You are on page 1of 6

Proceedings of the 2011 International Conference on Power Engineering, Energy and Electrical Drives Torremolinos (Málaga), Spain.

Torremolinos (Málaga), Spain. May 2011

Risk Analysis of Protection System’s Operation in


Distribution Networks with DG
S.A.M. Javadian, Student Member, IEEE M.-R. Haghifam, Senior Member, IEEE M. Massaeli
Islamic Azad University-Islamshahr Branch Tarbiat Modares University Artesh University
javadian@ieee.org haghifam@modares.ac.ir maryam_massaeli@hotmail.com

be happened because of DGs penetration, is introduced.


Abstract--Using Distributed Generation (DG) is an interesting Finally, suggested indexes are calculated for different cases
topic that has drawn attention of electrical engineers in recent and various capacities of DGs in order to performing risk
years. The presence of these generation units in distribution analysis.
systems, although has many advantages and benefits, has to be
applied after performing detailed studies and investigations due II. RECLOSER-FUSE MISS-COORDINATION PROBLEM
to their complexities in operation, control and protection of
network. One of the major effects of DGs is their effect on Fig. 1 and Fig. 2 show traditional recloser-fuse
protection operation of distribution networks. In this paper after coordination in a distribution system. Fig. 1 shows a fuse in
reviewing this influence, risk analysis of protection system’s the lateral feeder and a recloser which is located on the main
operation in a test distribution network according to various feeder. In order to have a correct operation, the fuse must be
locations and capacities of DGs has been performed. For this
purpose, three indexes for presenting the system’s risk has been coordinated with upstream recloser on the main feeder. The
introduced and calculated in different investigated cases. coordination philosophy here is that the fuse should only
operate for a permanent fault on the load feeder. For a
Index Terms--Distributed Generation; Distribution Network; temporary fault, recloser should disconnect the circuit with
Protection; Risk Analysis fast operation and give the fault a chance to clear. Only if the
fault is permanent, the fuse should be allowed to open. In this
I. INTRODUCTION way, the load feeder does not get disconnected for every
temporary fault. Recloser also provides back up to fuse
The presence of DGs in distribution networks, like many
through slow mode. Since temporary faults constitute 70% to
other technologies, has some disadvantages along with many
80% of faults occurring in distribution system, this
advantages it can have [2]-[9]. Among advantages of DGs
arrangement improves reliability while decreasing the
one can mention improvement in power quality and reliability
maintenance cost. Fig. 2 shows the recloser-fuse coordinated
and reduction of loss, meanwhile using DGs leads to
graph for all fault currents within Ifmin and Ifmax. This is called
complexity in operation, control and protection of distribution
the coordination range. Therefore, as long as the fault current
systems [1], [2]. Injection of DGs currents to a distribution
values for faults on lateral feeder are within the coordination
network results in losing radial configuration and
range, the recloser-fuse coordination is considered to be
consequently losing the existing coordination among
acceptable. It can be seen from Fig. 2 that fast characteristic
protection devices [2]-[7]. The extent at which protection
of the recloser lies below the MM characteristics of fuse
coordination is affected depends on the size, type and location
between Ifmin and Ifmax . Therefore, in coordination range the
of DG, in some cases coordination is lost completely and in
recloser operates in less time than the time sufficient to
other cases the coordination range diminishes [4], [5].
damage the fuse.
Regarding the influence of DGs on protection of distribution
Recloser
systems, so many researches have been performed so far as
well as some researches concerning how to tackle the Fuse
B1
resultant problems of applying DGs [1], [8]-[12].
The field of risk analysis has assumed increasing Fig. 1. Recloser-Fuse Arrangement
importance in recent years given the concern by both If Min If Max.
DIgSILENT

Coordination
engineers and scientists in most technical issues. It is one of 1000
Range

the powerful tools for solving engineering problems such as [s]

optimization ones. [13] 10

In this paper after reviewing the effect of connecting Recloser Slow Curve

distributed generation units to distribution network, a new Recloser Fast Curve


method for risk analysis of protection system’s operation is 0.1

Fuse TC
proposed. In the suggested method, three indexes for
Fuse MM
presenting the system’s risk are introduced. Then, a test 0.001
0.40 kV 100 1000 [pri.A] 10000

distribution network for risk analysis, in which all kinds of


Cub_0\Recloser Cub_2\MM Fuse
Cub_2\Breacker

protection miss-coordination among protective devices could Fig. 2. Recloser-Fuse Coordination Range

