Professional Documents
Culture Documents
HAZOP Study Report Template
HAZOP Study Report Template
1960 - 2001 1960 - 2001 1965 - 2001 1970 - 2001 1972 - 1974
Safety Check Lists Relative PHA What if
Review Ranking
continue to page 2
HAZOP was developed by Lawley (1974) of ICI. Based on early account by Elliott & Owen (1968)
Hazop studies are carried out by an experienced, multidisciplanary team, who review all physical
aspects of a process (lines, equipment, instrumentation) to discover potential hazards and
operability problems using a check list approach.
The basis for a HAZOP is a critical examination of information found in a word model, a process
flowsheet, a plant layout, equipment specification or a P&ID, (Piping and Instrument Drawing).
The principals of examination include: See tabs D1 to D3 for examples of computer forms.
1 Intention
2 Deviation
3 Causes
4 Consequences
(a) hazards
(b) operating difficulties
5 Safeguards
6 Recommendations / Actions
continue to page 3
3 Early HAZOP studies used the following set of Guide Words to systematically review the process:
continue to page 4
continue to page 5
HAZOP
Review By Documentation
Team
Table
continue to page 6
Select a process
section or
operating step
Explain design
intention
Select a process
variable or task
Examine
Consequences
associated with
contiue page down deviation
6 con't
List possible
causes of
deviation
Identify existing
safeguards to
prevent deviation
continue to page 7
continue to page 8
8 Common Mistakes
3 Taking unwarranted credit for safeguards See example on page 9 - one page d
10 Wrong technique for system being reviewed (See spreadsheet titled Fig 5.3)
continue to page 9
To Compressor Inlet
LAH
FV
Teams tend to quickly identify alarms, shut-dow
1 and controls, and claim them for safeguards.
Brainstorming Hazards
Operability
Analysis
Line by Line
Deviation
Analysis
s of computer forms.
set page break 2
an design flow
design flow
mponent additional to A
l components of A
Action
Develop action
items
Assess acceptability
of risk based on
consequences
items a
variables b
guide words c
questions d = axbxc
min./question e
minutes f = dxe
minutes/day g
days h=f/g
days/week I
weeks j=h/I
Tank or Heat
ID No. Deviation Column Vessel Line Exchanger Pump
1 High Flow X
2 High Level X X
3 High Interface X
4 High Pressure X X X
5 High Temperature X X X
6 High Concentration X X X
7 Low / No Flow X
8 Low Level X X
9 Low Interface X
10 Low Pressure X X X
11 Low Temperature X X X
12 Low Concentration X X X
13 Reverse / Misdirected Flow X
14 Tube Leak X
15 Tube Rupture X
16 Leak X X X X X
17 Rupture X X X X X
More Flow
Less Flow
More Pressure
Less Pressure
More Level
Less Level
Part of, wrong concentration
As well as, contaminants
other than, wrong material
More Reaction
Less Reaction
No Reaction
More Mixing
Less Mixing
More Corrosion
More Erosion
Sampling
on Processing, Aug 1992, p-140-C
Compressor
X
X
X
X
X
X
HAZOP STUDY REPORT
DATE: P & ID NUMBER:
NODE:
DESIGN INTENT OF THE SYSTEM:
HAZOP LEADER:
1)
2)
HAZOP TEAM MEMBERS
3)
4)
Guide Word Parameter Deviation Possible Cause Consequences Existing Safeguards Action Required Action by Action taken
1 Open
NO NO FLOW 2 Closed
etc
MORE FLOW
MORE TEMPERATURE
LESS FLOW
LESS TEMPERATURE
AS WELL AS
Utility failure,
OTHER THAN Maintenance, Leak,
Safety, Corrosion,
Instrumentation etc
PART OF
www.CC0099Chemical0000CCEngineeringFF0000Site01+000.Com
HAZOP STUDY REPORT
DATE: P & ID NUMBER:
NODE:
DESIGN INTENT OF THE SYSTEM:
HAZOP LEADER:
1)
2)
HAZOP TEAM MEMBERS
3)
4)
Guide Word Parameter Deviation Possible Cause Consequences Existing Safeguards Action Required Action by Action taken
1 Open
NO NO FLOW 2 Closed
etc
MORE FLOW
MORE TEMPERATURE
LESS FLOW
LESS TEMPERATURE
AS WELL AS
Utility failure,
OTHER THAN Maintenance, Leak,
Safety, Corrosion,
Instrumentation etc
PART OF
www.CC0099Chemical0000CCEngineeringFF0000Site01+000.Com