Professional Documents
Culture Documents
QC & Testing of Power Cables
QC & Testing of Power Cables
1
Power Cables Handbook
• Cable conformity
• Cabling quality
• Cable functionality
Many times, a fault in a cable can be seen well before it becomes an actual problem. A visual inspection
of all the cables in your facility is a great way to find trouble before it causes you a downtime. We look for
corrosion on the copper, cracks in the insulation, moisture on the cables and many other indicators of
damage to the cables.
Cable faults cost money and create disruption, so there is an enormous demand for cable test techniques
to ensure cables and joints are in good condition, and to allow cable faults to be located rapidly.
Cable testing to both predict and then deal with faults is a vital concern for all those involved with the
distribution of electricity. A wide range of test techniques and test equipment are available to allow this
concern to be effectively addressed, but cable testing can, nevertheless, be a challenging task.
For this reason, a resource that’s as important as the test equipment itself is access to expertise that will
help with selecting the best equipment for the job, and using it in such a way that it delivers the best
results.
2
Power Cables Handbook
• When using a calibrated torque wrench, reference ANSI/NETA Table 100.12 US Standard
Fasteners, Bolt Torque Values for Electrical Connections.
• The values of similar bolted connections must be compared and check which value shift by more
than fifty percent of the smallest value in the case where a low resistance ohmmeter is utilized.
• Look at the condition of the exposed cable jacket and insulation when performing a visual
inspection on low voltage wire and cable.
• Inspect compression-applied connections by verifying that the connector is properly rated for the
installed cable size and has the proper indentations.
• Perform an insulation-resistance test on each conductor with respect to ground and adjacent
conductors. Test period must be for 1 minute using a voltage according to manufacturer’s
published data.
• If no literature from the manufacturer is available, apply 500 volts dc for 300-volt rated cable and
1000 volts dc for 600-volt rated cable. Insulation-resistance values must be according to the
manufacturer’s published data. If no data from the manufacturer exists, the values should be no
less than 100 megohms. Perform continuity tests to ensure correct cable connection and phasing.
• Verify uniform resistance of parallel conductors using a low-resistance ohmmeter. Measure the
resistance of each cable individually and investigate deviations in resistance between parallel
conductors.
Given below are various kinds of tests that are conducted on cables:
The following tests are type test of electrical power cable.
3
Power Cables Handbook
Insulation Test:
• The insulation test also known as high resistance test is always made DC. The insulation test is
combined with a short-circuit test and high voltage test in DC.
• The insulation test combines several functions.
• The insulation test can perform:
o Determining insulation resistances from fifty kilo ohm to two thousand mega ohm at high
voltage i.e. from 20V to 2000V.
o Measurement of dielectric strength and detection of short circuits.
4
Power Cables Handbook
If there is no short circuit, the high voltage is applied. During the programmable rise time, if breakdown
occurs, the voltage is displayed and the test stops (the breakdown voltage is given in the error list).
If no breakdown occurs and if the voltage does not reach the required value (±10%), the message
U<Uprog appears in the error list.
Next, the voltage is applied for the duration of the programmed application time. If breakdown occurs
during this period, the moment when the fault appears is displayed in the error list and the test stops.
Lastly, if all goes well, at the end of the application time, the insulation test is made, and the insulation
resistance measured. The tester will add a measurement time as a function of the range requested. The
measurement time varies from 20ms to 240ms according to range.
To end the sequence, the tester reduces the high voltage and then discharges the unit tested to an earth
resistance (total time 20ms).
This procedure is identical at the end of every measurement of insulation.
The dielectric strength test detects any sudden variation in the increase of the test current outside the
programmed limit.
• The first conductor for which cross insulation is being measured shall be connected to Line terminal
of the megger. The remaining conductors looped together (with the help of crocodile clips) i. e.
Conductor 2 and onwards, are connected to Earth terminal of megger. Conductors at the other end
are left free.
• Now rotate the handle of megger or press push button of megger. The reading of meter will show
the cross Insulation between conductor 1 and rest of the conductors. Insulation reading shall be
recorded.
• Now connect next conductor to Line terminal of the megger & connect the remaining conductors to
earth terminal of the megger and take measurements.
5
Power Cables Handbook
Phasing Test:
The correct phasing of all LV circuits shall be checked at all positions where the LV cables are terminated
into fuse bases and where any LV cable is run from point to point.
This test shall be performed with an instrument designed for the purpose. Mains frequency voltage of 240
Volts is not acceptable for this test.
The neutral conductor shall be connected to the earth stake for this test.
Earth Resistance Test:
In any overhead or underground network, the earth resistance at any point along the length of a LV feeder
is to have a maximum resistance of 10 ohms prior to connection to the existing network.
In any overhead or underground network, the overall resistance to earth Shall be less than 1 ohm prior to
connection to the existing network.
High Voltage Test:
The high voltage test (also called dielectric strength test or hipot test) can be made in AC or DC. If the
high voltage test is made in DC, it is then combined with insulation; if the high voltage test is made in AC,
it is then, this is then, more stressful for the sample and made according to the sketch below.
Measurement of high voltage test under alternating current is performed using an alternating voltage
(50Hz) adjustable to an effective 50V to 1,500V. As is the case with direct current, the high voltage test
detects any sudden rise of current up to a programmed threshold.
The short circuit test is maintained by default. The rise time is more than 500 ms and the application time
at least one period.
Warning: The high voltage test under alternating current is penalized by the capacitive value of the tested
equipment. It must be remembered that the generator power is limited to 5 mA.
