DESCRIPTION CREW SIZE Hourly Production

Production Rate Per 12 hrs.


Per Unit
KERBING / BLOCK PAVING WORKS
P.C.C. Curve kerb base (to curves) 1 MASON, 1 HELPER 2,5 30 METRE
PCC to kerb base (Straight line) 1 MASON, 1 HELPER 3,0 36 METRE
Haunching to kerb base (Dumpes) 1 MASON, 1 HELPER 4 48 METRE
kerbstonse (Without PCC) 1 MASON, 1 HELPER 1,5 18 METRE
Interlock paving on pre prepared sub - base 1 MASON, 1 HELPER 2.4 SM
Screed works including preparation 1 MASON, 1 HELPER 1,5 18 METRE
Haunching ot Kerb Base (Mixing Truck) 1 MASON, 1 HELPER 10 M 120M