You are on page 1of 6

Production

Op System
Process System Description Line Contractor Contractor Name Subsystem Subsystem Description Type Desc
Type
Sequence
1100‐OP‐01 High Mountain Platforms & Roads Facility 1st K‐CC1‐101 MOTA ENGIL PERÚ S.A. 1110‐1001 Access Road Interoceanica ‐ Vizcachas FACILITY
1110‐1002 Access Road to Titire FACILITY
1110‐1003 Access Road from Pumping Station to Dam (North Side) FACILITY
1120‐1001 Titire Intake & Sandtrap Platform FACILITY
1120‐1003 Titire River Pump Station & Electrical Substation Platform FACILITY
1130‐1005 Vizcacha River Pump Station and Electrical Substation / E‐Room Platform FACILITY
1130‐1006 Vizcachas Operation Camp Platform FACILITY
6010‐1801 Construction Access Roads and Platforms / Early Works ‐ Titire FACILITY
6010‐1803 Waste Dump Titire FACILITY
6010‐1804 Waste Dump Vizcachas FACILITY
K‐CC1‐101, K‐EPC3‐108 MOTA ENGIL PERÚ S.A. / PROMET PERÚ SAC 6010‐1802 Construction Access Roads and Platforms / Early Works ‐ Vizcachas FACILITY
K‐CC1‐102 TECHINT SAC 1110‐1004 Auxiliary Access Roads FACILITY

1120‐OP‐01 Titire Water Pumping to Papujune Utility 1st K‐CC1‐101 MOTA ENGIL PERÚ S.A. 1120‐1002 Titire River Sandtrap PROCESS
1120‐1004 Titire River Intake PROCESS
1120‐1005 Titire River Gauging Stations T1 & T2 PROCESS
K‐CC1‐102 TECHINT SAC 1120‐5001 Titire River Pump Station PROCESS
1120‐6001 1120‐ER‐001 Electrical Room ‐ Titire River Pumping Station ELECTRICAL
1140‐5001 Fresh Water Pipeline ‐ Vizcachas Dam to Caracoles Ponds C‐1, C‐2 & C‐4 PROCESS
1140‐5002 Fresh Water Pipeline branch to Fresh & Fire Water Tank 2910‐TK‐001 PROCESS

1130‐OP‐01 Vizcachas Water Pumping to Papujune Utility 1st K‐CC1‐102 TECHINT SAC 1130‐5001 Vizcachas Pump Station PROCESS
1130‐6001 1130‐ER‐001 Electrical Room ‐ Vizcachas Pumping Station ELECTRICAL
K‐EPCN‐114 C2 MINING SOLUTIONS S.A.C. 1100‐8001 Structured Cabling ‐ High Mountain COMMUNICATIONS

1130‐OP‐02 Vizacachas Dam Utility 1st K‐CC1‐101 MOTA ENGIL PERÚ S.A. 1130‐1001 Diversion Channel PROCESS
1130‐1002 Dam Injection Curtains PROCESS
1130‐1003 Vizcacha River Dam (Including gates and hydraulic booth) PROCESS
1130‐1007 Vizcachas River Gauging Stations V1, V2 & V3 PROCESS
K‐CC1‐101, F‐CC1‐104 Mota Engil Perú S.A. / JJC Contratistas Generales 1130‐1004 Discharge Channel (Including delivery pipe to the community) PROCESS

2010‐OP‐01 Earthworks Area 2000 K‐CC2‐146A Facility 1st K‐CC2‐146A CONSORCIO COSAPI EPSA 2010‐1001 Platform and Access Road ‐ Primary Crusher FACILITY
2010‐1002 Access Road and Platform and Accumulation Pond ‐ Powder Magazine Storage FACILITY
2010‐1005 Platform and Access Road ‐ 2000‐T‐05 & 2000‐T‐06 FACILITY
2010‐1006 Platform and Access Road ‐ Mine Truck Shop FACILITY
2010‐1008 Platform and Access Road ‐ Light Vehicles Fuel Station FACILITY
2010‐1009 Platform and Access Road ‐ Potable Water, Fresh Water and Fire Loop FACILITY
2010‐1018 Platform TIE‐IN ‐ Line 8" FACILITY
2010‐1019 Organic Material Deposit ‐ DMO 2000‐TP‐04 FACILITY
2010‐1020 Organic Material Deposit ‐ DMO 2000‐TP‐06 FACILITY
2010‐1021 Quarry ‐ Accumulation Pond FACILITY
2840‐1001 Heavy Vehicle Fuel Station Platform FACILITY

2010‐OP‐02 Earthworks Area 2000 K‐CC2‐146B Facility 1st K‐CC2‐146B JJC CONTRATISTAS GENERALES SA 2010‐1011 Access Road to Pond 2000‐PC‐005 Km 0+600 @ Km 1+209.84 & CC‐2015 FACILITY
2010‐1012 Excedent Material Deposit ‐ DME‐01 FACILITY
2010‐1013 Excedent Material Deposit ‐ DME‐02 FACILITY
2010‐1014 Excedent Material Deposit ‐ DME‐03 FACILITY
2010‐1015 Excedent Material Deposit ‐ DME‐06 FACILITY
2010‐1016 Platform and Access Road to Contact Water Dam FACILITY
2010‐1017 Platform 2000‐T‐02 & Access Road to CC‐2006 FACILITY
2040‐1005 Platform 2000‐T‐01 FACILITY
2040‐1006 Platform 2000‐T‐07 FACILITY
K‐CC2‐146C JJC CONTRATISTAS GENERALES SA 2040‐1012 DME Construction Dump N° 1 West Side FACILITY

2030‐OP‐01 Mine 22.9 kV Power Distribution Utility 1st K‐EPCN‐114 C2 MINING SOLUTIONS S.A.C. 2030‐8001 Structured Cabling ‐ Mine Unit Substations COMMUNICATIONS
K‐EPCN‐154C COPEMI S A C CONSTRUCTORES 2030‐6001 Electrical Line 22.9 kV ‐ Circuit Nº 1 & 2 / Line 2030‐LA‐001 ELECTRICAL
2030‐6002 Electrical Line 22.9 kV (2030‐LA‐002) ELECTRICAL
2030‐6003 Electrical Line 22.9 kV 2030‐LA‐003 (Including 2030‐LA‐031) ELECTRICAL
2030‐6004 Mobile Substations 2030‐US‐001 @ 2030‐US‐004 ELECTRICAL

Contact Water Dam, Ponds & Pumping


Utility 1st PROCESS
2040‐OP‐01 Facilities K‐CC2‐146C JJC CONTRATISTAS GENERALES SA 2040‐0001 Pump Station Contact Water Dam
2040‐1071 CCR Control Dam PROCESS
2040‐5001 Eventual Water Pond (Including floating pumps) PROCESS
2040‐5002 Filtration Water Pipeline PROCESS
2040‐5003 Pipeline from Pumping Station to Tank 2950‐TK‐01 PROCESS
2040‐7001 Geotechnical Instrumentation PROCESS

2040‐OP‐02 Mine Water Management Phase I Utility 1st K‐CC2‐146B JJC CONTRATISTAS GENERALES SA 2040‐1008 Pond 2000‐PC‐005 PROCESS
2040‐1009 Pond 2000‐PC‐007 PROCESS
2040‐1010 Pond 2000‐PC‐001 and Access Road to Transfer Tank Platform PROCESS
2040‐1061 Collection Pond 2000‐PC‐001 PROCESS
6010‐1069 Access Road and Pond 6000‐PC‐001 PROCESS
K‐CC2‐146B, K‐EPC2‐194 JJC CONTRATISTAS GENERALES SA 2950‐5001 Mine Reclaim Water System Pumping Station PROCESS

2040‐OP‐03 Mine Water Management Phase II Utility 1st K‐CC2‐146A CONSORCIO COSAPI EPSA 2040‐1055 Collection Pond 2000‐PC‐003 PROCESS
2040‐1057 Collection Pond 2000‐PC‐009 PROCESS
2040‐1058 Connection Channel to Pond 2000‐PC‐10 PROCESS
CONSORCIO COSAPI EPSA / JJC CONTRATISTAS
PROCESS
K‐CC2‐146A, K‐CC2‐146C GENERALES SA 2040‐1056 Collection Pond 2000‐PC‐006
2040‐1059 Collection Pond 2000‐PC‐010 PROCESS
2040‐1060 Collection Pond & Acces Road 2000‐PN‐001 PROCESS
K‐CC2‐146B, K‐CC2‐146C JJC CONTRATISTAS GENERALES SA 2040‐1007 Pond 2000‐PC‐004 PROCESS
K‐CC3‐148A GYM Stracon 2950‐5002 Mine Reclaim Water pipeline to Papujune Fresh Water Drainage PROCESS

2040‐OP‐04 Mine Channels Facility 1st K‐CC2‐146A CONSORCIO COSAPI EPSA 2040‐1051 Channel C1 Year 25 and Water Intake NON PROCESS
K‐CC2‐146B JJC CONTRATISTAS GENERALES SA 2040‐1001 Channel C1 Year 5 and Water Intake NON PROCESS
2040‐1002 Channel C2 and Road NON PROCESS
2040‐1003 Channel C3 (Section I & II) NON PROCESS
2040‐1004 Channel C4, Water Intake and Access Ramp NON PROCESS
2040‐1011 Main Discharge Channel C1 Year 25 NON PROCESS