6
Power Cables Handbook
Quality
Plan
7
Power Cables Handbook
QUALITY PLAN
Physical
Properties
Chemical
Properties
Electrical
Properties
Work Instructions
Non-Electrical Tests
Electrical Tests
Packing, Lagging,
Transportation
QUALITY CHECK
TEST METHOD
ACCEPTANCE
SPECIFICATION
CRITERIA
(TMS)
8
Power Cables Handbook
INSPECTION OF
RAW-MATERIALS
9
Power Cables Handbook
RM Arrived Stores
Under Inspection
Sample Collection
as per W.I
Issue to Production
Return to
Supplier
Physical Check
Metallic Raw Materials
Copper, Aluminum,
Diameter Measure
Steel Wire, Steel Tape, Elongation Measure
Copper Tape, Tinned * Physical Check W.I
Copper Tensile Strength
* Sample Prepare W.I
Resistivity Measure * TMS
* Measuring Device
Physical Check * Sample Test W.I
Non-Metallic Raw- * Acceptance/Rejection
Elongation Test Criteria
Materials
PVC, XLPE, PE, LSHF, Tensile Test
Filler, Yarns, Tapes
Dimension Measure
Density Measure
10
Power Cables Handbook
SAMPLING PLAN
TESTING/CHECK SAMPLES
AS PER QUALITY PLAN
SCRAP
NOT Immediate Action OK
C/A – P/A
Remanufacture OK Or MRG
OK
11
Power Cables Handbook
SAMPLING PLAN
Non
Metal
• Non-Metallic: For same size, two
samples per shift
PRODUCTION • Sample Length: 20 cm
STAGES
Physical Check
Diameter Measure
Copper, Aluminum,
Elongation Measure
Tinned Copper
• Physical Check W.I
Tensile Strength
• Sample Prepare W.I
Resistivity Measure • TMS
• Calibrated Measuring
Physical Check Device
• Sample Test W.I
Lay Length • Acceptance/Rejection
Stranded Conductors Dimension Check Criteria
Mass Measure
DCR Measure
IN-PROCESS CHECK OF STAGES
12
Power Cables Handbook
Diameter Measure
Extruded
Insulation & Thermal Stability Check
Sheath
Mass Measure • Physical Check W.I
• Sample Prepare W.I
• Test Method Specification
Physical Check
(TMS)
• Calibrated Measuring
Devices
Diameter Measure • Sample Test W.I
• Acceptance/Rejection
Lay Length Criteria
Screening,
Assembly, Tape Thickness, Width
Armoring
Wires Lay Length
Physical Check
13
Power Cables Handbook
OK
Issue NCR Not Transfer to Packing
OK Test Result
Notification
Transport to Customer
QC Decision MRG
Follow Customer
For RW / Repair Satisfaction
Hi - Pot “ HV ” Test
PD Test
DCR Measurement
DC Sheath Test (MV/HV)
Physical Check
14
Power Cables Handbook
1- Routine Tests
Tests made by the manufacturer on each manufactured length of cable to check that each
length meetsthe specified requirements.
2- Sample Tests
Tests made by the manufacturer on samples of completed cable or components taken from a
completedcable, at a specified frequency, so as to verify that the finished product meets the
specified requirements.
3- Type Tests
Tests made before supplying, on a general commercial basis, a type of cable covered by this
standard, in order to demonstrate satisfactory performance characteristics to meet the
intended application.
NOTE These tests are of such a nature that, after they have been made, they need not be
repeated, unless changes are made in the cable materials or design or manufacturing process
which might change theperformance characteristics.
15
Power Cables Handbook
Routine Tests:
According to conductor type, the measured values of DCR should not exceed that specified in IEC
60228.
16
Power Cables Handbook
For single-core screened cables, the test voltage shall be applied for 5 min between the
conductor and the metallic screen.
Single-core unscreened cables shall be immersed in water at room temperature for 1 h
and the testvoltage then applied for 5 min between the conductor and the water.
17
Power Cables Handbook
▪ For multicore cables with individually screened cores, the test voltage shall be applied for 5 min
between each conductor and the metallic layer.
▪ For multicore cables without individually screened cores, the test voltage shall be applied for
5 min in succession between each insulated conductor and all the other conductors and
collective metalliclayers, if any.
▪ The conductors may be suitably connected for successive applications of the test voltage to
limit the totaltesting time, provided that the sequence of connections ensures that the voltage
is applied for at least 5 min without interruption between each conductor and each other
conductor, and between each conductorand the metallic layers, if any.
18
Power Cables Handbook
Test voltage
▪ The power frequency test voltage shall be 2,5 U0 + 2 kV. Values of single-phase test
voltages for the standard rated voltages are given in Table
▪ When a direct voltage is used, the applied voltage shall be 2,4 times the power frequency
test voltage.
▪ In all cases, the test voltage shall be increased gradually to the specified value.
Requirement
Sample Tests
1. Conductor examination
2. Measurement of thickness of insulation and of non-metallic sheaths (including extruded
separation sheaths, but excluding inner extruded coverings)
3. Measurement of thickness of lead sheath
4. Measurement of armor wires and tapes
5. Measurement of external diameter
6. Hot set test for EPR, XLPE insulations and elastomeric sheaths
19
Power Cables Handbook
Measurement of Thicknesses
Micrometer
Low Voltage
Cut the insulation from the core sample, long enough to give several dumb‐bells.
The test specimen should be prepared from the inner part of the insulation wall after
removing ridges and irregular conductor marks in order to be smooth and parallel on both
sides and 0.80 ‐ 2.00 mmin thickness.
20
Power Cables Handbook
▪ Samples are hung inside oven capable of maintaining the required temperature at 200 °C .
▪ Open the oven door momentarily and suspend the loaded test piece in the oven on wire shelf.
Shut the oven and start the time (clock).
▪ On the completion of 15 minutes, measure the elongation without opening the glass door.
▪ If the door has to be opened for the measurement, then the elongation should be
measured asquickly as possible, using the calibrated elongation card.
▪ After the hot‐set measurements, cut the weight off from below the lower gauge
mark, shut theOven and let the temperature be stable at 197 – 200 deg.C.
