Professional Documents
Culture Documents
Whole-Life Carbon and Buildings
Whole-Life Carbon and Buildings
Contents
Introduction...................................................................................................................... 3
Appendix 1 ..................................................................................................................... 21
Summary .......................................................................................................................... 21
References ....................................................................................................................... 22
Above: The polished concrete floor at The White Cube, London avoids
the need for, and the CO2 associated with, additional finishes.
Introduction
Whole-life performance is a term that has traditionally referred to the ¢¢ Reuse – reducing the embodied impact of new build through the
total cost of building ownership, but has more recently grown to include ability to reuse concrete buildings
broader sustainability issues, particularly embodied CO2. The result is that ¢¢ End of life – the absorption of CO2 into concrete through the
environmental considerations are increasingly vying with capital cost as a natural process of carbonation.
key design driver, leading to more holistic outcomes, in which whole-life
thinking has helped inform the choices made. However, in respect of The guide draws upon information from a broad range of sources
masonry and concrete-frame buildings, low capital cost and good whole- and provides a largely qualitative overview of these whole-life topics.
life performance are by no means mutually exclusive – a realisation that Going forward, it will soon be possible to validate the compelling CO2
has long been accepted in the public sector, but is also becoming more performance of concrete buildings in a more quantitative way, using
apparent in the commercial sector where low-energy, sustainable design Environmental Product Declarations (EPDs) and the more sophisticated
is now more often seen as a good way to future-proof property assets [1]. whole-life design tools that are being developed.
Concrete-frame construction will of course provide a durable structure, Finally, it is worth making the point that the ownership costs of concrete
which is a fundamental aspect of whole-life performance. But less buildings and their cradle-to-grave CO2 footprint are very much
understood is its compelling whole-life CO2 performance, resulting from interrelated; financial savings achieved through durability, low maintenance
several attributes largely unique to concrete buildings. These are the and thermal performance closely parallel the CO2 savings linked with these
focus of this guide, which sets out the ways in which these attributes can attributes.
be used to minimise CO2 emissions, both directly and through broader
indirect design opportunities that the use of concrete often enables.
More specifically, the guide covers: CONCRETE AND MASONRY BUILDINGS CAN
¢¢ Concrete specification – keeping the embodied CO2 of concrete HAVE THE LOWEST WHOLE LIFE CO2 COMPARED
to a minimum WITH ALTERNATIVE SOLUTIONS.
¢¢ Lean building design – using concrete for multiple roles,
enabling other materials to be designed out
¢¢ Operational energy - using concrete’s thermal mass to lower
operational emissions
Figure 1: Overview of opportunities to reduce lifecycle CO2 in concrete and masonry buildings.
Concrete Production –
the investment in embodied CO2
The whole-life performance virtues of concrete outlined in this guide can entirely offset the CO2 emissions
associated with its production, transportation and placement. In this sense, its initial CO2 footprint can be viewed
as an investment in embodied CO2 that can pay back over time. This has been helped by ongoing improvements in
the manufacture of concrete, including a 13% reduction in carbon intensity since 2008 [2].
Cement slag from the steel industry, often referred to as GGBS (ground granulated
blast-furnace slag) and fly ash from the power industry. Table 1 provides the
Concrete is made from cement, water, sand and stone or gravel. The embodied CO2 of different types of cement and cementitious materials.
approximate volume of materials used is shown in Figure 2, which
represents typical in-situ concrete. The process of extracting sand and Table 1: Cradle to gate embodied CO2 of UK cement and cementitious
gravel, crushing stone, combining the materials in a concrete plant and materials [3, 4]
transporting concrete to the construction site is responsible for a relatively
Cement / Cementitious material kgCO2 /tonne
small amount of concrete’s embodied CO2. The majority comes from the
cement, which makes up about 10% of concrete by volume, but accounts Portland cement (CEM 1) 913
for around 75-90% of its embodied impact.