2120‐OP‐01 Asana River Diversion Facility 1st K‐CC‐147A COSAPI MAS ERRASURI 2120‐01 Primary Portal & Main Tunnel 0+000 ‐ 0+042 NON PROCESS
2120‐03 Construction Window Portal NON PROCESS
K‐CC‐147C COSAPI MAS ERRASURI 2120‐02 Secondary Portal & Tunnel NON PROCESS
2120‐04 Construction Window Portal & Tunnel (5+940) NON PROCESS
2120‐05 Main Tunnel 0+042 ‐ 3+500 NON PROCESS
2120‐06 Main Tunnel 3+500 ‐ 5+940 NON PROCESS
2120‐07 Main Tunnel 5+940 ‐ 7+591.60 NON PROCESS
2120‐08 Outlet Portal ‐ Discharge Channel NON PROCESS
2120‐09 Shaft Access & Discharge Shaft (0+042) NON PROCESS
2120‐10 Miscelaneous Works of Main Tunnel 0+000 ‐ 7+591.60 NON PROCESS
2120‐11 Ventilation Works Diversion System NON PROCESS
2120‐14 Works Inside of Secondary Tunnel (0+082) NON PROCESS
2120‐15 Geotechnical Instrumentation of the Tunnel NON PROCESS
2120‐16 Flow Monitoring System PROCESS
2120‐17 Tunnel Water Infiltration System PROCESS
PROCESS
K‐CC2‐145 OBRASCON HUARTE LAIN SA ‐ SUCURSAL DEL PERU 2130‐01 Sarallenque Creek Intake
2130‐02 Sarallenque Channel PROCESS
2130‐03 Sarallenque Channel Access Roads NON PROCESS
2140‐01 Asana River Intake ‐ Connection Channel ‐ Gravel Chamber PROCESS
2140‐02 Asana River Bypass Channel PROCESS
2140‐03 Millune Creek Intake & Channel PROCESS
2140‐04 Rectified Millune Creek PROCESS
2140‐05 Millune Aqueduct PROCESS
2140‐06 Sarallenque Creek & Bypass Channel Entrance Shaft PROCESS
2140‐07 Barrier Construction Diversion NON PROCESS
2140‐08 Provisory Asana River Diversion FACILITY
2140‐09 Asana River Diversion Barrier (include spillway) PROCESS
2140‐10 Dissipation Pond PROCESS
2140‐11 Asana River Diversion Barrier Plinth PROCESS
2140‐14 Geotechnical Instrumentation of the Barrier PROCESS
2140‐15 Blanket Section Upstream (Elevation 3625 to 3641). PROCESS
2140‐16 Blanket Section Downstreeam PROCESS
6010‐05 C1 Channel FACILITY
6010‐06 C2 Channel FACILITY

2210‐OP‐01 Pioneer Mine Roads K‐CC2‐146A Facility 1st K‐CC2‐146A CONSORCIO COSAPI EPSA 2210‐1001 Pioneer Mine Roads ‐ Section 1 NON PROCESS
2210‐1002 Pioneer Mine Roads ‐ Sections 4B‐1 NON PROCESS
2210‐1003 Pioneer Mine Roads ‐ Sections 4B‐2 NON PROCESS
2210‐1004 Pioneer Mine Roads ‐ Sections 4C NON PROCESS
2210‐1005 Pioneer Mine Roads ‐ Sections 6 NON PROCESS
2210‐OP‐01 Pioneer Mine Roads K‐CC2‐146A Facility 1st K‐CC2‐146A CONSORCIO COSAPI EPSA 2210‐1006 Platform and Access Road ‐ Mine Shovel Assembly NON PROCESS
2210‐1007 Pioneer Mine Roads ‐ Sections 7A NON PROCESS
2210‐1008 Pioneer Mine Roads ‐ Sections 7B NON PROCESS
2210‐1009 Pioneer Mine Roads ‐ Sections 4D NON PROCESS

2610‐OP‐01 Primary Crusher 1 to Sacrifice Belt Process 1st K‐CC2‐170 CONSORCIO SACYR ‐ AJANI 2610‐1001 Primary Crusher Building NON PROCESS
2610‐5001 Primary Crusher 1 (Including Lubrication & Hydraulic Systems) PROCESS
2610‐5003 Primary Crusher 1 ‐ Auxiliary Equipment (Rock Breaker & Bridge Crane) PROCESS
2610‐5005 Primary Crusher 1 ‐ Dust Suppression PROCESS
2610‐5007 Primary Crushers 1 & 2 ‐ Dust Collector PROCESS
2630‐6001 2630‐ER‐001 Electrical Room ‐ Primary Crusher ELECTRICAL
2730‐5002 Belt Feeder 1 & Sacrifice Belt PROCESS
2730‐5004 Sacrifice Belt & Overland Conveyor Dust Suppression PROCESS
2910‐5001 Primary Crusher, Overland Conveyor & WTP Fire Water Distribution PROCESS
2910‐5002 Primary Crusher, Overland Conveyor & WTP Fresh Water Distribution PROCESS
K‐EPCN‐114 C2 MINING SOLUTIONS S.A.C. 2600‐8001 Structured Cabling ‐ Primary Crusher & Stockpile COMMUNICATIONS
K‐EPCN‐115 MG TRADING SAC 2610‐8002 Data Center ‐ Primary Crushing COMMUNICATIONS
K‐EPCN‐154C COPEMI S A C CONSTRUCTORES 5210‐6001 Electrical Line 22.9 kV ‐ 5210‐LA‐001 Primary Crusher / Truckshop & Derivations ELECTRICAL

2610‐OP‐02 Primary Crusher 2 to Stockpile Process 2nd K‐CC2‐170 CONSORCIO SACYR ‐ AJANI 2610‐5002 Primary Crusher 2 (Including Lubrication & Hydraulic Systems) PROCESS
2610‐5004 Primary Crusher 2 ‐ Auxiliary Equipment (Rock Breaker & Bridge Crane) PROCESS
2610‐5006 Primary Crusher 2 ‐ Dust Suppression PROCESS
2730‐5003 Belt Feeder 2 PROCESS

2610‐OP‐03 Overland Conveyor to Stockpile Process 1st K‐CC2‐170 CONSORCIO SACYR ‐ AJANI 2720‐6001 2720‐ER‐001 Electrical Room ‐ Coarse Ore Handling ELECTRICAL
2730‐5001 Overland Conveyor PROCESS
2730‐5005 Overland Conveyor Ventilation System PROCESS
K‐EPCN‐154C COPEMI S A C CONSTRUCTORES 5210‐6002 Electrical Line 22.9 kV ‐ 5210‐LA‐002 Overland Conveyor ELECTRICAL

2610‐OP‐04 Primary Crushing Air Systems Utility 1st K‐CC2‐170 CONSORCIO SACYR ‐ AJANI 2610‐5008 Primary Crushers 1 & 2 ‐ Plant and Instrument Air PROCESS

2810‐OP‐01 Truck Shop Facilities Utility 1st K‐EPC2‐104 JJC CONTRATISTAS GENERALES SA 2810‐9001 Truck Workshop PROCESS
2810‐9002 Truck Wash Station PROCESS
2810‐9003 Tire Change Workshop PROCESS
2810‐9004 Truck Lubrication Station PROCESS
2810‐9005 Offices / Canteen / Warehouse / Changehouse PROCESS
2830‐6001 2830‐ER‐001 Electrical Room ‐ Truck Shop ELECTRICAL
2830‐6002 2830‐ER‐002 Electrical Room ‐ Ancillary Facilities ELECTRICAL
K‐EPC2‐105 (blank) 2810‐9006 Truck Shop Utilities PROCESS
K‐EPCN‐114 C2 MINING SOLUTIONS S.A.C. 2810‐8001 Structured Cabling ‐ Mine Workshop COMMUNICATIONS

2850‐OP‐01 Explosives Magazine Utility 1st K‐CC2‐146A CONSORCIO COSAPI EPSA 2850‐1001 Platform and Storage Pond ‐ Explosive Magazine FACILITY
K‐CS‐292B CHEMTRADE SAC 2850‐1004 Magazine Access Booth FACILITY
2850‐9001 Ammonium Nitrate Storage NON PROCESS
2850‐9002 Emulsifying Agent Storage and Loading NON PROCESS
2850‐9003 High Explosive Magazine NON PROCESS
2850‐9004 Detonator Magazine NON PROCESS

2910‐OP‐01 Mine Water Systems Utility 1st K‐CC2‐170 CONSORCIO SACYR ‐ AJANI 2910‐5003 Mine Fresh / Fire Water Tank PROCESS