▪ Wait for 5 minutes and then take the test piece out, remove the load clamp and let it cool
down to roomtemperature (about 10 minutes).
▪ Measure the distance between the gauge marks and calculate the permanent set.
21
Power Cables Handbook
Curing the Sample for In-Process‐Testing ( For Un‐cured materials / Self‐curing materials)
For Low Voltage:
Boil two sample strips in water for one hour.
Take out one strip, cool it in running tap water and cut two dumb‐bells for testing.
Type Test
Type tests, electrical
• Insulation resistance measurement at ambient temperature
• Insulation resistance measurement at maximum conductor temperature
• Voltage test for 4 h
• Impulse test for cables of rated voltage 1,8/3 (3,6) kV
22
Power Cables Handbook
23
Power Cables Handbook
The volume resistivity shall be calculated from the measured insulation resistance by the following
formula:
where
ρ is the volume resistivity, in ohms · centimeters; R is the measured insulation resistance, in
ohms;l is the length of the cable, in centimeters;
D is the outer diameter of the insulation, in millimetres;
d is the inner diameter of the insulation, in millimetres.
The "insulation resistance constant “Ki" expressed in megohms. Kilometers may also be
calculated,using the formula:
24
Power Cables Handbook
Requirements
The values calculated from the measurements shall be not less than those specified in below Table.
25
Power Cables Handbook
Smoke Density,
IEC 60502-2:
Routine tests:
Routine tests are normally carried out on each manufactured length of cable.
1. Electrical resistance of conductors
2. Partial Discharge test
3. Voltage test
4. DC sheath test, if required
26
Power Cables Handbook
TEST VOLTAGES FOR MV CABLES
27
Power Cables Handbook
For single-core screened cables, the test voltage of 3.5 Uo shall be applied for 5 min
between theconductor and the metallic screen.
For multicore cables with individually screened cores, the test voltage of 3.5 Uo shall be
applied for 5 min between each conductor and the metallic layer.
For multicore cables without individually screened cores, the test voltage of 3.5
Uo shall be appliedfor 5 min in succession between each insulated conductor and all the
other conductors and collective metallic layers, if any.
The conductors may be suitably connected for successive applications of the test voltage tolimit the
total testing time.
Voltage Regulator is connected to the mains through a main power circuit breaker.
It supplies a variable voltage to the Exciter Transformer to adjust its output voltage to the proper value
required for the test.
Exciter Transformer supplies the necessary power to the resonant circuit (HV variable inductance
reactorand the test object.
For the series resonance, the exciter transformer is connected in series with the reactor (i.e. Type Test
Cage set‐ up).
For parallel resonance without excitation transformer, the reactor has an excitation transformer winding
which is in the same magnetic circuit as the reactor winding (i.e. Routine Test Cage set‐up).
HV Variable Reactor is the heart of the resonant circuit.
This device is designed to provide the complete reactive compensation to the highly capacitive load
(e.g. cable) when the system is turned to resonance.
The Capacitive Load represents the combined effects of the test object, voltage divider, filter capacitors
(if used) and stray capacitance due to the test set up.
A capacitive load is required for proper operation of the system in the series resonant mode.
Operating Desk: Where all functions related to HV testing are performed
28
Power Cables Handbook
Procedure
29
Power Cables Handbook
Sample tests
1. Conductor examination
2. Measurement of thickness of insulation and of non-metallic sheaths (including extruded
separation sheaths, but excluding inner extruded coverings)
3. Measurement of thickness of lead sheath
4. Measurement of armor wires and tapes
5. Measurement of external diameter
6. Voltage test for 4 hours
7. Hot set test for EPR, XLPE insulations and elastomeric sheaths
This test is applicable only to cables of rated voltage above 3,6/6 (7,2) kV
Sampling
The sample shall be a piece of completed cable at least 5 m in length between the test terminations.
Procedure
A power frequency voltage shall be applied for 4 h at ambient temperature between each conductor and
Test voltages
The test voltage shall be 4 U0. Values of the test voltage for the standard rated voltages are given
below.
30
Power Cables Handbook
Type tests:
Type tests, electrical
31
Power Cables Handbook
▪ The partial discharge test shall be carried out in accordance with IEC 60885-3 for cables and the
sensitivityas defined in IEC 60885-3 s hall be 10 pC or better.
▪ The test voltage shall be raised gradually to, and held at, 1,75 U0 for 10 s and then slowly reduced to 1,5
U0.
▪ There shall be no detectable discharge exceeding the declared sensitivity from the test object at 1,5 U0.
Voltage Test
The voltage test shall be made at ambient temperature using an alternating test voltage at power
frequency.
The test voltage shall be raised gradually to 2,5 U0 and then be held for 30 min between the conductor
and metal screen/sheath.
No breakdown shall occur.
32
Power Cables Handbook
EQUIPMENT:
1- Reactor:
Which provides the complete reactive compensation to the highly capacitive load (e.g. cable).
2- Exciter:
▪ Which gives necessary excitation to the resonant circuit.
▪ For the series resonance, the exciter transformer is connected in series with the reactor.
▪ For parallel resonance without excitation transformer, the reactor has an excitation transformer
winding which is in the same magnetic circuit as the reactor winding (i.e. Routine Test Cage set‐up).
3- Regulator:
▪ Which adjusts the output of the exciter transformer.
▪ It is also where the test system receives its line voltage.
4- Voltage Divider:
where it measures the output voltage of the reactor.
5- Operating Terminal:
Where all functions related to HV testing are performed
33
Power Cables Handbook
REQUIREMENT:
Routine Test:
AC Voltage test:
▪ The voltage test shall be made at ambient temperature.
▪ The test voltage shall be raised gradually to the specified value which shall then be held for 30
minutesbetween the conductor and metallic screen.