978-1-4244-9843-7/11/$26.00 ©2011 IEEE


If the fault persists after the recloser closes following the For case 3, the same fault current flows through the
second fast operation, then the fault has to be a permanent recloser and the fuse. This seems that recloser and fuses can
one and hence fuse must operate to clear the fault. As shown coordinate properly. However, increasing the current will
in Fig. 2, the TC curve of the fuse is below the slow curve of result in changing the coordination range, and no longer will
recloser in coordination range. Therefore, for a permanent maintain the coordination protection [14].
fault, fuse will open before recloser operates in the slow At last, in case 4, both DG and fault location are upstream
mode. If the fuse fails to operate, recloser will back it up by of recloser and the fault current will flow to fuse directly and
operating in the slow mode and finally locking out [5]. the recloser will not detect anything. Fuse blowing will not
After connection of DG, Maximum and minimum fault occur in this case [14].
currents for a fault on the load feeder will change and for any As a result, only fuse blowing in case 1 will be investigated
fault on load feeder, fuse will see more current than the in this study.
recloser. In addition, as conventional protection, a temporary III. FUSE-FUSE MISS-COORDINATION PROBLEM
fault, occurring mostly at lateral feeder, should be
discriminated by the fast operation of recloser. However, this Fig. 4 and Fig. 5 show how fuse-fuse coordination is
conventional scheme may not be held when DG is connected traditionally done in a radial distribution system without DG.
at the end of the feeder. It is possible that this temporary fault Fig. 4 shows the arrangement of two fuses to be coordinated.
is cleared by the lateral fuse, and be changed to a permanent Coordination of fuse1 and fuse2 means for any fault on
fault. These undesirable operations of protective devices feederl, fuse l should operate before fuse2 is damaged. This
called “Fuse Blowing” and certainly decrease the system would be achieved if TC characteristic of fusel is below the
reliability. MM characteristics of fuse2 by a safe margin for any fault on
In order to clarify the consequence of injected current, feeder1. Fig. 5 shows the coordination graphs. It shows the
depending on placement of DG toward the recloser, four fuses are coordinated for all fault currents within Ifmin and
different cases are depicted in Fig. 3 and tabulated in table I. Ifmax. This is called the coordination range. Therefore, as long
In case 1, fault current seen by the fuse is summation of as the fault current values for faults on feederl are within
both fault currents from the substation and the DG. It coordination range, the fuses are coordinated. [5]
indicates that system problem will occur whenever both DG Fig. 6 shows a typical distribution network with several
source and fault position are located behind the recloser. This fuses. When there is no DG connected to the system, fuse-
is the case of fuse blowing above mentioned. With this pairs F1-F2, F2-F3, F3-F4 and F5-F6 will be coordinated with
situation, it is possible that the miss-coordination of recloser each other. After connection of DG1, DG2 and DG3 the
and fuse will happen [14]. following changes in the system will be forced: [5]
In case 2, DG and fault location are respectively after and
before the recloser. In this case, reverse current flows through S
the recloser and fuse should operate first. However, it is F2 F1
possible that the recloser at the fast mode will operate faster
and meaninglessly cause the electricity interruption at the rear Fig. 4. Fuse-Fuse Arrangement
circuit. However, since the rear circuit can be automatically Fuse1 TC
restored within only few cycles after the fuse has operated, it
Fuse2 MM
brings about only a momentary electricity interruption, which
may be negligible [14]. Ifmax
Fuse2 TC
DG2 DG1 Fuse1 MM
~ ~
G G

