Professional Documents
Culture Documents
Case 1:
Case 2:
Case 3:
3. A financial analysis of two types of bridges based on capitalized cost and on the
following data is to be made:
Bridge A Bridge B
Initial Cost P200,000 P240,000
Cost of Renewal P200,000 P240,000
Salvage Value 0 P20,000
Annual Maintenance P1,000 None
Repairs every 5 years P10,000 P5,000
Life 30 years 40 years
4. Compare alternatives shown on the basis of their capitalized cost using an interest
rate of 10% per year.
Project A Project B
First Costs, Php P150,000 P800,000
Annual operating cost, Php P50,000 P12,000
Salvage Value, Php P8,000 P1,000,000
Life, years 5 years ∞