▪ The test voltage shall be at 2.5 Uo.
▪ No breakdown of the insulation shall occur.
Type Test:
Heat Cycling:
During the test period, a voltage of 2 Uo shall be applied to the sample.
Tan Δ Measurement:
A voltage Uo shall be applied to the cable during tan Δ measurement.
AC Voltage Test:
▪ After the impulse test, the cable sample shall be subjected at ambient temperature to a power frequency
voltage at 2.5 Uo for 15 minutes.
▪ No breakdown of the insulation shall occur.
34
Power Cables Handbook
Frequency of tests
The sample tests in items a) to h) and k) shall be carried out on one length from each batch of the same
type and cross-section of cable but shall be limited to not more than 10 % of the number of lengths in any
contract, rounded to the nearest whole number.
The frequency of the tests in items i) and j) shall be in accordance with agreed quality control
procedures. In the absence of such an agreement, one test shall be made for contracts with a
cable length greater than20 km.
35
Power Cables Handbook
▪ The cable length, or a sample thereof, shall be placed in the test room, which shall be maintained at a
reasonably constant temperature for at least 12 h before the test.
▪ If there is a doubt that the conductor or metal screen temperature is not the same as the room
temperature, the resistance shall be measured after the cable has been in the test room for 24 h.
▪ Alternatively, the resistance may be measured on a sample of conductor or metal screen, conditioned
forat least 1 h in a temperature-controlled liquid bath.
▪ The d.c. resistance of the conductor or metal screen shall be corrected
▪ The d.c. resistance of the conductor or metal screen shall be corrected to a temperature of 20°C and a1
km length in accordance with the formulae and factors given in IEC 60228.
▪ For screens other than copper or aluminium, temperature coefficients and correction formulae shall be
taken respectively from Table in slide # 67.
Requirement:
The corrected d.c. resistance of the conductor at 20°C shall not exceed either the appropriate
maximum
value specified in IEC 60228 or the declared value.
The corrected d.c. resistance of the metal screen at 20°C shall not exceed the declared value.
Where:
R’ = Resistance at θ°C
Ro = Resistance at 20°C
= Temp. Coefficient
36
Power Cables Handbook
The minimum thickness of the sheath shall not fall below 90 % of the nominal thickness by more
than 0,1mm for plain aluminium sheath:
37
Power Cables Handbook
Measurement of Capacitance
The capacitance shall be measured between conductor and metal screen/sheath at ambient
temperature,
where the ambient temperature shall be recorded with the test data.
The measured value of the capacitance shall be corrected to a 1 km length and shall not exceed the
declared nominal value by more than 8 %.
▪ Impulse testing systems are designed to generate impulse voltages that simulate lightning
strikes andswitching surges.
▪ This test is only required for cables with a nominal electric conductor stress > 8,0 kV/mm.
▪ The test shall be performed on a complete cable at least 10 m in length excluding test accessories, at
aconductor temperature 5°C to 10°C above maximum conductor temperature in normal operation.
▪ The assembly is heated by conductor current only, until the cable conductor reaches the required
temperature.
▪ The assembly shall withstand without failure or flashover 10 positive and 10 negative voltage values
as specified for each KV rating.
▪ Pictures below show Impulse test 2.4 MV, HV-EHV Resonant test system 700 KV.
38
Power Cables Handbook
1) Ethanol (ethyl-alcohol) of analytical grade or another suitable liquid for densities below 1 gm/cc.
2) Zinc chloride solution for densities equal to or greater than 1 gm/cc.
3) Distilled or deionized water.
4) Mixing cylinder.
5) 5) Thermostat.
6) 6) Hydrometer calibrated at (23,0 +/- 1°C).
7) Thermometer graduated in tenths of a degree Celsius
Procedure
• A sample from the insulation or the sheath to be tested, shall be taken perpendicularly to the
conductor axis and cut into small pieces of 1 mm to 2 mm edge length.
• The density shall be determined by putting the sample suspended in a liquid which does not react
with thematerial to be tested.
• Three pieces of the sample shall be placed in the liquid at a temperature of 23,0 °C.
The following liquids are suitable:
. for a density expected to be lower than 1 gm/cc, a mixture of ethanol and water;
. for a density of 1 gm/cc and higher, a mixture of zinc chloride and water.
39
Power Cables Handbook
Requirements
The results of the test shall comply with the requirements of HDPE given below.
Procedure
▪ The tube shall be filled within 5 min with tap water at a temperature of (20 ± 10) °C so that the height
of the water in the tube is 1 m above the cable centre (see Figure).
▪ The sample shall be allowed to stand for 24 h.
▪ The sample shall be subjected to sample shall then be subjected to 10 heatingcycles.
▪ The conductor shall be heated by a suitable method until it has reached a steady temperature5 °C
to 10 °C above the maximum conductor temperature in normal operation; not reach the boiling
point of water.
▪ The heating shall be applied for at least 8 h. The conductor temperature shall be maintained within
the stated temperature limits for at least 2 h of each heating period.
▪ The water head shall be maintained at 1 m.
Requirements
During the period of testing, no water shall emerge from the ends of the test piece.
40
Power Cables Handbook
IEC 62067:
Routine tests on cables and on the main insulation of prefabricated accessories:
1- Partial discharge test
2- Voltage test
3- Electrical test on over-sheath of the cable
41
Power Cables Handbook
The following tests shall be carried out on samples which, for the tests in items b) and g), may be
drum lengths of cable, taken to represent batches:
a) Conductor examination;
b) Measurement of electrical resistance of conductor and of metallic screen;
c) Measurement of thickness of insulation and over-sheath;
d) Measurement of thickness of metallic sheath;
e) Measurement of diameters, if required;
f) Hot set test for XLPE, EPR and HEPR insulations;
g) Measurement of capacitance;
h) Measurement of density of HDPE insulation;
i) Lightning impulse voltage test for a cable with calculated nominal electrical stress at conductor
screen > 8,0 kV/mm (to be calculated as per formulas in next slide).
j) Water penetration test, if applicable;
k) Tests on components of cables with a longitudinally applied metal foil.