Fly ash (from coal burning) 4
GGBS 67
Figure 2: Approximate composition of concrete (by volume)
Limestone fines 75
Figure 3: Embodied CO2 of cement with varying levels of fly ash/GGBS [5] Table 2: Cradle to gate embodied CO2 of concrete [4]
Concrete Concrete ECO2 (kgCO2 /m3)
1000 type
(slump
Embodied CO2 of cement (kg/tonne)
Aggregates are the major component of concrete, but account for very Table 2 provides more specific values relating to different types of concrete
little embodied CO2 as they are mostly naturally occurring, and thereby and applications. It shows the significant reduction in embodied CO2 that is
require minimal processing. They are also locally sourced, reducing the achieved through the use of fly ash and GGBS (also see Figure 3). Alongside
need for transportation. The average embodied CO2 for UK aggregates is this, a number of good-practice design measures can be adopted to ensure
4kgCO2/tonne [4]. The use of recycled aggregates may reduce this figure concrete is specified with the lowest possible CO2 impact. These include
slightly, but only if it is reused on site or transported 15km or less by road the following:
[6]. An average of around 5% of the aggregate used in concrete is recycled
¢¢ Do not over-specify strength
or secondary aggregate – that is, a by-product from another industry [7].
The precast sector uses the highest proportion of recycled aggregate, ¢¢ Consider the possibility of strength conformity at 56 days rather than
at 22% [8]. the conventional 28 days
¢¢ Specify responsibly sourced concrete and reinforcement
Designing out suspended ceilings to improve internal comfort and the effectiveness of natural ventilation –
an approach adopted at the White Collar Factory office development in
CO2 and material savings Old Street, London (see case study, below). The increase in floor-to-ceiling
height also enables single-sided ventilation to be effective at a floor depth
Internal finishes account for around 12-14% of the total embodied
7-10% greater than would otherwise be possible [15].
emissions associated with office buildings [10, 11] of which suspended
ceilings are a significant component. It therefore follows that the ability
to design them out in favour of an exposed structural soffit will bring a
worthwhile reduction, which can be up to 10kgCO2/m2, including site
wastage that occurs during installation [12]. In terms of the physical
quantity of materials used, up to six tonnes can be taken out of the design
for every 1,000m2 of floor space [12]. Future savings may also be realised
by avoiding the need to eventually replace the suspended ceilings, which
have a lifespan of around 24 years [13]. Other lifecycle impacts arising from
cleaning and maintenance are largely avoided with exposed concrete
soffits, although painted finishes may need to be reapplied periodically.
Concrete soffits can also provide operational CO2 savings by virtue of the
thermal mass they contain, which reduces peak cooling loads and helps to
deliver a more passive approach to maintaining comfort. For radiant cooling
to be effective, occupants must be able to physically see the concrete soffit
above them, which suspended ceilings largely prevent. The use of thermal
mass is covered on page 12 of this guide, which focuses on operational CO2.
Concrete soffits. Exposed in-situ concrete soffits at 5 Pancras Square, London (Architect: Bennetts Associates). © VIEW.
8 WHOLE-LIFE CARBON AND BUILDINGS
Figure 4: Embodied CO2 of building services in air-conditioned and non-airconditioned offices [16]
1. They do not affect the size of the foundations, since projects are not
designed around geothermal requirements. Instead, the assumed
heating/cooling output is based on that building’s structural design
requirements.
The use of energy piles has grown steadily in recent years. In 2012 there
were around 5,000 energy piles installed in the UK, resulting in an annual
© Alamy
CO2 saving of approximately 6,600 tonnes [22]. Recent projects include a
number of Crossrail stations, the Bulgari Hotel at Knightsbridge and One
New Change in the City of London (see case study). One New Change, City of London
Future uptake is set to increase, particularly if the technology can be adapted Completed in 2010, One New Change is a £500m office and retail
for use in the domestic sector, which is an application that Nottingham development, comprising 20,000m2 of retail space and 31,000m2 of
University has been researching. Work has also been undertaken at office space in the City of London. The building has a 2MW heating
Southampton University, which has been evaluating the thermal performance and cooling installation that makes use of energy piles linked to a
of energy piles. A key result highlighted by this work is the importance of the heat pump system. This is providing measured annual CO2 savings
concrete within the pile for short-term thermal storage [23]. of 300 tonnes and £65,000 in energy costs [22].
10 WHOLE-LIFE CARBON AND BUILDINGS
RESEARCH:
THE STRUCTURAL ENGINEER CAN PLAY AN IMPORTANT Operational and end-of-life impacts can be added to the cradle-to-site
approach of the research in order to obtain a whole life cycle comparison.
