NATIONAL PETROLEUM CONSTRUCTION COMPANY

APPENDIX B - SCHEDULE OF PRICES & RATES


NPCC ENQUIRY NO : YRD-MGT-2022/366/A/MJ
Quoted Discounted
Firm / Unit Price Excl. Unit Price Excl.
Item Item Desc Unit Desc Optional Qty. VAT VAT Difference Remarks
WAS NOW

Design Stage

Concept Design = 30% of Design (Phase 1 & 2)


Data collection (5 Discipline Engr. x 5 Days x 8 Hr./ Day=(5x5x8x150)=30,000 SR)
Development of Concept Design & Master plans for the
1 Lump Sum Firm 1.00 1,223,938.00 765,842.00 458,096.00 3 D Rendering 55,000 SR
Complete project (Phase 1 & 2) AbuDhabi Visit = 30,000 SR
The Environmental Impact Assessment = (250,000 x 1.1) = 275,000 SR

FEED Design development Phase -1


FEED Design development as Per The Scope of Work (Phase -
2 Lump Sum Firm 1.00 1,473,860.00 801,592.47 672,267.53 3 Drendering 65,000 SR
1) AbuDhabi Visit = 30,000 SR

FEED Design development Phase -2


FEED Design development as Per The Scope of Work (Phase -
3 Lump Sum Firm 1.00 387,828.00 247,873.00 139,955.00 3 D Rendering 47,500 SR
2) AbuDhabi Visit = 30,000 SR

FEED Design development as Per The Scope of Work (Phase - Bathymetric and Marine Survey & Studies (550,000 x 1.5) = 825,000 SR) and also provide
4 Lump Sum Optional - design the Facility no. 28,29,30,31)
2) Jetty and berth area (Facility no. 28,29,30,31)

Tendering Stage

The Engineering Consultant Fees to prepare and assemble the


technical bid documents and other information needed to float
2 Engineer x 29500/Month =59,000 SR
enquiry for the Yard construction works 2 Support Staff x 18,000/Month = 36,000 SR
5 Lump Sum Firm 1.00 95,000.00 95,000.00 -
Total = 59,000 + 36,000=95,000 SR
**this shall include the offers clarifications response,
technical analysis, award technical recommendation.

Supervision Stage

Engineering fees as for the office support works during the EPC
stage (inspection, testing & commissioning, reporting, review 1 Engr. x 2 Months x 5 Discipline
6 Lump Sum Firm 1.00 663,750.00 400,000.00 263,750.00 1 CAD x 1 Months x 5 Discipline
and endorse the Detailed Design, MAR review, and others as
per the scope of work)

7 Unit Rate for Engineering Inspection

7.1 Civil Engineer (inspections) SAR/Day - 1.00 2,500.00 2000

Legend:
1*) Bidders should quote in the unit of the measures specified by NPCC only.
2*) 'F' = Firm Scope , 'O' = Optional Scope.
NOTE: Quoted rate(s) shall remain firm and shall not be subject to revision or escalation through out the period
NATIONAL PETROLEUM CONSTRUCTION COMPANY
APPENDIX B - SCHEDULE OF PRICES & RATES
NPCC ENQUIRY NO : YRD-MGT-2022/366/A/MJ
Quoted Discounted
7.2 Electrical Engineer (inspection) SAR/Day - 1.00 2,500.00 2000

7.3 Mechanical Engineer (inspection) SAR/Day - 1.00 2,500.00 2000

7.4 Structure Engineer (inspection) SAR/Day - 1.00 2,500.00 2000

7.5 Architect (inspection) SAR/Day - 1.00 2,500.00 2000

Others

8 Drawings Printout (full size) - if requested by NPCC SAR/Set - - 3 Set x 397 Drawings x 20 SR/ Drawings = 23,820 SR

Authorities Fees as Required to Get full approved design


1 Engineer x 0.5 Month x 29500/Month =14,750 SR
9 Lump Sum - 1.00 118,750.00 118,750.00 1 Support Staff x 0.5 Month x 18,000/Month = 9,000 SR
** Fees Shall be as per Actual Total = (14,750 SR + 9,000) x 5 Authorities=23,750 x 5 = 118,750

3,963,126.00 2,429,057.47 1,534,068.53

TOTAL EXCLCLUDING VAT


TOTAL INCLUDING VAT

Legend:
1*) Bidders should quote in the unit of the measures specified by NPCC only.
2*) 'F' = Firm Scope , 'O' = Optional Scope.
NOTE: Quoted rate(s) shall remain firm and shall not be subject to revision or escalation through out the period
ENGINEERING CONSULTANCY SERVICES FOR PACKAGE 2, CONSTRUCTION OF NPCC KSA YARD FACILITIES

SUMMARY OF DESIGN COST

Item No. Item Description Total Amount (SR) Remarks

Development of Concept Design & Master plans for the Complete


1 375,842.00 30% of design Cost of Phase 1 & 2
project (Phase 1 & 2)

2 FEED Design development as Per The Scope of Work (Phase -1) 706,592.47 70% of design Cost of Phase 1

3 FEED Design development as Per The Scope of Work (Phase -2) 170,373.00 70% of design Cost of Phase 2

Design of Facility no. 28,29,30,31= 330,600


FEED Design development as Per The Scope of Work (Phase -2) Jetty Survey & Marine Study
4 880,000.00
and berth area (Facility no. 28,29,30,31) Third Party Cost + AJEC Coordination and handling Charges) =
800,000+400,000)

250,000.00 1 Engr. x 2 Months x 5 Discipline


Engineering fees as for the office support works during the 150,000.00 1 CAD. x 2 Months x 5 Discipline
6 EPC stage (inspection, testing & commissioning, reporting,
review and endorse the Detailed Design, MAR review, and 400,000.00 Total Amount for Item # 6
others as per the scope of work)
ENGINEERING CONSULTANCY SERVICES FOR PACKAGE 2, CONSTRUCTION OF NPCC KSA YARD FACILITIES

SUMMARY OF COST

Sr./ Hourly
Designation Monthly Salary
No. Salary

a Engineer 25,000 103

b CAD Designer 15,000 62

Sr./ No. of Unit Price Total Estimated


Designation Unit Man-hours Concept Design FEED Design
No. Drawings (SR) Amount (SR)

1 FEED Design development (Phase -1)

a Engineer Man-hours 5205 103 534,760.27


292
b CAD Designer Man-hours 7700 62 474,657.53 30% of Design 70% of Design

Total for Phase 1 12905 1,009,417.81

Total Cost for Phase 1 1,009,417.81 302,825.34 706,592.47

2 FEED Design development (Phase -2)

a Engineer Man-hours 1220 103 125,342.47


91 30% of Design 70% of Design
b CAD Designer Man-hours 1915 62 118,047.95

Total for Phase 2 3135 243,390.41 73,017.00 170,373.00

375,842.34

3 OPTIONAL COST (Phase 2)

I FEED Design development (Phase -2) Jetty and berth area (Facility no. 28,29,30,31)

a Engineer Man-hours 1740 103 178,767.12


24
b CAD Designer Man-hours 1160 62 71,506.85

Total 2900 250,273.97

Total Cost for Design Drawings 250,273.97

II Bathymetric and Marine Survey (Assessment Thirdy Party Price x 1.5) 605,000.00

Total Optional Cost (Item # I & II) 855,273.97

II Survey and Studies

a The Environmental Impact Assessment (Thirdy Party Price x 1.1) 275,000.00

b Bathymetric and Marine Survey (Thirdy Party Price x 1.1) 605,000.00

Total for Survey and Studies 880,000.00

Page 4 of 59
ENGINEERING CONSULTANCY SERVICES FOR PACKAGE 2, CONSTRUCTION OF NPCC KSA YARD FACILITIES

SUMMARY OF DRAWINGS AND COST

Ref. No. ESTIMATED NO. OF DRAWINGS ESTIMATED MAN-HOURS UNIT RATE (SR)
TOTAL AMOUNT
(Master FACILITIES
(SR)
Yard Plan)
AR SE ME EE & TE CE/ LS Total CAD ENGR. TOTAL CAD ENGR.

PHASE 1 b c d e f g=(b x e)+(c x f)

A BUILDING WORKS

GENERAL DRAWINGS 3 2 2 1 8 155 115 270 75 165 30,600.00

1 BEAM SHOP 2 2 2 3 9 235 160 395 75 165 44,025.00

2 PLATE SHOP 2 2 2 3 9 235 160 395 75 165 44,025.00

3 PIPE/TUBE SHOP 2 2 2 3 9 210 145 355 75 165 39,675.00

4 LEG AND PILES FABRICATION 3 2 2 3 10 255 170 425 75 165 47,175.00

5 AUTO BLASTING AND PAINTING MACHINE 2 2 3 3 10 270 185 455 75 165 50,775.00

6 TOWER CRANES LAYOUT 0 2 0 2 60 40 100 75 165 11,100.00

7, 8 & 9 GANTRY CRANES LAYOUT (25 MT & 10 MT) 0 8 0 8 240 160 400 75 165 44,400.00

10 CLOSED WAREHOUSE 1 3 3 4 5 15 375 255 630 75 165 70,200.00

11 CLOSED WAREHOUSE 2 3 3 4 5 15 375 255 630 75 165 70,200.00

12 OPEN SHEDS 1 1 0 2 60 40 100 75 165 11,100.00


13, 14, 15 &
GAS STORE (OXY, ACET., PROP., ARGON) 4 4 4 8 20 540 380 920 75 165 103,200.00
16
YARD SUPERVISORS OFFICE + QC FACILITY OFFICES
17 4 2 4 5 15 385 260 645 75 165 71,775.00
+ HSE FACITLITY OFFICES

