Task / Description Slow Ave Fast Units


Asphalt coatings, horizontal surfaces 3.5 4.2 5.8 m2/hr

Asphalt coatings, vertical surfaces 1.2 1.7 2.2 m2/hr

Bituminous Brushed application, 2 coats 4.8 5.0 6.3 m2/hr

Bituminous Brushed application, 3 coats 3.3 3.5 4.4 m2/hr

Bituminous Sheets, horizontal surfaces 3.8 4.0 4.8 m2/hr

Bituminous Sheets, vertical surfaces 3.3 3.5 4.2 m2/hr

Polythene Sheets, horizontal surfaces - 20.0 - m2/hr

Bentonite Sheets, horizontal surfaces 18.7 25.0 31.3 m2/hr

Bentonite Sheets, vertical surfaces 11.2 15.0 17.3 m2/hr

Epoxy Based application, 1 coat - 75.0 - m2/hr

Epoxy Based application, 2 coat - 38.0 - m2/hr