ROLE IN REDUCING A TYPICALLY SIZED BUILDING’S
EMBODIED CO2 BY AS MUCH AS 100KG OF CO2/M2
Reinforced in-situ concrete flat slab Steel beams and metal decking, Post-tensioned in-situ concrete flat Post-tensioned in-situ concrete
and columns acting compositely with in-situ slab and reinforced in-situ concrete flat slab and band beams with
concrete floor slabs. Steel columns columns reinforced in-situ concrete columns
Steel beams acting compositely Reinforced in-situ concrete beams Slimdek system comprising Long-span cellular steel beams
with precast concrete hollowcore and columns with precast concrete asymmetric beams and metal decking, and metal decking, both acting
floor slabs. Steel columns hollowcore floor slabs acting compositely with in-situ compositely with in-situ concrete
concrete floor slabs. Steel columns floor slab. Steel columns
WHOLE-LIFE CARBON AND BUILDINGS 11
Results for variation in specification offer the opportunity to mobilise the benefits of thermal mass through
exposed concrete floor soffits, an aspect not considered in this study.
and method The research proves that the material specification has the potential to
The research found little variation between the cradle-to-site eCO2 of many reduce the embodied CO2 of a building. The potential savings of over
of the structural solutions. However, the minimum-depth steel solution, 1,000 tonnes of embodied CO2 are real and demand examination by
Slimdek, consistently had the highest eCO2, adding some 2,000 tonnes of structural engineers.
CO2 to the lowest eCO2 scheme. Minimum-depth concrete solutions, such
as post-tensioned concrete, provided low eCO2 impact due to the efficient
use of materials. Also, surprisingly little variation was found in substructure DESIGN AND MATERIAL SPECIFICATION HAS THE
impact. POTENTIAL TO SAVE OVER 1,000 TONNES OF CO2
The first important conclusion is that most of the different design methods IN A BUILDING
have similar eCO2. The material specification can effect a real difference: for
example with a typical-sized office building there is the potential to save at
least 1,000 tonnes of CO2 through specification and design.
Flat slab vs slimdek
Second, the research found that the knock-on effects of changing the
structural scheme are relatively small as the changes in facade, foundation, For the office example, the lowest impact scheme is the flat slab option:
finishes and construction impacts were only 2-5% of the range in the Total eCO2 kgCO2/m2
superstructure impacts. However, the knock-on effects on operational Lowest bound spec 2,000 120
energy can be significant. Typical spec 2,900 180
Upper bound spec 4,000 240
The specification of concrete was determined to be the main factor in
achieving a low eCO2 solution. The impact of steel cannot be influenced
through specification whereas for concrete, it can. For example, the The highest impact scheme is Slimdek. The same investigation was
specification of a post-tensioned flat slab can save 15% of eCO2 and the done for this scheme:
specification of an RC flat slab can save 35%. This can be achieved by the
Total eCO2 kgCO2/m2
use of blended cements containing other cementitious materials, such as
Lowest bound spec 3,900 240
fly ash or GGBS. However, use of other cementitious materials can affect the
Typical spec 4,500 275
construction programme and this must be considered.
Upper bound spec 5,200 320
Furthermore, although not part of this study, the lowest impact frames
examined, such as the RC flat slab, hybrid in-situ and precast concrete, also
300
Structural eCO2 (kg/m2)
250
200
150
100
50
0
Flat slab
Composite
Using concrete’s thermal mass Concrete floors can also provide some convective cooling – that is, to
air that comes into contact with the concrete. This is more significant
By absorbing and storing excess heat during the day, concrete provides where the floor slab also forms part of a mechanical ventilation system
inertia against temperature fluctuations, reducing the need for mechanical – for example, with underfloor ventilation or the TermoDeck system. This
cooling. Heat retained by the concrete can be removed overnight by provides a beneficial uplift in cooling output. These and other systems
ventilating the building with cool night air. The process is often likened featuring exposed soffits are described in Concrete Floor Solutions for Passive
to a “thermal flywheel”, whereby much of the cooling load is shifted from and Active Cooling, available from The Concrete Centre.
daytime to night-time when it is more easily dealt with by passive means.