18 QC FACILITY OFFICES (COVERED IN S.NO 17) 0 0 0 0 0 0 0 0

19 HSE FACITLITY OFFICES (COVERED IN S.NO 17) 0 0 0 0 0

a YARD MANAGEMENT OFFICES 4 2 4 5 15 360 245 605 75 165 67,425.00

b AID / E&I / COMMISIONING FACILITIES 3 2 4 5 14 365 250 615 75 165 68,625.00

c CLIENT OFFICES 3 2 4 5 14 365 250 615 75 165 68,625.00

d MESS HALL 4 3 4 6 17 430 295 725 75 165 80,925.00

e CLINIC 3 2 4 4 13 340 230 570 75 165 63,450.00

f MOSQUE 6 4 4 5 19 505 340 845 75 165 93,975.00

g DOMESTIC PUMP ROOM 1 1 1 2 5 135 95 230 75 165 25,800.00

h FIRE PUMP ROOM 1 1 1 2 5 135 95 230 75 165 25,800.00

i GENERATOR 1 1 2 6 10 260 190 450 75 165 50,850.00

B SITE WORKS

I CIVIL 27 27 885 565 1450 75 165 159,600.00

II LANDSCAPE 6 6 155 95 250 75 165 27,300.00

III STRUCTURE 4 4 120 80 200 75 165 22,200.00

IV ELECTRICAL AND TELECOM 11 11 310 190 500 75 165 54,600.00

TOTAL DRAWINGS 55 57 57 90 33 292 7760 5245 13005 75 165 1,447,425.00

PHASE 2

A BUILDING WORKS

GENERAL DRAWINGS 3 2 2 1 8 160 115 275 75 165 30,975.00

20 & 21 SUB ASSEMBLY SHOPS 4 2 3 5 14 370 255 625 75 165 69,825.00

22 TOWER CRANES LAYOUT (COPY OF # 6) 0 2 0 0 2 30 15 45 75 165 4,725.00

23 OPEN SHEDS 1 1 0 0 2 60 40 100 75 165 11,100.00

24 EXOTIC MATERIAL WAREHOUSE 4 3 4 5 16 425 290 715 75 165 79,725.00

25 COLD WAREHOUSE 4 3 4 5 16 370 255 625 75 165 69,825.00

26 & 27 GANTRY CRANES LAYOUT (COPY OF # 8 & 9) 0 8 0 0 8 120 60 180 75 165 18,900.00

B SITE WORKS

I CIVIL 15 15 230 115 345 75 165 36,225.00

II LANDSCAPE 3 3 40 20 60 75 165 6,300.00

III STRUCTURE 1 1 20 10 30 75 165 3,150.00

IV ELECTRICAL AND TELECOM 6 6 90 45 135 75 165 14,175.00

TOTAL DRAWINGS 16 21 13 16 25 91 1915 1220 3135 75 165 344,925.00

OPTIONAL COST

1 BERTHING QUAY SIDE 123 6 8 14 510 1090 1600 75 165 218,100.00

2 HEAVY DUTY JETTY 5 5 10 650 650 1300 75 165 156,000.00

TOTAL DRAWINGS 11 13 0 0 24 1160 1740 2900 374,100.00

Page 5 of 5
ENGINEERING CONSULTANCY SERVICES FOR PACKAGE 2, CONSTRUCTION OF NPCC KSA YARD FACILITIES

LIST OF DRAWINGS - ARCHITECTURAL (PHASE 1)

NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

GENERAL DRAWINGS

AR-A0-000 COVER SHEET 0

AR-A0-001 LIST OF DRAWINGS 0

AR-A0-002 PERSPECTIVE VIEWS AND RENDERS 0

AR-A0-003 GENERAL NOTES, SYMBOLS, LEGENDS AND ABBREVIATIONS 0

AR-A0-004 ARCHITECTURAL SITE DEVELOPMENT PLANS 1

AR-A0-005 ENLARGED ARCHITECTURAL SITE DEVELOPMENT PLANS 2

SUB TOTAL 3

YARD MANAGEMENT OFFICES

AR-A0-100 FLOOR PLAN (WITH FURNITURE LAYOUT) / ROOF PLAN 1

AR-A0-101 FLOOR FINISH LAYOUT / REFLECTED CEILING PLAN / DETAILS 0

FURNITURE LAYOUT 0

AR-A0-103 ELEVATION A & B / C & D


1
SECTION 1 & 2

AR-A0-105 WALL SECTIONS, SCHEDULE & DETAILS 0

AR-A0-106 SCHEDULE OF INTERIOR / EXTERIOR FINISHES


1
AR-A0-107 SCHEDULE OF DOOR & WINDOWS TYPES / DETAILS

AR-A0-108 SCHEDULE OF KITCHENETE AND TOILETS / DETAILS 0

RAMPS AND STEPS SCHEDULE AND DETAILS 0

AR-A0-110 MISCELLANEOUS DETAILS 1

SUB TOTAL 4

AID / E&I / COMMISIONING FACILITIES

6
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

AR-A0-200 FLOOR PLAN / FURNITURE LAYOUT / ROOF PLAN 1

AR-A0-201 FLOOR FINISH LAYOUT / REFLECTED CEILING PLAN / DETAILS 0

AR-A0-202 ELEVATION A & B / C & D / SECTION 1 & 2 1

AR-A0-203 WALL SECTIONS, SCHEDULE & DETAILS 0

SCHEDULE OF INTERIOR / EXTERIOR FINISHES / SCHEDULE OF DOOR & WINDOWS


TYPES / DETAILS
AR-A0-204 1
SCHEDULE OF KITCHENETE AND TOILETS / RAMPS AND STEPS SCHEDULE AND
DETAILS / DETAILS

AR-A0-206 MISCELLANEOUS DETAILS 0

SUB TOTAL = 3

YARD SUPERVISORS OFFICE + QC FACILITY OFFICES + HSE FACITLITY OFFICES

AR-A0-301 FLOOR PLAN / FURNITURE LAYOUT / ROOF PLAN 1

AR-A0-302 FLOOR FINISH LAYOUT / REFLECTED CEILING PLAN / DETAILS 0

AR-A0-303 ELEVATION A & B / C & D / SECTION 1 & 2 1

AR-A0-304 WALL SECTIONS, SCHEDULE & DETAILS 0

SCHEDULE OF INTERIOR / EXTERIOR FINISHES / SCHEDULE OF DOOR & WINDOWS


TYPES / DETAILS
AR-A0-305 1
SCHEDULE OF KITCHENETE AND TOILETS / RAMPS AND STEPS SCHEDULE AND
DETAILS / DETAILS

AR-A0-307 MISCELLANEOUS DETAILS 1

SUB TOTAL 4

CLIENT OFFICES

AR-A0-400 FLOOR PLAN / FURNITURE LAYOUT / ROOF PLAN 1

AR-A0-401 FLOOR FINISH LAYOUT / REFLECTED CEILING PLAN / DETAILS 0

AR-A0-402 ELEVATION A & B / C & D / SECTION 1 & 2 1

AR-A0-403 WALL SECTIONS, SCHEDULE & DETAILS 0

SCHEDULE OF INTERIOR / EXTERIOR FINISHES / SCHEDULE OF DOOR & WINDOWS


TYPES / DETAILS
AR-A0-404 1
SCHEDULE OF KITCHENETE AND TOILETS / RAMPS AND STEPS SCHEDULE AND
DETAILS / DETAILS

7
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

SUB TOTAL 3

QC FACILITY OFFICES

AR-A0-500 FLOOR PLAN / FURNITURE LAYOUT / ROOF PLAN 0

AR-A0-501 FLOOR FINISH LAYOUT / REFLECTED CEILING PLAN / DETAILS 0

AR-A0-502 ELEVATION A & B / C & D / SECTION 1 & 2 0

AR-A0-503 WALL SECTIONS, SCHEDULE & DETAILS 0

SCHEDULE OF INTERIOR / EXTERIOR FINISHES / SCHEDULE OF DOOR & WINDOWS


AR-A0-504 0
TYPES / DETAILS
SCHEDULE OF KITCHENETE AND TOILETS / RAMPS AND STEPS SCHEDULE AND
AR-A0-505 0
DETAILS / DETAILS

SUB TOTAL 0

HSE FACITLITY OFFICES

AR-A0-600 FLOOR PLAN / FURNITURE LAYOUT / ROOF PLAN 0

AR-A0-601 FLOOR FINISH LAYOUT / REFLECTED CEILING PLAN / DETAILS 0

AR-A0-602 ELEVATION A & B / C & D / SECTION 1 & 2 0

AR-A0-603 WALL SECTIONS, SCHEDULE & DETAILS 0

SCHEDULE OF INTERIOR / EXTERIOR FINISHES / SCHEDULE OF DOOR & WINDOWS


AR-A0-604 0
TYPES / DETAILS
SCHEDULE OF KITCHENETE AND TOILETS / RAMPS AND STEPS SCHEDULE AND
AR-A0-605 0
DETAILS / DETAILS

