You are on page 1of 9

Risk management

Mobile cranes
overturning on
construction sites
A guide to loss prevention
Most incidents are as a result of
inadequate planning, unclear
responsibilities or unsafe use.

Each year, a number of mobile Common terms and definitions


cranes overturn on construction
sites causing serious accidents. Mobile crane: a self-powered crane Crane operator: person who is
This often involves personal with a boom, which may be fitted on operating the crane for the purpose
injury, significant property a mast (tower). It is capable of of positioning loads or erection of
damage and potential business travelling laden or unladen, without the crane.
interruption claims. the need for fixed runways. It relies
Slinger: person responsible for
on gravity for stability, with the
attaching and detaching the load to
This guidance document aims to chassis of the crane not having any
and from the crane and for the correct
provide supporting information capability to carry goods.
selection and use of lifting accessories.
to assist in preventing the
Crawler crane: an off-road mobile They are also responsible for initiating
overturning of mobile cranes.
crane which travels on site. They are the movement of the load.
There are different types of
mounted on a tracked chassis. Lifting
mobile crane in which the specific Signaller: person responsible for
capacities are typically greater than for
operating instructions for a directing the crane driver to ensure
mobile cranes and movement around
particular manufacturer and safe movement of the crane and load.
site is possible fully rigged. Crawler
model of crane should be referred cranes are generally employed for Working platform: temporary
to. This guide does not attempt longer durations and for undertaking geotechnical structure providing
to cover the design of cranes, routine lifts and movements over a stable working surface for mobile
nor does it cover all aspects of relatively short distances. cranes, piling rigs and other heavy
lifting operations. construction equipment.
Lift plan: The appointed person who
Further industry best practice is to plan the lift should have adequate Working Platform Certificate:
guidance is included towards the practical and theoretical knowledge a certificate which confirms the
end of this guidance document and experience. The plan will address working platform has been properly
and the reader is strongly the risks highlighted within the risk constructed in accordance with the
recommended to refer to BS 7121 assessment, resources required to design, and that it will be adequately
and the guide C703 when complete the lift, and the procedures maintained to ensure its ongoing
planning mobile crane operations. and responsibilities needed to ensure integrity. The certificate requires the
the safety of the lifting operation. signature of the main contractor on
The hazards which increase site and must be handed to the
Permit to Lift: a formal process
the risk of an overturning Appointed Person before lifting work
recording checks and approvals prior
occurrence are due to many commences. The certificate introduces
to confirming a lift may proceed.
various factors. These include; a system for defining specific
Appointed Person: a key person with responsibilities, increasing safety
− Unstable working platforms. the training, practical and theoretical awareness and highlighting the
− Subsurface voids. knowledge and experience required to importance of maintaining the
− High winds. plan and manage a lifting operation. platform in good condition.
− Poor level of routine
Crane supervisor: Appointed Person
maintenance.
who controls the lifting operation and
− Inexperienced crane operators
ensures that it is carried out in
and/or supervisors. accordance with the Appointed
− Excessive loads. Person’s safe system of work.
− Underrated crane capacity
− Poor crane operation such as use Crane coordinator: person who plans
of outriggers and bearing plates. and directs the sequence of operations
of cranes to ensure that they do not
− Poor management and planning
collide with other cranes, loads and
of the lifting operation.
other equipment.

2 Mobile cranes overturning on construction sites


Hirer and contractor responsibilities

Hired Crane (hired and managed) Contract Lift (fully contracted)

The employing organisation (hirer) is responsible for: The employing organisation (hirer) is responsible for:
− Carrying out all work in accordance with BS7121 and − Allowing access to site to site for a full survey to
Lifting Operations and Lifting Equipment Regulations be carried out for the risk assessment and method
98 (LOLER). statement(s).
− The safety and welfare of crane operator. − Informing crane owner of hazards which are not evident
− The safe operation of the crane. during site visit.
− Supplying a qualified and competent Appointed Person. − Supplying accurate information of the load to be lifted.
− Providing a qualified and competent slinger / signaller − Provide information of the load(s) to be lifted.
and crane supervisor.
− Planning the lift and operate a safe system of work.
− Producing risk assessment and method statement(s).
− Ensuring that the crane hired is of a suitable type
and capacity.
− Ensuring suitability of working platform.
− Verifying the credentials of the crane hire company
and certification supplied.