In practical terms, the concrete typically takes the form of an exposed soffit,
which provides a large surface area for heat transfer and the ability to store
a significant amount of heat within the floor slab. Buildings in which this THE THERMAL MASS IN EVERY SQUARE METRE
technique forms part of a low-energy cooling strategy typically produce OF EXPOSED CONCRETE SOFFIT CAN SAVE
far lower CO2 emissions than an alternative air-conditioned approach (see
HUNDREDS OF KILOGRAMS OF CO2 OVER THE
Figure 5).
LIFE OF A BUILDING.
Figure 5: Benchmark CO2 emissions from office buildings [25]
Kg CO2 /m2/year
Most of the heat absorbed into the soffit is by radiation from adjacent
surfaces at a higher temperature, which includes the building occupants,
who continue to benefit from this radiant cooling effect throughout the
day. The high level of thermal mass provided by the concrete ensures that
although a lot of heat may be absorbed, the soffit temperature remains
comparatively low.
WHOLE-LIFE CARBON AND BUILDINGS 13
Figure 6: Cumulative CO2 savings for each square metre of avoided finishes.
1000
900
800
700
CO2 savings (kgCO2/m2)
600
500 Key
Avoided air-conditioning
400 (in use CO2 emissions)
0
0 10 20 30 40 50 60 70 80 90 100 110 120
Option 1: Plain, flat slab Option 2: Profiled/flat slab with underfloor Option 3: Hollowcore slab with mechanical
mechanical ventilation ventilation supplied via the cores
The simplest option, providing a peak cooling Using a raised floor to distribute mechanical Typically referred to by its trademark Termodeck,
output of around 15-20W/m2. It can be used ventilation enables heat transfer from both sides this system increases heat transfer to and from
as part of an entirely passive system, or in of the slab, increasing the peak cooling output to the slab by channelling the ventilation supply
combination with mechanical cooling and around 25-35W/m2. The increased surface area of through its cores before entering the occupied
ventilation. a profiled soffit also improves heat transfer. space. This results in a peak cooling output of
around 40W/m2.
Option 4: Embedded ducts supplied by Option 5: Embedded pipework carrying chilled Option 6: Chilled beams located below an
mechanical ventilation water exposed soffit
Essentially the same as the hollowcore slab Embedding chilled water pipes allows a peak Chilled beams provide around 100-160Wm2
option, but using proprietary aluminium ducts cooling output of around 65W/m2 and is an of cooling and work well with the passive
embedded in precast or in-situ concrete (with increasingly popular option that can be used benefits of an exposed concrete soffit. They can
the trademark Concretcool). Peak cooling is with most types of precast or in-situ floor slab. also provide a convenient means of locating
around 65W/m2, helped by fins inside the ducts The passive output of the slab is supplemented mechanical and electrical services normally
that increase the surface area and heat transfer. by active cooling from the pipework, which concealed behind a ceiling void.
operates at high efficiency thanks to the large
soffit area and load-spreading effect of the
thermal mass.
