Activity ID Activity Name Duration Quantity Unit Crew Description Productivity No of crews Total man days

Activity ID Activity Name Duration Quantity Unit Crew Description Productivity No of crews Total man days
Typical Floor
Concrete
Carpenter 99
CNF01CN27 Slab Formwork 6 1,486 m² 15 17
Helper 99
Steel Fixer 830
CNF01CN30 Slab Rebar 6 83 t 0.1 138
Helper 830
Concrete Mason 17
CNF01CN32 Slab Concrete 1 87 m3 5 17
Helper 17
Steel Fixer 200
CNF01CN34 Columns & Walls Rebar 6 20 t 0.1 33
Helper 200
Carpenter 498
CNF01CN51 Columns & Walls Formwork 6 4,979 m² 10 83
Helper 498
Concrete Mason 68
CNF01CN52 Columns & Walls Concrete 1 342 m3 5 68
Helper 68
Finishes
General

CNF01FN33 Blockwork 9

CNF01FN35 Plaster 12

Dry Area

CNF01FN36 Paint Primer & Stucco 10

False Ceiling Fixer 16


CNF01FN37 False Ceiling Suspension 8 636 m² 40 2
Helper 16
False Ceiling Fixer 16
CNF01FN38 False Ceiling Boarding 8 636 m² 40 2
Helper 16

CNF01FN39 Floor Tiles 7

CNF01FN40 Paint 1st Coat 8

CNF01FN41 Wardrobes 12

CNF01FN42 Paint 2nd Coat 6

CNF01FN43 Paint Final Coat 2

Bathroom

CNF01FN44 Wall Tiles 10

CNF01FN45 False Ceiling Suspension 7

CNF01FN46 False Ceiling Boarding 7

CNF01FN47 Floor Tiles 6

Kitchen

CNF01FN48 Wall Paint 7

CNF01FN49 Ceiling Paint 8

CNF01FN50 Floor Tiles 6