Frequency of Tests
The sample tests in items a) to h) and k) in previous slide shall be carried out on one length from each
batch of the same type and cross-section of cable, but shall be limited to not more than 10 % of the
numberof lengths in any contract, rounded to the nearest whole number.
The frequency of the tests in items i) and j) in previous slide shall be in accordance with agreed quality
control procedures.
In the absence of such an agreement, one test shall be made for contracts with a cable length between
4km and 20 km and two tests for contracts with longer cable lengths.
▪ The cable length, or a sample thereof, shall be placed in the test room, which shall be maintained at a
reasonably constant temperature for at least 12 h before the test.
▪ If there is a doubt that the conductor or metal screen temperature is not the same as the room
temperature, the resistance shall be measured after the cable has been in the test room for 24 h.
▪ Alternatively, the resistance may be measured on a sample of conductor or metal screen, conditioned for
at least 1 h in a temperature-controlled liquid bath.
▪ The d.c. resistance of the conductor or metal screen shall be corrected
42
Power Cables Handbook
▪ The d.c. resistance of the conductor or metal screen shall be corrected to a temperature of 20°C and
a one km length in accordance with the formulae and factors given in IEC 60228.
▪ For screens other than copper or aluminium, temperature coefficients and correction formulae shall be
taken respectively from Table in page # 37.
Requirement:
The corrected d.c. resistance of the conductor at 20°C shall not exceed either the appropriate maximum
value specified in IEC 60228 or the declared value.
The corrected d.c. resistance of the metal screen at 20°C shall not exceed the declared value.
a) The voltage group is not higher that of the tested cable system.
b) the conductor cross-section is not larger than that of the tested cable;
c) the cable and the accessories have the same or a similar constructions as that of the tested cable
system(s);
d) the calculated nominal electrical stress and the impulse voltage stress calculated using nominal
dimensions at the cable conductor screen do not exceed the respective calculated stresses of
the tested cable system(s)by more than 10 %;
e) the calculated nominal electrical stress at the cable insulation screen and the impulse
voltage stress calculated using nominal dimensions do not exceed the respective
calculated stresses of the tested cablesystem(s);
f) the calculated nominal electrical stresses and the impulse voltage stresses calculated using
nominal dimensions within the main insulation parts of the accessory and at the cable and
accessory interfaces do notexceed the respective calculated stresses of the tested cable
system(s).
43
Power Cables Handbook
EQUIPMENT:
44
Power Cables Handbook
Procedure
▪ The cable shall have a U-bend diameter as per the following calculations.
❖ Bending Diameter Calculations:
▪ Turn the current adjust potentiometer until desired temperature or current is reached.
▪ The heating shall be applied for at least 8 hours and shall be followed by at least 16 hours of natural
cooling.
▪ The conductor temperature shall be maintained within the stated temperature limits at least for the
last twohours of each current loading period.
▪ The cycle of heating and cooling shall be carried out 20 times.
▪ Apply HV @ 2 Uo to the sample during the whole of the test period
45
Power Cables Handbook
▪ After the final cycle, the sample at ambient temperature shall be subjected to Partial discharge test.
▪ Refer to Inspection Test procedures of Partial Discharge Test as described before.
Requirement
No breakdown of the insulation shall occur
It is a dielectric test conducted on an electrical cable to demonstrate that the insulation will
withstandimpulses that strike it externally due to lightning during its service period.
High voltage surges resembling lightning that are simulated in laboratories are commonly
known as highvoltage impulses.
Equipment
▪ Impulse voltage generator: which generate impulse voltages simulating lightning strokes and switching
surges.
▪ Impulse generator charging rectifier and SCR control unit: which provides the rectified voltage input to
the impulse generator.
▪ Impulse voltage divider: which measures the output impulse voltage.
▪ Sphere‐gap: for calibration of output impulse voltage.
▪ Peak measurement device (DIAS 730): which provides a digital impulse analysis to the output impulse
voltage. It generates and records impulse shapes and parameters.
▪ Controlling module: Where impulse generation is being controlled.
46
Power Cables Handbook
Procedure
1- Insert the cable sample to the yoke of the Heat cycling transformer.
2- For H.V. cables, prepare cable end termination as per Work Instruction, and make an
electrical connectionas per diagram in previous slide.
3- Calibrate the impulse generator with positive polarity.
Note: Calibration can be done immediately before or during the period when the temperature of
the cable is maintained at a constant value.
4- For calibration of output impulse voltage, Increase the sphere gap setting so that
no flash over occursacross the gap during testing.
5- Enter the required test voltage at the “setting” control box (voltage as per page # 42).
6- Heat the sample cable and with the cable conductor temperature maintained at 85-100 °C,
apply a series of10 positive impulses to the sample.
7- Print the results recorded in the setting control box when 10 positive impulses are completed.
8- The impulse will automatically switch off when 10 positive impulse is completed.
9- Follow the same procedures above except that in the “setting” box, change polarity to “Negative”.
Note:
It is very important to exercise caution when applying impulse voltage to the cable.
It is highly recommended to test the cable with less voltage and increase until the required test
voltage is reached.
47
Power Cables Handbook
Non-electrical type tests on cable components and on complete cable, EHV Cables
48
Power Cables Handbook
Test Conditions
1- Ambient temperature
All tests are carried out at an ambient temperature of (20±15) C°.
2- Frequency and waveform of test voltage
The frequency of the alternating test voltage was in the range of 49 Hz to 61 Hz and the
Waveform was substantially sinusoidal.
