EOD Installation

with Recessed Pit

Applies to Edge-of-Dock levelers manufactured beginning Fig. 1 Upper and lower flange must
March 2009 with the serial numbers 10263626 and higher. have 1/4" x 1" x 8" strap anchors
alternating every 10" with outboard
Mechanical EOD levelers straps on top flange
12" Dock floor
1. Use a minimum 12" x 14" pit recess with an additional 3”
of clearance per side of leveler. See Fig. 1.
8"
2. Follow the section that addresses your installation and min.
then continue to the GENERAL INSTALLATION section 13"
in the your User’s Manual included with your leveler.
14"

All anchors
1/4"

Dock Face

8"
min. SECTION A-A
40°

Outboard strap
on top

Steel, ASTM A36


C8 X 11.5# min.

Steel, ASTM A36

1-1/2"
1/4" A

8-1/4" Weld corners


1"

3" x 3" x 1/4" curb angle


with anchors (by others)

Architect to specify thickness of


concrete floor and dock wall A
for specific application

Leveler deck width + 6"

April 2009 6007830A — EOD Recessed Pit Installation 1


©2009, 4Front Engineered Systems, Inc.
EOD Installation
with Recessed Pit

powered EOD levelers Fig. 2 Upper and lower flange must


have 1/4" x 1" x 8" strap anchors
1. Use a minimum 12" x 25" pit recess with an additional 3” alternating every 10" with outboard
of clearance per side of leveler. See Fig. 2. straps on top flange
12" Dock floor
2. Follow the section that addresses your installation and 3"
then continue to the GENERAL INSTALLATION section
in the your User’s Manual included with your leveler.
8"
min.
24"
25"

4"
All anchors
1/4"

Dock Face

8"
min. SECTION A-A
40° Outboard strap
on top
Push-button
control box
3/4" conduit
located as required
Steel, ASTM A36
C8 X 11.5# min. per local codes
(by others)

Steel, ASTM A36 Outdoor receptacle or 48"


junction box (by others)
1-1/2"
1/4" A

8-1/4" Weld corners

1"

3" x 3" x 1/4" curb angle


with anchors (by others)

Architect to specify thickness of


concrete floor and dock wall A
for specific application

Leveler deck width + 6"

2 6007830A — EOD Recessed Pit Installation April 2009