3010‐OP‐01 Earthworks Area 3000 K‐CC3‐148A Facility 1st K‐CC3‐148A CONSORCIO GYM STRACON 3010‐1001 Platform and Access Road ‐ Main Access Gate FACILITY
3010‐1002 Platform and Access Road ‐ Fuel Station FACILITY
3010‐1003 Platform and Access Road ‐ Sewage Treatment Plant FACILITY
3010‐1004 Platform and Access Road ‐ Unified Camp FACILITY
3010‐1006 Platform and Access Road ‐ Process Water Tank FACILITY
3010‐1007 Platform and Access Road ‐ Emergency Pond (Flotation) FACILITY
3010‐1008 Platform and Access Road ‐ Thickening, Filtration and Concentrate Storage FACILITY
3010‐1009 Platform and Access Road ‐ Tailings Thickeners FACILITY
3010‐1010 Platform and Access Road ‐ Lime Plant and Reagents FACILITY
3010‐1011 Platform and Access Road ‐ Regrinding and Flotation FACILITY
3010‐1012 Platform and Access Road ‐ Fresh Water Tank FACILITY
3010‐1013 Platform and Access Road ‐ Pebbles Crusher FACILITY
3010‐1014 Platform and Access Road ‐ Stockpile FACILITY
3010‐1015 Platform and Access Road ‐ Main Sub‐Station FACILITY
3010‐1016 Platform and Access Road ‐ Administration Buildings FACILITY
3010‐1017 Platform and Access Road ‐ Overland Conveyor Tunnel Exit FACILITY
3010‐1018 Platform and Access Road ‐ Waste Storage FACILITY
3010‐1019 Platform and Access Road ‐ Concentrator FACILITY
3010‐1020 Platform and Access Road ‐ Spill Pond FACILITY
3010‐1021 Papujune ‐ Drainage System NON PROCESS
3010‐1022 Papujune ‐ Sewage System NON PROCESS
3010‐1024 Contact and Non Contact Water Channel ‐ Main Gate Sector FACILITY
K‐CC5‐105C COLVIAS S A C 3010‐1023 Pond 3000‐PC‐004 and Access Road PROCESS

3010‐OP‐02 Papujune Plant General ‐ Civil & Structural Facility 1st K‐CC3‐172 GyM S A 3010‐1030 Papujune Plant Area General Works ‐ Civil / Concrete FACILITY
3010‐1031 Papujune Plant Area General Works ‐ Structural Steel FACILITY

Reclaim Conveyor Stockpile to Grinding ‐ Civil


Facility 1st FACILITY
3100‐OP‐01 & Structural K‐CC3‐172 GyM S A 3120‐1001 Stockpile Building ‐ Civil / Concrete
3120‐1002 Stockpile Building ‐ Structural Steel ‐ Dome NON PROCESS
3130‐1001 Reclaim Tunnel ‐ Civil / Concrete FACILITY
3130‐1002 Reclaim Tunnel ‐ Structural Steel FACILITY
3140‐1001 Feeders & Feed Conveyors to Grinding ‐ Civil / Concrete FACILITY
3140‐1002 Feeders & Feed Conveyors to Grinding ‐ Structural Steel FACILITY

3140‐OP‐01 Ore Feed to Grinding 1st Line Process 1st K‐CC3‐172 GyM S A 3130‐5002 Reclaim Tunnel SAG 2 ‐ Ventilation System PROCESS
3140‐0002 Reclaim Belt Feeders SAG 2 PROCESS
3140‐0004 SAG Mill 2 Feed Conveyor PROCESS
3140‐0006 Dust Collector ‐ Reclaim Belt Feeders SAG 2 PROCESS
3140‐5002 SAG Mill 2 Feed Conveyor Auxiliary Equipment PROCESS
3210‐0009 Balls Loading ‐ SAG Mill 2 PROCESS
3220‐6001 3220‐ER‐001 Electrical Room ‐ Pebbles Crusher ELECTRICAL

3140‐OP‐02 Ore Feed to Grinding 2nd Line Process 2nd K‐CC3‐172 GyM S A 3130‐5001 Reclaim Tunnel SAG 1 ‐ Ventilation System PROCESS
3140‐0001 Reclaim Belt Feeders SAG 1 PROCESS
3140‐0003 SAG Mill 1 Feed Conveyor PROCESS
3140‐0005 Dust Collector ‐ Reclaim Belt Feeders SAG 1 PROCESS
3140‐5001 SAG Mill 1 Feed Conveyor Auxiliary Equipment PROCESS
3210‐0020 Balls Loading ‐ SAG Mill 1 PROCESS

3200‐OP‐01 Mills and Pebbles ‐ Civil & Structural Facility 1st K‐CC3‐172 GyM S A 3210‐1001 Sag and Ball Mills ‐ Civil / Concrete FACILITY
3210‐1002 Grinding Building NON PROCESS
3220‐1001 Pebbles Crusher ‐ Civil / Concrete FACILITY
3220‐1002 Pebbles Crusher ‐ Building NON PROCESS

3210‐OP‐01 Grinding 1st Line Process 1st K‐CC3‐172 GyM S A 3210‐0005 SAG Mill 2 PROCESS
3210‐0006 Ball Mill 2 PROCESS
3210‐0007 SAG Mill 2 Discharge Box & Cyclone Feed Pumps PROCESS
3210‐0008 SAG Mill 2 Hydrocyclones PROCESS
3210‐0010 Balls Loading ‐ Ball Mills PROCESS
3210‐0014 Grinding Area Sump Pumps PROCESS
3210‐0015 Hydrocyclones Overflow Collection System PROCESS
3210‐0016 Grinding Area Spills Collection System PROCESS
3210‐0022 Hydrocyclones 3 & 4 Overflow Sampling System PROCESS
3210‐5003 Bridge Crane Hydrocyclones Area ‐ 3210‐CN‐003 PROCESS
3210‐5005 SAG Mill 2 Discharge Screen PROCESS
3210‐5006 Grinding Area Auxiliary Equipment PROCESS
3210‐6001 3210‐ER‐001 Electrical Room ‐ Grinding ELECTRICAL
3210‐6003 SAG Mill 2 Electrical Room 3210‐MI‐002ER ELECTRICAL
3210‐6005 Ball Mill 2 Electrical Room 3210‐MI‐004ER ELECTRICAL
3210‐7002 Size Analyzers ‐ Grinding (SAG Mill 1 &2 Feed, Pebbles) PROCESS

3210‐OP‐02 Grinding 2nd Line Process 2nd K‐CC3‐172 GyM S A 3210‐0001 SAG Mill 1 PROCESS
3210‐0002 Ball Mill 1 PROCESS
3210‐0003 SAG Mill 1 Discharge Box & Cyclone Feed Pumps PROCESS
3210‐0004 SAG Mill 1 Hydrocyclones PROCESS
3210‐0021 Hydrocyclones 1 & 2 Overflow Sampling System PROCESS
3210‐5004 SAG Mill 1 Discharge Screen PROCESS
3210‐6002 SAG Mill 1 Electrical Room 3210‐MI‐001ER ELECTRICAL
3210‐6004 Ball Mill 1 Electrical Room 3210‐MI‐003ER ELECTRICAL

3210‐OP‐03 Grinding Area Cooling Water 1st Line Utility 1st K‐CC3‐172 GyM S A 3210‐0011 Grinding Cooling Water System SAG & Ball 2 PROCESS

3210‐OP‐04 Grinding Area Seal Water 1st Line Utility 1st K‐CC3‐172 GyM S A 3210‐0013 Grinding Seal Water Circuit 1st Line PROCESS

3210‐OP‐05 Grinding Area Cooling Water 2nd Line Utility 2nd K‐CC3‐172 GyM S A 3210‐0017 Grinding Cooling Water System SAG & Ball 1 PROCESS

3210‐OP‐06 Grinding Area Seal Water 2nd Line Utility 2nd K‐CC3‐172 GyM S A 3210‐0018 Grinding Seal Water Circuit 2nd Line PROCESS
3210‐OP‐07 Grinding Area SAG Mills Bridge Crane Utility 1st K‐CC3‐172 GyM S A 3210‐5001 Bridge Crane SAG Mills Area ‐ 3210‐CN‐004 PROCESS

3210‐OP‐08 Grinding Area Ball Mills Bridge Crane Utility 1st K‐CC3‐172 GyM S A 3210‐5002 Bridge Crane Ball Mills Area ‐ 3210‐CN‐005 PROCESS

3220‐OP‐01 Pebbles Circuit 1st Line Process 1st K‐CC3‐172 GyM S A 3220‐0001 Pebbles Crusher Circuit 1st Line PROCESS
3220‐0002 Pebbles Crusher Circuit ‐ Auxiliary Equipment PROCESS

3220‐OP‐02 Pebbles Circuit 2nd Line Process 2nd K‐CC3‐172 GyM S A 3220‐003 Pebbles Crusher Circuit 2nd Line PROCESS

3300‐OP‐01 Flotation and Regrinding ‐ Civil & Structural Facility 1st K‐CC3‐172 GyM S A 3310‐1001 Copper Flotation ‐ Civil / Concrete FACILITY
3310‐1002 Copper Flotation ‐ Building NON PROCESS
3320‐1001 Regrind ‐ Civil / Concrete FACILITY
3320‐1002 Regrind ‐ Building NON PROCESS
3340‐1002 Coarse Particle Flotation ‐ Civil / Concrete FACILITY
3340‐1003 Coarse Particle Flotation ‐ Structural Steel FACILITY