Substation Circuit
Recloser
Ifmin
Breaker

Fuse Fuse To main feeder

Fault2 Fault1

Fig. 5. Fuse-Fuse Coordination Range


Load(1) Load(2)
A
Fig. 3. Alternate Cases for Recloser-Fuse Miss-coordination B G
S
TABLE I F4 F5
ALTERNATE CASES FOR RECLOSER-FUSE MISS-COORDINATION F3 D DG3
C I
Case DG Unit Fault Location F2 H
DG2
1 DG 1 Fault 1 F F6
E
2 DG 1 Fault 2 F1
DG1
3 DG 2 Fault 1 F7
4 DG 2 Fault 2 Fig. 6. A Typical Distribution Network with Several Fuses
1. Minimum and maximum fault current values for a fault will be interrupted as long as repair or switching times,
in section HI will increase from source side due to all depending on the location of the considered component,
upstream DGs. So, F5 and F6 will sense greater fault the location of the failed component, and the type of fault.
current than before, but will never have reverse fault Taking these interruption durations into account, the outage
currents. [5] duration for the load points connecting to the interrupted
2. For a fault in section CD, F3 and F4 will see downstream component is derived. So, the outage information of load
fault current, while for a fault in section AB, these fuses points can be directly calculated from the statistics of system
will see upstream fault current. The value of fault current components. Since in this study, both temporary and
seen by these fuses for a given fault in section AB or CD permanent faults, each of these three statistics should be
will be same. F1-F2 will also experience the same divided into two groups, i.e. permanent and temporary. So, the
situation for upstream and downstream faults. [5] average failure rate of each system component can be written
3. For a fault in section DE, F2 will see more fault current as (1).
than F3, while for a fault in section BC, F3 will see more i  P ,i  T ,i (1)
fault current than F2. In first case, fault currents will be
downstream, while in the second case, fault currents will Where:
be upstream. [5] λP,i average failure rate of permanent faults;
In case of (1) above, the fuse coordination is not likely to λT,i average failure rate of temporary faults;
be affected if fuses can still coordinate for increased fault Each of them gives its own average outage time. In case of
currents. This is because fuses still see only downstream permanent fault occurrence, rP,i is the repair time for
faults. The only change in the coordination graph of F5-F6 permanent faults, while rT,i is just few seconds in case of
will be the coordination range, since minimum and maximum temporary fault. Hence, average annual outage time for all
fault currents will change. If the increased fault current is so types of faults can be calculated as follows:
substantial, that the coordination range exceeds the extent of U P ,i  P ,i  rP ,i (2)
the fuse curves, then, of course, these fuses will no longer U T ,i  T ,i  rT ,i (3)
coordinate. [5]
Finally, the total average annual outage time and average
In case (2), there is a clear conflict. One of the most
outage time can be written using (4) and (5) respectively.
important features of a protection scheme is to clear only the
faulted part of the system. Following this requirement, for a U i  U P ,i  U T ,i (4)
fault in section CD, F3 should operate before F4, but for a ri  U i / i (5)
fault in section AB, F4 should operate before F3. Since both It should be considered that the repair time for temporary
fuses see the same fault current for a given upstream or faults is very short so that without protection miss-
downstream fault, this requirement cannot be fulfilled. This coordination all above equations can be easily written with
will be true for fuses F1-F2 also for a fault on section EF and only permanent terms.
section CD. [5]
However, there is a margin for case (3). Fig. 7 shows the A. Risk Evaluation of Recloser-Fuse Miss-Coordination
characteristics of fuses F2 and F3 without considering DG. Recloser-fuse miss-coordination will make permanent
Now, for a downstream fault, F2 will see more current (IF2) interruption for some of system components in case of
than F3 (IF3). The difference between IF2 and IF3 depends on temporary faults. For instance, lateral feeders and
size and type of DG2. It can be seen that as long as IF2 is more transformers may be interrupted as long as the repair time of
than IF3, the coordination will never be lost, since F2 will fuse, used to replace the fuse blown from the miss-
always operate before F3 is damaged, which is required for a coordination. In this case, the average failure rate can be
downstream fault. For upstream faults, IF3 will be greater than calculated from (1). But, average interruption time for
IF2. In this case, it can be seen from Fig. 7, that if the temporary faults will increase to the repair time of fuse (rf,i).
difference in currents is more than the shown margin, F3 will
operate before F2 is damaged, i.e., coordination still holds. F2 TC
F3 TC
However, if the difference is less than the margin, F2 will be
For Downstream
damaged before F3 operates, i.e., coordination is lost. Thus F3 MM
Fault
for a substantial fault current injection from DG, coordination F2 MM IF3
IF2
can hold in such conditions. [5]
IV. RISK ANALYSIS PROCEDURE IF2

