Auburn University CADS 5600/6600 Global Sourcing Dr.

Hongjoo Woo

Time & Action Calendar


Department: Bag/ Accessories
Season: SS23
Date created: 11-Nov-2022
Date approved: 17-Nov-2022

Step Activities Department Lead Time (days) Target Date 1 Target Date 2
1 Order confirmation Merchant 0 01-Dec-2022 01-Dec-2022
2 PO received Supplier 1 01-Dec-2022 02-Dec-2022
3 Fabric/ trims PO received Supplier 10 02-Dec-2022 12-Dec-2022
4 Size set submission Merchant 2 12-Dec-2022 14-Dec-2022
5 Fabric quality apporval Production Manager 14 14-Dec-2022 28-Dec-2022
6 Lab dip approval Production Manager 5 28-Dec-2022 01-Jan-2023
7 Transport (K->V) Merchant 1 01-Jan-2023 02-Jan-2023
8 PP manufacture Manufacturer 1 02-Jan-2023 03-Jan-2023
9 Transport (V->K) Merchant 1 03-Jan-2023 04-Jan-2023
10 PP meeting Merchant 0 04-Jan-2023 04-Jan-2023
11 PP updates & approval Production Manager 14 04-Jan-2023 18-Jan-2023
12 Production Production Manager 28 18-Jan-2023 14-Feb-2023
13 pattern grading Pattern master 5 18-Jan-2023 23-Jan-2023
14 cutting Cutting in-charge 2 23-Jan-2023 25-Jan-2023 Start date: 01-Dec-2022
15 re-cutting Cutting in-charge 1 25-Jan-2023 26-Jan-2023 Finish date: 23-Feb-2023
16 sewing Sewing in-charge 14 26-Jan-2023 09-Feb-2023 Production time: 28days
17 finishing Finishing in-charge 5 09-Feb-2023 14-Feb-2023 Lead Time: 88days
18 Packaging Finishing in-charge 5 14-Feb-2023 19-Feb-2023
19 Transport (V->K) Merchant 1 19-Feb-2023 20-Feb-2023
20 Inspection Quality control 3 20-Feb-2023 23-Feb-2023