WHOLE-LIFE CARBON AND BUILDINGS 15
Alongside savings in embodied CO2, the reuse of a building can also offer
many other advantages over new build, including:
The practicalities of reuse
¢¢ Avoidance of many of the planning constraints imposed on new build There are two key prerequisites for reusing a concrete frame, the first of
and less time spent in the planning process which is the continuing structural integrity of the building. Condition
¢¢ Less time spent on site surveys of older concrete-frame buildings often provide a favourable
outcome in terms of their ongoing structural viability and suitability for
¢¢ Existing buildings are often larger and have more car parking than
reuse, albeit subject to any minor repairs or localised strengthening that
permitted by current planning regulations
may be required [32]. The second requirement is the ability of the building’s
¢¢ Housing – Refurbishment can avoid the need to rehouse tenants, which form to meet current needs in terms of layout, slab-to-slab height, floor
is a costly and disruptive loads, servicing etc. This may be less of an issue in high-rise housing
¢¢ Housing – The current shortfall in new homes suggests that, by 2050, refurbishments, but is important in commercial projects, particularly where
70% of existing homes will still be in use, meaning reuse of housing has a change of use is required. These requirements are often broadly satisfied
an important part to play in reducing energy consumption and carbon in concrete-frame buildings despite little consideration being given to
emissions [27]. Residential tower blocks form a significant part of this, future reuse in the original design. A likely explanation for this is that many
with 3,500 in the UK, housing 800,000 people [26] existing buildings broadly conform to what is termed today as a “long life,
¢¢ Offices – The comparatively narrow floor plate often found in older loose fit” approach, which combines the use of durable materials with a
buildings can lend itself to natural ventilation from perimeter windows, format that is reasonably generous in terms of space and is not tailored
reducing the need for mechanical ventilation and air-conditioning [28]. too tightly to the building’s function [33]. In the case of offices, a partial
move away from deep-plan, heavily serviced spaces has also favoured
older, shallow-plan, concrete-frame offices that can help facilitate a more
Embodied CO2 savings passively controlled environment. It is also the case that concrete-frame
construction can often be cost-effectively repaired and upgraded [34],
The CO2 savings that can be realised from reuse are of course largely which can include the ability to:
project-specific, but will essentially equate to those of a new concrete
¢¢ Add floors or extensions to the building
frame, which represents the key difference between the new build and
reuse options. Based on a range of published studies [29, 30] the initial ¢¢ Add lift shafts and risers
embodied figure for the superstructure of an office is generally around 200- ¢¢ Increase the load on structural columns and floors
250kgCO2/m2 and is applicable to concrete and steel-frame buildings – that ¢¢ Reduce floor loads by removing screed, which also increases the slab-
is, both framing options have a similar CO2 footprint (see embodied CO2 of to-slab height
framed buildings, page 10). This provides an approximate indication of the
¢¢ Create openings in slabs
significant embodied CO2 savings that can be achieved through reuse. For
other building types, the figure may vary slightly – for example, hospitals ¢¢ Rationalise the mechanical servicing – for example, through the use of
and schools are likely to be about 5% and 10% higher respectively [30]. surface heating/cooling or chilled beams
¢¢ Remove suspended ceilings to increase slab-to-slab height and expose
the soffit’s thermal mass.
Focus on Reuse:
Elizabeth II Court, Winchester
Architect: Bennetts Associates
Structural Engineer: Gifford
M&E Engineer: Ernest Griffiths
Figure 9: Estimated reduction in the embodied CO2 of structural concrete due to carbonation [43]
20 WHOLE-LIFE CARBON AND BUILDINGS
University of Greenwich - the need for mechanical services was reduced through the use of exposed soffits, which also provides space and energy
savings. © VIEW.
WHOLE-LIFE CARBON AND BUILDINGS 21
Summary
¢¢ Avoided finishes and plant: Exposed concrete allows additional ¢¢ Low maintenance: Concrete's durability ensures a long service life
finishes and plant to be designed out, cutting embodied CO2 and with a minimal need for maintenance.
space requirements.
¢¢ Reuse of building: The longevity of concrete frame buildings
¢¢ Lower energy use: Concrete's thermal mass can significantly means they can often be reused, saving significant embodied CO2
reduce the energy needed for cooling. compared to new build.
¢¢ Carbonation: Concrete buildings absorb atmospheric CO2 over ¢¢ Carbonation at end-of-life: When concrete is crushed at the end
their lifecycle. of a building's life, atmospheric CO2 is rapidly absorbed due to the
huge increase in the concrete's surface area.
Embodied CO2 payback – exposed concrete floor slab CO2 emissions from air-conditioning
Average cooling output of slab = 0.03 kW/m2 (Termodeck system) Average coefficient of performance (COP) for air-conditioning system
assumed to be: 4.0
Annual cooling output (April-September):
0.03 kW/m2 x 1m2 x 1,056 hours = 32 kWh Grid supplied electricity currently emits:
0.522 kgCO2/kWh
Equivalent cooling from air-conditioning produces around 4.2 kgCO2
(see calculation opposite) So, every 32kWh of cooling produces:
(32/4) x 0.522 = 4.2 kgCO2
Note: The figure of 32kWh represents the annual cooling output from the
exposed concrete soffit (see calculation opposite).
