Professional Documents
Culture Documents
CEMN 281
SITE REPORT
(Electric high-speed train 6 th of October)
1
TABLE OF CONTENT
Table of Contents
1) Introduction .......................................................................................................................................... 3
2) Training site .......................................................................................................................................... 4
3) Typical system ...................................................................................................................................... 4
I. Piles ................................................................................................................................................... 4
➢ Construction procedure ............................................................................................................... 5
II. Pile cap ............................................................................................................................................ 13
➢ Construction procedure ............................................................................................................. 14
III. Piers ............................................................................................................................................ 21
➢ Construction procedure ............................................................................................................. 21
4) Construction problems ....................................................................................................................... 25
5) References .......................................................................................................................................... 26
2
1) Introduction
3
2) Training site
The training site was located in 6th of October city, West Somid
zone 2. The Arab Contractors company is in charge of 8km of the
railway, these 8km are divided into 2 sections each of 4km, the 2nd
section where I trained interferes with the monorail project in
somewhere along the section. The statical system of the 2nd section
has 3 different systems, the first 800m are designed as frames,
while the second is 2km with typical system held on piles, pile cap,
pier, pier cap and girders; this was the system I have viewed in
site, the last system which lasts for 1.2km is designed as retaining
wall system in which girders are rested on retaining walls instead
of resting on piers. The typical system span is 26m.
3) Typical system
As shown in figure the typical
system for piers consists of 5
major elements:1. Girders, 2. Pier
cap, 3. Pier, 4. Pile cap, 5. Pile.
I. Piles
Piles are foundation members
which made of timber, steel, and
concrete; these piles are either
cast in-site or pre-casted to be
driven or drilled in soil according
to the pile type in order to reach hard layer of soil with sufficient
bearing capacity to support the structure and transfers loads to the
ground.
There are many types of piles and many piling methods, but the
4
most widely used method for piling in Egypt is in-site rotary bored
piling; that is because it provides more tolerance in pile’s depth
and diameter as well as it can drill in hard soil such rocks for greater
depths, and it can bear heavy loads. CFA piling is also used but
when light loads are expected and used also for landscape projects,
both methods are categorized under the Bored piling, this type of
piling which depend on drilling the pile in-site and pour concrete in
the drilled cavity, unlike driven piling which depend on hammering
and vibrating a pre-casted pile in the soil, but this type of piling
results in excessive vibration in nearby area. The pile can be
classified into 2 main types according to the way it transfers loads;
it can either transfer loads through skin friction in loose soil or end-
bearing in hard soil such rocks. Bore piling has many challenges
such soil investigation which related to geophysical works using
borings to know soil properties to specify piles’ dimensions as well
as the appropriate methodology for piling on site. Now we will
discuss the construction procedures for the rotary bored piles
viewed on the high-speed train project.
➢ Construction procedure
5
productivity rate. The offset from circumference piles is
specified according to the excavator bucket width.
3. The surveying works locate the piles centers and axes using
steel sticks driven in soil. As shown in figure there is a steel
stick which is used as a reference while installing the casing
unit to match the center through measuring the distance from
the stick to the casing circumference it should equal to the
same distance specified by the surveying department. These
6
sticks are placed using total station at control points ()الروبير.
7
5. While drilling the pile, a mixture of bentonite and water
prepared in specific tanks with proportion of 37.5kg bentonite
for each 1m3 of water; this mixture called bentonite slurry has
many essential roles in piling process:1. It supports the
excavation by exerting hydrostatic pressure on its walls to
prevent the collapse of wall sides and retain pile area, 2. It
acts as a sealant, 3. Suspend detritus and prevent sludgy
layers building up at base of excavation depending on its
viscosity, 4. The low density of this mixture compared to
reinforced concrete allows concrete to replace the bentonite
slurry while pouring process using tremie pipes. The bentonite
slurry is tested twice; first it is tested in fresh condition and
then tested when it fills the excavation, the results of tests
must be within the following ranges: PH (9~11), viscosity
(30~40sec) for fresh sample and (70sec in AVG.) for used
sample, density (<1.15 t/m3), and sand content for used
sample (<3%).
8
6. Detritus and suspended sand in bentonite slurry are cleaned
either by using desander or replace the whole bentonite
slurry. Both methods are used in site. However, replacement
method was preferred in many conditions. The old bentonite
is placed in a ditch and new slurry is pumped in the
excavation, then a pump car come to extract the slurry in
liquid state so that the remaining slurry are viscous and then
excavator mix this slurry with sand to be in hard state to be
loaded in trucks to be scraped in drainage.