For each system component, three statistics are used to For Upstream
Fault
evaluate the system reliability, i.e. λ (average failure rate, IF3

f/yr), r (average outage time, hours), and U (average annual


outage time, hours/yr). In this study, λ is assumed to be Fig. 7. Coordination Margin with DG in Case of Different Fault Currents
through Fuses
resulted only from electricity faults. Each system component
Considering PHt and PLt for the probability of miss- V. RISK ANALYSIS IN THE TEST NETWORK
coordination for high and low impedance temporary faults In this paper, for performing the risk analysis of protection
respectively, the unavailability of temporary faults which are system’s operation the test network of Fig. 8 has been used.
changed to permanent ones due to protection miss- In the test network, after connection of DG1 and DG2, all
coordination can be derived from (6). kinds of previously described protection miss-coordination of
U T,i  (PT  λ T,i )  rf,i (6) fuse-fuse and recloser-fuse between protective devices of the
network can be happened.
It should be considered that in (6), it is assumed that rT,i is In the test network, the protection system consists of one
the same and equal to rf,i which is the repair time of fuse. This over-current relay, two reclosers, and five fuses which are
time is usually more than several minutes, so that the fault coordinated with each other according to protection graph of
can consider as a permanent fault. Fig. 9.
Fuses of the test network are installed in the beginning of
B. Risk Evaluation of Fuse-Fuse Miss-Coordination
sections B, C, F, H, and I. The two reclosers are installed in
Loss of fuse-fuse coordination causes a larger area to be
the beginning of the sections A and G. Also, the only over-
faced power outage. For example, when coordination of a
current relay of the network is installed in the beginning of
fuse and its upstream backup fuse lose, in case of a fault
the feeder (section A) to protect the whole network.
happening in the protection zone of the main fuse, the backup
In the test Network, before connection of DGs, because of
fuse will blow earlier than the main one. So, all electrical
the simplicity of the protection philosophy, the coordination
consumers which are connected to the protection zone of
of protective devices can be easily done. Now, assuming that
backup fuse will face power cut. But, if the protection
the protection miss-coordination can be happened with the
coordination remains, only the electrical consumers in the
probability of 0.01 in the test network before connection of
protection zone of the main fuse will lose the electricity.
DGs, the priviously introdused risk evaluation indexes are
Considering PHp and PLp for the probability of miss-
calculated and presented in table II.
coordination for high and low impedance permanent faults
For performing above calculations, parameters λ and U
respectively, the unavailability of permanent faults which
related to protection miss-coordination are calculated for
cause a bigger power outage due to protection miss-
every load points of the network firstly. Then, using
coordination can be derived from (7).
equations 8, 9, and 10, risk evaluation indexes are derived.
U P,i  (PP  λ P,i )  rp,i
~
(7) G
DG1

5
It should be considered that in (7), it is assumed that rP,i is A B C D E F G DG2

the same and equal to rp,i which is the repair time of

G
~
NET 1 2 3 4 7
permanent faults for equipment i. 6 8
I
H
C. Proposed Indexes for Risk Calculation 9 10
In this paper, three indexes for risk calculation have been
proposed which are Interruption Frequency Risk (IFR), Fig. 8. The Protection System’s Operation Risk Analysis Test Network
Interruption Duration Risk (IDR), and Energy Not Supplied 100000

Risk (ENSR). These indexes can be calculated from [s]

equations 8, 9, and 10 respectively.


1000

total number of customer interrubtions


because of protection miscoordination
IFR  10

total number of customers (8)


 ( PT T ,k  PP P,k ) N k
 Nk
0.1

sum of customer interrubtion durations


because of protection miss  coordination
0.001
20.00 kV 10 100 1000 10000 [pri.A] 100000

IDR  Fig. 9. Protection Coordination Graph in the Test Network


total number of customers (9)
TABLE II.