3- Waveform of the impulse test voltage
The impulse wave was having a virtual front time between 1 µs and 5 µs and nominal time
attain half peak value between 40 µs and 60 µs.
4- All test conditions are in accordance with IEC 60060-1.
49
Power Cables Handbook
Tests for determining mechanical properties of over sheaths before & after ageing ( IEC 60840 -12.4.3 )
12 days
Ageing tests on pieces of complete cable to check compatibility of materials ( IEC 60840 - 12.4.4 ) 10 days
Pressure test at high temperature on over sheaths ( IEC 60840 - 12.4.6 ) 1 day
Hot set test for XLPE insulation ( IEC 60840 - 12.4.10 ) 1 day
Measurement of density of HDPE outersheath ( IEC 60840 - 12.4.11 ) 1 day
Measurement of carbon black content of black PE oversheaths ( IEC 60840 - 12.4.12 ) 2 days
Tests of Outer Protection for Buried Joint ( IEC 60840 - Annex H ) 8 day
Water immersion & heat cycling(7 cycles) 4 days
DC Voltage tests 1 day
Check Insulation Thickness of cable
Impulse voltage tests 1 day
Prior to the electrical type test the insulation thickness of the cable is measured and the average
thickness isofchecked.
Examination test assembly 2 days
50
Power Cables Handbook
NOTES:
• If the average thickness of the insulation does not exceed the nominal value by more than 5% the
test voltages shall be as specified in table 4 (IEC 60840) for the rated voltage of the cable
• If the average thickness of the insulation exceeds the nominal value by more than 5% but by not
more 15% the test voltages shall be adjusted to give an electrical stress at the conductor screen
equal to the applying when the average thickness of the insulation is equal to the nominal value
and the test voltage are the normal value specified for the rated voltage of the cable
• The cable length used for the tests shall not have an average thickness exceeding the nominal
value by more than 15%.
51
Power Cables Handbook
BENDING
Cycle no 1
A B
Directio
Direction of
n of
pulling
pulling
C D
Directio
Direction of
n of
pulling
pulling
52
Power Cables Handbook
Outdoor
Water termination termination
5M
5 M 5M
53
Power Cables Handbook
1
4
54
Power Cables Handbook
55
Power Cables Handbook
4- WATER TERMINATION
56
Power Cables Handbook
H.V Transformer
Heating Current
Outdoor
Water termination termination
Heater transformer
5M
5 M 5M
Dummy cable
Heater transformer
57
Power Cables Handbook
H.V TRANSFORMER
OUTDOOR
TERMINATION
WATER
TERMINATION
HEATING
TRANSFORMERS
HEATING
TRANSFORMER
INSULATED JOINT
SF6 JOINT
THERMOCOUPLE
CONECTOR
DUMMY
Lightning Impulse Voltage Test followed by a power frequency AC voltage test for Cable &
Accessories
• The test shall be performed on the assembly with the cable conductor temperature 5 °C to 10 °C
above the maximum conductor temperature in normal operation.
• The impulse voltage shall be applied according to the procedure given in IEC 60230.
• The assembly shall withstand without failure or flashover 10 positive and 10 negative voltage.
• After the impulse voltage test, the assembly shall be subjected to a power frequency voltage test at
2,5 U0 for 15 min.
• No breakdown of the insulation or flashover shall occur.
58
Power Cables Handbook
• Waveform of lightning impulse test voltages In accordance with IEC 60230, the front time of the
standard lightning impulse voltage shall be between 1 μs and 5 μs.
The time to reach half value shall be 50 μs ± 10 μs as specified in IEC60060-1.
59
Power Cables Handbook
P.D measurement at ambient & high temperature after Lightning impulse voltage test
60
Power Cables Handbook
61
Power Cables Handbook
62
Power Cables Handbook
◎ Flame Retardant
Fire retardant cables are designed for use in fire situations where the spread of flames
along a cable route needs to be retarded. Due to relative low cost, fire retardant cables are
widely used as fire survival cables. No matter the cables are installed in single wire or in
bundles, during a fire, the flame spread will be retarded and the fire will be confined to a small
area, thus reducing the fire hazard due to fire propagation.
63
Power Cables Handbook
release during the conversion of CO to CO2 during the fire. Therefore, to control the heat
release is the most important concern for reducing the fire hazard. However, in European
countries, halogen content, the corrosivity of the gases, the smoke density and the toxicity of
the gas are equally important factors affecting the safety and survival of human during a fire.
This test details a method of test for the assessment of the flame propagation
characteristics of a single wire or cable. In this test, a 60cm cable sample is fixed vertically
inside a metallic box and a 175mm long flame is applied at 45℃ from a gas burner placed at
450mm from the top at the upper portion. The specimen is deemed to have passed this test,
if after burning has ceased, the charred or affected position does not reach within 50mm of the
lower edge of the top clamp which is equivalent to 425mm above the point of flame application.
The test method is not suitable for the testing of some small wires due to the melting of the
conductors during the time of application of the flame.
64
Power Cables Handbook
65
Power Cables Handbook
66
Power Cables Handbook
67
Power Cables Handbook
68
Power Cables Handbook
69
Power Cables Handbook
70
Power Cables Handbook
When cable faults occur between two defined cores, such as cable conductor and cable screen,
methods using time domain reflectometry (TDR) can be used to pre-locate the fault position. However,
in some cases and in certain cable structures, faults can happen between core to the cable sheath or
surrounding soil. This is especially the case in unshielded cables such as high voltage DC cables used
for railway power supply, low voltage cables, and signal or pilot cables. Since the soil or surrounding
medium cannot be accessed like a grounded metal sheath or screen, TDR can no longer be used. A
TDR pulse can only travel along a path as long as two parallel conductive paths are given. Therefore,
pre-location for cable sheath faults is conducted using measuring bridge techniques. HV
TECHNOLOGIES, Inc. offers this solution with the Shirla Sheath Test and Fault Location Device,
which uses the measuring bridge principle according to Murray and Glaser.
