Professional Documents
Culture Documents
SP-C02 Installation
SP-C02 Installation
2005
Contents
1 Technical Data............................................. 3
2 Dimensions and weights of packages ......... 4
4 Transport..................................................... 4
C2. Installation
securing device ...................................... 9
10 Start-up ...................................................... 17
-2- C2—Installation SP
10.2006
1 Technical Data
Room temperature
For guaranteed precision 20℃ ±3℃
For operation of machine 15℃ ~ 30℃
SP C2—Installation -3-
01.2006
Performance
Max. machining current 50A/100A
Best surface roughness Ra≤0.4µm
o
Lowest electrode wear ≤0.3 /oo
3 Transport means
4 Transport
Move the single part of the system to the installation site according to the instructions for
each one.
Caution: Move or lift the packed unit(s) or unpacked system elements only as described or
illustrated!
[1] Unload the packed system (components) from the road or rail vehicle with a fork lift truck or
elevator truck. If the crates are visibly damaged, do not unpack the system before notifying
our company and the insurance company.
● lifting capacity
main machine ≥3000kg
generator ≥1200kg
● fork length ≥1830mm
-4- C2—Installation SP
03.2005
[2] Do not drop or tip the packages.
[3] Open crates only under cover.
Warning: Airtight packing--please do not open!
- The parts of the system packed in the moisture barrier bag must remain at their place of
installation for 24 hours before opening the bag. This reduces the risk of corrosion due to
condensation.
- If there is visible damage to the system, inform our company or agents and the insurance
company. Photograph the damaged parts.
[4] Transport the system units to the place of installation. Let stand for the acclimatization
period (24 hours) before opening the bag.
The cartons of accessories delivered with the system are to be kept under lock and key
together with the dispatch documents to await check after the arrival of the commissioning
engineer.
Caution: The transport or lifting of system elements is only to take place as described or
illustrated below!
[1] Open the protective aluminum bag and pull it down to expose the machine.
SP C2—Installation -5-
03.2005
[4] Insert two steel tubes (Φ70mm, wall thinkness >10mm, length : one>1500mm, one > 2500
mm ) into lifting holes, and lift as shown in the following figure.
3. Soft materials
4. Brace L3
For SP1:
L1=1000mm
L2=2000mm
L3=1300mm
For SP3
L1=1500mm
L2=2500mm
L3=1800mm
Note: Soft materials should be padded where lift rope contacts the machine tool’s surface.
[5] Fit the attached machine seats, then place machine down (see Chapter 2 “installation
plan”).
-6- C2—Installation SP
03.2005
5.2 Generator
● Crane
The generator has four 25mm inner diameter eyebolts (lifting rings) to allow you to move the
unit. We recommend that you use two 610mm braces.
SP C2—Installation -7-
03.2005
CAUTION:
If you wish to lift the
generator without a brace,
it is imperative that you
proceed as shown in the
right diagram. Otherwise
you could damage the
cabinet.
[4] After lifting the generator, remove the four M10 screws (B) and the wooden beams. Screw
the four leveling screws into the base of the generator.
Screw
Air deflector
[6] Install the air deflector (foe 100A
generator), packed in the packing case.
See the right figure:
-8- C2—Installation SP
03.2005
5.3 Dielectric Unit
[1] Pull down the protective aluminum shroud to expose the dielectric unit.
[2] Remove the screws securing the dielectric unit.
[3] Move the unit with a fork lift truck or crane.
● Crane
Screw
Facing the system, remove the bellows to expose the work table securing device in red.
Remove it, then replace the bellows.
Facing SP3 machine, remove the left protection cover to expose the red securing block for
the saddle. Remove it and replace the cover. For SP1, remove the lower left plate of the
protection cover to expose the red securing block. Remove it and replace the plate.
SP C2—Installation -9-
03.2005
6.3 Remove the spindle shipping brace
- 10 - C2—Installation SP
01.2006
7.3 Installation of the machine
Caution: Moving or lifting system units must take place only as described or illustrated above.
Transport the system components to the final installation location and assemble according to
the installation plan.
The choice of the place of installation is very important for a precision machine tool. The
accuracy of the work-piece depends on it.
●Vibrations
If possible, do not install this system near machines that transmit vibrations through the
foundations (loss of the precision of alignment of the machine). If sources of disturbance are
unavoidable, mount the machine on vibration-damping elements. Fixing with anchor bolts is not
necessary.
● Dust
Install the system in a room as free dust as possible. Locate your machine away from
equipment used to machine graphite. Graphite dust is highly conductive and can cause short
circuits in electronic components. Locate your machine away from grinders, sand blasters and
chip producing equipment. Dust particles from grinders, for example, are highly abrasive and
can cause abnormal wear on ball screws, rails and table.
SP C2—Installation - 11 -
03.2005
7.3.3 Installation layout
- 12 - C2—Installation SP
03.2005
[2] Foundation drawings
X Y Z A B C
SP1 3000 mm 2700 mm 300 mm 1500mm 1200mm 500mm
SP3 3800 mm 4200 mm 300 mm 2360mm 1700mm 700mm
SP C2—Installation - 13 -
03.2005
[3] Machine feet schematics
CG
460
CG
700
- 14 - C2—Installation SP
10.2006
8 Level the machine
Windscreen
Note: User need take out the windscreen from accessory box and
install it on the cabinet for 100A cabinet.
10 Start-up
Note: ALL the above work should be carried out exclusively by our service technicians.
10.2 Start up
After the above checks and
confirmation, perform as
follows:
SP C2—Installation - 17 -
03.2005
upon completion of setting.
12 Functional checks
- 18 - C2—Installation SP