 (U T ,k  U P,k ) N k RISK ANALYSIS RESULTS IN TEST NETWORK BEFORE CONNECTING DGS
N k λLP 0.1 PLP 0.01
rf 0.5
IFR 0.0353
ENSR = total energy not supplied because of λLt 0.4 PLt 0.01 IDR 0.0327
protection miss-coordination (10) λHP 0.05 PHP 0.01
rp 5 ENSR 0.147
  La ,k (U T ,k  U P ,k ) λHt 0.2 PHt 0.01
A typical calculation procedure for calculation of λ and U after connection of both DGs and increasing their capacity
related to protection miss-coordination is presented in table without and with considering island operation of DGs.
III. The table presents the calculations for bus No. 4. In the According to these figures, it can be concluded that
table, the value of zero in each column related to probability increasing the capacity of DGs will increase the IDR and IFR
of miss-coordination means that fault happening in that of the network. Also, the islanding operation of DGs has not
section will not cause protection miss-coordination, or the any effect on these indexes. On the other hand, the ENSR
related protection miss-coordination will not affect the power index is very dependent to the island operation of DGs. As it
outage of that bus. For example, in the table, all values of can be seen from the simulation results, if the island operation
protection miss-coordination probabilities for faults on of DGs does not considered, the ENSR will be increased by
section A are zero. The reason is that there is no fuse installed increasing the capacity of DGs. But, by considering the island
on this section. So, all faults on this section cannot lose the operation, the protection system will have lower risk on
protection coordination among protective devices of the energy not supplied by increasing the capacity of DGs.
network. On the other hand, in table III, the value of Pp for The other conclusion that can be made from the simulation
permanents faults on sections C, D, and F equals zero because results is that DGs which are connected to the end of
these faults will blow the fuse of section B in case of distribution feeders have lower effect on the protection
protection miss-coordination and otherwise they will blow the system. For example, comparing Fig. 12 proves that DG2 has
fuse of section C. In both cases, all consumers connected to lower effect on ENSR than DG1. This fact is because of two
bus 4 will face power outage. So, this protection miss- main reasons; first, DG2 will have lower effect on short
coordination will not affect the risk of bus No. 4. It is obvious circuit currents in the network and consequently on the
that this protection miss-coordination has a great effect on protection coordination, and second, the protection miss-
risk indexes in bus 3. coordination made by DG2 will cause less power outage in
For analyzing the effect of DG on the risk of protection the network.
system’s operation in the test network, two diesel generators
has been considered for connecting to the network. As TABLE III.
mentioned above, connection of DG1 and DG2 can cause all TYPICAL RISK CALCULATION FOR BUS 4 OF THE TEST NETWORK
kinds of protection miss-coordination among protective Section λP λT rf rp PP PT λP×PP λT×PT UP UT
A 0.1 0.4 0.5 5 0 0 0 0 0 0
devices of the test network.
B 0.1 0.4 0.5 5 0 0.01 0 0.004 0 0.002
For performing risk analysis and investigating the effect of C 0.1 0.4 0.5 5 0 0.01 0 0.004 0 0.002
location and capacity of DGs on system’s risk, the D 0.1 0.4 0.5 5 0 0.01 0 0.004 0 0.002
calculations have been done 3 main steps. In the first step, E 0.1 0.4 0.5 5 0 0.01 0 0.004 0 0.002
only DG1 has been considered to be connected to the network F 0.1 0.4 0.5 5 0.01 0.01 0.001 0.004 0.005 0.002
G 0.1 0.4 0.5 5 0.01 0 0.001 0 0.005 0
and the risk indexes have been calculated for the network for H 0.1 0.4 0.5 5 0.01 0.01 0.001 0.004 0.005 0.002
various capacities of DG1. Then, in the second step, only I 0.1 0.4 0.5 5 0 0 0 0 0 0
DG2 has been considered to be connected to the network and Total for 4 N 100 L 0.5 0.003 0.024 0.015 0.012
the risk indexes have been calculated for the network for
various capacities of DG2. Finally in the last step, both DG1 0.5 0.6

and DG2 have been considered to be connected to the 0.4


0.5

network and the risk indexes have been calculated for the 0.3
0.4
ID R
IF R

0.3
network for various capacities of DG1 and DG2. 0.2
0.2
Also, in each step, in order to presenting the advantages of 0.1 0.1
connecting DGs to distribution networks, which will be 0 0

reached by islanding operation of DGs, risk indexes have 0 0.5 1 1.5 2 2.5 3 0 0.5 1 1.5 2 2.5 3