The crane owner (contractor) is responsible for: The crane owner (contractor) is responsible for:
− Providing a suitable crane that is properly maintained, − Providing a suitable crane that is properly maintained,
thoroughly examined, tested and certified. thoroughly examined, tested and certified.
− Providing a CPCS qualified competent operator. − Providing a CPCS qualified Appointed Person.
− Providing a qualified and competent slinger / signaller
and crane supervisor.
− Providing a CPCS qualified competent operator.
− Providing risk assessment and method statement.
− Organising and controlling the lifting operation.
− Planning the lift and operation of the safe system
of work.
− Carry out all work in accordance with BS7121 and Lifting
Operations and Lifting Equipment Regulations 98
(LOLER)

Mobile cranes overturning on construction sites 3


Key components in preventing the
overturning of mobile cranes include:

Management and planning operators should hold a valid and within Lifting Operations and
The root cause of many overturning CPCS card. Lifting Equipment Regulations and
occurrences is due to poor Provision and Use of Work Equipment
3. Appointed Person
management and planning of the lift. Regulations.
The Appointed Person has overall
The following elements are vital to
5. Contract lift vs crane hire
ensuring a lift is carried out safely and control of the lifting operation. Their
An organisation that requires a load
without incident. responsibilities include:
to be moved, and does not have its
1. Safe system of work − Planning of the lifting operation own craneage, has two options. These
A safe system of work should be (including approval of risk are; crane hire or the employment
established and maintained for every assessments, lift categorisations of a contractor to carry out the lifting
crane installation operation and lifting and method statements), crane operation (Contract lift). If an individual
operation. A safe system of work and lifting accessory selection, or organisation does not have expertise
should include: instruction, supervision and in lifting operations, they should not
consulting with responsible bodies. hire cranes but should opt for the
− Planning of the lifting operation − Ensuring the outcomes of planning contract lift option. Insurance
including preparation of the lift process are recorded in the lift plan. arrangements should be clarified.
plan. Selection, provision and use − Ensuring adequate pre-operational A summary of the options can be found
of a suitable crane(s) and checks, intermediate inspections, in the table on page 3.
work equipment. maintenance and thorough
− Any necessary preparation of a site 6. Complexity of lift
examination of equipment is
for the lifting operation which The duties and extent of planning
completed.
may include entry / exit routes for involved for a lift will vary depending on
− Taking responsibility for the
the crane(s). the complexity.
organisation and control of the lifting
− Any rigging / derigging or setting operation. Lifts are categorised as follows;
up of crane, Inspection, maintenance, − Ensuring the crane supervisor and
thorough examination and testing − Basic,
other members of the lifting team are
of the crane(s) equipment ensuring − Intermediate or
fully briefed on the contents, scope
reports are available. − Complex
and limits of the method statement.
− The provision of properly trained and The categorisation is a function of the
competent personnel who have been Being familiar with the relevant parts level of hazards present within the area
made aware of their responsibilities of the project health and safety plan of the crane operation, which are
under the Health and Safety at Work where the lifting operation is being established through the risk
etc. Act 1974. carried out on a site where the assessment process. Detailed guidance
− Adequate supervision by properly Construction (Design and is further provided within BS 7121-1.
trained competent personnel having Management) Regulations 2015 apply.
Some of the duties, but not the 7. Risk assessment and method
the necessary authority.
responsibilities, may be delegated for statement
− Prevention of unauthorised
simple lifts. The Appointed Person An essential element of any crane
movement or use at all times.
should consult with other experts operation is the production of a risk
− Coordination of crane movements to
including temporary works engineers assessment and method statement.
avoid collisions between cranes and The risk assessment should be
and crane suppliers.
other type of plant or structures. carried out by the Appointed Person
− The safety of persons not involved in 4. Crane maintenance and identify the hazards and risks
the installation or lifting operation The crane(s) should be in a satisfactory associated with the lifting operation.
and the need for the operator, unless Reference should be made to the
condition and operating order at all
in imminent danger, to remain in overall site risk assessments included
times. Planned maintenance should be
control of the crane throughout the in the CDM Construction Phase
undertaken in line with manufacturers
lifting operation. Plan CIC80. The Appointed Person
instructions and thorough
2. Selection and duties of personnel examinations completed. The report of should ensure that a full method
All those involved in a lifting operation thorough examination, test certificates statement is prepared, detailing
must be competent, adequately and documentation in place should be the safe system of work and control
trained and aware of their duties which available for review. Detailed measures for the lifting operation.
is detailed in BS7121-1. All crane requirements are included in BS7121 A ‘Permit to Lift’ is a useful

