Professional Documents
Culture Documents
Management Tools
Management Tools
For managing a construction project different management tools are used. Different bar
charts and softwares are used for effective competition of a project. By proper utilization of
these tools projects can be easily managed in construction industry. Critical Path Method
(CPM), Project Evaluation and Review Technique (PERT) are the mainly used methods for
construction project management.
CPM : CPM stands for “Critical Path Method”. In CPM, the whole project consists of a
number of clearly recognizable jobs or operations called activities. Activities are usually the
operations which take time to carry out, and on which resources are expended. CPM networks
are generally used for repetitive type projects or for those projects for which fairly accurate
estimate of time for completion of each activity can be made.
PERT : PERT stands for “Program Evaluation and Review Technique”. The method was
basically developed by the Navy Special Projects Office in co-operation with Booz, Allen and
Hamilton, a management consulting firm and Lockheed Missile system Division for evaluating
the feasibility of existing schedules on Polaris Missile program and for reporting progress.
PERT system is preferred for those projects or operations which are of non-repetitive nature
or for those projects in which precise time determination for various activities cannot be
made. In such projects, management cannot be guided by the past experience. They are
referred to as once through operations or project.
4. It encourages discipline.
13. Interfering Float : It is the difference between total float and free
float.
14. Critical Path : The events which have no float or slack are the
critical events (TE = TL). The path joining such critical event is
called the critical path.
15. Critical Activities : The activities lying on the critical path are
called critical activities. Critical activity has a zero float.
3.5 FORMATION OF NETWORK
The following steps are found to be useful in the development of a network for a proposed
project:
1. Objective.
2. Plan break down.
3. Sequencing.
4. Development.
5. Drawing.
6. Check.
7. Re draw and Introduce.
8. Number.
Objective : Objective specifies the task to be undertaken and policy of its execution. This
specification defines the project and determines the way in which it is to be carried out.
Plan Break Down : After establishing objective of the task, the planner has to adopt either
forward planning or backward planning to achieve the goal. This backward or forward
thinking will give a list of activities and events to be performed to achieve the task. To get
the list of activities we need to study the difficulties which are to be overcome and we need
to arrange proper facilities for facing the difficulties. We need to safeguard the facilities.
Sequencing : In the above step we got a list of activities which are to be done for the
completion of the project. In these activities similar activities are sub-grouped for easy
understanding and fast completion of the project.
Development : The activities listed above should be located on paper so that a visual effect of
movement along the time scale is obtained. Events should be located in such a way that they
represent initial picture of the relation amongst them. This relationship gives the details of
manpower, money, material and other resources required during a particular period of time.
The following points must be kept in view while locating the nodes :
Basic Rules
4. No activity can start until its tail end event has occurred.
5. Any arrow should represent singular situation.
6. Representation of the network should be such that every
activity is completed to reach the end objective.
7. All constrains and indeterminacies should be shown properly
on the network by use of appropriate dummies.
8. All constrains and indeterminacies should be shown properly
on the network by use of appropriate dummies.
9. Logic of network should always be maintained.
10. It is usual practice to show the time flow from left to right.
3.6 Calculates time on CPM network identifying critical activities, critical path, free float and total float.
Draw the Network diagram for a project based on the following data
B E 7
3
F
6
D
2 6
J
A E
B F K
1 3 5 8
L
C
G 7
4
Identify the critical path. Find the total duration of the Project. Drawing the Tabular form
sharing EST, LST, EFT, LFT and FLOAT.
Draw the CPM Network diagram for the following data
Activity Duration in Days
1–2 3
1-3 4
2-4 2
3-4 3
3-5 6
3-6 4
4-7 4
5-7 5
5-8 7
6-8 4
6-9 3
7-9 2
8-9 3
Draw the CPM Network diagram for the following data
Activity 1-2 1-3 1-4 2-5 3-6 3-7 4-7 5-6 5-8 6-9 7-9 8-10 9-11 10-11
Duration 8 9 8 4 6 7 5 4 8 4 6 6 9 7
Identify the critical path. Find the total duration of the project.
Draw the Tabular form showing EST, LST, EFT, LFTand FLOAT.