DG1 (MW) DG1(MW)


been calculating for two conditions; first, DGs cannot operate
in their island mode, and second, DGs have the permission to Fig. 10. IFR and IDR in the Test Network After Connection of DG1 and
Increasing Its Capacity (With and Without Island Operation of DG)
continue their operation after a short switching time for
isolation of occurred faults, and supply their neighbor 0.5 0.7

consumers locally. 0.4


0.6
0.5
Fig. 10 and Fig. 11 show the increscent of IFR and IDR in 0.3 0.4
ID R
IF R

the test network after connection of DG1 and DG2 and 0.2 0.3

increasing their capacity respectively. Also, Fig. 12 illustrates 0.1


0.2
0.1
the increscent of ENSR in the test network after connection of 0 0

DG1 and DG2 and increasing their capacity. 0 0.5 1 1.5 2 2.5 3 0 0.5 1 1.5 2 2.5 3

DG2 (MW)
Fig. 13 shows the increscent of IFR and IDR in the test DG2 (MW)

network after connection of both DGs and increasing their Fig. 11. IFR and IDR in the Test Network After Connection of DG2 and
Increasing Its Capacity (With and Without Island Operation of DG)
capacity. Also, Fig. 14 presents the ENSR in the test network
3 3.5 REFERENCES
2.5 3
2.5
[1] S. A. M. Javadian , M.-R. Haghifam, “Designing a New Protection
2 Without Islanding
Without Islanding System for Distribution Networks including DG,” The 9th IET
ENSR

ENSR
2
1.5
1.5 International conf. on Developments in Power System Protection, 17 -
1
1 20 March 2008, pp. 675-680.
With Islanding
0.5 0.5 [2] P. P. Barker, R. W. de Mello, “Determining the impact of distributed
With Islanding
0 0 generation on power systems: part1-radial distribution systems,” IEEE
0 0.5 1 1.5 2 2.5 3 0 0.5 1 1.5 2 2.5 3 Trans. Power Delivery, vol. 15, pp. 486–493, Apr. 2000.
DG1 (MW) DG2 (MW) [3] R. C. Dugan, T. E. McDermott, “Operating conflicts for Distributed
Generation interconnected with Utility Distribution Systems,” IEEE
Fig. 12. ENSR in the Test Network After Connection of DG1 (and DG2) and Industry Applications Magazines, 19-25, Mar/Apr. 2002.
Increasing Its Capacity (With and Without Island Operation of DG) [4] K. Kauhaniemi, L. Kumpulainen, “Impact of distributed generation on
the protection of distribution networks,” Developments in Power
System Protection, Eighth IEE International Conference , 5-8 April
1.5 1.5 2004, Vol.1, pp. 315 - 318.
[5] A. Girgis, S. Brahma, “Effect of Distributed Generation on Protective
1 1
Device Coordination in Distribution System,” Power Engineering,
IDR
IFR

0.5 0.5
LESCOPE'01. 2001 Large Engineering Systems Conference, 11-13
July 2001, pp. 115 – 119.
0
3
0
3
[6] M. T. Doyle, “Reviewing the Impacts of Distributed Generation on
2
2
3 2
2
3 Distribution System Protection,” Power Engineering Society Summer
1 1
0 0
1
0 0
1 Meeting, 2002 IEEE Vol.1, pp.103-105.
DG2(MW) DG1 (MW) DG2 (MW) DG1 (MW) [7] N. Hadjsaid, J. Canard, F. Dumas, “Dispersed generation impact on
Fig. 13. IFR and IDR in the Test Network After Connection of DG1and DG2 distribution networks,” IEEE Comput. Appl. Power, vol. 12, pp. 22–28,
and Increasing Their Capacity (With and Without Island Operation of DGs) Apr. 1999.
[8] S. Brahma, A. Girgis, “Microprocessor-Based Reclosing to Coordinate
Fuse and Recloser in a System with High Penetration of Distributed
ENSR (Without Islanding)

