of Work : QC ENGINEER
Material inspection for Civil construction work
Verification/ inspection and monitoring quality activities of Civil Work review QA/QC
Documents
Developed Quality Management documents, namely Inspection and Test Plans (ITP) and
relate Checklists, Site Quality Plans, Manufacturing Plans etc.
Reviewed the construction drawings.
Corresponded with contractor’s Engineer and internal disciplines (engineering, construction,
scheduling, etc.) for the preparation of ITP.
Raised Non-Conformance Reports (NCR) and monitored them for their effective closeout.
Ensured the QMS documents are reviewed internally and get approved by the contractor and
owner.
Ensured that the project personnel are aware of ITP and carry out inspections and tests as per
approved ITP.
Conducted regular site visits and followed the construction activities.
Conducted Factory Acceptance Test (FAT) before delivery material's, ensures that the
product can consistently meet the expectations.
Conducted QMS & Quality Control induction for staff.
Conducted Quality Audit at site periodically.
Coordination with IPMT and contractors for inspection activities
Coordination with surveyor regarding schedule joint survey followed the construction
activities before joint inspection with contractor and owner.make ITS (Inspection & Test
Schedule) for the next 2 weeks' work
make summary Piling Platform (RFCC New Flare) and summary compressive strength test
(CST)
SITE MANAGER
Review daily and weekly report from Project Controller
Conducted regular site visits and followed the construction activities.
Monitoring for material requirements for the site.
Update monitoring working progress
Corresponded with Consultan’s Engineer, owner and internal disciplines (engineering,
construction, scheduling, etc.) for the preparation of work
Follow up Engineering for making method statement
Monitoring man power on site
Follow up case and monitored them for their effective closeout.
Responsible for quality of materials and any works
Apply occupational health and safety in every work activity
Civil Supervisor
A.Coordination with Engineering regarding the methods used in the work
B. Directing workers at toolbox meeting before starting work
C. Coordination with HSE for every activity that takes place so that the work can run safely.
D. Ensured that permit to work complete before starting work
E. Trying to achieve the company's target according to the schedule.
F. Make daily and monthly progress reports.
G. Coordinate with Quality Control to achieve work quality according to owner's standards
H. perform with effective and efficient work in order to achieve maximum progress.
I. Analyzing problems that occur in the field so that work can continue.
J. Running the K3 program to keep the work area clean
K. Make a material request