PROJECT PROPSAL

Project Name: CORN FIELD id #19009 Project Period: 4 MONTHS/MONTHLY


Project Manager: ALEX FERRO Project Due Date: JAN 31, 2024
Compiled By: ALEX FERRO Date Submitted: OCT 10, 2023

Summary
Item Current Prior Status Summary
Status
Project Status On Time On Time Corn Farming on site project # 19009
Scope On Time On Time This project will cover the whole usable
area of project 19009 11.3 hcrs
Schedule On Time On Time Project is ahead on schedule.

Cost On Budget On Budget Current budget fits the project proposal


Risk Yes Yes Risks on this project may involve weather
changes and overflowing of river due to
heavy rains.

Tasks
Task Status Objective Planned Actual Progress Deliverabl Photos
Complete e
Farmall On To till the October 0%
Not Started
Tractor Time whole 25, 2023
usable area
of the said
project
area. 11.3
hcrs
Clearing of Finishe To clear the October September 100% Done
fences d fences of 20, 2023 25, 2023
the said .
project to
prevent rat
infestations.
Rotovator On Final tilling Novembe 0% Not
Tractor Time on the lands r 30, 2023 Started
of 19009
Carabao On Laying of December 0% Not
Laying Time Corn hills to 1, 2023 Started
be planted
Planting of On To plant all Dec 1, 2, 0% Not

Copy furnish: Finance Department


Seeds and Time the seeds 3, 2023 Started
application on the
of whole
fertilizers usable
areas.
Insecticide Not Spraying of Febuary 1, 0% Not
Application Started insecticide 2024, Started
on the
whole corn April 1,
field. 2024
Fertilizer Not Spraying of March 1, 0% Not
Application Started fertilizers 2024 Started
on the
whole corn
field
Weeding Not Removing March 1, 0% Not
Started of stray 2024 Started
weeds.

April 1,
2024
Harvesting Not Harvesting May 1, 0% Not
Started of the 2024 Started
whole corn
field

Issues
Issue When Identified Action or Ignore Owner Resolved
SCATTERED RAIN MONTH OF IGNORED N/A Yes
SHOWERS OCTOBER
None
None

Budget
Item Allocation Spent Spent Spent to Date
percentage.
FARMAL TRACTOR 29,900.00 0% 0.00 0.00
FENCE CLEARING 80,000.00 0% 0.00 0.00
ROTOVATOR 36,400.00. 0% 0.00 0.00
TRACTOR
CARABAO LAYING 18,200.00 0%
INSECTICIDE 10,500.00 0% 0.00 0.00
APPLICATION
FERTILIZER 5,250.00 0% 0.00 0.00
APPLICATION
WEEDING 10,500.00 0% 0.00 0.00

Copy furnish: Finance Department


Accomplishments
 FENCE CLEARING WERE DONE ON LOT FINISHED EARLIER THAN EXPECTED.

[List accomplishments over reporting period, including activities, meetings, deliverables, etc.]

Expected Accomplishments
 FENCE CLEARING IS EXPECTED TO BE FINISHED ON OR BEFORE OCT 15, 2022.
 FARMALL TILLING IS EXPECTED TO START AT LEAST 1 HECTAR ON OR BEFORE SEPT. 25,
2022. (WILL BE BASED ON CURRENT WEATHER)
 LAYING OUT OF HILLS EXPECTED FOLLOWING ON ROTOVATOR TO BE FINISHED BY NOV.
30, 2022.
 PLACING OF SEEDS IS ALSO EXPECTED AT LEAST 1 HECTARE ON DEC. 1, 2022.
 INSECTICIDE APPLICATION MUST BE FINISHED BY FEB. 6, 2021 AND APRIL 6, 2023.
 FERTILIZER APPLICATION MUST BE FINISHED BY MARCH 6, 2023.
 MONTH OF MAY IS THE EXPECTED HARVESTING MONTH OF THE FIELD.

[List accomplishments expected to be achieved over next reporting period.]

Copy furnish: Finance Department


INDEX “A”
SOUTH

NORTH

Copy furnish: Finance Department


INDEX “B”
NORTH

Copy furnish: Finance Department


SOUTH

Copy furnish: Finance Department


INDEX “C”
NORTH

SOUTH

Copy furnish: Finance Department