You are on page 1of 8

RENCANA ANGGARAN BIAYA

Propinsi : Jawa Timur Lokasi : Dsn. Krajan RT. 00 RW. 00


Kabupaten : Situbondo Jenis Kegiatan : Saluran Drainase
Kecamatan : Cipta Desa Ukuran/Dimensi : 72 m'
Desa : ..................

VOLUME Harga Jumlah Jumlah


URAIAN Dari Dari Satuan Satuan Swadaya Dana Desa
Total
Swadaya Dana Desa ( Rp. ) Rp Rp
BAHAN a b c= a - b d f g=bxf h=cxf
1 Semen 40 kg 61.00 61.00 Zak 58,000 3,538,000
2 Pasir 10.00 10.00 m2 225,000 2,250,000
3 Pasir Urug 2.00 2.00 m3 150,000 300,000
4 Batu Bata 9300.00 9300.00 bh 700 6,510,000
5 Buis Beton U 30 148.00 148.00 m 85,000 12,580,000

Sub Total 1) 25,178,000


ALAT
1 Arco 0.00 bh 550,000 -
2 Sekrop 0.00 bh 75,000 -
3 Timba 0.00 bh 11,000 -
4 Benang 0.00 bh 7,000 -

Sub Total 2) -
UPAH
1 Pekerja 190.00 190.00 Oh 70,000 13,300,000
2 Tukang 102.00 102.00 Oh 80,000 8,160,000

Sub Total 3) - 21,460,000


Total biaya ( Dana Desa + Swada 46,638,000
Sumber Dana Total biaya Dana Desa 46,638,000
Total biaya Swadaya -
Terbilang :
Lima Puluh Dua Juta Seratus Tiga Puluh Ribu Rupiah

Dibuat Oleh,
Kader Teknis Tim Pengelola Kegiatan (TPK)
Desa ................. Desa .....................

................................ ................................

Mengetahui,
Kepala Desa .............

.................................

hal1
HARGA SATUAN BAHAN, ALAT, DAN UPAH

Tenaga Kerja Satuan Harga


Pekerja Oh 80,000
Tukang Oh 90,000

Bahan Satuan Harga Alat Satuan Harga


1 Pasir m³ 145,000 1 Meteran bh 33,000
2 Semen (40kg) zak 58,000 2 Benang roll 7,000
3 Kanstin bh 28,000
4 Paving m² 58,000
5 Mahkota bh 4,000
6 Batu Bata bh 700
7 Buis beton U 30 bh 65,000
8 Koral m3 350,000
9 Besi Ø 10 ljr 85,000
10 Bendrat kg 22,000
11 Kayu thn 4/6 Ljr 55,000
12 Papan 2/20 lbr 25,000
13 Paku kg 22,000
14 Tripleks lbr 75,000
15 Pipa PVC 3" lbr 225,000
Kabupaten : Situbondo Jenis Prasarana : Saluran Drainase
Kecamatan : Cipta Desa Take Of Sheet Lokasi : Dsn. ..............
Desa : ..................... Volume : 119.00 m

Ø10-15 Ø10-15
Pekerjaan Beton jml = 198.00 m
= P x L x T x jml 6.6. Pek. Beton (K.225), slump (12 ± 2) cm
T = 0.60 x 0.60 x 0.10 x ### = 7.13 m³ Semen = 8.80 x 7.13 = 62.73 zak
L Pasir = 0.52 x 7.13 = 3.72 m³
Batu pecah= 0.76 x 7.13 = 5.44 m³
Ø10 - 15
Ø10
- 15
Pekerja = 1.65 x 7.13 = 11.76 Oh
Tukang = 0.28 x 7.13 = 1.96 Oh
P

Pembesian
Ø 10 = (( P / 0,15) + 1) x L x jml 6.17 Pembesian 1 kg dengan besi
= 5.0 x 0.60 x 198.0 = 594 m Besi Ø 8 = 0.95 x 736.56 = 703.1 kg
= (( L / 0,15) + 1) x P x jml = 1,188.0 : 11.00 = 108.00 ljr
P= 0.6 m T = ### m L = ### m Ø 10 = 5.00 x 0.6 x 198.0 = 594 m Kw. bendra= 0.015 x 736.56 = 11.00 kg
Total = 1,188 m Pekerja = 0.040 x 736.56 = 29.46 Oh
berat = 1188 x 0.62 = 737 kg Tukang = 0.030 x 736.56 = 22.10 Oh

Begisting Begisting
= 0.60 x 0.6 = 71.3 Trileks = 0.14 x 71.28 = 4.16 lbr
Reng 2/3 = 1.00 x 71.28 = bendel
1.00
Paku = 0.02 x 71.28 = 1.07 kg
Pekerja = 0.520 x 71.28 = 37.07 Oh
Tukang = 0.260 x 71.28 = 18.53 Oh

