ENGINEERING DESIGN DEPARTMENT

JOB REQUEST FORM

TO: ACS / JMP DATE: 21-Oct-23


CC: MTB / HOL

TYPE OF WORK:
Design Completion Schedule Estimate

Construction Drafting
Design Review Inspection & Elevation
Cost Estimate Others

DATE NEEDED :
LEVEL OF PRIORITY :

WORK DESCRIPTION

EDC BACMAN Palayan Binary Power Plant, Sorsogon City, Sorsogon

Palayan PP and Proposed Wall Reinforcement Plan

CAD: REV. 0 DRAWINGS

ESTIMATING: REFERENCE FOR COST ESTIMATE

PROVIDED WITH:

Sketch Drawing Report Others

Requesting Party : TEAM 1

Project : SAME AS ABOVE Prepared by : AVBP


Location : Checked by : VGL
Cost Center : Approved by : VGL

For Engineering Design Use Only


Action:
Approved Hold, Insufficient Data/Info Others

Disapproved Hold, Requires Site Inspection


By : Date :

Completion Target : Request No. :


Starting Date : Date Received :
Estimated Man-hour :
Personnel Assignment
Coordinator :
ME : SE :
PR : EE :
CE : IE :
PE : DA :