SUB TOTAL 0

MESS HALL

AR-A0-700 FLOOR PLAN / FURNITURE LAYOUT/ ROOF PLAN 1

AR-A0-701 FLOOR FINISH LAYOUT / REFLECTED CEILING PLAN / DETAILS 0

FURNITURE LAYOUT 0

AR-A0-703 ELEVATION A & B / C & D


1
AR-A0-704 SECTION 1 & 2

AR-A0-705 WALL SECTIONS, SCHEDULE & DETAILS 0

8
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

SCHEDULE OF INTERIOR / EXTERIOR FINISHES


AR-A0-706 1
SCHEDULE OF DOOR & WINDOWS TYPES / DETAILS

AR-A0-708 SCHEDULE OF KITCHENETE AND TOILETS / DETAILS 1

RAMPS AND STEPS SCHEDULE AND DETAILS 0

MISCELLANEOUS DETAILS 0

SUB TOTAL 4

CLINIC

AR-A0-800 FLOOR PLAN / FURNITURE LAYOUT / ROOF PLAN 1

AR-A0-801 FLOOR FINISH LAYOUT / REFLECTED CEILING PLAN / DETAILS 0

AR-A0-802 ELEVATION A & B / C & D / SECTION 1 & 2 1

AR-A0-803 WALL SECTIONS, SCHEDULE & DETAILS 0

SCHEDULE OF INTERIOR / EXTERIOR FINISHES / SCHEDULE OF DOOR & WINDOWS


TYPES / DETAILS
AR-A0-804 1
SCHEDULE OF KITCHENETE AND TOILETS / RAMPS AND STEPS SCHEDULE AND
DETAILS / DETAILS

SUB TOTAL 3

MOSQUE

AR-A0-900 FLOOR PLAN / FURNITURE LAYOUT / ROOF PLAN 1

AR-A0-901 FLOOR FINISH LAYOUT / REFLECTED CEILING PLAN / DETAILS 0

AR-A0-902 ELEVATION A & B / C & D / SECTION 1 & 2 1

AR-A0-903 WALL SECTIONS, SCHEDULE & DETAILS 0

SCHEDULE OF DOOR & WINDOWS TYPES / DETAILS / SCHEDULE OF INTERIOR /


AR-A0-904 1
EXTERIOR FINISHES

AR-A0-905 ABLUTION AND TOILETS / DETAILS 1

RAMPS AND STEPS SCHEDULE AND DETAILS 0

AR-A0-906 MINERATE / MEHRAB DETAILS 1

AR-A0-907 MISCELLANEOUS DETAILS 1

9
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

SUB TOTAL 6

CLOSED WAREHOUSE 1

AR-A0-WRHS-100 FLOOR PLAN / FURNITURE LAYOUT / ROOF PLAN 1

AR-A0-WRHS-101 FLOOR FINISH LAYOUT / REFLECTED CEILING PLAN / DETAILS 0

AR-A0-WRHS-102 ELEVATION A & B / C & D / SECTION 1 & 2 1

AR-A0-WRHS-103 WALL SECTIONS, SCHEDULE & DETAILS 0

SCHEDULE OF INTERIOR / EXTERIOR FINISHES / SCHEDULE OF DOOR & WINDOWS


TYPES / DETAILS
AR-A0-WRHS-104 1
RAMPS, DOCKS AND STEPS SCHEDULE AND DETAILS / DETAILS

SUB TOTAL 3

CLOSED WAREHOUSE 2

AR-A0-WRHS-101 FLOOR PLAN / FURNITURE LAYOUT / ROOF PLAN 1

AR-A0-WRHS-102 FLOOR FINISH LAYOUT / REFLECTED CEILING PLAN / DETAILS 0

AR-A0-WRHS-103 ELEVATION A & B / C & D / SECTION 1 & 2 1

AR-A0-WRHS-104 WALL SECTIONS, SCHEDULE & DETAILS 0

SCHEDULE OF INTERIOR / EXTERIOR FINISHES / SCHEDULE OF DOOR & WINDOWS


TYPES / DETAILS
AR-A0-WRHS-105 1
RAMPS, DOCKS AND STEPS SCHEDULE AND DETAILS / DETAILS

SUB TOTAL 3

TOWER CRANES LAYOUT

AR-A0-CRN-100 TOWER CRANE SCHEDULE AND LAYOUT PLAN 0

AR-A0-CRN-101 ELEVATIONS / SECTIONS 0

AR-A0-CRN-102 DETAILS 0

SUB TOTAL 0

GANTRY CRANES LAYOUT

AR-A0-CRN-200 GANTRY CRANE SCHEDULE AND LAYOUT PLAN 0

10
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

AR-A0-CRN-201 ELEVATIONS / SECTIONS 0

AR-A0-CRN-202 DETAILS 0

SUB TOTAL 0

DOMESTIC PUMP ROOM

FLOOR PLAN / ROOF PLAN / FINISHING SCHEDULE / DOORS AND WINDOWS


AR-A0-DPMP-100 1
ELEVATION / SECTIONS / DETAILS

SUB TOTAL 1

FIRE PUMP ROOM

FLOOR PLAN / ROOF PLAN / FINISHING SCHEDULE / DOORS AND WINDOWS


AR-A0-FPMP-100 1
ELEVATION / SECTIONS / DETAILS

SUB TOTAL 1

GENERATOR

FLOOR PLAN / ROOF PLAN / FINISHING SCHEDULE / DOORS AND WINDOWS


AR-A0-GSST-100 1
ELEVATION / SECTIONS / DETAILS

SUB TOTAL 1

OPEN SHEDS

OPN SHED SCHEDULE AND LAYOUT PLAN / FINISHING LAYOUT


AR-A0-SHD-100 1
SECTIONS / DETAILS

SUB TOTAL 1

BEAM SHOP

AR-A0-BM-100 ASSEMBLY LAYOUT PLAN / FINISHING SCHEDULE / ROOF PLAN 1

AR-A0-BM-101 ELEVATION A & B / C & D / SECTION 1 & 2 / DETAILS 1

SUB TOTAL 2

PLATE SHOP

11
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

AR-A0-PL-100 ASSEMBLY LAYOUT PLAN / FINISHING SCHEDULE / ROOF PLAN 1

AR-A0-PL-101 ELEVATION A & B / C & D / SECTION 1 & 2 / DETAILS 1

SUB TOTAL 2

PIPE/TUBE SHOP

AR-A0-PT-100 ASSEMBLY LAYOUT PLAN / FINISHING SCHEDULE / ROOF PLAN 1

AR-A0-PT-101 ELEVATION A & B / C & D / SECTION 1 & 2 / DETAILS 1

SUB TOTAL 2

LEG AND PILES FABRICATION

AR-A0-FAB-100 ASSEMBLY LAYOUT PLAN / FINISHING SCHEDULE / ROOF PLAN 1

AR-A0-FAB-101 ELEVATION A & B / C & D / SECTION 1 & 2 / DETAILS 1

AR-A0-FAB-102 MISCELLANEOUS DETAILS 1

SUB TOTAL 3

AUTO BLASTING AND PAINTING MACHINE

AR-A0-PNT-100 ASSEMBLY LAYOUT PLAN / FINISHING SCHEDULE / ROOF PLAN 1

AR-A0-PNT-101 SECTIONS DETAILS 1

SUB TOTAL 2

INDUSTRIAL GAS STORE (OXYGEN, ACETYLENE, PROPANE/LPG, ARGON)

LAYOUT PLAN / FINISHING SCHEDULE


AR-A0-GAS-100 4
SECTIONS AND MISC. DETAILS

SUB TOTAL 4

TOTAL DRAWINGS = 55

12
ENGINEERING CONSULTANCY SERVICES FOR PACKAGE 2, CONSTRUCTION OF NPCC KSA YARD FACILITIES

LIST OF DRAWINGS - STRUCTURAL (PHASE 2)

NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

GENERAL DRAWINGS

SE-A0-000 COVER SHEET 0

SE-A0-001 LIST OF DRAWINGS 0

SE-A0-003 GENERAL NOTES, SYMBOLS, LEGENDS AND ABBREVIATIONS 2

SUB TOTAL = 2

YARD MANAGEMENT OFFICES

FOUNDATION / GRADE BEAM LAYOUT PLAN / DETAILS


SE-A0-100 1
GRADE LAYOUT PLAN

FIRST FLOOR AND ROOF FRAMING PLAN / DETAILS


SE-A0-102 1
ROOF FRAMING PLAN

SCHEDULE & MISCELLANEOUS DETAILS


SE-A0-104 0
MISCELLANEOUS DETAILS

SUB TOTAL = 2

AID / E&I / COMMISIONING FACILITIES

FOUNDATION / GRADE BEAM LAYOUT PLAN / DETAILS


SE-A0-200 1
GRADE LAYOUT PLAN

FIRST FLOOR AND ROOF FRAMING PLAN / DETAILS


SE-A0-202 1
ROOF FRAMING PLAN

SCHEDULE & MISCELLANEOUS DETAILS


SE-A0-204 0
MISCELLANEOUS DETAILS

SUB TOTAL = 2

YARD SUPERVISORS OFFICE + QC FACILITY OFFICES + HSE FACITLITY OFFICES

8
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

SE-A0-300 FOUNDATION / GRADE BEAM LAYOUT PLAN / DETAILS


1
GRADE LAYOUT PLAN

SE-A0-302 FIRST FLOOR AND ROOF FRAMING PLAN / DETAILS


1
ROOF FRAMING PLAN

SE-A0-304 SCHEDULE 0

SE-A0-305 MISCELLANEOUS DETAILS 0

SUB TOTAL = 2

CLIENT OFFICES

SE-A0-400 FOUNDATION / GRADE BEAM LAYOUT PLAN / DETAILS


1
GRADE LAYOUT PLAN

SE-A0-402 FIRST FLOOR AND ROOF FRAMING PLAN / DETAILS


1
ROOF FRAMING PLAN

SE-A0-404 SCHEDULE & MISCELLANEOUS DETAILS


0
MISCELLANEOUS DETAILS

SUB TOTAL = 2

QC FACILITY OFFICES

SE-A0-500 FOUNDATION LAYOUT PLAN 0

SE-A0-501 GRADE LAYOUT PLAN 0

SE-A0-502 FIRST FLOOR FRAMING PLAN 0

SE-A0-503 ROOF FRAMING PLAN 0

SE-A0-504 SCHEDULE 0

SE-A0-505 MISCELLANEOUS DETAILS 0

SUB TOTAL = 0

HSE FACITLITY OFFICES

9
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

SE-A0-600 FOUNDATION LAYOUT PLAN 0

SE-A0-601 GRADE LAYOUT PLAN 0

SE-A0-602 FIRST FLOOR FRAMING PLAN 0

SE-A0-603 ROOF FRAMING PLAN 0

SE-A0-604 SCHEDULE 0

SE-A0-605 MISCELLANEOUS DETAILS 0

SUB TOTAL = 0

MESS HALL

FOUNDATION / GRADE BEAM LAYOUT PLAN / DETAILS


SE-A0-700 1
GRADE LAYOUT PLAN

FIRST FLOOR AND ROOF FRAMING PLAN / DETAILS


SE-A0-702 1
ROOF FRAMING PLAN

SE-A0-704 SCHEDULE 0

SE-A0-709 RAMPS AND STAIR DETAILS 0

SE-A0-710 MISCELLANEOUS DETAILS 1

SUB TOTAL = 3

CLINIC

FOUNDATION / GRADE BEAM LAYOUT PLAN / DETAILS


SE-A0-800 1
GRADE LAYOUT PLAN

FIRST FLOOR AND ROOF FRAMING PLAN / DETAILS


SE-A0-802 1
ROOF FRAMING PLAN

SCHEDULE & MISCELLANEOUS DETAILS


SE-A0-804 0
MISCELLANEOUS DETAILS

SUB TOTAL = 2

10
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

MOSQUE

FOUNDATION / GRADE BEAM LAYOUT PLAN / DETAILS


SE-A0-900 1
GRADE LAYOUT PLAN

FIRST FLOOR AND ROOF FRAMING PLAN / DETAILS


SE-A0-902 1
ROOF FRAMING PLAN

SE-A0-904 SCHEDULE & MISCELLANEOUS DETAILS 1

SE-A0-905 MEHRAB DETAILS


1
SE-A0-906 MINARET DETAILS

SUB TOTAL = 4

CLOSED WAREHOUSE 1

FIRST FLOOR AND ROOF FRAMING PLAN / DETAILS


SE-A0-WRHS-100 1
GRADE LAYOUT PLAN

SE-A0-WRHS-102 ROOF FRAMING PLAN 1

SCHEDULE & MISCELLANEOUS DETAILS


SE-A0-WRHS-103 1
MISCELLANEOUS DETAILS

SUB TOTAL = 3

CLOSED WAREHOUSE 2

FOUNDATION / GRADE BEAM LAYOUT PLAN


SE-A0-WRHS-200 1
GRADE LAYOUT PLAN

SE-A0-WRHS-202 ROOF FRAMING PLAN 1

SCHEDULE & MISCELLANEOUS DETAILS


SE-A0-WRHS-203 1
MISCELLANEOUS DETAILS

SUB TOTAL = 3

TOWER CRANES LAYOUT

11
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

SE-A0-CRN-100 TOWER CRANE FOUNATION PLAN


1
ELEVATIONS / SECTIONS

SE-A0-CRN-102 MISCELLANEOUS DETAILS 1

SUB TOTAL = 2

GANTRY CRANES LAYOUT

SE-A0-CRN-200 TOWER CRANE FOUNATION PLAN


4
ELEVATIONS / SECTIONS

SE-A0-CRN-202 MISCELLANEOUS DETAILS 4

SUB TOTAL = 8

DOMESTIC PUMP ROOM

SE-A0-DPMP-100 LAYOUT PLANS


1
SE-A0-DPMP-101 SECTIONAL AND MISCELLANEOUS DETAILS

SUB TOTAL = 1

FIRE PUMP ROOM

SE-A0-FPMP-100 LAYOUT PLANS


1
SE-A0-FPMP-101 SECTIONAL AND MISCELLANEOUS DETAILS

SUB TOTAL = 1

GENERATOR

SE-A0-GSST-100 LAYOUT PLANS


1
SE-A0-GSST-101 MISCELLANEOUS DETAILS

SUB TOTAL = 1

OPEN SHEDS

LAYOUT PLANS
SE-A0-SHD-100 1
MISCELLANEOUS DETAILS

12
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

SUB TOTAL = 1

BEAM SHOP

LAYOUT PLANS 1
SE-A0-BM-100
MISCELLANEOUS DETAILS 1

SUB TOTAL = 2

PLATE SHOP

SE-A0-PL-100 LAYOUT PLANS 1

SE-A0-PL-101 MISCELLANEOUS DETAILS 1

SUB TOTAL = 2

PIPE/TUBE SHOP

SE-A0-DPMP-100 LAYOUT PLANS 1

SE-A0-DPMP-101 MISCELLANEOUS DETAILS 1

SUB TOTAL = 2

LEG AND PILES FABRICATION

SE-A0-FAB-100 LAYOUT PLANS 1

SE-A0-FAB-101 MISCELLANEOUS DETAILS 1

SUB TOTAL = 2

AUTO BLASTING AND PAINTING MACHINE

SE-A0-PNT-100 LAYOUT PLANS 1

SE-A0-PNT-101 MISCELLANEOUS DETAILS 1

SUB TOTAL = 2

INDUSTRIAL GAS STORE (OXYGEN, ACETYLENE, PROPANE/LPG, ARGON)