4 Mobile cranes overturning on construction sites


mechanism to ensure all pre-lift geotechnical engineer is required the strength of the ground where
checks are undertaken. before setting up in such a location. ground conditions are poor or where
10. Checklists there is a lack of data on the nature
8. Crane selection and access
The management, planning and of the subsoil.
The choice of a suitable mobile
crane is governed by a number of execution of a crane lift has to take Typical categories include:
factors including the characteristics into account many aspects. It is
− Greenfield sites - particular problem
of the load to be lifted (weight and recommended that the use of areas are adjacent to rivers, estuaries
dimensions), radii, heights of lifts, checklists and pro-formas are and floodplains where soft alluvial
areas of movement, frequency employed to ensure all aspects are deposits and high groundwater
and types of lifting operations, addressed. These may include (but tables can be expected.
length of time on site, ground not limited to) key elements of the − Beaches - low sand density and a
conditions and space available safe system of work, the load and the variable groundwater level can
for access, erection, travelling, lift, the location, specifying and create difficult conditions.
operation and dismantling. operating teams, the crane, the lifting − Brownfield sites - unknown previous
gear and any temporary works. Sample use including basements, storage
9. Crane Siting
checklists are included in C703. tanks, poorly-filled open pits and
The siting of the crane should take
into account the crane standing and The mechanism of overturning is poorly-compacted fill, etc.
support conditions, the effect of wind often as a result of a failure of the − Paved areas - tarmacked or paved
and the adequacy of access to allow ground or supporting structure areas can appear deceptively strong
the placing or erection of the crane beneath the crane or the crane but lead to outriggers perforating
in its working position. This will also outriggers. The following aspects through weak surfacing. Lightly-
include dismantling and removing are key to ensuring an adequate trafficked car parks, estate roads
from site. foundation is provided. and footpaths should be scrutinised.
− Town centre sites – consider
Particular care needs to be taken when 11. Site categories and underground hazards including
siting mobile cranes in or near the high underground hazards services, drainage pipes, buried
risk areas, for instance at the edge of Sites can be split into a number of cables, basements and tunnels
open trenches and excavations as categories to highlight the most beneath paved areas. This can lead
these are likely to collapse without likely hazards that need to be to outriggers perforating in to the
warning (see C703). An engineering considered and risk assessed. More void below.
assessment by a competent attention is required to establish
12. Ground investigation Excavations, trenches, or other holes References and guidance:
– BS 7121-1:2016 – Code of practice for safe use of
Before a crane arrives on site, existing should be suitably backfilled to avoid cranes (www.bsigroup.com)
information on the nature of the creating soft spots. The edge of the – BS 7121-3:2017+A1:2019 – Mobile cranes
– CIRIA Publication C703:2003 – Crane stability on
soils should have been investigated platform needs to be clearly defined site (www.ciria.org)
Reference should be made to any and ground preparation should extend – BRE Report 470 – Working platforms for tracked
existing site ground reports, and beyond the working area required. plant (www.brebookshop.com)
– CPA/Crane Interest Group – Best Practice Guide
particular attention paid to the
16. Working Platform Certificate for Risk Assessment and Method Statement for a
character of the ground at shallow Contract Lift: 2018 (www.cpa.uk.net)
Consideration should be given to – Working Platform Certificate (www.fps.org.uk)
depths where the mobile crane(s)
using a ‘Working Platform Certificate’
will be sited. Disclaimer: The guidance in this document refers to
to ensure that the correct procedures industry best practice loss control advice. Adoption of
13. Ground bearing capacity have been followed, the ground is the advice contained within this document does not
imply compliance with industry, statutory or HSBEI
An assessment of the ground bearing adequate to support crane activity guidelines, nor does it guarantee that related losses
capacity is required to determine and that there are no irregularities will not occur.

