PERHITUNGAN VOLUME

NO. SKETS GAMBAR URAIAN PEKERJAAN DAN PERHITUNGAN VOLUME SAT.


I PEKERJAAN PERSIAPAN : 1. Pembersihan Lahan
L (m) B (m) A = (L + 4) x (B + 4)

12,50 10,50
= 239,250 m2

L 2. Pemasangan Bowplank + Vitzet


L (m) B (m) K = 2 x (( L + 2 ) + ( B + 2 ))

12,50 10,50
= 54,000 m
b
3. Penyediaan Air Kerja 1,000 LS

II PEKERJAAN TANAH DAN URUGAN 1. Galian Tanah Pondasi


a. Pondasi Bangunan Induk
b (m) h (m) L (m) V = (bxh)xL

1,00 0,80 78,00


h h = 62,400 m3

b b. Pondasi Teras
b b (m) h (m) L (m) V = (bxh)xL

0,60 0,60 17,50


= 6,300 m3
Volume Total Galian Tanah Pondasi 68,700 m3

2. Urugan Tanah Kembali


Vgalian (m) 1
V = x VG
4
68,700
= 17,175 m3

3. Urugan Pasir Di Bawah Pondasi

b (m) h (m) L (m) V = (bxh)xL


h h
B. Induk 1,00 0,10 78,00
b b = 7,800 m3
b b
B. Teras 0,60 0,10 17,50
= 1,050 m3

V total = 8,850 m3
4. Urugan Pasir Peninggi Lantai

h h A (m2) L (m) b (m) h (m) V = [ A - (L x b )] x h


B. induk 97,000 78,000 0,150 0,200 = 17,060 m3
B. teras 13,375 17,500 0,150 0,150 = 1,613 m3
KM/WC 7,500 16,000 0,150 0,150 = 0,765
V total = 19,438 m3
PERHITUNGAN VOLUME

NO. SKETS GAMBAR URAIAN PEKERJAAN DAN PERHITUNGAN VOLUME SAT.


III PEKERJAAN PASANGAN DAN PLESTERAN 1. Pasangan Aanstamping Batu Karang/ Kali

b (m) h (m) L (m) V = (bxh)xL

B. Induk 1,00 0,20 78,00


= 15,600 m3

B. Teras 0,60 0,20 17,50


= 2,100 m3

b Volume Total Pasangan Aanstamping Batu Karang/ Kali 17,700 m3


b
2. Pasangan Pondasi Batu Karang/ Kali
a a. Pondasi Bangunan Induk
a+b
V = xh xL
a (m) b (m) h (m) L (m) 2

0,25 0,80 0,85 78,00


h = 34,808 m3
b
b b. Pondasi Teras

b b b (m) h(m) L(m) V = (bxh)xL

0,40 0,55 17,50


= 3,850 m3

Volume Total Pasangan Pondasi Batu Karang/ Kali 38,658 m3

h1 h2 3. Pasangan Tembok Trasraam


a. Tembok Trasraam untuk WC/ KM (1 pc : 3 psr)

Lw (m) P (m) h1 (m) VT = [( Lw - P ) x h1 ]

16,00 1,60 1,50


= 21,600 m2

b. Tembok Trasraam untuk B. Induk (1 pc : 3 psr)

L (m) h2 (m) VT = [ L x h2 ]

28,50 0,50
= 14,250 m2
Volume Total Pasangan Tembok Trasraam 35,850 m2

4. Pasangan Tembok Biasa (1 pc : 5 psr)


a. Tembok Bangunan Induk

L (m) h (m) AK (m2) ATK (m2) LT (m) V = [( L x h ) - AK - ATK ] - LT

78,000 3,300 48,700 2,000 35,850


= 170,850 m2
PERHITUNGAN VOLUME

NO. SKETS GAMBAR URAIAN PEKERJAAN DAN PERHITUNGAN VOLUME SAT.


b. Tembok Gewel
1
V = x a x h - Ak
h a (m) h (m) t (m) Ak (m2) 2
gewel 1 = 11,504
9,00 2,60 0,12 0,20
1
V = x a x h - Ak x 2
gewel 2 2
10,50 3,00 0,12 0,20
= 31,100 m2
a Volume Total Pasangan Tembok Biasa 213,454 m2
5. Plesteran Tembok Trasraam (1 pc : 3 psr)
a. Tembok KM/ WC (1.50 m)

Lw (m) P (m) h (m) A = [ ( Lw - P ) x h ] x 2

16,00 1,600 1,50


= 43,200 m2
b. Tembok Bangunan Induk (0.50 m)

L (m) P (m) h (m) A = [ ( Lw - P ) x h ] x 2

28,50 0,000 0,50


= 28,500 m2
Luas Total Plesteran Tembok Trasraam 71,700 m2

6. Plesteran Tembok Biasa (1 pc : 5 psr)


a. Tembok Bangunan Induk

L (m) h (m) AT (m2) Agwl (m2) AK (m2) ATK (m2) A = [ ( L x h ) x2 - AT - Ak - ATK ] + Agwl