SE-A0-GAS-100 LAYOUT PLANS AND DETAILS


4
MISCELLANEOUS DETAILS

13
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

SUB TOTAL = 4

TOTAL DRAWINGS = 53

14
ENGINEERING CONSULTANCY SERVICES FOR PACKAGE 2, CONSTRUCTION OF NPCC KSA YARD FACILITIES

LIST OF DRAWINGS - MECHANICAL (PHASE 1)

NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

GENERAL DRAWINGS

HVAC GENERAL DRAWINGS

HV-A0-000 HVAC GENERAL NOTES, SYMBOLS, LEGENDS AND ABBREVIATIONS 0

HV-A0-001 HVAC MISCELLANEOUS STANDARD DETAILS (SHEET 1 OF 2) 0

HV-A0-002 HVAC MISCELLANEOUS STANDARD DETAILS (SHEET 2 OF 2) 0

SUB TOTAL = 0

PLUMBING GENERAL DRAWINGS

PG-A0-000 PLUMBING GENERAL NOTES, SYMBOLS, LEGENDS AND ABBREVIATIONS 1

PG-A0-001 PLUMBING MISCELLANEOUS STANDARD DETAILS (SHEET 1 OF 2) 0

PG-A0-002 PLUMBING MISCELLANEOUS STANDARD DETAILS (SHEET 2 OF 2) 0

SUB TOTAL = 1

FIRE PROTECTION GENERAL DRAWINGS

FP-A0-000 FIRE PROTECTION GENERAL NOTES, SYMBOLS, LEGENDS AND ABBREVIATIONS 1

FP-A0-001 FIRE PROTECTION MISCELLANEOUS STANDARD DETAILS (SHEET 1 OF 2) 0

FP-A0-002 FIRE PROTECTION MISCELLANEOUS STANDARD DETAILS (SHEET 2 OF 2) 0

SUB TOTAL = 1

TOTAL FOR GENERAL 2

YARD MANAGEMENT OFFICES

HVAC DRAWINGS

HV-A0-100 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT


1
HV-A0-101 HVAC EQUIPMENT SCHEDULE

HV-A0-102 HVAC SCHEMATIC DRAWING 0

15
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

SUB TOTAL = 1

PLUMBING DRAWINGS

PG-A0-100 FLOOR PLAN / ROOF PLAN WATER SUPPLY SYSTEM LAYOUT 1

PG-A0-101
1
PG-A0-102 FLOOR PLAN / ROOF PLAN DRAINAGE SYSTEM LAYOUT

PG-A0-103 0

SUB TOTAL = 2

FIRE PROTECTION DRAWINGS

FP-A0-100 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT 1

SUB TOTAL = 1

TOTAL FOR YARD MANAGEMENT OFFICES 4

ID / E&I / COMMISIONING FACILITIES

HVAC DRAWINGS

HV-A0-200 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT


1
HV-A0-201 HVAC EQUIPMENT SCHEDULE

HV-A0-202 HVAC SCHEMATIC DRAWING 0

SUB TOTAL = 1

PLUMBING DRAWINGS

PG-A0-200 FLOOR PLAN / ROOF PLAN WATER SUPPLY SYSTEM LAYOUT


1
PG-A0-201

PG-A0-202 FLOOR PLAN / ROOF PLAN DRAINAGE SYSTEM LAYOUT


1
PG-A0-203

SUB TOTAL = 2

FIRE PROTECTION DRAWINGS

16
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

PG-A0-200 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT 1

SUB TOTAL = 1

TOTAL FOR ID / E&I / COMMISIONING FACILITIES 4

YARD SUPERVISORS OFFICE

HVAC DRAWINGS

HV-A0-300 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT


1
HV-A0-301 HVAC EQUIPMENT SCHEDULE

HV-A0-302 HVAC SCHEMATIC DRAWING 0

SUB TOTAL = 1

PLUMBING DRAWINGS

PG-A0-300 FLOOR PLAN / ROOF PLAN WATER SUPPLY SYSTEM LAYOUT


1
PG-A0-301

PG-A0-302 FLOOR PLAN / ROOF PLAN DRAINAGE SYSTEM LAYOUT


1
PG-A0-303

SUB TOTAL = 2

FIRE PROTECTION DRAWINGS

FP-A0-300 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT 1

SUB TOTAL = 1

TOTAL FOR YARD SUPERVISORS OFFICE 4

CLIENT OFFICES

HVAC DRAWINGS

HV-A0-400 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT


1
HV-A0-401 HVAC EQUIPMENT SCHEDULE

HV-A0-402 HVAC SCHEMATIC DRAWING 0

17
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

SUB TOTAL = 1

PLUMBING DRAWINGS

PG-A0-400 FLOOR PLAN / ROOF PLAN WATER SUPPLY SYSTEM LAYOUT


1
PG-A0-401

PG-A0-402 FLOOR PLAN / ROOF PLAN DRAINAGE SYSTEM LAYOUT


1
PG-A0-403

SUB TOTAL = 2

FIRE PROTECTION DRAWINGS

FP-A0-400 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT 1

SUB TOTAL = 1

TOTAL FOR CLIENT OFFICES 4

QC FACILITY OFFICES

HVAC DRAWINGS

HV-A0-500 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT 0

HV-A0-501 HVAC EQUIPMENT SCHEDULE 0

HV-A0-502 HVAC SCHEMATIC DRAWING 0

SUB TOTAL = 0

PLUMBING DRAWINGS

PG-A0-500 FLOOR PLAN / ROOF PLAN WATER SUPPLY SYSTEM LAYOUT 0

PG-A0-501

PG-A0-502 FLOOR PLAN / ROOF PLAN DRAINAGE SYSTEM LAYOUT 0

PG-A0-503

SUB TOTAL = 0

FIRE PROTECTION DRAWINGS

18
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

FP-A0-500 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT 0

SUB TOTAL = 0

TOTAL FOR QC FACILITY OFFICES 0

HSE FACITLITY OFFICES

HVAC DRAWINGS

HV-A0-600 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT 0

HV-A0-601 HVAC EQUIPMENT SCHEDULE 0

HV-A0-602 HVAC SCHEMATIC DRAWING 0

SUB TOTAL = 0

PLUMBING DRAWINGS

AR-A0-600 FLOOR PLAN / ROOF PLAN WATER SUPPLY SYSTEM LAYOUT 0

AR-A0-601 0

AR-A0-602 FLOOR PLAN / ROOF PLAN DRAINAGE SYSTEM LAYOUT 0

AR-A0-603 0

SUB TOTAL = 0

FIRE PROTECTION DRAWINGS

FP-A0-600 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT 0

SUB TOTAL = 0

TOTAL FOR HSE FACITLITY OFFICES 0

MESS HALL

HVAC DRAWINGS

HV-A0-700 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT


1
HV-A0-701 HVAC EQUIPMENT SCHEDULE

HV-A0-702 HVAC SCHEMATIC DRAWING 0

19
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

SUB TOTAL = 1

PLUMBING DRAWINGS

PG-A0-700 FLOOR PLAN / ROOF PLAN WATER SUPPLY SYSTEM LAYOUT


1
PG-A0-701

PG-A0-702 FLOOR PLAN / ROOF PLAN DRAINAGE SYSTEM LAYOUT


1
PG-A0-703

SUB TOTAL = 2

FIRE PROTECTION DRAWINGS

FP-A0-700 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT 1

SUB TOTAL = 1

TOTAL FOR MESS HALL 4

CLINIC

HVAC DRAWINGS

HV-A0-800 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT


1
HV-A0-801 HVAC EQUIPMENT SCHEDULE

HV-A0-802 HVAC SCHEMATIC DRAWING 0

SUB TOTAL = 1

PLUMBING DRAWINGS

PG-A0-800 FLOOR PLAN / ROOF PLAN WATER SUPPLY SYSTEM LAYOUT


1
PG-A0-801

PG-A0-802 FLOOR PLAN / ROOF PLAN DRAINAGE SYSTEM LAYOUT


1
PG-A0-803

SUB TOTAL = 2

FIRE PROTECTION DRAWINGS

20
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

FP-A0-800 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT 1

SUB TOTAL = 1

TOTAL FOR CLINIC 4

MOSQUE

HVAC DRAWINGS

HV-A0-900 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT


1
HV-A0-901 HVAC EQUIPMENT SCHEDULE

HV-A0-902 HVAC SCHEMATIC DRAWING 0

SUB TOTAL = 1

PLUMBING DRAWINGS

PG-A0-900 FLOOR PLAN / ROOF PLAN WATER SUPPLY SYSTEM LAYOUT


1
PG-A0-901

PG-A0-902 FLOOR PLAN / ROOF PLAN DRAINAGE SYSTEM LAYOUT


1
PG-A0-903

SUB TOTAL = 2

FIRE PROTECTION DRAWINGS

FP-A0-900 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT 1

SUB TOTAL = 1

TOTAL FOR MOSQUE 4

CLOSED WAREHOUSE 1

HVAC DRAWINGS

HV-A0-WRHS-1000 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT


1
HV-A0-WRHS-1001 HVAC EQUIPMENT SCHEDULE

HV-A0-WRHS-1002 HVAC SCHEMATIC DRAWING 0

21
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

SUB TOTAL = 1

PLUMBING DRAWINGS

PG-A0-WRHS-1000 FLOOR PLAN WATER SUPPLY SYSTEM LAYOUT (TOILET)


1

PG-A0-WRHS-1002 FLOOR PLAN / ROOF PLAN DRAINAGE SYSTEM LAYOUT (TOILET)


1

SUB TOTAL = 2

FIRE PROTECTION DRAWINGS

FP-A0-WRHS-1000 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT 1

SUB TOTAL = 1

TOTAL FOR CLOSED WAREHOUSE 1 4

CLOSED WAREHOUSE 2

HVAC DRAWINGS

HV-A0-WRHS-1100 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT


1
HV-A0-WRHS-1101 HVAC EQUIPMENT SCHEDULE

HV-A0-WRHS-1102 HVAC SCHEMATIC DRAWING 0

SUB TOTAL = 1

PLUMBING DRAWINGS

PG-A0-WRHS-1100 FLOOR PLAN WATER SUPPLY SYSTEM LAYOUT (TOILET)