the size and type of crane foundation that could result in local subsidence
required. This can be calculated with or toppling. Further detailed guidance
reference to the ground investigation on working platforms for tracked
reports and should be carried out by plant and a sample working platform
a competent geotechnical engineer. certificate is available from the
It should be noted that the presence Federation of Piling Specialists.
of water tends to reduce the strength
The issue of a ‘Working Platform
of soils and can lead to a reduced
Certificate’ should be an aspect of
capacity, since the initial bearing
the ‘Permit to Lift’.
capacity assessment.
17. Outrigger foundations
14. Settlement
The crane outriggers should be
Settlement must be kept to a
extended and the tyres lifted clear of
minimum to avoid the slew ring being
the ground.
out of the horizontal resulting
in the jib not being in a vertical plane. The outrigger feet are relatively small
This can result in side loads on the and transfer high pressures on the
jib and possible failure of the jib. ground. The pressure can be reduced
by the provision of suitable spreader
Excessive settlement can also attract
mats which, depending on the
additional loading onto the outriggers
allowable bearing pressure of the
or tracks that is settling. Level
subsoil, could consist of timber mats,
indicators and inclinometers should
timber and ply plates, proprietary
be utilised. If settlement occurs,
mats, steel grillages, concrete pads
then the foundation will need to
or piles (for high loads in week soil
be reassessed.
conditions). Calculations will be
15. Working platforms and design required and the Appointed Person
A working platform may be required should consult with the temporary
to provide a designated area of the works design engineer and crane
site over which mobile and crawler supplier. Outriggers should always
cranes can travel during their delivery be positioned central to the spreader
and movement around the site, lifting mats, which should be in contact
operations and removal. The design, with the ground over its entire
installation, maintenance and repair surface area.
of the working platform should be the
A useful best practice guide and
responsibility of the main contractor.
pro-formas on producing a risk
The appointed person should consult assessment and method statement
with a temporary works engineer on for a contract lift is available from
the detailed requirements. The the CPA Crane Interest Group
platform should be free-draining to (www.cpa.uk.net).
prevent the build-up of water. In
certain cases, separation/filter
membranes may be required beneath
the platform. Appropriate factors of
safety should be employed in the
design and regular checks undertaken
to ensure the platform is not disturbed
by other construction activity.

6 Mobile cranes overturning on construction sites


Case studies
Case study 1
Two construction companies were
prosecuted by the HSE following the
overturning of a 35-tonne truck-
mounted telescopic crane on site.
The collapse occurred after one of the
outriggers, which supported the crane,
sank into the ground.
The crane driver was forced to leap
to safety and the 5.7-tonne beam that
was being lifted into place narrowly
missed two employees as it fell. The
principal contractor and crane operator
were both fined and ordered to pay
substantial costs.
The incident could have been avoided
had the planning and supervision of the
lifting operation not been so deficient.
The crane overturned because it was
© Manchester Evening News Syndication
being operated, with the knowledge of
both companies, in a part of the site spread of the crane. Clear warnings site. The risk assessments which had
that had not been prepared for such were ignored in the run-up to the been produced were inadequate as they
activities. The roadway was not wide incident about the ground bearing only considered use at a completely
enough to accommodate the outrigger capacity for the use of cranes on the different part of the site.

