ERECTION SCHEDULE (LAUNCHER)

PROYEK JALAN TOL LAMPUNG

TOTAL Sep/2017 Oct/2017 Nov/2017


No Description
GIRDER 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5
1 Mobilisasi Alat & Asesoris Jembatan Ways Seputih
2 Setting & Installing Launcher di A2
3 Launching Launcher ke P1, Setting Asesoris
5 Erection Girder A2-P2 17
6 Load Test
7 Erection Girder P2-P1 16
8 Launching Launcher ke P1 & A1 Setting Asesoris
9 Erection Girder P1-A1 15