915.59
OE.2.3.7.1 CONCRETO PREMEZCLADO f'c=210 kg/cm2 EN m³ 78.48 431.35 33,852.35
COLUMNAS
OE.2.3.7.2 ENCOFRADO Y DESENCOFRADO NORMAL EN m² 750.49 78.58 58,973.50
COLUMNAS
OE.2.3.7.3 ACERO CORR. COLUMNAS F'Y 4200 KG/CM2 G-60 kg 13,198.48 6.75 89,089.74
OE.2.3.8 VIGAS Hmax=0.6m 433,666.95
OE.2.3.8.1 CONCRETO PREMEZCLADO f'c=210 kg/cm2 EN VIGAS m³ 217.01 373.60 81,074.94
OE.2.3.8.2 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m² 1,468.46 79.84 117,241.85
OE.2.3.8.3 ACERO CORR. VIGAS F'Y 4200 KG/CM2 G-60 kg 34,866.69 6.75 235,350.16
OE.2.3.7 LOSAS MACIZAS 21,673.65
OE.2.3.7.1 CONCRETO PREMEZCLADO f'c=210 kg/cm2 LOSAS m³ 16.87 357.25 6,026.81
MACIZAS
OE.2.3.7.2 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS m² 114.36 67.14 7,678.13
MACIZAS
OE.2.3.7.3 ACERO CORR. LOSA ALIGERADA F'Y 4200 KG/CM2 G-60 kg 1,180.55 6.75 7,968.71
OE.2.3.9.2 LOSAS ALIGERADAS CONVENCIONALES Hmax=0.25m 347,478.56
OE.2.3.9.2.1 CONCRETO PREMEZCLADO f'c=210 kg/cm2 EN LOSA m³ 192.72 380.05 73,243.24
ALIGERADA

Gracias por su compra


Item Descripción Unid. Cant. Precio Parcial Sub Total
OE.2.3.9.2.2 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSA m² 1,990.99 69.86 139,090.56
ALIGERADA
OE.2.3.9.2.3 LADRILLO HUECO DE ARCILLA 15 x 30 x 30 cm und 16,007.00 3.77 60,346.39
OE.2.3.9.2.4 ACERO CORR. LOSA ALIGERADA F'Y 4200 KG/CM2 G-60 kg 11,081.24 6.75 74,798.37
OE.2.3.11 CAJA DE ASCENSORES Y SIMILARES 58,190.53
OE.2.3.11.1 CONCRETO PREMEZCLADO f'c=210 kg/cm2 EN CAJA DE m³ 27.14 375.17 10,182.11
ASCENSOR
OE.2.3.11.2 ENCOFRADO Y DESENCOFRADO NORMAL EN CAJA DE m² 204.82 83.96 17,196.69
ASCENSORES
OE.2.3.11.3 ACERO CORR. CAJAS DE ASCENSOR F'Y 4200 KG/CM2 G- kg 4,564.70 6.75 30,811.73
60
OE.2.3.12 CISTERNAS SUBTERRÁNEAS 27,547.02
OE.2.3.12.1 CONCRETO PREMEZCLADO f'c=210 kg/cm2 EN CISTERNA m³ 20.01 424.78 8,499.85
OE.2.3.12.2 ENCOFRADO Y DESENCOFRADO NORMAL EN CISTERNA m² 145.22 64.33 9,342.00
OE.2.3.12.3 ACERO CORR. CISTERNA F'Y 4200 KG/CM2 G-60 kg 1,470.48 6.60 9,705.17

Costo Directo 1,470,630.97


Gastos Generales 9.7512906% 143,405.50
Utilidad 10.00% 147,063.10
Parcial 1,761,099.57
I.G.V. 18.00% 316,997.92
TOTAL : 2,078,097.49

[Son: dos millones setenta y ocho mil noventa y siete Soles con cuarenta y nueve céntimos]