Ditch where old slurry is placed Pump car hoes extracting liquid slurry
9
7. Reinforcement stage takes place once bentonite slurry is
cleaned or replaced. Steel cage assembly takes places in site.
It consists of multiple connections each of 12m they are
welded together while being installed using crane, the
smallest connection in length is preferred to be installed first,
then it is held in position by steel rebars supported on the
casing while the following connection is welded with it. The
last connection is attached to the casing unit using steel hook.
Pile is centered and keeps the concrete cover using concrete
hollow cylinders ( )البسكوتهthis cylinder has height equals to the
concrete cover which is 7.5cm, these concrete cylinders are
attached to the steel cage using steel sticks welded to the
cage.
11
9. Finally, concrete pouring stage; concrete mixers transfer the
mixed concrete from plants to site. The concrete pouring
process in piles differs from other concrete elements pouring
stage, that is because of the great depth of piles as it reaches
up to 36m in the project and it is recommended that the
highest free fall of concrete should not exceed 1.5m to avoid
segregation of concrete components, here comes the tremie
pipes role, these pipes are connected together till reaching
the required depth, the assembly consists of cone and pipe
sections each of 3 or 4m, then the concrete mixers pour the
mixed concrete in the cone, each concrete mixers can carry
up to 8~9 m3 , a concrete base with steel gates is placed over
the casing unit to avoid accumulation of concrete in the cone
and pipes, hand hammers is also used to help the flow in pipe.
A specific rope is used to measure the poured concrete depth
to measure if there is an excess in concrete amount as the
concrete is denser than the bentonite slurry different velocity
of the load at the end of the rope is recognized and the depth
is recorded from the marked rope. Concrete volume is greater
than pile volume by 2 m3 to ensure pure concrete is filling the
whole excavation. In tremie
pouring a specific proportion of the
last connection should be buried in
concrete to avoid caving and
separation in pile. To ensure the
concrete characteristics many
samples of the concrete cubes are
taken from every patch to be
tested in compression.
12
Concrete cubes used for testing Cone section of tremie Measuring concrete depth
in compression system in the excavation
13
organized by the super structure and ground movement,
transferring the loads of the building to the foundations and ground
soil despite loads are vertical or inclined, and facilitating the
superstructure to stay on a consistent and solid core rather than
staying directly on ground.
➢ Construction procedure
1. After piles hardened, the excavator excavates the area of
the pile cap and offset equals to the bucket width from
circumferential piles. Then, a 10cm layer of plain concrete
is poured to ease the working environment during the rebar
placement and pile head removal. Surveying works place
the pile cap boundary using total station and mark them
using steel sticks driven in the ground then they must
ensure the bottom of pile cap matches the specified level
in the workshop drawings using levels, the workers keep
digging and filling till the ground almost flat and has the
exact level in the drawings. After ground leveling and pile
cap boundaries are placed a plastic sheet is placed over the
ground to prevent the soil to extract the water from
concrete after being poured then the boundaries are
surrounded by muski wood and concrete mixers pour the
concrete to the top if the steel sticks.
Pile head tied up to be Pile head after removal Pile head removal by
lifted by crane excavator hammer
15
beams supporting the muski wood decks are used for
countering the openings occurred in formwork during
concrete pouring stage, as well as through these steel
bars( )الزراجينand bolts( )العصافيرwe can adjust the verticality
of the pile cap formwork to reach the required tolerance.
16
4. Then, pile cap rebars are placed. There are 3 main
elements in pile cap reinforcement: main rebars, shear
links, and clips. The bottom reinforcement consists of 2
layers of rebars with hooks(angles) in opposite directions
to resist flexural stresses, it is supposed that bigger
proportion of reinforcement placed in the main direction
and less in the secondary one, but in this project the pile
cap is almost squared so the loads will be distributed
uniformly in both directions. Additional rebars around the
pile was added due to the high stresses in this place. A
concrete hollow cylinders are attached to the bottom layer
of bars and to the hooks to guarantee the concrete cover.
Then, stirrups are placed around pile development
length()سوست, and Pier dowel bars are placed and tied with
the bottom rebars. Column stirrups are then placed not just
around column circumference, but with additional links and
clips. Shear links are placed vertically to resist seismic
loads and 8 clips are placed around each pile to resist high
shear force in this place and to avoid punching shear, both
elements act as vertical stirrups to link between top and
bottom rebars. All rebars are tied up together using steel
wires and there are vertical and horizontal bars welded
together to ease the place the rebars in pile cap ( القوايم و
)االوتار. After placing the top rebars 2 layers with the
additional rebars at piles locations, side face shear bars are
placed ( )البرنداتto keep the rebars hooks (angles) vertical
and placed every 25cm and should be placed inwardly, but
to facilitate they are placed outwardly reducing concrete
cover.