ENSR (With Islanding)

8 1 Generation,” IEEE PES Winter Meeting, 2002, Vol.1, pp. 453 – 458.
6
[9] S. Brahma, A. Girgis, “Development of Adaptive Protection Scheme
4 0.5
for Distribution Systems with High Penetration of Distributed
Generation,” IEEE Trans. Power Delivery, VOL. 19, NO. 1,
2
JANUARY 2004, 56-63.
0
3
0
3 [10] A. Farzanehrafat, S. A. M. Javadian, S. M. T. Bathaee, M.-R.
2
2
3 2
2
3
Haghifam, “Maintaining the Recloser-Fuse Coordination in
1 1
0 0
1
0 0
1 Distribution Systems in Presence of DG by Determining DG’s Size,”
DG2 (MW) DG1 (MW) DG2 (MW) DG1 (MW) The 9th IET International conf. on Developments in Power System
Fig. 14. ENSR in the Test Network After Connection of DG1and DG2 and Protection, 17 - 20 March 2008, pp. 124-129.
Increasing Their Capacity (With and Without Island Operation of DGs) [11] N. Rezaei, M.-R. Haghifam, “Protection scheme for a distribution
system with distributed generation using neural networks,”
VI. CONCLUSIONS International Journal of Electrical Power & Energy Systems, Volume
30, Issue 4, May 2008, pp. 235-241.
In this paper after reviewing the effect of connecting [12] S. A. M. Javadian, and M.-R. Haghifam, “Protection of Distribution
Networks in Presence of DG Using Distribution Automation System
distributed generation units to distribution network, a new Capabilities,” Proc. 2008 IEEE Power Engineering Society General
method for risk analysis of protection system’s operation has Meeting, 20-24 July 2008, pp. 1-6.
been proposed. In the suggested method, three indexes for [13] S. A. M. Javadian, and M.-R. Haghifam, “Optimal Placement of
protective Devices in Distribution Networks Based on Risk Analysis,”
presenting the system’s risk have been introduced. Then, a 2010 IEEE/PES T&D Latin America Conference, 8-10 Nov. 2010, pp.
test distribution network for risk analysis, in which all kinds 1-8.
of protection miss-coordination among protective devices [14] S. Chaitusaney, A. Yokoyama, “Reliability Analysis of Distribution
System with Distributed Generation Considering Loss of Protection
could be happened because of DGs penetration, has been coordination,” 9th International Conference on Probabilistic Methods
introduced. Finally, suggested indexes have been calculated Applied to Power Systems, June 11-15, 2006, pp. 1-8.
for different cases and various capacities of DGs in order to [15] M.-R. Haghifam, H. Falaghi, O. P. Malik, "Risk-based distributed
generation placement," IET Generation Transmission Distribution,
performing risk analysis. Simulation results show that 2008, 2, (2), pp. 252-260.
without islanding operation of DGs the protection system’s [16] S.A.M. Javadian, R. Tamizkar, M.-R.Haghifam, “A protection and
risk will increase after connection of DG while islanding reconfiguration scheme for distribution for distribution networks with
DG,” Proc. IEEE PowerTech 2009, 28 June – 2 July 2009, Bucharest,
operation has a great effect on risk indexes and can decrease Romania, pp. 1-8.
total risk of the system. Also, DGs which are connected to the [17] S.A.M. Javadian, M.-R. Haghifam, N. Rezaei “A Fault Location and
end of distribution feeders have lower influence on system’s Protection Scheme for Distribution Systems in presence of DG Using
MLP Neural Networks,” 2009 IEEE Power Engineering Society
risk and can result in better performance of protection system General Meeting, 26-30 July 2009, Calgary, Alberta, Canada, pp.1-8.
in comparison with DGs connected to the beginning of the
same feeder.

You might also like