Professional Documents
Culture Documents
CM-FM-QHSE-01-06 Internal Audit Report 2020
CM-FM-QHSE-01-06 Internal Audit Report 2020
CM-FM-QHSE-01-06
Audit Results:
Based on the results of the audit, the audit team determined that the management system was effectively implemented and
maintained per defined requirements and is deemed capable to achieve expected outputs.
Summary of the evidence relating to Record and checklist covers all areas and procedures. There was no non-conformity on
the audit. Sampled several opportunities for improvement recorded.
Documents / Records:
1. QHSE manual CM-MM-01 Edition 3, updated on 26th March 2020
2. Internal & External issues, updated on 26th March 2020
3. Clause 6.1 Address risks and opportunities
[Review and update risks and opportunities of the organization]
4. Clause 6.2 objectives, target and plans
[Review and update objective, target and plan of the organization]
5. Clause 7.5 Documented Information
[some of documents in a few department not registered to master list document and need to register]
6. Clause 9.2 Internal Audit
[Internal audit procedure and all the related forms, implemented 2 times in a year]
7. Clause 10.2 NC and Corrective action
[NC and Corrective action procedure and all the related forms]
8. Clause 9.3 Management Review
[Management Review procedure and all the related forms, implemented 1 in a year]
Documents / Records:
1) Clause 6.2 objectives, target & what plans
[Target for Scrap of 2020: 7%; optimal design using NC program; reuse SMO 254 Scrap for Scrubber body plate and
socket was achieved 100%]
2) Clause 7.4 Prove how the external communication processes
[with e-mail and phone call, attendant meeting with customer]
3) Clause 7.5 Documented Information
[Some of form record not register in master list document]
4) Clause 8.3 Prove the design & development requirements have been met
[Design Procedure and the forms]
Documents / Records:
1. Clause 6.2 objectives, target & what plans
[Target for FAT: Scrubber air leak test and sea water pipe hydro test with owner/class was achieved 100%]
2. Clause 7.1.5 Monitoring and measuring resources
[record of calibration certificate, material traceability list, Receiving inspection, pipe inside check]
3. Clause 7.5 Documented Information
[Procedure and related forms already registered to Master List Document]
Documents / Records:
1) Clause 6.2 objectives, target & what plans
[According this situation, no target and plan to do]
2) Clause 8.5.1 Prove control of production and service provision
[Production status – progress report; monitoring production schedule based on delivery date from master schedule]
3) Clause 7.5 Documented information
[Procedure and related forms already registered to Master List Document]
Documents / Records:
No. CM-FM-QHSE-01-06
Documents / Records:
1. Clause 6.2 objectives, target & what plans
[Less paper and online system have been achieved]
2. Clause 7.2 Prove the competence of person(s) doing work
[Recruitment procedure and the forms]
3. Clause 7.4 Prove the training plan and budget
[Training procedure and related forms]
4. Clause 7.5 documented information
[all documents and records are well registered]
Documents / Records:
1) Clause 6.2 objectives, target & plans
[No commissioning activity because there is no project]
2) Clause 7.4 Prove how the external communication processes
[with e-mail and phone call, attendant meeting with customer]
3) Clause 7.5 documented information
[Procedure already registered]
Documents / Records:
1. Clause 6.2 objectives, target & plans
[The target is well achieved]
2. Clause 6.1.2 Hazard Identification Risk Assessment & Environmental Aspect Impact
[HIRA & EAI Recorded and review with all related department on production]
3. Clause 6.1.3 Legal regulations and other requirements
[All Legal regulations and other requirements are recorded and implementation as per related to company process]
No. CM-FM-QHSE-01-06
Documents / Records:
1. Clause 6.2 objectives, target & plans
• Correct information regarding docking schedule in order to prepare a shipment arrangement (achieved 80%)
• Vendor selection to do provide the best cost (achieved 80%)
• Minimize parsial shipment in order to be able to cut the handling cost (achieved 50%)
2. Clause 7.5 Documented information
[Document is control Recorded]