17
Bottom rebars hooks and steel wires Additional rebars at pile location Side face shear bars البرندات
Reinforcement details
Bottom reinforcement Pile stirrups السوست
5. After the consultant approved the steel works, the pile cap
is ready for concrete casting stage. Concrete mixers charge
concrete into concrete pumps to pour it in the pile cap
18
formwork. Concrete samples are taken to be tested in
compression, each patch from concrete mixer should be
tested to ensure the quality of the concrete mixture. In
casting process vibrator is used to eliminate air bubbles by
vigorously shaking the freshly poured concrete, because
these bubbles weaken the concrete. The pump keeps
pouring concrete until reaching a wooden sign that specify
the reinforced concrete level( )المتلوتهand then workers level
the surface to be flat. After concrete pouring is finished, a
chemical substance called Antisol is applied to fresh
concrete surface to form impervious layer which protects
the concrete from rapid water evaporation during initial
curing stages. This evaporation would cause bleeding for
concrete which weaken the concrete as it forms air
channels in concrete.
Top rebars and concrete cover and string to locate Concrete being charged from
the axes mixer into the pump
Bitumen barrels Steel bars cutting off Curing by plastic and wet sand
قص الزراجين covering
21
2. Pier dowels placed over the bottom rebars of pile cap differ in
their length (staggard connections) to avoid the presence of
weak pockets during jointing pier rebars and to guarantee
sufficient overlap length 1m or 65 times rebar diameter. The
pier in this project is rectangular with rounded edges. Wooden
decks are placed over the steel scaffoldings, these decks must
guarantee the verticality of rebars and to keep them in place
till concrete is poured; a test is carried out for this purpose
using rope with wooden piece and a cylindrical load at its end,
this load is suspended vertically from the edge of top wooden
deck to each of the other wooden decks’ tops, the edge of the
wooden piece should be matched with the edge of the
load()خيط ميزان الشاغول. After making sure that wooden
decks( )الحطهare placed accurately, the level of the decks are
adjusted to meet the top level of pier using wing nuts ()فتايل.
The pier rebars are lifted by crane and suspended to be
attached to pier dowels using steel wires. Then, pier stirrups
are distributed over the length (الكانات )تقسيط.
Staggard connections
22
Pier rebars installation using crane Top view of pier RFT
23
3. Special steel formwork is used for piers as it is economical
than using standard wood formwork. Steel formwork is
installed around the pier rebars with 5cm concrete cover, this
cover is set using concrete hollow cylinder ()البسكوته. Then,
reinforced concrete blocks are prepared and casted in site,
the function of these blocks is to support the jacks holding the
steel formwork; through these jacks we can adjust the
verticality of the pier to reach the required tolerance. Finally,
concrete is poured to a specific level and development length
( )االشايرis left to be embedded in pier cap reinforcement.
Concrete block RFT Casted concrete block Pier concrete cover ()البسكوت
24
These were the constructed elements in stage 1 while stage 2
includes pier caps and girders. There were a lot of problems
occurred during the construction process, some problems we be
discussed and how these problems were solved.
4) Construction problems
In construction process there were 2 fatal problems occurred
during training, but engineers managed to solve them efficiently;
the first problem was losing the rotary piling machine bucket in the
excavation at 13m depth, it was hard to extract the bucket out of
the excavation, this loss was estimated to be 900k L.E. The
problem was reported to the design department to re design the
distribution of the piles and they managed to displace the pile and
changing the pile cap dimensions and RFT to be able to withstand
the expected loads without any problems.
The second problem is common and has procedure to follow when
it happens, but it is fatal as it damages assets and waste money
as well; this problem is related to the form works, as concrete being
poured it exerts hydrostatic pressure on the form sides and if these
forms are not made properly according to the workshop drawings,
it results to openings in formwork and concrete collapse outside
the form. Once this happens forms
must be replaced, and all the
casted concrete should be flush
out and rebars should be
scratched out of the concrete.
Delaying the construction process
as well as mess up the site
working area make this problem
classified as a fatal one.
25
5) References
• https://www.alsina.com/en/bridge-construction-typology-the-piers/
• https://english.ahram.org.eg/News/467004.aspx
• https://theconstructor.org/others/bentonite-uses-
construction/13332/?amp=1
Training certificate
26