71
Power Cables Handbook
The Murray and Glaser measuring bridge principles used in the Shirla Sheath Test and Fault
Location Device are based upon the simple Wheatstone Bridge measuring principle. This bridge
consists of two voltage dividers, which when balanced, have a ratio of R 1/R2 = R3/RX and the meter
reads zero. In order to determine the fault resistance (RX) of the faulted cable, R2 must be adjusted until
the measuring device reads zero. In this case, RX = (R2/R1) * R3
72
Power Cables Handbook
The measuring bridge circuit according to Murray is applied when only one additional healthy conductor
(auxiliary line) is present. Ideally this additional conductor has the same diameter and conductor
material so as to not have different resistance values affect the measurement. The resistance of the
loop bridge at the cable ends is also included in the measurement, and therefore, this must be of very
low resistance. In this case RX = (R2/R1) * (R3 + RLoop Bridge + R3b), where R3 is the resistance of the
auxiliary line, RLoop Bridge is the resistance of the loop bridge, and R3b is the resistance of the cable to
the fault from the loop bridge. The distance to the fault can then be calculated.
Using the Shirla, the Murray measuring bridge is connected to the cable in the following way. It is
important to remember that when trying to force a current flow from the sheath to earth through the fault
only, both ends of the cable sheath need to be disconnected from earth.
73
Power Cables Handbook
Glaser Bridge
The bridge measurement according to Glaser requires operation via two auxiliary lines. The advantage
is that different parameters of the conductors, such as material, cross-section and length, will not affect
the accuracy of the measurement. The major difference to the Murray method is that the forward path
defined via the two auxiliary lines is compensated and the remaining effective external circuit is the
sheath only. The influence of the R3 auxiliary line is eliminated and the bridge only sees the ratio of the
voltage divider in the cable. This compensation is very helpful, as the sheath is always of different
diameter compared to the core. In this case RX = (R2/R1 + RH) * R3b
Using the Shirla, the Glaser measuring bridge is connected to the cable in the following way. It is
important to remember that when trying to force a current flow from the sheath to earth through the fault
only, both ends of the cable sheath need to be disconnected from earth.
74
Power Cables Handbook
75
Power Cables Handbook
Testing should be performed by qualified personnel taking all appropriate safety precautions. The
responsible safety officer should be consulted regarding the equipment and the appropriate personnel
protection requirements.
IMPORTANT NOTE: The significance of performing DC high voltage tests on non-shielded, non-metallic
sheathed cable is dependent upon the environment in which it is installed because the characteristics
of the return circuits are unknown. The environment must be carefully considered or the test results
may not be significant.
In fact, these tests can result in damage to the cable insulation.
Humidity, condensation and actual precipitation on the surface of a cable termination can increase the
leakage current by several orders of magnitude.
Humidity also increases the corona current, which is included in the total leakage current. Wind prevents
the accumulation of space charges at all bare energized terminals. This results in an increase of corona.
It is desirable to reduce or eliminate corona current at the bare metal extremities of cable or terminations.
This may be accomplished by covering these areas with plastic envelopes, plastic or glass containers,
plastic wrap, or suitable electrical putty.
Let’s see now the general guidelines for high potential (Hi-Pot) DC testing of medium
voltage cables:
76
Power Cables Handbook
1. Pre-test Guidelines
a. Testing equipment
Direct current test equipment is commercially available with a wide range of voltages. The Operator’s
Manual for the particular test set being used should be read and well understood.
Accessory equipment necessary to safely conduct high voltage tests such as safety barriers,
rubber gloves, non-conducting hard hats, and, where necessary, arc ash protection must be used.
77
Power Cables Handbook
It is also advantageous to maintain these grounds longer and while reconnecting circuit components.
Acceptance testing is performed to detect any defects in cable insulation and
terminations which may have resulted from poor workmanship or mechanical damage. This proof test
confirms the integrity of the insulation and accessories before the cable is placed into service.
After installation and before the cable is placed in regular service, the test voltages specified in Table c.1.
should be applied for 15 consecutive minutes. Record the leakage current at one minute intervals for the
duration of the test.
Table c.1. – ICEA dc Field Test Voltages
ICEA S-97-682 Utility Shielded Power Cables Rated 5,000-46,000 Volts
Table – ICEA dc Field Test Voltages (ICEA S-97-682 Utility Shielded Power Cables Rated 5,000-46,000 Volts)
At any time during the warranty period, the cable circuit may be removed from service and tested at a
reduced voltage (normally 65% of the original acceptance value) for 5 consecutive minutes. Record
the leakage current at one minute intervals for the duration of the test.
Routine periodic DC maintenance testing of cables for the evaluation of the insulation strength is
not a common practice.
Some power cable users, particularly in the continuous process industries, have adopted a program of
testing circuits during planned outages, preferring breakdowns during testing rather than experiencing a
service outage during regular operations.
It is nearly impossible to recommend test voltage values for maintenance testing without having a history
of the cable circuit. An arbitrary test voltage level could result in a cable failure in a circuit that would
otherwise have provided long trouble-free service at normal operating ac voltage. Periodic off-line partial
discharge testing at very low frequencies (VLF) is a diagnostic method for monitoring the insulation
degradation of medium voltage cable. This type of testing is discretionary and generally not recommended.
78
Power Cables Handbook
CABLE TESTING
1. Switch the MAIN BREAKER ON of the test equipment. The AC ON lamp will light.
2. Close external interlock switch, if used.
3. Push the HV ON push button. The HV ON lamp will light. The VOLTAGE CONTROL must be at 0
(RESET) for the HV ON push button to operate. CAUTION: The unit is now capable of producing
high voltage at the OUTPUT.