1
PG-A0-WRHS-1101

PG-A0-WRHS-1102 FLOOR PLAN / ROOF PLAN DRAINAGE SYSTEM LAYOUT (TOILET)


1
PG-A0-WRHS-1103

SUB TOTAL = 2

FIRE PROTECTION DRAWINGS

22
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

FP-A0-WRHS-1100 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT 1

SUB TOTAL = 1

TOTAL FOR CLOSED WAREHOUSE 2 4

TOWER CRANES LAYOUT

TOWER CRANES LAYOUT AND DETAILS 0

TOTAL TOWER CRANES LAYOUT 0

GANTRY CRANES LAYOUT

GANTRY CRANES LAYOUT AND DETAILS 0

TOTAL GANTRY CRANES 0

DOMESTIC PUMP ROOM

HVAC DRAWINGS

ME-A0-DPMP-1400 HVAC +PG+FP 1

SUB TOTAL = 1

PLUMBING DRAWINGS

PG-A0-DPMP-1400 FLOOR PLAN / ROOF PLAN DRAINAGE LAYOUT 0

SUB TOTAL = 0

FIRE PROTECTION DRAWINGS

FP-A0-DPMP-1400 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT 0

SUB TOTAL = 0

TOTAL FOR DOMESTIC PUMP ROOM 1

FIRE PUMP ROOM

HVAC DRAWINGS

HV-A0-FPMP-1500 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT 0

23
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

HV-A0-FPMP-1501 HVAC EQUIPMENT SCHEDULE 0

SUB TOTAL = 0

PLUMBING DRAWINGS

PG-A0-FPMP-1500 FLOOR PLAN / ROOF PLAN DRAINAGE LAYOUT 0

SUB TOTAL = 0

FIRE PROTECTION DRAWINGS

FP-A0-FPMP-1500 FLOOR PLAN FIRE PUMP SYSTEM LAYOUT AND SECTIONS 1

SUB TOTAL = 1

TOTAL FOR FIRE PUMP ROOM 1

GENERATOR ROOM

HVAC DRAWINGS

HC-A0-GSST-1600 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT


1
HC-A0-GSST-1601 HVAC EQUIPMENT SCHEDULE

HC-A0-GSST-1602 HVAC SCHEMATIC DRAWING 0

SUB TOTAL = 1

PLUMBING DRAWINGS

PG-A0-GSST-1600 FLOOR PLAN / ROOF PLAN DRAINAGE LAYOUT 0

PG-A0-GSST-1601 FLOOR PLAN / ROOF PLAN FUEL SYSTEM SUPPLY LAYOUT 0

SUB TOTAL = 0

FIRE PROTECTION DRAWINGS

FP-A0-GSST-1600 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT 1

SUB TOTAL = 1

TOTAL FOR GENERATOR ROOM 2

OPEN SHEDS

24
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

HVAC DRAWINGS

HV-A0-SHD-1700 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT 0

SUB TOTAL = 0

PLUMBING DRAWINGS

PG-A0-SHD-1700 ROOF PLAN DRAINAGE LAYOUT 0

SUB TOTAL = 0

FIRE PROTECTION DRAWINGS

FP-A0-SHD-1700 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT 0

SUB TOTAL = 0

TOTAL FOR OPEN SHEDS 0

BEAM SHOP

HVAC DRAWINGS

HV-A0-BM-1900 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT


1
HV-A0-BM-1901 HVAC EQUIPMENT SCHEDULE

SUB TOTAL = 1

PLUMBING DRAWINGS

PG-A0-BM-1900 ROOF PLAN DRAINAGE LAYOUT 0

SUB TOTAL = 0

FIRE PROTECTION DRAWINGS

FP-A0-BM-1900 ELEVATION A & B / C & D / SECTION 1 & 2 / DETAILS & ROOF PLAN DRAINAGE LAYOUT 1

SUB TOTAL = 1

TOTAL FOR BEAM SHOP 2

PLATE SHOP

HVAC DRAWINGS

25
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

HV-A0-PL-2000 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT


1
HV-A0-PL-2001 HVAC EQUIPMENT SCHEDULE

SUB TOTAL = 1

PLUMBING DRAWINGS

PG-A0-PL-2000 0

SUB TOTAL = 0

FIRE PROTECTION DRAWINGS

FP-A0-PL-2000 ELEVATION A & B / C & D / SECTION 1 & 2 / DETAILS & ROOF PLAN DRAINAGE LAYOUT 1

SUB TOTAL = 1

TOTAL FOR PLATE SHOP 2

PIPE/TUBE SHOP

HVAC DRAWINGS

HV-A0-PT-2100 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT


1
HV-A0-PT-2101 HVAC EQUIPMENT SCHEDULE

SUB TOTAL = 1

PLUMBING DRAWINGS

PG-A0-PT-2100 0

SUB TOTAL = 0

FIRE PROTECTION DRAWINGS

FP-A0-PT-2100 ELEVATION A & B / C & D / SECTION 1 & 2 / DETAILS & ROOF PLAN DRAINAGE LAYOUT 1

SUB TOTAL = 1

TOTAL FOR PIPE/TUBE SHOP 2

LEG AND PILES FABRICATION

HVAC DRAWINGS

26
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

HV-A0-FAB-2200 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT


1
HV-A0-FAB-2201 HVAC EQUIPMENT SCHEDULE

SUB TOTAL = 1

PLUMBING DRAWINGS

PG-A0-FAB-2200 0

SUB TOTAL = 0

FIRE PROTECTION DRAWINGS

FP-A0-FAB-2200 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT ROOF PLAN DRAINAGE LAYOUT 1

SUB TOTAL = 1

TOTAL FOR LEG AND PILES FABRICATION 2

AUTO BLASTING AND PAINTING MACHINE

HVAC DRAWINGS

HV-A0-PNT-2300 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT


1
HV-A0-PNT-2301 HVAC EQUIPMENT SCHEDULE

SUB TOTAL = 1

PLUMBING DRAWINGS

PG-A0-PNT-2300 1

SUB TOTAL = 1

FIRE PROTECTION DRAWINGS

FP-A0-PNT-2300 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT ROOF PLAN DRAINAGE LAYOUT 1

SUB TOTAL = 1

TOTAL AUTO BLASTING AND PAINTING MACHINE 3

INDUSTRIAL GAS STORE (OXYGEN, ACETYLENE, PROPANE/LPG, ARGON)

HVAC DRAWINGS

27
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

HV-A0-GAS-2400 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT


1
HV-A0-GAS-2401 HVAC EQUIPMENT SCHEDULE AND DETAILS

SUB TOTAL = 1

FIRE PROTECTION DRAWINGS

FP-A0-GAS-2400 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT AND DETAILS 3

SUB TOTAL = 3

INDUSTRIAL GAS STORE (OXYGEN, ACETYLENE, PROPANE/LPG, ARGON) 4

TOTAL DRAWINGS = 57

28
ENGINEERING CONSULTANCY SERVICES FOR PACKAGE 2, CONSTRUCTION OF NPCC KSA YARD FACILITIES

LIST OF DRAWINGS - ELECTRICAL (PHASE 1)

NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

GENERAL DRAWINGS

EE-A0-000 COVER SHEET 0

EE-A0-001 LIST OF DRAWINGS 0

EE-A0-002 GENERAL NOTES, SYMBOLS, LEGENDS AND ABBREVIATIONS 1

SUB TOTAL = 1

YARD MANAGEMENT OFFICES + CLINICS

EE-A0-100 GROUND FLOOR LIGHTING LAYOUT PLAN 1

EE-A0-101 GROUND FLOOR POWER LAYOUT PLAN


1
EE-A0-102 ROOF LIGHTING & POWER LAYOUT PLAN

EE-A0-103 GROUNDING LAYOUT PLAN 1

TC-A0-101 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN 1

TC-A0-102 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN 1

SUB TOTAL = 5

AID / E&I / COMMISIONING FACILITIES

EE-A0-200 GROUND FLOOR LIGHTING LAYOUT PLAN 1

EE-A0-201 GROUND FLOOR POWER LAYOUT PLAN


1
EE-A0-202 ROOF LIGHTING & POWER LAYOUT PLAN

EE-A0-203 GROUNDING LAYOUT PLAN & LIGHTNING PROTECTION LAYOUT PLAN 1

TC-A0-201 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN 1

TC-A0-202 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN 1

SUB TOTAL = 5

YARD SUPERVISORS OFFICE

28
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

EE-A0-300 GROUND FLOOR LIGHTING LAYOUT PLAN 1

EE-A0-301 GROUND FLOOR POWER LAYOUT PLAN


1
EE-A0-302 ROOF LIGHTING & POWER LAYOUT PLAN

EE-A0-303 GROUNDING LAYOUT PLAN 1

TC-A0-301 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN 1

TC-A0-302 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN 1

SUB TOTAL = 5

CLIENT OFFICES

EE-A0-400 GROUND FLOOR LIGHTING LAYOUT PLAN 1

EE-A0-401 GROUND FLOOR POWER LAYOUT PLAN


1
EE-A0-402 ROOF LIGHTING & POWER LAYOUT PLAN

EE-A0-403 GROUNDING LAYOUT PLAN 1

TC-A0-401 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN 1

TC-A0-402 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN 1

SUB TOTAL = 5

QC FACILITY OFFICES

EE-A0-500 GROUND FLOOR LIGHTING LAYOUT PLAN 0

EE-A0-501 GROUND FLOOR POWER LAYOUT PLAN 0

EE-A0-502 ROOF LIGHTING & POWER LAYOUT PLAN 0

EE-A0-503 GROUNDING LAYOUT PLAN 0

TC-A0-501 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN 0

TC-A0-502 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN 0

SUB TOTAL = 0

HSE FACITLITY OFFICES

29
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

EE-A0-600 GROUND FLOOR LIGHTING LAYOUT PLAN 0

EE-A0-601 GROUND FLOOR POWER LAYOUT PLAN 0

EE-A0-602 ROOF LIGHTING & POWER LAYOUT PLAN 0

EE-A0-603 GROUNDING LAYOUT PLAN 0

TC-A0-601 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN 0

TC-A0-602 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN 0

SUB TOTAL = 0

MESS HALL

EE-A0-700 GROUND FLOOR LIGHTING LAYOUT PLAN 1

EE-A0-701 GROUND FLOOR POWER LAYOUT PLAN 1

EE-A0-702 ROOF LIGHTING & POWER LAYOUT PLAN 1

EE-A0-703 GROUNDING LAYOUT PLAN 1

TC-A0-701 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN 1

TC-A0-702 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN 1

SUB TOTAL = 6

CLINIC

EE-A0-800 GROUND FLOOR LIGHTING LAYOUT PLAN 1

EE-A0-801 GROUND FLOOR POWER LAYOUT PLAN


1
ROOF LIGHTING & POWER LAYOUT PLAN

EE-A0-803 GROUNDING LAYOUT PLAN 1

TC-A0-801 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN


1
TC-A0-802 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN

SUB TOTAL = 4

MOSQUE

30
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

EE-A0-900 GROUND FLOOR LIGHTING LAYOUT PLAN 1

EE-A0-901 GROUND FLOOR POWER LAYOUT PLAN 1

EE-A0-902 ROOF LIGHTING & POWER LAYOUT PLAN 1

EE-A0-903 GROUNDING LAYOUT PLAN 1

TC-A0-901 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN


1
TC-A0-902 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN

SUB TOTAL = 5

CLOSED WAREHOUSE 1

EE-A0-1000 GROUND FLOOR LIGHTING LAYOUT PLAN 1

EE-A0-1001 GROUND FLOOR POWER LAYOUT PLAN 1

EE-A0-1002 ROOF LIGHTING & POWER LAYOUT PLAN 1

EE-A0-1003 GROUNDING & LIGHTNING PROTECTION LAYOUT PLAN 1

TC-A0-1001 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN


1
TC-A0-1002 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN

SUB TOTAL = 5

CLOSED WAREHOUSE 2

EE-A0-1100 GROUND FLOOR LIGHTING LAYOUT PLAN 1

EE-A0-1101 GROUND FLOOR POWER LAYOUT PLAN 1

EE-A0-1102 ROOF LIGHTING & POWER LAYOUT PLAN 1

EE-A0-1103 GROUNDING & LIGHTNING PROTECTION LAYOUT PLAN 1

TC-A0-1101 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN


1
TC-A0-1102 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN

SUB TOTAL = 5

DOMESTIC PUMP ROOM

31
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

GROUND FLOOR LIGHTING , POWER LAYOUT PLAN, LOAD SCHEDULE & SINGLE LINE
EE-A0-DPMP-100 1
DIAGRAM
GROUND FLOOR DATA/VOICE, CCTV, FIRE ALARM SYSTEM LAYOUT PLAN & RISER
TC-A0-DPMP-101 1
DIAGRAM

