You are on page 1of 33

Lecture 05 (b)

Planning the Project

1
THE WORK BREAKDOWN
STRUCTURE

2
2
Simple Approach for Creating the
WBS
• Gather project team
• Provide team members with pad of
sticky-notes
• Team members write down all tasks they
can think of.
• Sticky-notes placed and arranged on wall

3
A Partial WBS (Gozinto Chart) for an Annual
Tribute Dinner Project

4
A Linear Responsibility Chart

5
◆ What is WBS ?
◆ What the WBS is used for ?
◆ Why and how to use the WBS

Examples
– Job creation process
– Group WBS exercise

6
What is WBS:
In planning a project, the manager must
structure the work into small elements. It is
– An outline of the work that is to be done to
complete the project
– A way to organize and control the project
– A method to ensure that the plan is complete
–A basis for all of your formal project
management steps
– Anything not in the WBS is not in the project
7
• WBS Terminology:

– WBS summary tasks


The categories organizing the work.
This is a higher level than the actual work packages

– Code of accounts
Uniquely identifies each element of the WBS.

– Work packages
A deliverable at the lowest level of the WBS.

– WBS dictionary
Includes work package instructions for the assigned team member.

8
• Example
– Landscape project

• 1. Design landscape
• 2. Lawn
• 2.1 Acquire lawn material
• 2.2 Install sprinkler system
• 2.2.1 Identify sprinkler locations
• 2.2.2 Dig trenches
• 2.2.3 Install pipe and hardware
• 2.2.4 Cover sprinkler system
• 2.3 Plant grass

9
• Summary Tasks:

– Lawn
– Install sprinkler system

10
• Code of Accounts:
– 1.
– 2.
– 2.1
– 2.2
– 2.2.1
– 2.2.2
– 2.2.3
– 2.2.4
– 2.3 11
• Work Packages:
– Design Landscape
– Acquire land material
– Install sprinkler system
– Identify sprinkler locations
– Dig trenches
– Install pipe and hardware
– Cover sprinkler system
– Plant grass
12
• Work Packages:
– Represent units of work at a level where work is
performed.

– Clearly distinguish work packages from others.

– Assigned to a functional group.


– Limit the work to be performed to relatively short
periods of time.

13
• Example: Job Creation Process:

– Task description
Hire new employee for Product Specialist position.

– Goals and Objectives:


Fill position by June 15, 2011 and have trained by end of July.

– Job Description:
Provide the job description here with performance criteria.

– Acceptance Criteria:
Mr. Jamal must provide approval of selected candidate before the
job offer is made, and provide acceptance upon completion of
probationary period.

14
• Work packages should be…

– Relatively short in time span.


– Measurable by cost.
– Assignable to an individual, department, or
company.

• Two Approaches:
– Low-level WBS
Created from a perspective of activities or
tasks expressed as action verbs.
15
Example: Low-level WBS (Making Chocolate
cakes)
1. Preparation
1.1 Read recipe
1.2 Check ingredients at home
1.3 Make shopping list
1.4 Go on shopping trip
and so on…
16
– High-level WBS

Based on products, requirements, or deliverables


Created from a perspective of the project scope
definition
Expressed as nouns

Example:
Program: New plant Construction and start up
Project 1: Analytical study
Task 1: Marketing/Production study
Task 2: Cost Effectiveness Analysis

Project 2: Design and Layout


Task 1: Product Processing Sketches
Task 2: Product Processing blueprints

17
• How should I break down the project?
– By geographically separated areas for product
or activities.
– By major chronological time periods
– By structural, process, system, or device
components.
– By “intermediate” deliverables required in the
production of the “end” deliverables.
– By separate areas of responsibility,
departments, or functional areas.
18
• By geographically separated areas for product or activities:

Rock Tour

Europe USA Asia

New York City

October 15, 2011

19
• By structural, process, system, or device components:

Airplane
Pilot
HVAC Engine
Controls
AC
Refrigerant
s
20
21

• By “intermediate” deliverables required in the production of the “end”


deliverables:

Software
Requirements Prototype Products
Interface
Graphics

21
22

22
Action Plan:

In the hierarchical planning system, the objectives are


taken from the project plan. these objectives help in
identifying the set of required activities for the objectives
to be met, a critical part of the action plan. Each activity
has a specific outcome associated with it, and these
activities are further decomposed into sub activities and
sub events, which in turn are further sub divided.

23
Action Plan

Deliverables

Measure
Accomplishment

Key Constraints

Estimated Immediate
Tasks Estimated Duration Assigned to
Resources Predecessors

24
Objective Career Day
Steps Responsibility Time Predecessor Resources
(weeks)
1. Contact Organizations

a. Print Forms Secretary 6 ----------- Print Shop

b. Contact Organizations Program manager 15 1.a Word Processing

c. Collect Display Information Office Manager 4 1.b

d. Gather College Particulars Secretary 4 1.b

e. Print programs Secretary 6 1.d Print Shop

f. Print participant certificates Graduate Assistant 8 -------- Print Shop

2. Banquet and Refreshments

a. Select Guest Speaker Program manager 14 ---------

b. Organize Food Program manager 3 1.B Career

Partial Action Plan for a


c. Organize Refreshments Director 10 1.b Purchasing

College Career Day 25


1 Actual responsibility 2 General Supervision 3 Must be Considered
4 May be Consulted 5 Must be notified 6 Final Approval 26
Simplified Linear Responsibility Chart
MULTIDISCIPLINARY TEAMS
-- BALANCING PLEASURE AND
PAIN

27
Design Structure Matrix (DSM)
• Traditional project management tools tend
to focus on which tasks have to be
completed in order for other to start.

• Another important question is what


information is needed from other tasks to
complete another task.

28
Example DSM for Project with Six
Activities

29
Modified DSM to Show Activities to Be
Completed Concurrently

30
Empowerment and Work Teams
• Participatory management.
• Success of empowered teams depends
heavily on how team program
implemented.

31
Advantages of Empowerment
• High quality solutions.
• Avoid micromanagement.
• Team has accountability for part of project
deliverable.
• Synergistic solutions.
• Tool for timely evaluation and feedback.

32
Copyright
Copyright © 2005 John Wiley & Sons, Inc.
All rights reserved. Reproduction or translation of this work beyond that
permitted in Section 117 of the 1976 United States Copyright Act
without express permission of the copyright owner is unlawful.
Request for further information should be addressed to the
Permissions Department, John Wiley & Sons, Inc. The purchaser
may make back-up copies for his/her own use only and not for
distribution or resale. The Publisher assumes no responsibility for
errors, omissions, or damages, caused by the use of these programs
or from the use of the information herein.

33

You might also like