4. Advance the VOLTAGE CONTROL slowly until the desired test voltage is read on the OUTPUT
VOLTAGE kilo-volt meter.
79
Power Cables Handbook
5. Maintain the test voltage for 15 minutes. The OUTPUT CURRENT meter indicates the leakage
current of the specimen under test. Select appropriate current range. See manufacturer’s instruction
manual for notes on interpretation of current readings.
6. After maintaining test voltage for 15 minutes, turn the VOLTAGE CONTROL, slowly, in the
counterclockwise direction to 0 (RESET).
7. Press the HV OFF push button, or open the external interlock switch.
8. Allow sufficient time for the specimen charge to bleed off, which is indicated when the kilo-volt meter
reading returns to zero.
9. Switch MAIN BREAKER off. WARNING: The specimen under test may retain a lethal electrical
charge even when the test set is turned off. The specimen must be discharged with a properly
grounded grounding stick. Keep the HV terminal of the specimen and the test set’s output
cable grounded at all times except when actually performing tests. Do not approach the HV
module until ground bonds have been applied.
10. Results shall be filed and recorded on applicable test form per approved SATIP.
NOTE: Plot the test voltage vs. leakage current on graph paper as the test The step voltage slope
should be reasonable linear for the graphic plots.
80
Power Cables Handbook
SAFETY PRECAUTION
o Secure the approved work permit from the concerned Representative before starting any work.
o Fire Watcher with Fire Extinguisher shall be assigned at work area whenever there is hot work.
o All electrical tools shall be checked and color-coded.
o Hazardous area and its precautionary measure requirements shall be properly discussed to the
working crew following all safety requirements.
o Continuous monitoring and checking shall be conducted by concerned supervisor/foreman to detect
and correct unsafe practices while performing the work activities.
o Provide warning sign and sufficient barricade on working areas to avoid unauthorized entry. Only
assigned personnel shall be allowed in the area.
o Safety harness with double lanyards shall be used when working at elevated temporary platforms
(1.8 meters and above).
o Safety Supervisor shall monitor the work activities to help and protect all assigned workers against
exposure to safety hazards. He shall ensure that Personal Protective Equipments (PPE’s) are being
supplied and used and shall comply with Contractor and client applicable general instruction and
standards.
o Toolbox meeting shall be conducted by Electrical Supervisor daily so that work activities will be
properly coordinated to all concerned and all safety measures will be carried out on the entire work
duration.
o Housekeeping shall be maintained and working area shall be kept clean and tidy in accordance with
Site Housekeeping Procedure.
o Job Hazard and Risk Assessment of this procedure shall be disseminated and explained to workers
for safety awareness.
All tools utilized in a classified area should be intrinsically safe and suitable for hazardous areas.
81
Power Cables Handbook
59
82
Power Cables Handbook
Measurements with a frequency close to 0Hz are leading to results according to DC measurements
(ks=0), with higher frequencies the results represent the conductor design described by the ks factor.
It can be assumed that the area of application of the formulae (2) and (3) are limited in terms of the
frequency. In this paper both values have been derived by analytical calculations and compared with
the measured values.
The block diagram of used equipment is given in figure 6.
The voltage taps of the cable conductor impedance and shunt are used for the measurement of the
conductor voltage drop and the injected AC current. The AC source is the combination of a function
generator (to generate sine wave of variable frequency) and a power amplifier (suited for impedances
down to 2 Ohm). The shunt is specially designed for high-accuracy current measurements with very low
phase displacement.
In an on-line measurement following data are processed and calculated:
Frequency [Hz]
Voltage [V] and Current [A]
Phase difference [rad]
Active Power [W]
Reactive and apparent power [VA]
Efficiency factor cos-phi and tan delta
Serial and parallel resistance [Ohm]
The accuracy of the measured phase difference has been determined to approx.
The phase error uncertainty has been determined to approx. +/- 5 x 10-5, the total measurement
uncertainty was < 0.01% of the actual input range.
An overview of the equipment needed for the AC resistance measurement is shown in figure 7.
83
Power Cables Handbook
The measurements have been performed with low current magnitude, any distortion by line frequency
was easily to suppress. The used measurement equipment showed a high sensitivity. Thus, the
measurements can be performed at extremely low current magnitude (e.g. 0.2%
of the rated current) excluding any thermal effects and so enabling the use of a low power AC current
sources.
The measurements have been performed on two different cables:
1. BNC cable type RG58
2. 500kV XLPE cable
• Conductor: 2500mm2 copper conductor, round, segmented, stranded, longitudinal water-tight
• Screen/metallic sheath: copper wire and copper tape cross section 300 mm², longitudinal water-tight.
RESULTS
With variable frequency it becomes possible to fit the measured AC resistance data as a function of AC
frequency to the analytical skin effect function (first-order Bessel function) by parameter identification,
resulting in a precise estimate of the ks factor. Furthermore, this procedure provides a 'built-in' self-check
to verify the results: extrapolating the identified curve for f → 0 should deliver the DC resistance of the
conductor, which can be easily cross-checked by DC resistance measurement.
The result of the measurement of the AC resistance measurement for both measured cables are shown in
figure 8 and 9.
84
Power Cables Handbook
Regarding the 500kV XLPE cable 2500mm2 in figure 9 the significant break starts at 20Hz. From here
there is a dependence of the frequency obvious. Compared to the BNC cable the break starts
approximately two dimensions lower.
Up to 100Hz the measurement results are in good accordance with the calculated values of a first-order
Bessel function, but above 100Hz the calculation differs from the measurement. The steepness of the
measured development is much higher than the calculated. It must be assumed, that so far unknown
effects cause this deviation.
85
Power Cables Handbook
86
Power Cables Handbook
h- Schering Bridge
1- Tan Δ Measurement
2- Capacitance Measurement
87
Power Cables Handbook
88
Power Cables Handbook
89
Power Cables Handbook
90