8 8 12 12 20 20
2 4 5 8 8 26 26
6
10
8 4
0 0 9 11 16 20 7 33
1 3 6 9 11
9 6 4 9
24 24 33
8
6
4 7
5
8 13 16 18
1 1-2 8 0 8 0 8 0 0
2 1-3 9 0 9 2 11 2 0
3 1-4 8 0 8 5 13 5 0
4 2-5 4 8 12 8 12 0 0
5 3-6 6 9 15 14 20 5 1
6 3-7 7 9 16 11 18 2 0
7 4-7 5 8 13 13 18 5 3
8 5-6 4 12 16 16 20 4 0
9 5-8 8 12 20 12 20 0 0
10 6- 9 4 16 20 20 24 4 2
11 7- 9 6 16 22 18 24 2 2
12 8 - 10 6 20 26 20 26 0 0
13 9 - 11 9 22 31 24 33 2 2
14 10 - 11 7 26 33 26 33 0 0
A project has eleven activities. The expected time of each activity is given below.
S.No. Activity Duration in Days
1. 1-2 4
2. 2-3 3
3. 2-4 5
4. 2-5 6
5. 3-6 4
6. 5-6 7
7. 5-7 8
8. 4-7 8
9. 6-8 5
10. 7-8 7
11. 8-9 9
Draw the project network and identify the critical path. Draw the
tabular form showing EST, LST, EFT, LFT and Float.
7 6 17 20
3 6
4
4 4 3 10 10 7 5 25 25 34
1 2 5 8 9
4 6 9
0 0 5 8 34
7
4 7
8
19 10 18 18
Critical Path : 1-2-5-7-8-9
Total Duration of the Project = 34 Days
S.No. Activity Duration EST EFT LST LFT Total Free
Float Float
1 1-2 4 0 4 0 4 0 0
2 2-3 3 4 7 13 16 9 0
3 2-4 5 4 9 5 10 1 0
4 2-5 6 4 10 4 10 0 0
5 3-6 4 7 11 16 20 9 6
6 5-6 7 10 17 13 20 3 0
7 5-7 8 10 18 10 18 0 0
8 4-7 8 9 17 10 18 1 1
9 6-8 5 17 22 20 25 3 3
10 7-8 7 18 25 18 25 0 0
11 8-9 9 25 34 25 34 0 0
The table given below represents the activities of the network for construction of a rolling
mill. The expected duration of the activities for the network also given.
(b) Find the critical path and time of completion of the project
(c) Prepare time schedule indicate EST, LST, EFT, LFT and Float
Activity 0-1 1-2 2-3 2-4 2-7 3-4 3-7 4-5 4-6 5-6 6-7 7-8
Duration 6 12 10 36 6 8 10 14 16 8 12 8
1 0-1 6 0 6 0 6 0 0
2 1-2 12 6 18 6 18 0 0
3 2-3 10 18 28 36 46 18 0
4 2-4 36 18 54 18 54 0 0
5 2-7 6 18 24 82 88 64 64
6 3-4 8 28 36 46 54 18 18
7 3-7 10 28 38 78 88 50 50
8 4-5 14 54 68 54 68 0 0
9 4-6 16 54 70 60 76 6 6
10 5-6 8 68 76 68 76 0 0
11 6-7 12 76 88 76 88 0 0
12 7-8 8 88 96 88 96 0 0
The critical path method is a project management tool developed in the U.S. in 1957. CPM
may not be appropriate for all projects. There are some limitations for CPM which we need
to check. The major limitations are given below.
1. CPM is not suitable for the projects which cannot be broken into
discrete activities with known completion times. For example, on a
new project, activity durations may be hard to estimate.
2. Some comments say that it takes too much time to identify all
activities and inter relate them to get multiple project paths. This
cases user frustration throughout the project.
3. CPM stops working in practical situations in which employees are
often re-allocated across projects and activities. This
Only one time estimate is required for Three Time Estimate (in the form of
each activity. Pessimistic time, Optimistic Time and
Most likely time) for each activity.
Time and cost both are controlling Time is only the controlling factor and
factors. There is an optimum duration the cost is assumed proportional to the
of the project at which the project cost project duration.
is minimum and this can be obtained by
crashing the network.
Critical events must have zero slack. Critical events may be positive/Zero/
negative depending upon the project
scheduled completion time.