Perhitungan Molen (Concrete mixer)


Kapasitas alat = 125 L/6 HP
Efektif perhari = 5 jam
Produktif per hari = 3.50 m³ Molen
Koef Per m³ = 1.00 : 3.50 = 0.29 Sewa Mole= 0.29 x 7.13 = 2.00 hr
Mob/demo = = 1.00 ls
PERHITUNGAN VOLUME PEKERJAAN DRAENASE U / TAKE OFF SHEET

No Uraian Panjang Lebar Tinggi Luas Volume


I PEKERJAAN PENGGALIAN
Galian Tanah

148.00 0.60 0.50 88.80 44.40


0,5

0,6
0,50
0,5
0,15
0,25 5 10, 15
0,15
0,50
,0,10
II PASANGAN BATU BATA 1/2 BATU ( 1 : 6 ) M2
Pasngan Bata
119.00 0.40 95.20
29.00 0.50 29.00
0,50 124.20

148

III PASANGAN BUIS BET0N 1/2 O 30 ( 1 : 6 ) M2


Pasangan Buis
148.00 1.00 148.00

IV Urugan Pasir Urug 5 cm 148.00 0.30 0.05 2.22

V Plesteran dan acian tebal 1,5 cm (2X 242 )=484 0.50 0.15
148.00 0.30 133.20 133.20
p=0,21+0,15+0,12=0,48
ANALISA PERHITUNGAN
Harga sat. Bahan Upah Total
No Uraian Analisa Volume Kebutuhan
Rp. Rp Rp. Rp.
A.1 Galian Tanah pondasi untuk tiap m3
Pekerja 0.7500 44.40 m3 33.30 Oh 80,000 2,664,000 2,664,000
A.1 Galian Tanah pondasi untuk tiap m 3

Pasir Urug 1.0000 2.22 m3 2.22 m3 145,000 321,900 321,900


Pekerja 0.3000 2.22 m3 0.67 Oh 80,000 53,280 53,280
G.II/4 Pasangan Batu Merah 1/2 batu ( m2 ) adukan 1 : 6 untuk tiap m2
Batu Bata 75.0000 124.20 m2 9,315.00 biji 700 6,520,500 6,520,500
Semen 0.2875 124.20 m2 35.71 zak 58,000 2,071,035 2,071,035
Pasir 0.0490 124.20 m2 6.09 m3 145,000 882,441 882,441
Tukang Batu 0.1750 124.20 m2 21.74 Oh 90,000 1,956,150 1,956,150
Pekerja 0.5250 124.20 m2 65.21 Oh 80,000 5,216,400 5,216,400

G. X / 4Plesteran dan Acian Dinding Luar Dalam ( 1 : 6 ) m2


Semen 0.1560 133.20 m2 20.78 zak 58,000 1,205,194 1,205,194
Pasir 0.0240 133.20 m2 3.20 m3 145,000 463,536 463,536
Tukang Batu 0.2000 133.20 m2 26.64 Oh 90,000 2,397,600 2,397,600
Pekerja 0.1500 133.20 m2 19.98 Oh 80,000 1,598,400 1,598,400

G.1 Pemasangan Buis Beton 1/2 0 30


Semen 0.01 148 m3 1.48 zak 58,000 85,840 85,840
Pasir Pasang 0.008 148 m3 1.184 m3 145,000 171,680 171,680
Buis beton 1/2 O 1 148 m2 148 m2 85,000 12,580,000 12,580,000
Tukang 0.15 148 m3 22.2 Oh 90,000 1,998,000 1,998,000
Pekerja 0.250 148 m3 37.00 Oh 80,000 2,960,000 2,960,000

Pembersiahan Lokasi
Pekerja 0.0100 296.00 m3 2.96 Oh 80,000 236,800 236,800

Pembuangan bekas galian


Pekerja 0.7000 44.40 m3 31.08 Oh 80,000 2,486,400 2,486,400
Kabupaten : Situbondo Jenis Prasarana : Jalan Paving
Kecamatan : Cipta Desa Take Of Sheet Lokasi : Dsn. ..............
Desa : ................... Volume : 119 x 2,2 m

