Activity Start Date End Date Duration Status

1-Oct 3-Oct 3 Pending


Drilling Phase 1
4-Oct 5-Oct 2 Pending
Casing
5-Oct 5-Oct 1 Pending
Cementation
6-Oct 6-Oct 1 Pending
Wait on Cement
7-Oct 11-Oct 5 Pending
Drilling Phase 2
12-Oct 14-Oct 3 Pending
Coring
15-Oct 17-Oct 3 Pending
Logging
18-Oct 19-Oct 2 Pending
Conditioning
19-Oct 21-Oct 3 Pending
Logging
22-Oct 23-Oct 2 Pending
Casing
24-Oct 25-Oct 2 Pending
Cementation
25-Oct 25-Oct 1 Pending
Wait on Cement
26-Oct 28-Oct 3 Pending
Well Testing
29-Oct 30-Oct 2 Pending
Perforation
31-Oct 5-Nov 6 Pending
Well Production

https://www.youtube.com/watch?v=kpLnxV3a1bE
1-Oct

2-Oct

3-Oct

4-Oct

5-Oct

6-Oct

7-Oct

8-Oct

9-Oct

10-Oct

11-Oct

12-Oct

13-Oct

14-Oct

15-Oct

16-Oct
PROJECT SCHEDULE-PLANNING (Ghantt Cha
17-Oct

18-Oct

19-Oct
Ghantt Chart)

20-Oct

21-Oct

22-Oct

23-Oct

24-Oct

25-Oct

26-Oct

27-Oct

28-Oct

29-Oct

30-Oct

31-Oct

1-Nov
2-Nov

3-Nov

4-Nov

5-Nov
Steps
1 Date format in-dd-mm Format for all the dates
2 Duration= (Start-End date)=+1
3 Status Formula= IF(AND(G$3>=$C4,G$3<=$D4)$F4,"")
4 Need to put $ sign prior to Row/Colum which will be Freeze. (Not Changing)
5 Home-Conditional Formatting-New Rule-Format only cells that contain -equal to-Completed-Fill effects
6 New Rule-Format only cells that contain -equal to-Pending-Fill Effects-
7 Data Validation-Setting-Allow list- Source Completed,Pending
8 Format-customs cells-General- ;;;
9 Raw Height-25, View-Remove Gridlines-Text alignment-center-centure
eted-Fill effects
Drilling Phase 1
Casing
Cementation
Wait on Cement
Drilling Phase 2
Coring
Logging
Conditioning
Logging
Casing
Cementation
Wait on Cement
Well Testing
Perforation
Well Production