VALOR PLANEADO (PV)

POR CADA COLUMNA NOS PAGARAN $us 100

AVANCE PROGRAMADO

PARCIAL ACUM

VALOR GANADO (EV)

AVANCE REAL EJECUTADO

PARCIAL ACUM

COSTO REAL (AC)


AVANCE REAL EJECUTADO
P.U. COSTO REAL

PARCIAL ACUM
INDICADORES DE PLAZO

SV = EV-PV

SPI = EV/PV

INDICADORES DE COSTO

CV = EV-AC

CPI = EV/AC

EAC = BAC / CPI

ESTIMATED AT COMPLETION
SEM 1 SEM 2 SEM 3 SEM 4

AVANCE PROGRAMADO 1 2 2 1
P.U 100 100 100 100
PARCIAL 100 200 200 100
PARCIAL ACUM 100 300 500 600

PPTO TOTAL
CURVA S BAC
BUDGET AT COMPLETION

HOY

SEM 1 SEM 2 SEM 3 SEM 4

VANCE REAL EJECUTADO 1 1 2


P.U. 100 100 100
PARCIAL 100 100 200
PARCIAL ACUM 100 200 400

SEM 1 SEM 2 SEM 3 SEM 4

VANCE REAL EJECUTADO 1 1 2


P.U. COSTO REAL 150 90 110
PARCIAL 150 90 220
PARCIAL ACUM 150 240 460

SEM 1 SEM 2 SEM 3

SV 0.00 -100.00 -100.00


SPI 1.00 0.67 0.80
CV -50.00 -40.00 -60.00
CPI 0.67 0.83 0.87
BAC 600 600 600 presupuesto
EAC 900 720 690 como terminare