SUB TOTAL = 2

FIRE PUMP ROOM

EE-A0-DPMP-200 GROUND FLOOR LIGHTING &POWER LAYOUT PLAN, 1

TC-A0-DPMP-201 GROUND FLOOR DATA/VOICE, CCTV & FIRE ALARM SYSTEM LAYOUT PLAN 1

SUB TOTAL = 2

GENERATOR ROOM

EE-A0-GSST-100 GROUND FLOOR LIGHTING LAYOUT PLAN 1

EE-A0-GSST-101 GROUND FLOOR POWER LAYOUT PLAN 1

EE-A0-GSST-102 ROOF LIGHTING & POWER LAYOUT PLAN 1

EE-A0-GSST-103 GROUNDING & LIGHTNING PROTECTION LAYOUT PLAN 1

EE-A0-GSST-104 SINGLE LINE DIAGRAM 1

TC-A0-GSST-101 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN


1
TC-A0-GSST-102 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN

SUB TOTAL = 6

BEAM SHOP

EE-A0-BM-100 GROUND FLOOR LIGHTING & POWER LAYOUT PLAN 1

EE-A0-BM-102 GROUNDING LAYOUT PLAN 1

TC-A0-BM-101 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN


1
TC-A0-BM-102 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN

SUB TOTAL = 3

PLATE SHOP

EE-A0-PL-100 GROUND FLOOR LIGHTING & POWER LAYOUT PLAN 1

32
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

EE-A0-PL-102 GROUNDING LAYOUT PLAN 1

TC-A0-PL-101 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN


1
TC-A0-PL-102 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN

SUB TOTAL = 3

PIPE/TUBE SHOP

EE-A0-PT-100 GROUND FLOOR LIGHTING & POWER LAYOUT PLAN 1

EE-A0-PT-102 GROUNDING LAYOUT PLAN 1

TC-A0-PT-101 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN


1
TC-A0-PT-102 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN

SUB TOTAL = 3

LEG AND PILES FABRICATION

EE-A0-FAB-100 GROUND FLOOR LIGHTING & POWER LAYOUT PLAN 1

EE-A0-FAB-102 GROUNDING LAYOUT PLAN 1

TC-A0-FAB-101 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN


1
TC-A0-FAB-102 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN

SUB TOTAL = 3

AUTO BLASTING AND PAINTING MACHINE

EE-A0-PNT-100 GROUND FLOOR LIGHTING & POWER LAYOUT PLAN 1

EE-A0-PNT-102 GROUNDING LAYOUT PLAN 1

TC-A0-PNT-101 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN


1
TC-A0-PNT-102 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN

SUB TOTAL = 3

INDUSTRIAL GAS STORE (OXYGEN, ACETYLENE, PROPANE/LPG, ARGON)

EE-A0-GAS-100 GROUND FLOOR LIGHTING & POWER LAYOUT PLAN 2

33
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

EE-A0-GAS-102 GROUNDING LAYOUT PLAN AND DETAILS 2

TC-A0-GAS-101 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN 2

TC-A0-GAS-102 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN 2

SUB TOTAL = 8

TOTAL DRAWINGS = 79

34
ENGINEERING CONSULTANCY SERVICES FOR PACKAGE 2, CONSTRUCTION OF NPCC KSA YARD FACILITIES

LIST OF DRAWINGS - SITE WORKS

NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

SURVEY

GE-A1-007 OVERALL TOPOGRAPHIC SURVEY PLAN 1

GE-A1-008 ENLARGE TOPOGRAPHIC SURVEY PLAN (SCALE 1 : 1000) 2

DEMOLITION

D-A1-001 DEMOLITION PLAN 1

CIVIL

ROAD

CE-A1-001 OVERALL SITE DEVELOPMENT PLAN 1

CE-A1-002 OVERALL SETTING OUT KEY PLAN 1

CE-A1-003 ENLARGED SETTING OUT PLAN (SCALE 1 : 1000) 2

CE-A1-004 ROAD CORRIDOR SECTIONS 2

CE-A1-005 ROAD MARKING AND SIGNAGE LAYOUT PLAN

CE-A1-006 ENLARGED ROAD MARKING AND SIGNAGE PLAN (SCALE 1 : 1000)

CE-A1-008 COORDINATE SETTING OUT DATA 2

SITE GRADING AND STORM DRAINAGE SYSTEM

CE-A1-013 ROUGH GRADING PLAN 1

CE-A1-014 SITE GRADING & STORM DRAINAGE SYSTEM KEY PLAN 1

CE-A1-015 ENLARGED SITE GRADING & STORM DRAINAGE PLAN (SCALE 1 : 1000) 2

CE-A1-018 STORM WATER MISCELLANEOUS DETAILS

POTABLE/ FIRE WATER SYSTEM

CE-A1-024 POTABLE/ FIRE WATER SYSTEM LAYOUT KEY PLAN 1

CE-A1-025 ENLARGE POTABLE/ FIRE WATER SYSTEM LAYOUT PLAN (SCALE 1 : 1000) 2

34
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

CE-A1-028 POTABLE WATER MISCELLANEOUS DETAILS 0

INDUSTRIAL GAS SYSTEM

CE-A1-030 INDUSTRIAL GAS SYSTEM LAYOUT PLAN 1

CE-A1-031 INDUSTRIAL GAS SYSTEM ENLARGED PLAN (SCALE 1 : 1000) 2

CE-A1-032 INDUSTRIAL GAS MISCELLANEOUS DETAILS 1

SANITARY SEWER SYSTEM

CE-A1-040 OVERALL SANITARY SEWERAGE SYSTEM LAYOUT PLAN 1

CE-A1-041 ENLARGED SANITARY SEWERAGE SYSTEM LAYOUT PLAN (SCALE 1 : 1000) 2

CE-A1-043 SANITARY SEWERAGE SYSTEM MISCELLANEOUS DETAILS 1

SUB-TOTAL 1 27

STRUCTURAL-INFRASTRUCTURE

SE-A1-001 GENERAL NOTES, ABBREVIATIONS & MISCELLANEOUS DETAILS

SE-A1-005 BUTTERFLY VALVE CHAMBER REINFORCEMENT AND DETAILS 1

SE-A1-006 AIR RELEASE VALVE CHAMBER REINFORCEMENT AND DETAILS 1

SE-A1-007 WASHOUT VALVE CHAMBER REINFORCEMENT AND DETAILS 1

SE-A1-008 STORM WATER CHAMBER/ MANHOLE DETAILS 1

SE-A1-008 STRUCTURAL MISCELLANEOUS DETAILS 0

SUB-TOTAL 2 4

LANDSCAPE

LS-A1-001 MASTER PLAN 1

LS-A1-002 ENLARGED MASTER PLAN & SITE FURNITURE LAYOUT PLAN (SCALE 1 : 1000) 2

LS-A1-003 HARDSCAPE SCHEDULE AND SECTION DETAIL 1

LS-A1-005 SHADED PARKING DETAIL 1

LS-A1-006 GATE AND FENCE DETAILS 1

35
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

SUB-TOTAL 3 6

ELECTRICAL

EE-A1-001 OVERALL STREET LIGHTING AND LOW VOLTAGE DISTRIBUTION PLAN 1

ENLARGED STREET LIGHTING AND LOW VOLTAGE DISTRIBUTION PLAN (SCALE 1 :


EE-A1-002 2
1000)

EE-A1-003 OVERALL MEDIUM VOLTAGE, 13.8KV DISTRIBUTION PLAN 1

EE-A1-004 ENLARGED MEDIUM VOLTAGE, 13.8KV DISTRIBUTION PLAN (SCALE 1 : 1000) 2

EE-A1-006 13.8KV POWER DISTRIBUTION SYSTEM SINGLE LINE DIAGRAM 1

TELECOM

EE-A1-007 OVERALL TELECOMMUNICATION DISTRIBUTION PLAN 1

EE-A1-008 ENLARGED TELECOMMUNICATION DISTRIBUTION PLAN (SCALE 1 : 1000) 2

EE-A1-009 MISCELLANEOUS DETAILS (FDT DETAILS, DUCT BANK DETAILS- FOC DETAILS) 1

SUB-TOTAL 4 11

TOTAL FOR SITE(SUB-TOTAL 1+2+3+4) 48

36
ENGINEERING CONSULTANCY SERVICES FOR PACKAGE 2, CONSTRUCTION OF NPCC KSA YARD FACILITIES

LIST OF DRAWINGS - ARCHITECTURAL (PHASE 2)

NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

GENERAL DRAWINGS

AR-A0-000 COVER SHEET 0

AR-A0-001 LIST OF DRAWINGS 0

AR-A0-002 PERSPECTIVE VIEWS AND RENDERS 0

AR-A0-003 GENERAL NOTES, SYMBOLS, LEGENDS AND ABBREVIATIONS 0

AR-A0-004 ARCHITECTURAL SITE DEVELOPMENT PLANS 1

AR-A0-005 ENLARGED ARCHITECTURAL SITE DEVELOPMENT PLANS 2

SUB TOTAL = 3

COLD WAREHOUSE

AR-A0-WRHS-200 FLOOR PLAN / FURNITURE LAYOUT / ROOF PLAN 1

AR-A0-WRHS-201 FLOOR FINISH LAYOUT / REFLECTED CEILING PLAN / DETAILS 0

AR-A0-WRHS-202 ELEVATION A & B / C & D / SECTION 1 & 2 1

AR-A0-WRHS-203 WALL SECTIONS, SCHEDULE & DETAILS 1

SCHEDULE OF INTERIOR / EXTERIOR FINISHES / SCHEDULE OF DOOR & WINDOWS


TYPES / DETAILS
AR-A0-WRHS-204 1
RAMPS, DOCKS AND STEPS SCHEDULE AND DETAILS / DETAILS

SUB TOTAL = 4

EXOTIC MATERIAL WAREHOUSE

AR-A0-WRHS-201 FLOOR PLAN / FURNITURE LAYOUT / ROOF PLAN 1

AR-A0-WRHS-202 FLOOR FINISH LAYOUT / REFLECTED CEILING PLAN / DETAILS 0

AR-A0-WRHS-203 ELEVATION A & B / C & D / SECTION 1 & 2 1

AR-A0-WRHS-204 WALL SECTIONS, SCHEDULE & DETAILS 1

SCHEDULE OF INTERIOR / EXTERIOR FINISHES / SCHEDULE OF DOOR & WINDOWS


TYPES / DETAILS
AR-A0-WRHS-205 1

37
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG
AR-A0-WRHS-205 1
RAMPS, DOCKS AND STEPS SCHEDULE AND DETAILS / DETAILS