Volume Galian Kanstin (P x L x T) 6.1. Pekerjaan galian tanah untuk kanstin


= 119 x 0.14 x 0.10 x 2 = 3.33 m³ Pekerja = 0.75 x 3.33 = 2.50 Oh
Pekerjaan pembersihan
Panjang jalan 119 m Panjang kanstin (50x30x10)cm Pekerja = 0.05 x 238.00 = 11.90 Oh
= 119 x 4 = 476 m¹ Pekerjaan pasang kanstin
Jumlah kanstin /m = 2.20 bh Kanstin = 2.50 x 476 = 1195 bh
Pasang mahkota Semen = 0.017 x 119.00 = 3.00zak
Luas 1 mahkota = 0.0372 m2 Pasir pasan = 0.020 x 119.00 = 2.38 m³
kebutuhan mahkota = (119/0,3)x2 = 1586.7 bh Pekerja = 0.250 x 476 = 119.00 Oh
Paving
Kanstin
Luas mahkota = 1587 x 0.037 = 59.0 m2 Tukang = 0.125 x 476 = 59.50 Oh

Pekerjaan paving
Pasir Urug = 0.08 x 84.0 = 6.72 m³
Pasang paving Paving = 1.00 x 84.0 = 84.00 m²
V1 = Luas paving Pekerja = 0.27 x 84.0 = 22.67 Oh
I = 119.0 x 0.6 x 2 = 143 m² Tukang = 0.15 x 84.0 = 12.60 Oh
143.00 m²
= 143 - 59.0 = 84.0 m² Pekerjaan paving pengunci
50cm
30cm 10 cm Pasir Urug = 0.08 x 59.0 = 4.72 m³
Mahkota = 1.00 x 1586.7 = 1587.00 bh
30 cm

KANSTIN
Pekerja = 0.27 x 59.0 = 15.94 Oh
Tukang = 0.15 x 59.0 = 8.85 Oh
Delatasi
10cm
10,5 cm

21 cm 21 cm 6 cm

PAVINGSTONE
Mahkota
5 cm

30 cm
RENCANA ANGGARAN BIAYA
Propinsi : Jawa Timur Lokasi : Dsn. ........
Kabupaten : Situbondo Panjang : 119 x 2,2 m
Kecamatan : Cipta Desa
Desa : ...........

VOLUME Jumlah Jumlah


Harga Satuan
URAIAN Dari Dari Dana Satuan Swadaya DD
Total
Swadaya DD ( Rp. ) ( Rp. ) ( Rp )
a b c=a-b d e g=bxf h=cxe
BAHAN
1 Kanstin 1,195.00 1,195.00 bh 28,000.00 - 33,460,000.00
2 Pasir 16.00 16.00 m³ 145,000.00 - 2,320,000.00
3 Paving 84.00 84.00 m² 58,000.00 - 4,872,000.00
4 Mahkota 1,587.00 1,587.00 Bh 4,000.00 - 6,348,000.00
5 Semen 40 kg 127.00 127.00 zak 58,000.00 - 7,366,000.00
6 Batu Bata 9,300.00 9,300.00 bh 700.00 - 6,510,000.00
7 Buis Beton U 30 148.00 148.00 bh 65,000.00 - 9,620,000.00
8 Koral 5.00 5.00 m³ 350,000.00 - 1,750,000.00
9 Besi Ø 10 108.00 108.00 ljr 85,000.00 - 9,180,000.00
10 Bendrat 11.00 11.00 kg 22,000.00 - 242,000.00
11 Kayu 4/6 8.00 8.00 kg 55,000.00 - 440,000.00
12 Paku 1.00 1.00 kg 22,000.00 - 22,000.00
13 Tripleks 4.00 4.00 lbr 75,000.00 - 300,000.00
14 Pipa PVC 3" 30.00 30.00 Jjr 225,000.00 - 6,750,000.00

SUB TOTAL I - 89,180,000.00


UPAH
1 Pekerja 440.00 440.00 Oh 80,000.00 - 35,200,000.00
2 Tukang 226.00 226.00 Oh 90,000.00 - 20,340,000.00
3 Pemotongan Pohon 2.00 2.00 bh 500,000.00 - 1,000,000.00
SUB TOTAL II - 56,540,000.00
BIAYA OPRASIONAL
1 Perencanaan 1.00 1.00 ls 2,000,000.00 - 2,000,000.00
2 Benang 1.00 1.00 bh 7,000.00 - 7,000.00
3 Meteran 1.00 1.00 bh 33,000.00 - 33,000.00

SUB TOTAL III - 2,040,000.00


Total Biaya DD (I + II + III) 147,760,000.00
Sumber Dana
Total Biaya Swadaya (I + II + III) -
JUMLAH TOTAL ( DD + Swadaya ) -
Terbilang :
Seratus Empat Puluh Tujuh Juta Tujuh Ratus Enam Puluh Ribu Rupiah

Mengetahui, Pengelola Kegiatan (TPK)


Kepala Desa .................... Desa .........................

............................. .............................

Perencana,

.............................

You might also like