Professional Documents
Culture Documents
03 - 14 Feb 2022
COMPULSARY DOCUMENT
Construction safety planning SIPP & Daily Check Hirarc Workers List
OTHERS ( IF RELATED)
SDS Competence Certificate B. ownership form Calibration Certificate Other:
COMMENCEMENT DATE: _____/_____/_____ TIME _________ HRS COMPLETION DATE: ______/______ /______ TIME:_________ HRS
I UNDERTAKE TO COMMUNICATE THE HAZARDS TO THE WORKFORCE / VENDOR AND TO STOP THE WORK IMMEDIATELY IN THE
EVENT OF CHANGE OF CONDITION / INCOMPATIBLE WORK.
NOTE: SOFTCOPY COMPULSARY AND ATTACHMENT MUST SUBMIT TO EHS DEPT. 24H BEFORE START WORK.
STAGE 4: PERMIT CANCELLATION BY EHS DEPT. / MANAGER (IF ANY VIOLATION HAPPEN)
Name Signature Emp. No. Date & time
IMPORTANT: ANY CHANGES IN THE ABOVE & CHECKLIST CONDITIONS WILL IMMEDIATELY INVALIDATE THIS PERMIT
ESV-02-000 (Form 16) Rev. 02 - 03 May 2021 Page 1/2
DESCRIPTION OF WORK:
IMPORTANT : If the requirements stipulated in the Daily Checklist are not met, permit will be automatically INVALIDATED
ESV-02-000 (Form 7) Rev.02 - 03 May 2021 Page 1/1
DESCRIPTION OF WORK:
The following are to be checked and confirmed before commencement of working at height:
(a) Worker understand job scope and working at height SOP (ensure at least 2 person work - buddy system).
(b) Scaffolding/ladder already inspected in good condition.
(c) Lifting equipment ( e.g.: sky lift) has valid certificate of fitness.
(d) Suitable fall prevention already applied (harness/safety belt/guarding).
(e) Surrounding and weather in good condition (Wind speed is below 25km/h).
(f) Suitable fall prevention already applied (life line,harness/safety belt/guarding).
NOTES: 1) Please tick (/) the column below (checked by Subcontractor & verified by IEM PIC).
2) IEM PIC must close this form and hand over to EHS.
IMPORTANT : If the requirements stipulated in the Daily Checklist are not met, permit will be automatically INVALIDATED
ESV-02-000 (Form 16) Rev. 02 - 03 May 2021 Page 2/2
INSTRUCTOR COMPANY
10
11
12
13
14
15
16
17
18
19
20
TTE (M) ENGINEERING (M) SDN.BHD.
Work Location Process / Work Activities Date Prepared By Initial Review By
B2 - Production Speaker Installation Work 15/10/2022 AMIR IZAN FIDA'IY
HAZARD DEFINITION CURRENT & PLANNING CONTROL RISK ANALYSIS RISK CONTROL AND STATUS
(1) Elimination
(2) Substitution
JOB STEP A/N/E (3) Isolation / Engineering
HAZARD CONSEQUENCES L S R ADDITIONAL ACTION STATUS RESPONSIBILITY
(4) Administration
(5) PPE
Note: Minimum Administration Control is required
1) Only allow trained person with IEM Module B and
Register to conduct work inside Workers list to
enter for IEM Premises.
Workmen not
Pre-construction health 1) Identify/prepare related layout drawing and identify
aware of the
& safety meeting On-Site any risky area. Supervisor/
1 N hazards or workers First aid injury 1 1 1 Nil
where work will be 4) Follow procedures stated in the work HSE Team
do not receive
performed. permit/checklist (if any)
suitable training
4) TBM and identify potential hazards before start.
4) Set-up Traffic Control Equipment (if needed).