SUB TOTAL = 4

TOWER CRANES LAYOUT

AR-A0-CRN-100 TOWER CRANE SCHEDULE AND LAYOUT PLAN 0

AR-A0-CRN-101 ELEVATIONS / SECTIONS 0

AR-A0-CRN-102 DETAILS 0

SUB TOTAL = 0

GANTRY CRANES LAYOUT

AR-A0-CRN-200 GANTRY CRANE SCHEDULE AND LAYOUT PLAN 0

AR-A0-CRN-201 ELEVATIONS / SECTIONS 0

AR-A0-CRN-202 DETAILS 0

SUB TOTAL = 0

OPEN SHEDS

OPN SHED SCHEDULE AND LAYOUT PLAN / FINISHING LAYOUT


AR-A0-SHD-100 1
SECTIONS / DETAILS

SUB TOTAL = 1

SUB ASSEMBLY SHOPS 1 & 2

SUB ASSEMBLY SHOP SCHEDULE AND LAYOUT PLAN / FINISHING SCHEDULE / ROOF
AR-A0-ASS-100 1
PLAN

AR-A0-ASS-101 ELEVATION A & B / C & D / SECTION 1 & 2 / DETAILS 2

AR-A0-ASS-102 MISCELLANEOUS DETAILS 1

SUB TOTAL = 4

TOTAL DRAWINGS = 16

38
ENGINEERING CONSULTANCY SERVICES FOR PACKAGE 2, CONSTRUCTION OF NPCC KSA YARD FACILITIES

LIST OF DRAWINGS - STRUCTURAL (PHASE 2)

NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

GENERAL DRAWINGS

SE-A0-000 COVER SHEET 0

SE-A0-001 LIST OF DRAWINGS 0

SE-A0-003 GENERAL NOTES, SYMBOLS, LEGENDS AND ABBREVIATIONS 2

SUB TOTAL 2

COLD WAREHOUSE

FOUNDATION / GRADE BEAM LAYOUT PLAN


SE-A0-WRHS-300 1
GRADE LAYOUT PLAN

SE-A0-WRHS-302 ROOF FRAMING PLAN 1

SCHEDULE & MISCELLANEOUS DETAILS


SE-A0-WRHS-303 1
MISCELLANEOUS DETAILS

SUB TOTAL 3

EXOTIC MATERIAL WAREHOUSE

FOUNDATION / GRADE BEAM LAYOUT PLAN


SE-A0-WRHS-400 1
GRADE LAYOUT PLAN

SE-A0-WRHS-402 ROOF FRAMING PLAN 1

SCHEDULE & MISCELLANEOUS DETAILS


SE-A0-WRHS-403 1
MISCELLANEOUS DETAILS

SUB TOTAL = 3

TOWER CRANES LAYOUT

SE-A0-CRN-100 TOWER CRANE FOUNATION PLAN


1
ELEVATIONS / SECTIONS

3
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

SE-A0-CRN-102 MISCELLANEOUS DETAILS 1

SUB TOTAL = 2

GANTRY CRANES LAYOUT

SE-A0-CRN-200 TOWER CRANE FOUNATION PLAN


4
ELEVATIONS / SECTIONS

SE-A0-CRN-202 MISCELLANEOUS DETAILS 4

SUB TOTAL = 8

OPEN SHEDS

LAYOUT PLANS
SE-A0-SHD-100 1
MISCELLANEOUS DETAILS

SUB TOTAL = 1

SUB ASSEMBLY SHOPS 1 & 2

SE-A0-ASS-100 LAYOUT PLANS 1

SE-A0-ASS-101 MISCELLANEOUS DETAILS 1

SUB TOTAL = 2

TOTAL DRAWINGS = 21

4
ENGINEERING CONSULTANCY SERVICES FOR PACKAGE 2, CONSTRUCTION OF NPCC KSA YARD FACILITIES

LIST OF DRAWINGS - MECHANICAL (PHASE 2)

NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

GENERAL DRAWINGS

HVAC GENERAL DRAWINGS

HV-A0-000 HVAC GENERAL NOTES, SYMBOLS, LEGENDS AND ABBREVIATIONS 0

HV-A0-001 HVAC MISCELLANEOUS STANDARD DETAILS (SHEET 1 OF 2) 0

HV-A0-002 HVAC MISCELLANEOUS STANDARD DETAILS (SHEET 2 OF 2) 0

SUB TOTAL = 0

PLUMBING GENERAL DRAWINGS

PG-A0-000 PLUMBING GENERAL NOTES, SYMBOLS, LEGENDS AND ABBREVIATIONS 1

PG-A0-001 PLUMBING MISCELLANEOUS STANDARD DETAILS (SHEET 1 OF 2) 0

PG-A0-002 PLUMBING MISCELLANEOUS STANDARD DETAILS (SHEET 2 OF 2) 0

SUB TOTAL = 1

FIRE PROTECTION GENERAL DRAWINGS

FP-A0-000 FIRE PROTECTION GENERAL NOTES, SYMBOLS, LEGENDS AND ABBREVIATIONS 1

FP-A0-001 FIRE PROTECTION MISCELLANEOUS STANDARD DETAILS (SHEET 1 OF 2) 0

FP-A0-002 FIRE PROTECTION MISCELLANEOUS STANDARD DETAILS (SHEET 2 OF 2) 0

SUB TOTAL = 1

TOTAL FOR GENERAL 2

COLD WAREHOUSE

HVAC DRAWINGS

HV-A0-WRHS-1200 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT


1
HV-A0-WRHS-1201 HVAC EQUIPMENT SCHEDULE

HV-A0-WRHS-1202 HVAC SCHEMATIC DRAWING 0

5
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

SUB TOTAL = 1

PLUMBING DRAWINGS

PG-A0-WRHS-1200 FLOOR PLAN WATER SUPPLY SYSTEM LAYOUT (TOILET)


1
PG-A0-WRHS-1201

PG-A0-WRHS-1202 FLOOR PLAN / ROOF PLAN DRAINAGE SYSTEM LAYOUT (TOILET)


1
PG-A0-WRHS-1203

SUB TOTAL = 2

FIRE PROTECTION DRAWINGS

FP-A0-WRHS-1200 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT 1

SUB TOTAL = 1

TOTAL FOR COLD WAREHOUSE 4

EXOTIC MATERIAL WAREHOUSE

HVAC DRAWINGS

HV-A0-WRHS-1300 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT


1
HV-A0-WRHS-1301 HVAC EQUIPMENT SCHEDULE

HV-A0-WRHS-1302 HVAC SCHEMATIC DRAWING 0

SUB TOTAL = 1

PLUMBING DRAWINGS

PG-A0-WRHS-1300 FLOOR PLAN WATER SUPPLY SYSTEM LAYOUT (TOILET) 1

PG-A0-WRHS-1302 FLOOR PLAN / ROOF PLAN DRAINAGE SYSTEM LAYOUT (TOILET) 1

SUB TOTAL = 2

FIRE PROTECTION DRAWINGS

6
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

FP-A0-WRHS-1300 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT 1

SUB TOTAL = 1

TOTAL FOR EXOTIC MATERIAL WAREHOUSE 4

TOWER CRANES LAYOUT

TOWER CRANES LAYOUT AND DETAILS 0

TOTAL TOWER CRANES LAYOUT 0

GANTRY CRANES LAYOUT

GANTRY CRANES LAYOUT AND DETAILS 0

TOTAL GANTRY CRANES 0

OPEN SHEDS

HVAC DRAWINGS

HV-A0-SHD-1700 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT 0

SUB TOTAL = 0

PLUMBING DRAWINGS

PG-A0-SHD-1700 ROOF PLAN DRAINAGE LAYOUT 0

SUB TOTAL = 0

FIRE PROTECTION DRAWINGS

FP-A0-SHD-1700 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT 0

SUB TOTAL = 0

TOTAL FOR OPEN SHEDS 0

SUB ASSEMBLY SHOPS

HVAC DRAWINGS

HV-A0-ASS-1800 HVAC FLOOR PLAN / ROOF PLAN SYSTEM LAYOUT


1
HV-A0-ASS-1801 HVAC EQUIPMENT SCHEDULE

7
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

SUB TOTAL = 1

PLUMBING DRAWINGS

PG-A0-ASS-1800 ROOF PLAN DRAINAGE LAYOUT 1

SUB TOTAL = 1

FIRE PROTECTION DRAWINGS

FP-A0-ASS-1800 FLOOR PLAN PLAN FIRE PROTECTION LAYOUT 1

SUB TOTAL = 1

TOTAL FOR SUB ASSEMBLY SHOPS 3

TOTAL DRAWINGS = 13

8
ENGINEERING CONSULTANCY SERVICES FOR PACKAGE 2, CONSTRUCTION OF NPCC KSA YARD FACILITIES

LIST OF DRAWINGS - ELECTRICAL (PHASE 2)

NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

GENERAL DRAWINGS

EE-A0-000 COVER SHEET 0

EE-A0-001 LIST OF DRAWINGS 0

EE-A0-002 GENERAL NOTES, SYMBOLS, LEGENDS AND ABBREVIATIONS 1

SUB TOTAL = 1

BUILDINGS

COLD WAREHOUSE

EE-A0-1200 GROUND FLOOR LIGHTING LAYOUT PLAN 1

EE-A0-1201 GROUND FLOOR POWER LAYOUT PLAN 1

EE-A0-1202 ROOF LIGHTING & POWER LAYOUT PLAN 1

EE-A0-1203 GROUNDING LAYOUT PLAN 1

TC-A0-1201 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN


1
TC-A0-1202 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN

SUB TOTAL = 5

EXOTIC MATERIAL WAREHOUSE

EE-A0-1300 GROUND FLOOR LIGHTING LAYOUT PLAN 1

EE-A0-1301 GROUND FLOOR POWER LAYOUT PLAN 1

EE-A0-1302 ROOF LIGHTING & POWER LAYOUT PLAN AND GROUNDING 1

EE-A0-1303 GROUNDING LAYOUT PLAN 1

TC-A0-1301 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN


1
TC-A0-1302 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN

SUB TOTAL = 5

9
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

SUB ASSEMBLY SHOPS 1 & 2

EE-A0-ASS-100 GROUND FLOOR LIGHTING LAYOUT PLAN 1

EE-A0-ASS-101 GROUND FLOOR POWER LAYOUT PLAN 1

EE-A0-ASS-102 GROUNDING & LIGHTNING PROTECTION LAYOUT PLAN 1

TC-A0-ASS-101 GROUND FLOOR DATA/VOICE & CCTV SYSTEM LAYOUT PLAN 1

TC-A0-ASS-102 GROUND FLOOR FIRE ALARM SYSTEM LAYOUT PLAN 1

SUB TOTAL = 5

TOTAL DRAWINGS = 16

10
ENGINEERING CONSULTANCY SERVICES FOR PACKAGE 2, CONSTRUCTION OF NPCC KSA YARD FACILITIES

LIST OF DRAWINGS - SITE WORKS (PHASE 2)

NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

SURVEY

GE-A1-007 OVERALL TOPOGRAPHIC SURVEY PLAN 1

GE-A1-008 ENLARGE TOPOGRAPHIC SURVEY PLAN (SCALE 1 : 1000) 1

DEMOLITION

D-A1-001 DEMOLITION PLAN 0

CIVIL

ROAD

CE-A1-001 OVERALL SITE DEVELOPMENT PLAN 1

CE-A1-002 OVERALL SETTING OUT KEY PLAN 1

CE-A1-003 ENLARGED SETTING OUT PLAN (SCALE 1 : 1000) 1

CE-A1-004 ROAD CORRIDOR SECTIONS 1

CE-A1-005 ROAD MARKING AND SIGNAGE LAYOUT PLAN

CE-A1-006 ENLARGED ROAD MARKING AND SIGNAGE PLAN (SCALE 1 : 1000)

CE-A1-008 COORDINATE SETTING OUT DATA 0

SITE GRADING AND STORM DRAINAGE SYSTEM

CE-A1-013 ROUGH GRADING PLAN 1

CE-A1-014 SITE GRADING & STORM DRAINAGE SYSTEM KEY PLAN 1

CE-A1-015 ENLARGED SITE GRADING & STORM DRAINAGE PLAN (SCALE 1 : 1000) 1

CE-A1-018 STORM WATER MISCELLANEOUS DETAILS

POTABLE/ FIRE WATER SYSTEM

CE-A1-024 POTABLE/ FIRE WATER SYSTEM LAYOUT KEY PLAN 1

CE-A1-025 ENLARGE POTABLE/ FIRE WATER SYSTEM LAYOUT PLAN (SCALE 1 : 1000) 1

11
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

CE-A1-028 POTABLE WATER MISCELLANEOUS DETAILS 0

INDUSTRIAL GAS SYSTEM

CE-A1-030 INDUSTRIAL GAS SYSTEM LAYOUT PLAN 1

CE-A1-031 INDUSTRIAL GAS SYSTEM ENLARGED PLAN (SCALE 1 : 1000) 1

CE-A1-032 INDUSTRIAL GAS MISCELLANEOUS DETAILS 0

SANITARY SEWER SYSTEM

CE-A1-040 OVERALL SANITARY SEWERAGE SYSTEM LAYOUT PLAN 1

CE-A1-041 ENLARGED SANITARY SEWERAGE SYSTEM LAYOUT PLAN (SCALE 1 : 1000) 1

CE-A1-043 SANITARY SEWERAGE SYSTEM MISCELLANEOUS DETAILS 0

SUB-TOTAL 1 15

STRUCTURAL-INFRASTRUCTURE

SE-A1-001 GENERAL NOTES, ABBREVIATIONS & MISCELLANEOUS DETAILS

SE-A1-005 BUTTERFLY VALVE CHAMBER REINFORCEMENT AND DETAILS 0

SE-A1-006 AIR RELEASE VALVE CHAMBER REINFORCEMENT AND DETAILS 0

SE-A1-007 WASHOUT VALVE CHAMBER REINFORCEMENT AND DETAILS 0

SE-A1-008 STORM WATER CHAMBER/ MANHOLE DETAILS 1

SE-A1-008 STRUCTURAL MISCELLANEOUS DETAILS 0

SUB-TOTAL 2 1

LANDSCAPE

LS-A1-001 MASTER PLAN 1

LS-A1-002 ENLARGED MASTER PLAN & SITE FURNITURE LAYOUT PLAN (SCALE 1 : 1000) 1

LS-A1-003 HARDSCAPE SCHEDULE AND SECTION DETAIL 1

LS-A1-005 SHADED PARKING DETAIL 0

LS-A1-006 GATE AND FENCE DETAILS 0

12
NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

SUB-TOTAL 3 3

ELECTRICAL

EE-A1-001 OVERALL STREET LIGHTING AND LOW VOLTAGE DISTRIBUTION PLAN 1

ENLARGED STREET LIGHTING AND LOW VOLTAGE DISTRIBUTION PLAN (SCALE 1 :


EE-A1-002 1
1000)

EE-A1-003 OVERALL MEDIUM VOLTAGE, 13.8KV DISTRIBUTION PLAN 1

EE-A1-004 ENLARGED MEDIUM VOLTAGE, 13.8KV DISTRIBUTION PLAN (SCALE 1 : 1000) 1

EE-A1-006 13.8KV POWER DISTRIBUTION SYSTEM SINGLE LINE DIAGRAM 0

TELECOM

EE-A1-007 OVERALL TELECOMMUNICATION DISTRIBUTION PLAN 1

EE-A1-008 ENLARGED TELECOMMUNICATION DISTRIBUTION PLAN (SCALE 1 : 1000) 1

EE-A1-009 MISCELLANEOUS DETAILS (FDT DETAILS, DUCT BANK DETAILS- FOC DETAILS) 0

SUB-TOTAL 4 6

TOTAL FOR SITE(SUB-TOTAL 1+2+3+4) 25

13
ENGINEERING CONSULTANCY SERVICES FOR PACKAGE 2, CONSTRUCTION OF NPCC KSA YARD FACILITIES

LIST OF DRAWINGS FOR OPTIONAL FACILITIES

NO. OF
DRAWING NO. DRAWING TITLE
ESTIMATED DWG

ARCHITECTURAL

BERTHING QUAY SIDE 123

AR-A0-BRT-100 BERTHING LAYOUT PLANS AND DETAILS 4

AR-A0-BRT-101 SECTIONS AND MISC. DETAILS 2

SUB TOTAL = 6

HEAVY DUTY JETTY

AR-A0-JTY-100 JETTY LAYOUT PLANS AND DETAILS 3

AR-A0-JTY-101 SECTIONS AND MISC. DETAILS 2

SUB TOTAL = 5

TOTAL FOR ARCHITECTURAL 11

STRUCTURAL

BERTHING QUAY SIDE 123

SE-A0-BRT-100 LAYOUT PLANS AND DETAILS 4

SE-A0-BRT-101 MISCELLANEOUS DETAILS 4

SUB TOTAL = 8

HEAVY DUTY JETTY

SE-A0-JTY-100 LAYOUT PLANS AND DETAILS 3

SE-A0-JTY-101 MISCELLANEOUS DETAILS 2

SUB TOTAL = 5

TOTAL FOR STRUCTIRAL 13

TOTAL FOR OPTIONAL FACILITIES (BEARTHING & HEAVY DUTY JETTY) 24

1
ENGINEERING CONSULTANCY SERVICES FOR PACKAGE 2, CONSTRUCTION OF NPCC KSA YARD FACILITIES
MAN-HOUR DETAIL FOR PREPARATIONS OF NPCC DOCUMENTS
ESTIMATED
TOTAL AMOUNT
S/ NO. DESCRIPTIONS MAN-HOUR UNIT RATES (SR)
(SR)
DETAILS
1 ARCHITECTURAL
BILL OF QUANTITIES (BOQ) 160 160 25,600.00
TECHNICAL SPECIFICATION 192 160 30,720.00
DESIGN ANALYSIS REPORS/ DESIGN CRITERIA 48 160 7,680.00
FF&E MASTER FOLLOW 96 160 15,360.00
3 D RENDERING 336 160 53,760.00
SUB-TOTAL FOR ARCHITECTURAL 832 133,120.00
2 STRUCTRUAL
BILL OF QUANTITIES (BOQ) 160 160 25,600.00
TECHNICAL SPECIFICATION 144 160 23,040.00
DESIGN ANALYSIS REPORS/ DESIGN CRITERIA 48 160 7,680.00
STRUCTURAL DESIGN CALCULATIONS 320 160 51,200.00
SUB-TOTAL FOR STRUCTURAL 672 107,520.00
3 MECHANICAL
BILL OF QUANTITIES (BOQ) 160 160 25,600.00
TECHNICAL SPECIFICATION 192 160 30,720.00
DESIGN ANALYSIS REPORS/ DESIGN CRITERIA 48 160 7,680.00
FF&E MASTER FOLLOW 96 160 15,360.00
DESIGN CALCULATIONS/ HYDRAULIC ANALYSIS 336 160 53,760.00
SUB-TOTAL FOR MECHANICAL 832 133,120.00
4 ELECTRICAL AND TELECOM
BILL OF QUANTITIES (BOQ) 160 160 25,600.00
TECHNICAL SPECIFICATION 192 160 30,720.00
DESIGN ANALYSIS REPORS/ DESIGN CRITERIA 48 160 7,680.00
ELECTRICAL & TELECOM DRAWINGS & CALCULATIO 336 160 53,760.00
SUB-TOTAL FOR ELECTRICAL 736 117,760.00
5 CIVIL/ LANDSCAPE
BILL OF QUANTITIES (BOQ) 96 160 15,360.00
TECHNICAL SPECIFICATION 192 160 30,720.00
DESIGN ANALYSIS REPORS/ DESIGN CRITERIA 48 160 7,680.00
SCHEDULE OF SD, PW, FW, SS & IRR 96 160 15,360.00
DESIGN CALCULATIONS ( SD, PW, FW, SS & IRR) 192 160 30,720.00
LANDSCAPE PRESENTATION 48 160 7,680.00
SUB-TOTAL FOR CIVIL 672 107,520.00
TOTAL MAN-HOUR FOR DOCUMENTS 3744 599,040.00

165

617760
Remarks

1 Engr. x 1 days x 20 buildings 30,720.00


1 Engr. x 24 days
1 Engr. x 6 days
1 Engr. x 12 days
1 Engr. x 2 days x 21 buildings

1 Engr. x 1 days x 20 buildings


1 Engr. x 18 days
1 Engr. x 6 days
1 Engr. x 2 days x 20 buildings

1 Engr. x 1 days x 20 buildings


1 Engr. x 24 days
1 Engr. x 6 days
1 Engr. x 12 days
1 Engr. x 2 days x 21 buildings

1 Engr. x 1 days x 20 buildings


1 Engr. x 24 days
1 Engr. x 6 days
1 Engr. x 2 days x 21 buildings

1 Engr. x 12 days
1 Engr. x 24 days
1 Engr. x 6 days
1 Engr. x 12 days
1 Engr. x 24 days
1 Engr. x 6 days