78,000 3,300 71,700 27,054 48,700 2,0000


= 419,454 m2

7. Plesteran Pondasi Tepi Luar (1 pc : 4 psr)

b (m) h (m) L (m) A = (b+h)xL

B. Induk 0,050 0,350 28,500


= 11,400 m2

Teras 0,125 0,250 17,500


= 6,563 m2
A total = 17,963
Luas Total Plesteran Tembok ( Apl ) 437,416 m2

8. Acian Tembok

Apl (m2) AAC = APl

437,416
= 437,416 m2
PERHITUNGAN VOLUME

NO. SKETS GAMBAR URAIAN PEKERJAAN DAN PERHITUNGAN VOLUME SAT.


IV PEKERJAAN BETON 1. Cor Beton Sloof (1 pc : 3 psr : 5 Krl)
V = (bxh)xL
b (m) h (m) L (m) = 2,340
B. induk 0,150 0,200 78,000 = 0,525 m3
B. teras 0,150 0,200 17,500 V total = 2,865 m3

2. Cor Beton Kolom Praktis (1 pc : 3 Psr : 5 Krl)

b1 h a (m) a' (m) h (m) n (Buah) V = [( b x b' ) x h ] x n

0,12 0,12 3,30 24


b b = 1,140 m3
3. Cor Beton Kolom Teras (1 pc : 3 psr : 5 Krl)

a (m) a' (m) h (m) n (Buah) V = [( b x b' ) x h ] x n

0,20 0,20 3,30 2


= 0,264 m3

4. Cor Beton Ringbalk (1 pc : 3 psr : 5 Krl) V = (bxh)xL


L2 = 2,57
b (m) h (m) L (m) = 0,525
b B. induk 0,15 0,20 85,50 m3
L1 B. teras 0,15 0,20 17,50 Vtotal = 3,090 m3

5. Cor Beton Meja Dapur (1 pc : 3 Psr : 5 Krl)


a. Plat Meja :
L1 (m) L2 (m) b (m) t (m) V = [( L1 x b ) + (L2 x b )] x t
t
1,50 1,50 0,60 0,10
h = 0,180 m3

b b. Kaki Meja :
b (m) h (m) t (m) n (buah) V = [( b x h ) x t ] x n

0,60 0,60 0,10 6


= 0,216 m3

Volume Total Cor Meja Dapur 0,396 m3

6. Cor Beton Neut (1 pc : 3 psr : 5 Krl)

b (m) h (m) t (m) n (buah) V = [( b x h ) x t ] x n

0,12 0,10 0,05 16


= 0,010 m3
PERHITUNGAN VOLUME

NO. SKETS GAMBAR URAIAN PEKERJAAN DAN PERHITUNGAN VOLUME SAT.


V PEKERJAAN KAYU DAN KACA 1. Pasangan Kayu Kosen Klas I (5/12)

Type b (m) h (m) L (m) n (unit) V = [( b x h ) x L ] x n

PJ 1 0,05 0,12 22,05 2


= 0,265 m3

P1 0,05 0,12 7,20 1


= 0,043 m3

P2 0,05 0,12 7,00 3


= 0,126 m3

P3 0,05 0,12 6,80 2


= 0,082 m3

J2 0,05 0,12 10,30 4


= 0,247 m3

BV 1 0,05 0,12 3,05 3


= 0,055 m3
PJ1
Volume Total Kayu Kosen Klas I ( 6/12 ) 0,818 m3

2. Pasangnan Daun Pintu Panil Kayu

b (m) h (m) n (unit) A = (bxh)xn

0,920 2,000 3
= 5,520 m2
3. Pasangan Daun Pintu Double Teacwood 3 mm

b (m) h (m) n (unit) A = (( b1 + b2) x h ) x n


P1 P2
0,820 2,000 3
= 4,920 m2
P3
4. Pasangan Daun Pintu Double Teacwood Lapis Alluminium

b (m) h (m) n (unit) A = (bxh)xn

0,720 2,000 2
= 2,880 m2

5. Pasangan Daun Jendela Kaca 3 mm dan ventilasi


BV1 a. Type PJ1
b (m) h (m) n (Buah) A = (bxh)xn
J1 Ventilasi P 0,92 0,42 2 = 0,773
Ventilasi J 0,82 0,42 6 = 2,066
Jendela 0,82 1,82 6 = 8,954 m2
PERHITUNGAN VOLUME

NO. SKETS GAMBAR URAIAN PEKERJAAN DAN PERHITUNGAN VOLUME SAT.