3310‐OP‐01 Rougher Flotation 1st Line Process 1st K‐CC3‐172 GyM S A 3310‐0003 Rougher Flotation Cells L3 PROCESS
3310‐0004 Rougher Flotation Cells L4 PROCESS
3310‐0013 Sampling and Analyzer ‐ Flotation PROCESS
3310‐0020 Rougher Flotation Cells Feed PROCESS
3310‐6001 3310‐ER‐001 Electrical Room ‐ Flotation ELECTRICAL

3310‐OP‐02 Rougher Flotation 2nd Line Process 2nd K‐CC3‐172 GyM S A 3310‐0001 Rougher Flotation Cells L1 PROCESS
3310‐0002 Rougher Flotation Cells L2 PROCESS

3310‐OP‐03 Scavenger & Cleaner Flotation 1st Line Process 1st K‐CC3‐172 GyM S A 3310‐0005 Cleaner Flotation Cells Feed 1st Line PROCESS
3310‐0006 Cleaner Flotation Cells L1 PROCESS
3310‐0008 Scavenger Flotation Cells L1 PROCESS

3310‐OP‐04 Scavenger & Cleaner Flotation 2nd Line Process 2nd K‐CC3‐172 GyM S A 3310‐0007 Cleaner Flotation Cells L2 PROCESS
3310‐0009 Scavenger Flotation Cells L2 PROCESS
3310‐0021 Cleaner Flotation Cells Feed 2nd Line PROCESS

3310‐OP‐05 Column Cells Flotation 1st Line Process 1st K‐CC3‐172 GyM S A 3310‐0010 Column Flotation Cells Feed PROCESS
3310‐0011 Columns Flotation Cells 71 & 72 PROCESS

3310‐OP‐06 Column Cells Flotation 2nd Line Process 2nd K‐CC3‐172 GyM S A 3310‐0012 Columns Flotation Cells 73 & 74 PROCESS

3310‐OP‐07 Flotation Air Blowers 1st Line Utility 1st K‐CC3‐172 GyM S A 3310‐0017 Flotation Area Air Blowers ‐ Rougher L3 & L4 ‐ Scavenger L1 PROCESS

3310‐OP‐08 Flotation Air Blowers 2nd Line Utility 2nd K‐CC3‐172 GyM S A 3310‐0018 Flotation Area Air Blowers ‐ Rougher L1 & L2 ‐ Scavenger L2 PROCESS

3310‐OP‐09 Flotation Area Tower Crane Utility 1st K‐CC3‐172 GyM S A 3310‐5001 Flotation Area Tower Crane 3310‐CN‐001 PROCESS

3320‐OP‐01 Regrind 1st Line Process 1st K‐CC3‐172 GyM S A 3320‐0001 Regrind Circuit N°1 PROCESS
3320‐0002 Regrind Circuit N°2 PROCESS
3320‐0006 Sampling and Analyzer ‐ Regrind PROCESS
3320‐0007 Regrind Auxiliary Equipment PROCESS
3320‐0008 Regrind Area Spills Collection System PROCESS
3320‐6001 3320‐ER‐001 Electrical Room ‐ Regrind ELECTRICAL

3320‐OP‐02 Regrind 2nd Line Process 2nd K‐CC3‐172 GyM S A 3320‐0003 Regrind Circuit N°3 PROCESS

3400‐OP‐01 Molybdenum Plant ‐ Civil & Structural Facility 1st K‐CC3‐172 GyM S A 3410‐1001 Molybdenum Plant ‐ Civil / Concrete FACILITY
3410‐1002 Molybdenum Plant ‐ Building NON PROCESS

Molybdenum Plant ‐ Rougher & 1st/2nd


Process Moly PROCESS
3410‐OP‐01 Cleaner Flotation K‐CC3‐172 GyM S A 3410‐0001 Molybdenum Rougher Cells L1 & L2
3410‐0002 Molybdenum 1st Cleaner Cells L1 & L2 PROCESS
3410‐0003 Molybdenum 2nd Cleaner Cells L1 & L2 PROCESS
3410‐0005 2nd Cleaner L1 & L2 PROCESS
3410‐0010 Sampling and Analyzer ‐ Molybdenum PROCESS
3410‐0012 Gas Extraction and Cleaning PROCESS

Molybdenum Plant ‐ 3rd/4th Cleaner


Process Moly PROCESS
3410‐OP‐02 Flotation & Thickening K‐CC3‐172 GyM S A 3410‐0004 Molybdenum 3rd & 4th Cleaner Column Cells
3410‐0006 Molybdenum Concentrate Thickening & Storage PROCESS
3410‐0009 Cooper Concentrate Transfer to Thickening PROCESS

Molybdenum Plant ‐ Filtering and


Process Moly PROCESS
3410‐OP‐03 Concentrate Dispatch K‐CC3‐172 GyM S A 3410‐0008 Molybdenum Filtration, Drying and Dispatch

3500‐OP‐01 Lime and Reagents Plant ‐ Civil & Structural Facility 1st K‐CC3‐172 GyM S A 3510‐1001 Lime Plant ‐ Civil / Concrete FACILITY
3510‐1002 Lime Plant ‐ Structural Steel FACILITY
3520‐1001 Reagents and Flocculant Plant ‐ Civil / Concrete FACILITY
3520‐1002 Reagents and Flocculant Plant ‐ Structural Steel FACILITY
3530‐1001 Sodium Sulphide Plant ‐ Civil / Concrete FACILITY
3530‐1002 Sodium Sulphide Plant ‐ Structural Steel FACILITY
3540‐1001 Sulphuric Acid Plant ‐ Civil / Concrete FACILITY
3540‐1002 Sulphuric Acid Plant ‐ Structural Steel FACILITY

3510‐OP‐01 Lime Plant & Distribution 1st Line Utility 1st K‐CC3‐172 GyM S A 3510‐0001 Lime Plant PROCESS
3510‐0002 Lime Storage and Distribution ‐ Grinding & Flotation 1st Line PROCESS

3510‐OP‐02 Lime Distribution 2nd Line Utility 2nd K‐CC3‐172 GyM S A 3510‐0004 Lime Distribution ‐ Grinding & Flotation 2nd Line PROCESS

3510‐OP‐03 Lime Distribution Moly Plant Utility Moly K‐CC3‐172 GyM S A 3510‐0003 Lime Storage and Distribution ‐ Molybdenum Plant PROCESS

Utility 1st PROCESS


3520‐OP‐01 Reagents ‐ Collector 1 (AP‐3894) Distribution K‐CC3‐172 GyM S A 3520‐0001 Collector 1 (AP‐3894)

Utility 1st PROCESS


3520‐OP‐02 Reagents ‐ Collector 2 (Xanthate) Distribution K‐CC3‐172 GyM S A 3520‐0002 Collector 2 (Xanthate)

3520‐OP‐03 Reagents ‐ Collector 3 (AP‐404) Distribution Utility 1st K‐CC3‐172 GyM S A 3520‐0003 Collector 3 (AP‐404) PROCESS

3520‐OP‐04 Reagents ‐ Frother 1 (MIBC) Distribution Utility 1st K‐CC3‐172 GyM S A 3520‐0004 Frother 1 (MIBC) PROCESS

Reagents ‐ Frother 2 (Dowfroth 250)


Utility 1st PROCESS
3520‐OP‐05 Distribution K‐CC3‐172 GyM S A 3520‐0005 Frother 2 (Dowfroth 250)

3520‐OP‐06 Reagents ‐ Diesel Distribution Utility 2nd K‐CC3‐172 GyM S A 3520‐0006 Diesel ‐ Grinding & Flotation PROCESS

Reagents ‐ Antifroth & Diesel Distribution


Utility Moly PROCESS
3520‐OP‐07 Moly Plant K‐CC3‐172 GyM S A 3520‐0007 Antifroth & Diesel ‐ Molybdenuum Plant

3520‐OP‐08 Reagents ‐ Flocculant Distribution Utility 1st K‐CC3‐172 GyM S A 3520‐0008 Flocculant Tailings Thickeners PROCESS

Reagents ‐ Sodium Sulphide Distribution Moly


Utility Moly PROCESS
3530‐OP‐01 Plant K‐CC3‐172 GyM S A 3530‐0001 NaHS Sodium Sulphide Mixing, Storage and Distribution

Reagents ‐ Sulphuric Acid Distribution Moly


Utility Moly PROCESS
3540‐OP‐01 Plant K‐CC3‐172 GyM S A 3540‐0001 Sulphuric Acid ‐ Storage and Distribution

Thickening, Filtering and Storage ‐ Civil &


Facility 1st FACILITY
3600‐OP‐01 Structural K‐CC3‐172 GyM S A 3610‐1001 Filtration Area Site Preparation ‐ Civil / Concrete
3610‐1002 Filtration Area ‐ Building FACILITY
3620‐1001 Copper Concentrate Thickening ‐ Civil / Concrete FACILITY
3620‐1002 Copper Concentrate Thickening ‐ Structural Steel FACILITY
3630‐1001 Copper Concentrate Filtering and Storage ‐ Civil / Concrete FACILITY
3630‐1002 Copper Concentrate Filtering and Storage ‐ Building NON PROCESS