Case study 2
The principal contractor and crane The extended 50-metre jib fell across but confusion arose as to whether the
hire company were ordered to pay the site, narrowly missing workers and job had been set up on a ‘crane-hire’
a substantial fine and costs after a a nearby busy road. only or ‘contract-lift’ basis (where
serious communications failure led to The 80-tonne crane was supplied and planning of the lifting operation is
a mobile crane toppling over on site. operated by the crane hire company included).
This meant both firms neglected the
planning of the lift and led to vital roles
for the job not being assigned.
A competent person should have been
appointed to plan the lift, either
provided by the crane hire company if
it was a contract hire arrangement or
by the hirer if it was a hire-only
agreement. The crane hire company
should have ensured this happened
when it set up the contract.
Important information — including the
weights being lifted and ground
conditions — were not passed on to the
workers involved. The crane was
overloaded and was being operated on
poor ground. A larger crane and ground
mats to spread the load of the crane‘s
outriggers should have been used.
© Health & Safety Executive

Mobile cranes overturning on construction sites 7


Hazards and mitigation
Overturning hazard Controls to mitigate the risk

Failure of the ground


Unstable/uncompacted working Undertake a suitable and sufficient site investigation to determine the nature of the
surface ground conditions. Ensure a suitably designed and compacted working platform is
installed and maintained.
Underground hazards including Obtain existing services drawings and undertake trial pits, probing and cable
services, drainage pipes, buried cables, detection to identify all buried services and voids.
basements and tunnels, etc. beneath
paved areas
Open excavations and slopes Ensure crane is set up a suitable distance from the edge of open
excavations and slopes.
Poor ground conditions – adjacent to Undertake a suitable and sufficient site investigation to determine the nature of
rivers, estuaries, marshes, floodplains, the ground conditions. Monitor groundwater and soil saturation levels. Ensure a
beaches, landfill sites and areas with suitably designed and compacted working platform is installed and maintained.
a high groundwater level Use suitable bearing plates beneath outriggers.

Management and planning failures


Inexperienced supervisors and Ensure only competent, trained persons are employed (see BS 7121-1). Consider a
crane operators Contract Lift if competence of supervisors is in doubt.
Unclear roles and responsibilities Ensure key positions are established and individuals appointed detailing their roles
and responsibilities.
Movement or set-up in unauthorised Provide a sketch illustrating the permissible set-up location(s) and allowable access
locations route(s). Prevent access to unsafe areas with barriers.
Uncontrolled lifting operations Ensure all lifting operations are included within a Lift Plan, including a risk
assessment, a method statement and a ‘Permit to Lift’.

Incorrect factor of safety in design Ensure a competent designer is employed and suitable Factor of Safety (FoS) used.
of working platform Clarify if the design criterion refers to ultimate bearing capacity (ground failure) or
allowable bearing pressure (including an FoS). See C703 for guidance.

Overloading
Load too heavy Ensure the load to be lifted is not greater than permitted in the lift plan. The rated
capacity indicator/limiter should be maintained in good working order.
High wind loading Establish site wind speed limits (red/amber/green). Use an anemometer to monitor
in-service wind speeds. Monitor weather forecasts. Adhere to manufacturers
tolerances for wind speed.
Lifting radius too far Stay within the agreed lifting location and radius. Avoid swinging of loads or
travelling with high loads.

Mechanical failure
Poorly maintained crane Ensure crane is regularly maintained in accordance with manufacturers
instructions and in line with the Lifting Operations and Lifting Equipment
Regulations (LOLER) and Provision and Use of Work Equipment Regulations
(PUWER) requirements

8 Mobile cranes overturning on construction sites


© 2022 HSB Engineering Insurance Limited and HSB Engineering Insurance Services Limited. All rights reserved.

HSBEI-1307-0622-3

Picture credits: Getty Images

HSB Engineering Insurance Limited, registered in England and Wales: 02396114, Chancery Place, 50 Brown Street, Manchester M2 2JT. Registered as a branch in
Ireland: 906020, 28 Windsor Place, Lower Pembroke Street, Dublin 2. HSB Engineering Insurance Limited is authorised by the Prudential Regulation Authority and
regulated by the Financial Conduct Authority and the Prudential Regulation Authority in the United Kingdom, and is authorised and regulated by the Central Bank of
Ireland as a third country branch in the Republic of Ireland.

HSB Engineering Insurance Services Limited, registered in England and Wales: 03010292, Chancery Place, 50 Brown Street, Manchester M2 2JT.
Registered as a branch in Ireland: 906105, 28 Windsor Place, Lower Pembroke Street, Dublin 2.

www.hsbeil.com

You might also like