References
1. Non-domestic Real Estate Climatic Change Model, Royal Institute of Chartered Surveyors, 2012
2. 8th Concrete Industry Sustainability Performance Report, 2014 performance data, Mineral Products Association
3. Embodied CO2e of UK cement, additions and cementitious material, Fact Sheet 18, Mineral Products Association, July 2015
4. Specifying Sustainable Concrete, MPA The Concrete Centre, 2015
5. Based on table 6, Specifying Sustainable Concrete, MPA The Concrete Centre, 2015
6. Concrete and the Green Guide, The Concrete Centre, 2009
7. 5th Concrete Industry Sustainability Performance Report, 2008-2013 performance data, Mineral Products Association
8. Sustainability Matters 2015, MPA British Precast, 2015
9. P. Horsley and C. Ranatunga, Carbon Footprint Comparison of Fast Form versus Timber Shuttering, June 2015 (www.fastformsystems.com)
10. Assessment of CO2 emissions reduction in high-rise concrete office buildings using different material use options, C.K. Chau, W.K. Hui, W.Y. Ng and
G. Powell, Resource, Conservation and Recycling 61 (2012), pp22-34
11. S.C. Kaethner and J.A. Burridge, Embodied CO2 of Structural Frames, The Structural Engineer, Vol 90, May 2012, pp33-40
12. Design Detail Sheet – Exposed ceiling, Waste & Resources Action Programme (Wrap)
13. BCIS, Building Cost Information service, Life expectancy of building components, 2006
14. British Council for Offices, Guide to Specification 2009
15. G. Hawkins, Rules of Thumb, Guidelines for Building Services, (5th edition, 2011), Building Services and Research and Information Association (BSRIA).
The figure quoted is based on requirements for single-sided ventilation.
16. R. Hitchin, Embodied Carbon and Building Services, CIBSE research report 9, 2013
17. A. Cooper, D. Doran, The Facts of Life, CIBSE Journal, February 2015
18. Design Detail Sheet – Polished concrete floor, Waste & Resources Action Programme (Wrap)
19. Cutting embodied carbon in construction projects, Waste & Resources Action Programme (Wrap)
20. Energy Piles: A pioneering approach. www.skanska.co.uk/services/cementation-piling-and-foundations
21. F.G.H. Koene, W.G.J. van Helden and J.C. Romer, Energy piles as effective ground heat exchangers, in Proc. TERRASTOCK 2000, Stuttgart, Germany, 28
August – 1 September, pp227-232
22. T. Amis and F. Loveridge. Therm Foundations, CIBSE Journal, August 2014
23. F. Loveridge and W. Powrie, Performance of piled foundations used as heat exchangers, 18th International Conference for Soil Mechanics and
Geotechnical Engineering, Paris, France, September 2-5, 2013
24. Air conditioning - maximising comfort, minimising energy consumption, Carbon Trust, March 2012
25. The values plotted for the “typical” and “best practice” offices are based on those published in the 2012 edition of CIBSE Guide F (Energy efficiency in
Buildings). A value for high thermal mass offices is not published in Guide F, so the value used is based on an average of the following buildings:
1. Edinburgh Gate Building, Harlow, 2. Innovate Building, Leeds, 3. Elizabeth Fry Building, Norwich, 4. Ionica Building, Cambridge, 5. Canon Headquarters,
Reigate, 6. Inland Revenue building, Nottingham
26. P. Buxton, Refurbishment is the height of fashion, Building Design Online, Bdonline.co.uk, February 2013
27. K. Crawford, C. Johnson, F. Davies, S. Joo and S. Bell, Demolition or Refurbishment of Social Housing? University College London, October 2014
28. C. Kendrick, A. Martin and W. Booth, Refurbishment of Air-Conditioned Buildings for Natural Ventilation, Technical note TN 8/98. BSRIA, 1998
29. D. Clark and D. Bradley, Embodied carbon of steel versus concrete buildings, Cundall Johnston & Partners LLP, July 2013. The studies reviewed are:
− IStructE research paper – Concrete Centre / Arup, 2012
− Sustainable Concrete Architecture – David Bennett, RIBA Publishing, 2010
− Steel Construction Industry – Eaton & Amato, 1998
− British Constructional Steelwork Association – Target Zero Office study, 2011
− Cundall R&D project, 2013
30. S.C. Kaethner and J.A. Burridge, Embodied CO2 of Structural Frames, The Structural Engineer, Vol 90, May 2012, pp33-40
31. S. Kennett, Altered Towers, Building Magazine, 16 May 2008