3620‐OP‐01 Copper Concentrate Thickener 1st Line Process 1st K‐CC3‐172 GyM S A 3420‐6001 3420‐ER‐001 Electrical Room ‐ Molybdenum Plant ELECTRICAL
3620‐0002 Concentrate Feed & Copper Concentrate Thickening PROCESS
3620‐6001 Power Supply to Thickening and Filtering ELECTRICAL
K‐EPCN‐154C COPEMI S A C CONSTRUCTORES 5210‐6003 Electrical Line 22.9 kV ‐ 5210‐LA‐003 Molybdenum Plant ELECTRICAL

3620‐OP‐02 Copper Concentrate Thickener 2nd Line Process 2nd K‐CC3‐172 GyM S A 3620‐0001 Cu/Mo Concentrate Thickening PROCESS

3630‐OP‐01 Copper Concentrate Filtering 1st Line Process 1st K‐CC3‐172 GyM S A 3630‐0001 Concentrate Distribution Box & Cu Tank PROCESS
3630‐0002 Cu Concentrate Filters N°1 & N°2 PROCESS
3630‐0003 Copper Concentrate Storage and Load Out PROCESS
3630‐0006 Filtrate Water PROCESS
3630‐0007 Concentrate Filter Dust Collection PROCESS
3630‐OP‐02 Copper Concentrate Filtering 2nd Line Process 2nd K‐CC3‐172 GyM S A 3630‐0008 Cu Concentrate Filter N°3 PROCESS
3630‐0010 Cu‐Mo Concentrate Tank PROCESS

3630‐OP‐03 Concentrate Filtering Air Systems Utility 1st K‐CC3‐172 GyM S A 3630‐0004 Concentrate Filter Plant Air Compressors PROCESS
3630‐0005 Concentrate Filter Instrument Air Compressors PROCESS

3700‐OP‐01 Tailings Thickeners ‐ Civil & Structural Facility 1st K‐CC3‐172 GyM S A 3710‐1001 Tailings Thickeners ‐ Civil / Concrete FACILITY
3710‐1002 Tailings Thickeners ‐ Structural Steel FACILITY
3720‐1001 Water Recovery System ‐ Civil / Concrete FACILITY
3720‐1002 Water Recovery System ‐ Structural Steel FACILITY

3710‐OP‐01 Tailings Thickeners 1st Line Process 1st K‐CC3‐172 GyM S A 3710‐0002 Tailings Thickener 2 PROCESS
3710‐0003 Tailings Dristibution to Thickeners & Disposal PROCESS
3740‐6001 3740‐ER‐001 Electrical Room ‐ Tailings Thickening ELECTRICAL

3710‐OP‐02 Tailings Thickeners 2nd Line Process 2nd K‐CC3‐172 GyM S A 3710‐0001 Tailings Thickener 1 PROCESS

3720‐OP‐01 Grinding Process Water 1st Line Utility 1st K‐CC3‐172 GyM S A 3210‐0012 Grinding Process Water Circuit 1st Line PROCESS

3720‐OP‐02 Plant Process Water 2nd Line Utility 2nd K‐CC3‐172 GyM S A 3210‐0019 Grinding Process Water Circuit 2nd Line PROCESS
3310‐0019 Flotation Process Water Circuit 2nd Line PROCESS

3720‐OP‐03 Water Recovery System Utility 1st K‐CC3‐172 GyM S A 3720‐0001 Water Recovery System PROCESS

3720‐OP‐04 Flotation Process Water 1st Line Utility 1st K‐CC3‐172 GyM S A 3310‐0016 Flotation Process Water Circuit 1st Line PROCESS

3720‐OP‐05 Moly Plant Process Water Utility Moly K‐CC3‐172 GyM S A 3410‐0013 Molybdenum Plant Process Water Circuit PROCESS

3810‐OP‐01 Plant Administration Building Utility 1st K‐EPC3‐185 TECNO FAST SAC 3810‐9001 Plant Administration Building & Control Room NON PROCESS
K‐EPCN‐114 C2 MINING SOLUTIONS S.A.C. 3810‐8001 Structured Cabling ‐ Papujune Administration Buildings COMMUNICATIONS
K‐EPCN‐115 MG TRADING SAC 3810‐8003 Data Center ‐ Papujune Administration Buildings COMMUNICATIONS
K‐EPCN‐154C COPEMI S A C CONSTRUCTORES 5210‐6004 22.9 kV Power Line 5210‐LA‐005 Admin Building / Plant Services ELECTRICAL

3810‐OP‐02 Polyclinic Utility 2nd K‐EPC3‐185 TECNO FAST SAC 3810‐9002 Polyclinic Building NON PROCESS

3810‐OP‐03 Warehouse Buildings Utility 1st K‐EPC3‐185 TECNO FAST SAC 3810‐9003 Support Administration Building and Warehouse NON PROCESS

3810‐OP‐04 Main Control Room Process 1st K‐EPC3‐185 TECNO FAST SAC 3810‐9004 Main Control Room PROCESS

3820‐OP‐01 Plant Services Buildings ‐ Metallurgy Lab Utility 1st K‐EPC3‐185 TECNO FAST SAC 3820‐9001 Metallurgy Lab NON PROCESS
4120‐9001 Soil Mechanics Laboratory NON PROCESS
K‐EPCN‐114 C2 MINING SOLUTIONS S.A.C. 3820‐8001 Structured Cabling ‐ Plant Services COMMUNICATIONS

3820‐OP‐02 Plant Services Buildings ‐ Plant Workshop Utility 2nd K‐EPC3‐185 TECNO FAST SAC 3820‐9002 Plant Workshop NON PROCESS

3900‐OP‐01 Plant Utilities ‐ Civil & Infrastructure Facility 1st K‐CC3‐172 GyM S A 3910‐1001 Compressor Room ‐ Civil / Concrete FACILITY
3910‐1002 Compressor Room ‐ Buiding FACILITY
3930‐1001 Fresh Water Tank and System ‐ Civil / Concrete FACILITY
3930‐1002 Fresh Water Tank and System ‐ Structural Steel FACILITY
3940‐1001 Potable Water System ‐ Civil / Concrete FACILITY
3940‐1002 Potable Water System ‐ Structural Steel FACILITY
3950‐1001 Plant Area Sewage Treatment Plant ‐ Civil / Concrete FACILITY
3950‐1002 Plant Area Sewage Treatment Plant ‐ Structural Steel FACILITY
3960‐1001 Fire Water System ‐ Civil / Concrete FACILITY
3960‐1002 Fire Water System ‐ Structural Steel FACILITY
3970‐1001 Reclaim Water Tank ‐ Civil / Concrete FACILITY
3970‐1002 Reclaim Water Tank ‐ Structural Steel FACILITY
3980‐1001 Waste And Scrap Yard ‐ Civil / Concrete FACILITY
3980‐1002 Waste And Scrap Yard ‐ Structural Steel FACILITY
3990‐1001 Water Treatment Plant ‐ Civil / Concrete FACILITY
3990‐1002 Water Treatment Plant ‐ Structural Steel FACILITY

3910‐OP‐01 Plant & Instrument Air 1st Line Utility 1st K‐CC3‐172 GyM S A 3910‐5001 Plant Air Compressors and Distribution ‐ Second Cleaner Column Cells PROCESS
3910‐5002 Instrument Air System including Accumulators and Distribution 1st Line PROCESS
3910‐5003 Plant Air Compressors and Distribution ‐ Hose Stations 1st Line PROCESS

3910‐OP‐02 Plant & Instrument Air 2nd Line Utility 2nd K‐CC3‐172 GyM S A 3910‐5004 Instrument Air Distribution 2nd Line PROCESS
3910‐5005 Plant Air Distribution 2nd line PROCESS

3920‐OP‐01 Light Vehicle Fuel Stations Facility 1st K‐CS‐216 CORPORACION PRIMAX SA 2610‐9001 Light Vehicles Fuel Station ‐ Quellaveco FACILITY
3920‐9001 Light Vehicle Fuel Station ‐ Papujune NON PROCESS
6020‐9007 Light Vehicle Fuel Station ‐ Cortadera FACILITY

3930‐OP‐01 Fresh Water Tank and Distribution 1st Line Utility 1st K‐CC3‐172 GyM S A 3930‐0001 Fresh Water Tank and Distribution 1st Line PROCESS

3930‐OP‐02 Gland Water Distribution 1st Line Utility 1st K‐CC3‐172 GyM S A 3930‐0002 Gland Water Distribution 1st Line PROCESS

Fresh Water from Ponds C1, C2 & C4 to


Utility 1st PROCESS
3930‐OP‐03 Process Water Tank 3720‐TK‐002 K‐CC3‐148A GYM Stracon 3930‐5001 Fresh Water from Ponds C1, C2 & C4 to Process Water Tank 3720‐TK‐002

3930‐OP‐04 Fresh Water Distribution 2nd Line Utility 2nd K‐CC3‐172 GyM S A 3930‐0003 Fresh Water Distribution 2nd Line PROCESS

3930‐OP‐05 Fresh Water Distribution Moly Plant Utility Moly K‐CC3‐172 GyM S A 3930‐0004 Fresh Water Distribution Moly Plant PROCESS