b. Type P 1
ventilasi 0,92 0,42 1 = 0,386 m2

c. Type J 2
b (m) h (m) n (lubang) A = (bxh)xn

ventilasi J 0,72 0,42 8


= 2,419 m2

Jendela 0,72 1,22 8


= 7,027 m2

d. Type BV
b (m) h (m) n (lubang) A = (bxh)xn

BV 0,62 0,42 4
= 1,042 m2

Total Luas Pasangan Daun Jendela Dan Ventilasi ( Kaca 3 mm ) 22,668 m2


8. Pasangan Kayu Kap dan Gording
a. Pasangan Kuda - Kuda 1 ( KK I )
b (m) h (m) L (m) n (Jlh) V = [( b x h ) x L ] x n

Tiang Nok 0,08 0,12 2,95 2


= 0,057 m3

Kaki Kuda 0,08 0,12 6,90 4


= 0,265 m3

Blk. Tarik 0,08 0,12 11,40 2


= 0,219 m3

Blk. Penyokong 0,08 0,12 4,35 8


= 0,334 m3

Blk. Pangapit 0,04 0,12 2,40 4


= 0,046 m3

Blk. Pengunci 0,08 0,12 1,00 8


= 0,077 m3
V total = 0,997 m3
b. Pasangan Kuda - Kuda 2 ( KK II )
b (m) h (m) L (m) n (Jlh) V = [( b x h ) x L ] x n

Tiang Nok 0,08 0,12 2,45 2


= 0,0470 m3

Kaki Kuda 0,08 0,12 5,68 4


= 0,2181 m3

Blk. Tarik 0,08 0,12 8,12 2


= 0,1559 m3

Blk. Penyokong 0,08 0,12 2,80 8


= 0,2150 m3

Blk. Pengapit 0,04 0,12 2,08 4


= 0,0399 m3

Blk. Pengunci 0,08 0,12 1,00 8


= 0,0768 m3
V total = 0,7528 m3
PERHITUNGAN VOLUME

NO. SKETS GAMBAR URAIAN PEKERJAAN DAN PERHITUNGAN VOLUME SAT.

e. Balok gewel KK I (8/12)

b (m) h (m) L (m) n(m) V = [( b x h ) x L ] x n

0,08 0,12 13,80 2


= 0,2650 m3

f. Balok gewel KK II (8/12)

b (m) h (m) L (m) n(m) V = [( b x h ) x L ] x n

0,08 0,12 11,36 2


= 0,2181

g. Balok Bubungan (6/12)

b (m) h (m) L (m) V = (bxh)xL

0,06 0,12 15,50


= 0,1116 m3

h. Balok Gording (6/12)

b (m) h (m) L (m) V = (bxh)xL

0,06 0,12 284,50


= 2,048 m3

Volume Total Pasangan Kayu Kap (8/12) 4,3933 m3

9. Pasangan Listplank Papan (3/20)

L (m) n (uit) L' = Lxn

64,50 2,00
= 129,000 m1
PERHITUNGAN VOLUME

NO. SKETS GAMBAR URAIAN PEKERJAAN DAN PERHITUNGAN VOLUME SAT.


VI PASANGAN ATAP DAN PLAFOND 1. Pasangan Atap Seng Gelombang BJLS 0.30
b. Daerah persegi
Daerah b (m) L (m) h(L/cos30) A = b x h
A 6 5,50 6,35 = 38,100 m2
B 6 5,50 6,35 = 38,100 m2
C D C 9,5 6,25 7,22 = 68,590 m2
D 9,5 6,25 7,22 = 68,590 m2
Luas Total Pasangan Atap Gelombang Seng BJLS 0,30mm A total = 213,380 m2
2. Pasangan atap seng licin BJLS 0,30mm

A B L bubungan (m) L = L
14,5 = 14,500 m1

3. Pasangan Plafond Tripleks dan rangka

AB (m2) AE (m2) APl = ( AB + AE )

114,270 47,870
= 162,140 m2

4. Pasangan List Plafond Profil

L (m) L' = L B. induk + L emperan

B. Induk 139,600
= 239,600 m1

Emperan 100,000

Panjang Total List Plafond Profil 239,600 m1


VII PEKERJAAN LANTAI
1. Pasangan Tegel Keramik 30/30

AB (m2) Aw (m2) L (m) b (m) A = ( AB - AW )-( Lx b)

123,750 7,500 95,500 0,150


= 101,925 m2
PERHITUNGAN VOLUME

NO. SKETS GAMBAR URAIAN PEKERJAAN DAN PERHITUNGAN VOLUME SAT.