32. Greening the Skyline – The challenge and opportunities of tower block retrofit, Green Alliance event at the RIBA, November 2014
33. P. Buchanan, Ten Shades of Green, The Architectural League of New York, (www.tenshadesofgreen.org)
34. C.A Gold and A.J. Martin, Refurbishment of Concrete Buildings: Structural and Services Options, Guidance Notes GN 8/99, British Cement Association
(BCA), Building Services Research and Information Association (BSRIA), 1999
35. ECD Architects, Greening the Skyline – the challenge and opportunities of tower block retrofit, Green Alliance event at the RIBA, November 2014
WHOLE-LIFE CARBON AND BUILDINGS 23
36. A. Smith, Wimbledon Ace, CIBSE Journal, May 2015 ( a case study of Mansel Court; an office refurbishment project)
37. T Whitehead, London’s concrete quarter, bdonline.co.uk, 21 February 2014
38. T. Kikuchi and Y. Kuroda, Carbon dioxide uptake in demolished and crushed concrete, Journal of Advanced Concrete Technology 9, 2011, pp115-124
39. C.J. Engelsen and H. Justnes, CO2 Binding by concrete – summary of the state of the art and an assessment of the total binding of CO2 by carbonation in
the Norwegian concrete stock, 2014, SINTEF Byggforsk
40. https://en.wikipedia.org/wiki/Pantheon, Rome
41. UK waste return data from the NFDC was supplied to The Concrete Centre in April 2014
42. Meeting with NFDC, April 2014
43. Based on calculation methodology detailed in: K. Pommer and C. Pade, Uptake of carbon dioxide in the life cycle inventory of concrete, Danish
Technological Institute, October 2005. Secondary life carbonation based on proportion of CaO assumed to ultimately carbonate as detailed in: C.J.
Engelsen and H. Justnes, CO2 Binding by concrete – summary of the state of the art and an assessment of the total binding of CO2 by carbonation in the
Norwegian concrete stock, 2014, SINTEF Byggforsk
44. Closing the loop: what type of concrete reuse is the most sustainable option?, Technical Report A-2015/1860, European Cement Research Academy,
November 2015
45. Inside Science, BBC Radio 4, 15 January 2014
46. Professor D. Manning, How Does it Work? – Engineering the Soil Carbon Sink, Department of Civil Engineering and Geoscience, Newcastle University
47. Concrete carbonation forms part of a building’s whole-life CO2 performance, in accordance with BS EN 15804: 2012, Sustainability of construction works
– Environmental product declarations – Core rules for the product category of construction products
The Concrete Centre’s vision is to make The Concrete Centre provides design
concrete the material of choice. We provide guidance, seminars, courses, online
material, design and construction guidance. resources and industry research to the
Our aim is to enable all those involved in the design community.
design, use and performance of concrete to
realise the potential of the material. For more information and downloads, visit:
www.concretecentre.com/publications
The Concrete Centre is part of the www.concretecentre.com/events
Mineral Products Association, the www.concretecentre.com/cq
trade association for the aggregates,
asphalt, cement, concrete, dimension stone, Subscribe to our email updates:
lime, mortar and silica sand industries. www.concretecentre.com/register
www.mineralproducts.org
Follow us on Twitter:
@concretecentre
@thisisconcrete
www.concretecentre.com
The Concrete Centre, Gillingham House, 38-44 Gillingham Street, London SW1V 1HU
Ref. TCC/05/30
ISBN 978-1-908257-17-8
First published 2016
© MPA The Concrete Centre 2016
All advice or information from MPA The Concrete Centre is intended only for use in the UK by those who will evaluate
the significance and limitations of its contents and take responsibility for its use and application. No liability (including
that for negligence) for any loss resulting from such advice or information is accepted by the Mineral Products
Association or its subcontractors, suppliers or advisors. Readers should note that the publications from MPA The
Concrete Centre are subject to revision from time to time and should therefore ensure that they are in possession of
the latest version.
Printed onto 9Lives silk comprising 55% recycled fibre with 45% ECF virgin fibre.
Certified by the Forest Stewardship Council.