3930‐OP‐06 Gland Water Distribution 2nd Line Utility 2nd K‐CC3‐172 GyM S A 3930‐0005 Gland Water Distribution 2nd Line PROCESS

3940‐OP‐01 Potable Water Plant & Distribution Utility 1st K‐CC3‐172 GyM S A 3940‐9001 Potable Water Plant & Distribution PROCESS

3940‐OP‐02 RO Water Plant & Distribution Utility 1st K‐CC3‐172 GyM S A 3940‐9002 RO Water Plant & Distribution PROCESS

3940‐OP‐03 Emergency Showers & Eyewash Stations Utility 1st K‐CC3‐172 GyM S A 3940‐9003 Emergency Shower and Eyewash Stations PROCESS

3940‐OP‐04 Potable Water Distribution Moly Plant Utility Moly K‐CC3‐172 GyM S A 3940‐9004 Potable Water Distribution Moly Plant PROCESS

Emergency Showers & Eyewash Stations Moly


Utility Moly PROCESS
3940‐OP‐05 Plant K‐CC3‐172 GyM S A 3940‐9005 Emergency Shower and Eyewash Stations Moly Plant

3950‐OP‐01 Plant Area Sewage Treatment Utility 1st K‐CC3‐172 GyM S A 3950‐9001 Plant Area Sewage Treatment Plant Collection PROCESS
3950‐9002 Plant Area Sewage Treatment Plant PROCESS

3960‐OP‐01 Fire Water System Utility 1st K‐CC3‐148A CONSORCIO GYM STRACON 3960‐9001 Fire Water System & Distribution PROCESS

4010‐OP‐01 Platforms & Roads Tailings Dam Facility 1st K‐CC4‐153A JCC ‐ BESALCO PERÚ S A C 4010‐1001 Access Road and Platforms ‐ Cyclone Station to Drainage Pond FACILITY
4010‐1002 Access Road ‐ Starter Dam FACILITY
4010‐1003 Access Road ‐ Drainage Pond FACILITY
4010‐1004 Access Road ‐ Water Recovery Towers FACILITY
4010‐1005 Access Road and Platform ‐ Slime Discharge South Section FACILITY
4010‐1006 Platform ‐ Electrical Rooms FACILITY
K‐CCN‐143 CONSORCIO GYM OSSA 4110‐1014 Excedent Material Deposit ‐ DME‐04 FACILITY
4110‐1015 Excedent Material Deposit ‐ DME‐05 FACILITY

4030‐OP‐01 Power Supply to Cortadera (60 kV) Utility 1st K‐CC3‐172 GyM S A 5110‐6006 Electrical Room 5110‐ER‐004 (GIS 60 kV) ELECTRICAL
K‐EPCN‐154C COPEMI S A C CONSTRUCTORES 4030‐6001 60 kV Transmission Line ‐ Cortadera ELECTRICAL

4110‐OP‐01 Tailings Channel Process 1st K‐CC4‐153A BESALCO PERU S A C 4110‐1013 Tailings Transportation ‐ Capillune Bridge NON PROCESS
4110‐5001 Tailings Channel Auxiliary Equipment PROCESS
K‐CC4‐153A‐MOD1 BESALCO PERU S A C 4110‐1003 Section 1 ‐ Tailings Channel Thickeners to Bridge N°1 ‐ Prog. (0+000 A 3+300) PROCESS
Section 2 ‐ Tailings Channel Bridge N°1 to Salveani‐Capillune Tunnel Entry Portal ‐ Prog. (3+300
PROCESS
4110‐1004 A 4+520)
Section 3 ‐ Tailings Channel Salveani‐Capillune Tunnel Exit Portal to Capillune Bridge Exit ‐
PROCESS
4110‐1005 Prog. (5+600 A 8+160)
Section 4 ‐ Tailings Channel Capillune Bridge to Capillune‐Cortadera Tunnel Entry Portal ‐ Prog.
PROCESS
4110‐1006 (8+160 A 10+220)
Section 5 ‐ Tailings Channel Capillune‐Cortadera Tunnel Exit Portal to North Discharge ‐ Prog.
PROCESS
4110‐1007 (0+000 A 1+800)
Section 6 ‐ Tailings Channel Capillune‐Cortadera Tunnel Exit Portal to Bridge N°2 ‐ Prog.
PROCESS
4110‐1008 (10+740 A 13+300)
4110‐1009 Section 7 ‐ Tailings Channel Bridge N°2 Exit to Bridge N°3 ‐ Prog. (13+300 A 14+040) PROCESS
PROCESS
4110‐1010 Section 8 ‐ Tailings Channel Bridge N°3 Exit to Intermediate Station ‐ Prog. (14+040 A 14+400)
4110‐1011 Section 9 ‐ Tailings Channel Intermediate Station to Bridge N°4 ‐ Prog. (14+400 A 16+320) PROCESS
4110‐1012 Section 10 ‐ Tailings Channel Bridge N°4 to Cyclones Station ‐ Prog. (16+320 A 18+420) PROCESS
K‐CCN‐143 CONSORCIO GYM OSSA 4110‐1001 Salveani ‐ Capillune Tunnel NON PROCESS
4110‐1002 Capillune ‐ Cortadera Tunnel NON PROCESS

4120‐OP‐01 Cyclones Station Process 1st K‐CC4‐153A BESALCO PERU S A C 4120‐0001 Tailings Cyclones Stations PROCESS
4120‐0002 Cyclones Feed and Distribution PROCESS
4120‐OP‐01 Cyclones Station Process 1st K‐CC4‐153A BESALCO PERU S A C 4120‐5001 Cyclones Stations Auxiliary Equipment PROCESS
K‐CC4‐153A‐MOD1 BESALCO PERU S A C 4120‐6001 4120‐ER‐002 Electrical Room ‐ Tailings Dam Cyclones Station ELECTRICAL

4140‐OP‐01 Taiings Emergency Ponds Process 1st K‐CC4‐153A BESALCO PERU S A C 4140‐0001 Tailings Emergency Pond 1 PROCESS
4140‐0002 Tailings Emergency Pond 2 PROCESS
4140‐0003 Tailings Emergency Pond 3 PROCESS
4140‐0004 Tailings Emergency Pond 4 PROCESS

4150‐OP‐01 Tailings Distribution Process 1st K‐CC4‐153A BESALCO PERU S A C 4150‐0001 Sands Distribution PROCESS
4150‐0002 Tailings and Slime Distribution PROCESS

4210‐OP‐01 Starter Dam and Ancillary Works Process 1st K‐CC4‐153A BJJC ‐ BESALCO PERÚ S A C 4240‐1008 Final Leakbrake & Monitoring Vault PROCESS
JJC ‐ BESALCO PERÚ S A C 4210‐1001 Starter Dam & Cutoff Trench ‐ Level 3036 @ 3082 PROCESS
4210‐1002 Starter Dam ‐ Level 3082 @ 3118.5 PROCESS
4210‐1003 Starter Dam ‐ Level 3118.5 @ 3170 PROCESS
4220‐1001 Injections Curtain ‐ Level 3036 @ 3082 PROCESS
4220‐1002 Injections Curtain ‐ Level 3082 @ 3118.50 PROCESS
4220‐1003 Injections Curtain ‐ Level 3118.50 @ 3170 PROCESS
4220‐1004 Injections Curtain and Final Leakbrake Downstream PROCESS
4230‐7001 Geotecnic Instrumentation PROCESS
4240‐1001 Starter Dam Drainage System PROCESS
4240‐1002 Sands Dam Drainage System PROCESS
4240‐1003 Sentine and Drain Pond PROCESS
4240‐1004 Filtration System PROCESS
4240‐1005 Basal Drain Works PROCESS
4240‐1006 Sand Stop Blocks PROCESS
4240‐1007 Drain Pool and Sentine PROCESS
4370‐1001 Drain Area Monitoring Wells PROCESS

4310‐OP‐01 Water Recovery from Drainage System Process 1st K‐CC4‐153A BESALCO PERU S A C 4310‐5001 Infiltration Water Recovery Auxiliary Equipment PROCESS
K‐CC4‐153A‐MOD1 BESALCO PERU S A C 4310‐6001 4310‐ER‐020 Electrical Room ‐ Water Recovery from Drainage System ELECTRICAL
4310‐7001 Tailings Dam Seepage Control System CONTROL SYSTEM
4310‐8001 Tailings Dam Seepage Communications & Fiber Optic System COMMUNICATIONS
4310‐9002 Infiltration Water Recovery Pond PROCESS
4310‐9003 Infiltration Water Pumping Station PROCESS
4310‐9004 Infiltration Water Reception Pond & Distribution PROCESS