2. Pasangan Tegel Mozaik (KM/ WC) 20/20


AW (m2) b (m) L (m) A = Aw - ( b x L )

7,500 0,150 16,000


= 5,100 m2

3. Pasangan Tegel Porselin 10/20


a. Meja Dapur :
L1 (m) L2 (m) b (m) h (m) A = ( L1 + L2 ) x b
= 1,800 m2
1,50 1,50 0,60 0,60

As = ( b samping x h ) x n
a. Kaki Meja Dapur : = 0,72 m2
b samping (m) b depan (m) h (m) n (jml)
samping depan Ad = ( b depan x h ) x n
0,60 0,10 0,60
2,00 3,00 = 0,18 m2

b. KM/ WC :
Lw (m) P (m) h (m) A = ( Lw - P ) x h

16,00 1,54 1,50


= 21,690 m2

Luas Total Pasangan Tegel Porselin 24,390 m2


4. Pasangan Tegel Plint 10/30

L (m) LTK (m) LK (m) A = [ L - LK - LTK)

95,50 1,00 7,10


= 87,400 m1

VIII PEKERJAAN INSTALASI LISTRIK DAN AIR 1 Pasangan Titik Lampu = 19 Buah
2 Pasangan Lampu TL 40 Watt = 2 Buah
3 Pasangan Lampu spiral 25 Watt = 9 Buah
4 Pasangan Lampu spiral 15 Watt = 2 Buah
5 Pasangan Saklar Tunggal = 6 Buah
6 Pasangan SaklarGanda = 3 Buah
7 Pasangan Stop Kontak = 7 Buah
8 Pasangan Sekring Cast = 1 Buah
9 Pasangan Arde Pembumian = 1 Buah
10 Pasangan Wastafel = 1 Buah
11 Pasangan Bak Air Porselin = 2 Buah
12 Pasangan Closed Jongkok = 2 Buah
13 Pasangan Septic Tank dan Peresapan = 2 Buah
14 Pasangan Instalasi Air Bersih = 1 Buah
15 Pasangan Instalasi Air Kotor = 1 Buah
16 Pasangan Floor Drain = 3 Buah
17 Pasangan Kran Air = 4 Buah
PERHITUNGAN VOLUME

NO. SKETS GAMBAR URAIAN PEKERJAAN DAN PERHITUNGAN VOLUME SAT.


IX PEKERJAAN FINISHING 1. Cat Tembok
AAC (m2) A = AAC

437,416
= 437,416 m2

2. Cat Plafond
Apl (m2) A = APl

162,140
= 162,140 m2
3. Menie Kayu
a. Untuk Kosen :

Type b (m) h (m) L (m) n (unit) Am = [ 2 x ( b + h )] x L x n

PJ 1 0,05 0,12 21,85 2


= 14,858 m2

P1 0,05 0,12 7,00 1


= 2,380 m2

P2 0,05 0,12 6,80 3


= 6,936 m2

P3 0,05 0,12 6,60 2


= 4,488 m2

J2 0,05 0,12 9,90 4


= 13,464 m2

BV 1 0,05 0,12 4,20 3


= 4,284 m2

b. Untuk Listplank :

h (m) L (m) b (m) n A = ( 2 x ( b + h )) x L x n

0,200 64,500 0,02 2


= 56,760 m2

Luas Total Menie Kayu (Kosen & Listplank) 103,170 m2


PERHITUNGAN VOLUME

NO. SKETS GAMBAR URAIAN PEKERJAAN DAN PERHITUNGAN VOLUME SAT.


4. Cat Kayu
a. Untuk Kusen

Type Am (m2) LL (m) h (m) n (m) Ac = Am -((LL x h) x n)

PJ 1 14,858 21,85 0,12 2


A = 9,614 m2

P1 2,380 7 0,12 1
A = 1,540 m2

P2 6,936 6,8 0,12 3


A = 4,488 m2

P3 4,488 6,6 0,12 2


A = 2,904 m2

J2 13,464 9,9 0,12 4


A = 8,712 m2

BV 1 4,284 4,2 0,12 3


A = 2,772 m2

b. Untuk List Plank

Am (m2) b (m) h (m) L (m) Ac = Am- (( b + h ) x L )

56,760 0,020 0,200 64,500


= 42,570 m2

Luas Total Cat Kayu 72,600 m2


5. Cat Seng
As (m2) A = As

213,380
= 213,380 m2

6. Teac oil
Apn (m2) A = Apn x 2

5,520
= 11,040 m2

X PEKERJAAN PENGGANTUNG DAN PENGUNCI 1 Pasangan Kunci Double Slaag = 6


2 Pasangan Kunci KM/ WC = 2
3 Pasangan Grendel = 31
4 Pasangan Engsel = 86
5 Pasangan Kait Angin = 31
6 Pasangan Anker Doc = 68
7 Pasangan Mur, Baut dan Beugel U = 1

XI PEKERJAAN LAIN - LAIN 1. Pasangan Saluran Keliling Bangunan (Buis Beton U 30 cm) = 46,000 m1

2. Pembersihan Kembali = 1 LS
0,866
7,506
5,058
9,134
7,506
10,115