5) Check PPE suitable for the job task
VERIFIED BY: CONTRACTOR PIC REVIEWS BY: IEM PROJECT PIC (PROJECT OWNERS) REVIEWS BY: IEM EHS
Below Ceiling
4. Ensure ladder in good condition
1. To climb on
Platform / A frame 5. To wear harness and hook to solid structure.
4 ladder and make 3. Apply buddy system
hole on the ceiling 4. Ensure that the ladder is placed on a level, stable
surface by cordless surface.
drill machine. 4. Avoid climbing a ladder in wet shoes as this
increases the risk of slipping Continues monitoring by
3. Never work from the top three rungs of the supervisor team
2. To install 5 nos of
1.Minor/major injury ladder.
bracket and new 1.Falling from height -Close monitoring by M
N 2.Backpain muscular 3. Maintain three point contact on the ladder - SUPERVISOR /HSE
speaker using hand 2.Ergonomic hazard 2 4 8 supervisor
tools. (bolt and nut 3.Electrical hazard 3.Electrical shock two feet and one hand, or two hands and one foot. Sufficient lighting while
-
installation) 4.Edge sharp object 4. Inhalation 3. Never place ladders near power lines, on ice,
work above ceiling.
Height : 2.3 Mtr 5.Dust or against unstable surfaces or structures -Do not drop any tools
5. Wearing PPE such safety helmet, safety shoes, from above ceiling
Above Ceiling glove, N95 mask and safety harness.
3. Ensure power supply switched off (LOTO)
4. To do cable pulling prior start by IEM PIC.
from existing speaker to 4. To install plastic cover for drill point to
new speaker location in prevent dust.
range 30 mtr max.
VERIFIED BY: CONTRACTOR PIC REVIEWS BY: IEM PROJECT PIC (PROJECT OWNERS) REVIEWS BY: IEM EHS
VERIFIED BY: CONTRACTOR PIC REVIEWS BY: IEM PROJECT PIC (PROJECT OWNERS) REVIEWS BY: IEM EHS
Likelyhood indicate “PROBABILITY” for any Incident / Accident to happen as below table (if work conducted strictly follow HIRARC control):
Rating 1 2 3 4 5
Inconceivable Remote Conceivable Possible Most Likely
Likelyhood to happen Maybe Happen in the Normally to happen Normally to happen
Impossible to happen Never Happen inside IEM
future (Yearly Basis) (Monthly Basis) (week Basis)
Severity indicate how “SEVERE” the injury /damage can accur if any Incident / Accident happen (take the highest severity if accident/incident happen):
Severity Rating Category
Catastrophic 5 More than one (1) fatality, property / equipment damage which can’t be repair (total damage)
Fatal 4 One (1) fatality, property / equipment damage which can be repair
Serious 3 Permanent injury to any employees body part
Minor 2 Lost Time Injury but employees can recover back
Negligible 1 First aid injury to employees
High Risk (H) (15-25) Work can’t proceed, immediate action need to be taken and been monitored closely
Medium Risk (M) (5-12) Work can be proceed and further risk control improvement can be reviewed
Low Risk (L) (1-4) Work can be proceed follow existng risk control
B2 PRODUCTION
1 Unit
LJ
L'l■J
Z1-3 REALLOCATION OF
DOUBLE LEAVE DOOR
e
1 Unit
� - - -- - - -- ·-zli-LCS Z8-LC3
Z8-�C2 , Z7-LC5•2
Z8-LC2 I
X
I
I
V
27-16 29-13
I
• e
I
!
■ ■ ■ ■ ■ ■ ■ ■ ■ ■
I Z/.17 Z7-18
V
I
I 27-17 29-14
B?- I
A
Z1-LC-1 I
I
I
1 Unit
I Zli-LC1-2,
e
I
I
I Z8-LC3-2 �
I
I
I �g·:
ZS· C2-1 ZS.LC2·1 Z7-19 �
� ZT-21 Z7-20 �
■ ■ e
27-24 B::- Z9-21 ZS- 0 Z9-19
2 Unit
u u tJ u