4320‐OP‐01 Water Recovery from Tailings Dam Phase 1 Process 1st K‐CC4‐153A‐MOD1 BESALCO PERU S A C 4320‐0001 Water Recovery Tower N°1 ‐ Structure PROCESS
4320‐0002 Water Recovery Tower N°1 ‐ Pumping System PROCESS
4320‐0003 Water Recovery Towers ‐ Auxiliary Equipment PROCESS
4320‐6001 4320‐ER‐040 Electrical Room ‐ Water Recovery from Ponds ELECTRICAL
4320‐6002 4320‐ER‐060 Electrical Room ‐ Water Recovery from Ponds ELECTRICAL
4320‐7001 Water Recovery Tower 1 Control System CONTROL SYSTEM
4320‐8001 Water Recovery Tower 1 Communications & Fiber Optic System COMMUNICATIONS
4320‐8002 Water Recovery Tower 2 Communications & Fiber Optic System COMMUNICATIONS
4330‐0001 Intermediate Pump Station PROCESS
4330‐0002 Pipeline Intermediate Pump Station to Papujune PROCESS
4330‐6001 4330‐ER‐001 Electrical Room ‐ Pumping Station from Intermediate Station ELECTRICAL
4330‐7001 Water Recovery Intermediate Station Control System CONTROL SYSTEM
4330‐8001 Water Recovery Intermediate Station Communications & Fiber Optic System COMMUNICATIONS
4340‐0001 Cyclone Station Dilution and Flushing Water PROCESS

4320‐OP‐02 Water Recovery from Tailings Dam Phase 2 Process 2nd K‐CC4‐153A‐MOD1 BESALCO PERU S A C 4320‐0004 Water Recovery Tower N°2 ‐ Structure PROCESS
4320‐0005 Water Recovery Tower N°3 ‐ Structure PROCESS
4320‐0006 Water Recovery Tower N°2 ‐ Pumping System (FUTURE) PROCESS
4320‐0007 Water Recovery Tower N°3 ‐ Pumping System (FUTURE) PROCESS
4320‐7002 Water Recovery Tower 2 Control System CONTROL SYSTEM

5010‐OP‐01 Main Access Facilities Facility 1st K‐EPC3‐185 TECNO FAST SAC 5010‐9001 Main Access Booth and Check Points FACILITY
5010‐9002 Main Exit Booth and Check Points FACILITY
5010‐9003 Truck Inspection Check Point NON PROCESS

Utility 1st ELECTRICAL


5110‐OP‐01 Main 220 / 22.9 kV Substation K‐BOOT‐107B (blank) 5110‐6005 Electrical Room 5110‐ER‐001 (GIS 220 kV y Transformadores de Potencia 5110‐TF‐001 @ 003)
K‐CC3‐172 GyM S A 5110‐6002 Electrical Room 5110‐ER‐003 (Emergency Generators & Transformers) ELECTRICAL
5110‐6004 Electrical Room 5110‐ER‐002 (GIS 22.9 kV) ELECTRICAL
5110‐6007 Harmonic Filters 5110‐HA‐001 @ 003 ELECTRICAL
K‐EPCN‐114 C2 MINING SOLUTIONS S.A.C. 5000‐8001 Structured Cabling ‐ Papujune Main Substation and Montalvo Subststation COMMUNICATIONS
COMMUNICATIONS
5000‐8002 Papujune Main Substation and Montalvo Subststation Communications & Fiber Optic System

5660‐OP‐01 Radio Communications System Phase 1 Utility 1st K‐CS‐201 MG TRADING SAC 5660‐8013 Radio Communications System P.25 ‐ Phase 1 COMMUNICATIONS
K‐EPCN‐113 MG TRADING SAC 5660‐8001 Tower Samanape Hil ‐ Area 2000 ‐ Phase 1 COMMUNICATIONS
5660‐8005 Lloquene Hill Tower ‐ Area 4000 ‐ Phase 1 COMMUNICATIONS
5660‐8007 Cellular Antenna ‐ Site EBC Pre‐Assemble ‐ Area 4000 ‐ Phase 1 COMMUNICATIONS

5660‐OP‐02 Radio Communications System Phase 2 Utility 1st K‐CS‐201 MG TRADING SAC 5660‐8014 Radio Communications System P.25 ‐ Phase 2 COMMUNICATIONS
K‐EPCN‐113 MG TRADING SAC 5660‐8002 Tower Collunco Hill ‐ Area 1000 ‐ Phase 2 COMMUNICATIONS
5660‐8004 Tower Ojelaca Hill ‐ Area 1000 ‐ Phase 2 COMMUNICATIONS
5660‐8008 Tower Enersur Port ‐ Area 5000 ‐ Phase 2 COMMUNICATIONS
5660‐8009 Cellular Antenna ‐ Site EBC Quellaveco ‐ Area 2000 ‐ Phase 2 COMMUNICATIONS
5660‐8011 Cellular Antenna ‐ Site EBC Salveani ‐ Area 3000 ‐ Phase 2 COMMUNICATIONS
5660‐8012 Tower Millune Hill ‐ Area 2000 ‐ Phase 2 COMMUNICATIONS

5660‐OP‐03 Radio Communications System Phase 3 Utility 1st K‐CS‐201 MG TRADING SAC 5660‐8015 Radio Communications System P.25 ‐ Phase 3 COMMUNICATIONS
K‐EPCN‐113 MG TRADING SAC 5660‐8003 Tower Asana Hill ‐ Area 1000 ‐ Phase 3 COMMUNICATIONS
5660‐8006 Tower Los Angeles ‐ Area 5000 ‐ Phase 3 COMMUNICATIONS
5660‐8010 Cellular Antenna ‐ Site EBC Apacheta ‐ Area 1000 ‐ Phase 3 COMMUNICATIONS

5800‐OP‐01 Port Facilities Facility 1st K‐EPCN‐114 C2 MINING SOLUTIONS S.A.C. 5820‐8001 Structured Cabling ‐ Port Buildings COMMUNICATIONS
K‐EPCN‐115 MG TRADING SAC 5820‐8002 Data Center ‐ Port Buildings COMMUNICATIONS

6010‐OP‐01 Temporary Platforms & Roads K‐CC2‐146A Facility 1st K‐CC2‐146A CONSORCIO COSAPI EPSA 6010‐1101 Platform and Access Road to 2000‐T‐04 FACILITY
6010‐1102 Platform and Access Road to 2000‐T‐05 and 2000‐T‐06 FACILITY
6010‐1103 Platform and Access Road to 2000‐T‐08 FACILITY
6010‐1104 Platform and Access Road to 2000‐T‐09 FACILITY
6010‐1105 Platform and Access Road to 2000‐T‐10 FACILITY
6010‐1106 Platform and Access Road to 2000‐T‐11 FACILITY

6010‐OP‐02 Temporary Platforms & Roads K‐CC2‐146B Facility 1st K‐CC2‐146B JJC CONTRATISTAS GENERALES SA 6010‐1060 Temporary Platform and Access Road to Magazine (2000‐T50) FACILITY
6010‐1061 Temporary Platform and Access to 2000‐T61 FACILITY
6010‐1062 Temporary Platform and Access to 2000‐T62 FACILITY
6010‐1063 Temporary Platform and Access to 2000‐T63 FACILITY
6010‐1064 Access Road and Platform to Transfer Tank FACILITY
6010‐1067 Platform 4000‐T13 FACILITY
6010‐1068 Platform 4000‐T14 FACILITY
6020‐9002 Interconnection of Stormwater Collection System to the WFC Asana System FACILITY
Water for Construction Pipeline and Distribution to Truck Feeds / Pond 2000‐PC‐04, N°2 &
FACILITY
6020‐9005 Concrete Plant ‐ Quellaveco
6020‐9006 Water for Construction Pipeline ‐ Transfer Tank Platform @ 6000‐TK‐002 PROCESS

6010‐OP‐03 Temporary Platforms & Roads K‐CC3‐148A Facility 1st K‐CC3‐148A CONSORCIO GYM STRACON 6010‐1001 T‐19 Sector Moly Sur FACILITY
6010‐1002 T‐20 Recover Water Sector FACILITY
6010‐1003 T‐35 Exit Portal Platform Sector FACILITY
6010‐1004 T‐5 Batch Plant FACILITY
6010‐1005 T‐7 EPCM Temporary Facilities FACILITY
6010‐1006 Papujune ‐ DME 1 FACILITY
6010‐1007 T‐10 Lime Plant Sector FACILITY
6010‐1008 T‐12 Stockpile Sector 1 (South) FACILITY
6010‐1009 T‐13 Stockpile Sector 2 (North) FACILITY
6010‐1010 T‐14 Grinding Platform Sector FACILITY
6010‐1011 T‐9 Thickeners Sector FACILITY
6010‐1012 T‐18 North Moly Sector FACILITY
6010‐1013 T‐21 Administration Sector FACILITY
6010‐1014 T‐1 Gate Checkpoint Sector FACILITY
6010‐1015 T‐2 Gate Checkpoint Sector FACILITY
6010‐1016 T‐16 Gate Checkpoint Sector FACILITY
6010‐1017 Temporary Explosives Magazine ‐ Caracoles FACILITY
6010‐1018 Papujune ‐ DME 2 Optional FACILITY
6010‐1019 Platform DME Salveani, Acceso Road and Collection Pond FACILITY
6020‐9001 Water for Constuction Pipeline ‐ Papujune FACILITY

Facility 1st FACILITY


6010‐OP‐04 Temporary Platforms & Roads OHL K‐CC2‐145 OBRASCON HUARTE LAIN SA ‐ SUCURSAL DEL PERU 6010‐07 Access Roads to Construction Platforms (PB2, PB3A, PB3B & PB4)
Upper Contruction Road and Connection Road Downstream the Barrier. Existent Road
FACILITY
6010‐08 Downstream the Barrier
6010‐09 Access Road to Quellaveco Ponds FACILITY
6010‐11 Existent Road Improvement and Dump Access FACILITY
6010‐12 Dump Sector 1 FACILITY
6010‐OP‐04 Temporary Platforms & Roads OHL Facility 1st K‐CC2‐145 OBRASCON HUARTE LAIN SA ‐ SUCURSAL DEL PERU 6010‐13 Dump Sector 2 FACILITY
6010‐14 Dump Sector 3 FACILITY
6010‐15 Modular Bridge 1 (New) FACILITY
6010‐16 Modular Bridge 2 (Relocated) FACILITY
6010‐19 Quarry Bypass. Expoitation and Closure FACILITY
6010‐21 Quimsuta Intake Improvement Works FACILITY
K‐CC5‐106 OBRASCON HUARTE LAIN SA‐SUCURSAL DEL PERU 6010‐01 Platform PB2 (includes sediment pond) FACILITY
6010‐02 Platform PB3A (includes sediment ponds PB3A & PB3B) FACILITY
6010‐03 Platform PB3B FACILITY
6010‐04 Platform PB4 (includes sediment pond) FACILITY
6010‐17 Quarry Q1. Expoitation and Closure FACILITY
6010‐18 Quarry Sarallenque. Expoitation and Closure FACILITY
K‐CCN‐800 ECOP S A C INGENIERIA Y CONSTRUCCION 6010‐20 Quarry Q1 Setup FACILITY

6030‐OP‐01 EPCM Offices 300 Facility 1st K‐CS‐247 (blank) 6020‐9030 Potable Water Treatment Plant NON PROCESS
6020‐9031 Sewage Treatment Plant NON PROCESS
K‐CS‐808 WCARO CONSULTORES Y CONTRATISTAS SRL 6030‐9001 EPCM Offices ‐ 70 NON PROCESS
K‐TFN‐001B TECNO FAST SAC. 6030‐9010 EPCM Offices ‐ 300 ‐ 1st Floor NON PROCESS
6030‐9011 Electrical Generation Plant ELECTRICAL
6030‐9012 Water Treatment Plant NON PROCESS
6030‐9013 Waste Water Treatment Plant NON PROCESS
6030‐9014 Fire Protection System NON PROCESS

6040‐OP‐01 Warehouse Facilities Facility 1st K‐CCN‐206 ECOP S A C INGENIERIA Y CONSTRUCCION 6040‐1001 Platform Nº 1 ‐ Stock Area FACILITY
6040‐1002 Platform Nº 2 ‐ Stock Area FACILITY
6040‐1003 Platform Nº 3 ‐ Warehouse Equipment FACILITY
6040‐1004 Platform Nº 4 ‐ Warehouse Equipment FACILITY
6040‐1005 Platform Nº 5 ‐ Warehouse Equipment FACILITY
6040‐1006 Platform Nº 6 ‐ Preservation of Equipment FACILITY
6040‐1007 Platform Nº 7 ‐ Warehouse Equipment FACILITY
6040‐1008 Platform Nº 8 ‐ Warehouse Equipment FACILITY
6040‐1009 Platform Nº 9 ‐ Warehouse FACILITY
6040‐1010 Platform Nº 10 ‐ Pre Assembly FACILITY
6040‐1011 Platform Nº 11 ‐ Cable´s Yard FACILITY
6040‐1012 Access Road FACILITY
6040‐1013 Access Gate (Includes Drainage) FACILITY
6040‐1014 Accumulation and Sedimentation Pond (Includes Access Road) FACILITY
6040‐1015 Dump DME FACILITY
6040‐1016 Fencing FACILITY
K‐TFN‐004B TECNO FAST SAC 6040‐1017 Construction Warehouse Building FACILITY
6040‐1018 Complementary Buildings ‐ Kitchen & Bathroom FACILITY
6040‐1019 Complementary Buildings ‐ Safety Gates & Parking Lots FACILITY
6040‐1020 Electrical Generation & Distribution ELECTRICAL
6040‐1021 Potable Water, Sewage Distribution and Fire System NON PROCESS

6050‐OP‐01 Salveani Camp Facility 1st K‐CC3‐148A, K‐EPC3‐108 CONSORCIO GYM STRACON / PROMET PERÚ SAC 6050‐9003 Workers Building 3 NON PROCESS
6050‐9004 Workers Building 4 NON PROCESS
6050‐9005 Workers Building 5 NON PROCESS
6050‐9006 Workers Building 6 NON PROCESS
6050‐9013 Multipurpose Building NON PROCESS
CONSORCIO GYM STRACON PROMET PERÚ SAC 6050‐9015 Power Generation ELECTRICAL
K‐EPC3‐108 PROMET PERÚ SAC 6050‐9001 Workers Building 1 NON PROCESS
6050‐9002 Workers Building 2 NON PROCESS
6050‐9007 Managers/ Supervisors Buidling 1 NON PROCESS
6050‐9008 Managers/ Supervisors Buidling 2 NON PROCESS
6050‐9009 Managers/ Supervisors Buidling 3 NON PROCESS
6050‐9010 Managers/ Supervisors Buidling 4 NON PROCESS
6050‐9011 Supervisors Building 1 NON PROCESS
6050‐9012 Supervisors Building 2 NON PROCESS
6050‐9014 Services Buildings NON PROCESS
6050‐9016 Potable Water Plant & RO Plant NON PROCESS
6050‐9017 Sewage Treatment Plant NON PROCESS
6050‐9018 Exterior Electrical Grid (includes communication services) ELECTRICAL
6050‐9019 Exterior Sanitary Facilities NON PROCESS
6050‐9021 Fire Protection System NON PROCESS
6050‐9022 Supervisors Building 3 NON PROCESS

6050‐OP‐02 Caracoles Camp Facility 1st K‐EPC3‐195 TECNO FAST SAC. 6050‐9031 Supervisors Building A (48) NON PROCESS
6050‐9032 Supervisors Building A (52) NON PROCESS
6050‐9033 Workers Building A (96) NON PROCESS
6050‐9034 Workers Building B (96) NON PROCESS
6050‐9035 Workers Building A (108) NON PROCESS
6050‐9036 Workers Building B (108) NON PROCESS
6050‐9037 Services Buildings NON PROCESS
6050‐9038 Power Generation ELECTRICAL
6050‐9039 Exterior Electrical Grid ELECTRICAL
6050‐9040 Potable Water Plant NON PROCESS
6050‐9041 Exterior Sanitary Facilities NON PROCESS
6050‐9042 Fire Protection System NON PROCESS
6050‐9043 Sewage Water Treatment Plant NON PROCESS

6050‐OP‐03 Cortadera Camp Facility 1st K‐CCN‐800 ECOP S A C INGENIERIA Y CONSTRUCCION 6050‐1002 Platform and Access Road 2 & 3 ‐ Parking Lots FACILITY
6050‐1003 Platform and Access Road ‐ PTAP FACILITY
6050‐1004 Platform and Access Road ‐ PTAR FACILITY
6050‐1005 Platform and Access Road ‐ Collection Pond 1 FACILITY
6050‐1006 Platform and Access Road ‐ Collection Pond 2 FACILITY
6050‐1007 Platform ‐ Surface Drain System FACILITY
6050‐1008 Improvement of Existing Road ‐ Northern Side FACILITY
K‐EPC4‐116 TECNO FAST SAC. 6050‐9050 Module ‐ Operators Bedroom (380 workers) NON PROCESS
6050‐9051 Module ‐ Operators Bedroom (356 workers) NON PROCESS
6050‐9052 Module ‐ Mixed Operators Bedroom (164 workers) NON PROCESS
6050‐9053 Module ‐ Mixed Supervisors Bedroom (144 workers) NON PROCESS
6050‐9054 Module ‐ Supervisors Bedroom (96 workers) NON PROCESS
6050‐9055 Module ‐ Managers Bedroom (60 workers) NON PROCESS
6050‐9056 Kitchen ‐ Dinning Room NON PROCESS
6050‐9057 Sport Field NON PROCESS
6050‐9058 Module ‐ Medical Center NON PROCESS
6050‐9060 Clothing Storage ‐ Clean & Dirty NON PROCESS
6050‐9061 Clothing Storage ‐ Shift Change NON PROCESS
6050‐9062 Storage Wareouse ‐ Camp NON PROCESS
6050‐9063 Electrical Generation Station ELECTRICAL
6050‐9064 Power Grid ELECTRICAL
6050‐9065 Lightning Protection System ELECTRICAL
6050‐9066 Potable Water Treatment Plant ‐ PTAP NON PROCESS
6050‐9067 Potable Water Network NON PROCESS
6050‐9068 Waste Water Treatment Plant ‐ PTAR NON PROCESS
6050‐9069 Drainage Network NON PROCESS
6050‐9070 Parking Lot ‐ Trucks FACILITY
6050‐9071 Parking Lot ‐ Buses FACILITY
6050‐9072 Fire Protection Water System NON PROCESS

Grand Total