You are on page 1of 2

PERHITUNGAN PEKERJAAN DRAINASE BETON

DUKUH REMBUL, DESA TUMBREP, KECAMATAN BANDAR


No. ITEM PEKERJAAN PERHITUNGAN VOLUME KETERANGAN
1. DRAINASE BETON SAMPING KIRI JALAN 31,71 m3 Cor Beton
POTONGAN 1 - 1 I - PEKERJAAN DRAINASE BETON SAMPING KIRI JALAN L = 106.50 M (POTONGAN 1 - 1)
1. V.1 Dinding Kiri Drainase Beton
Panjang = 106,50 m
Tebal = 0,12 m
Tinggi = 0,40 m
Volume = 106,50 x 0,12 x 0,40 = 5,11 m3
2. V.2 Dinding Kanan Drainase Beton
Panjang = 106,50 m
Tebal = 0,12 m
Tinggi = 0,40 m
Volume = 106,50 x 0,12 x 0,40 = 5,11 m3
3. V.3 Lantai Drainase Beton
Panjang = 106,50 m
Tebal = 0,10 m
Lebar = 0,54 m
Volume = 106,50 x 0,10 x 0,54 = 5,75 m3

2. DRAINASE BETON SAMPING KANAN JALAN


POTONGAN 2 - 2 II - PEKERJAAN DRAINASE BETON SAMPING KANAN JALAN L = 104.90 M (POTONGAN 2 - 2)
1. V.1 Dinding Kiri Drainase Beton
Panjang = 104,90 m
Tebal = 0,12 m
Tinggi = 0,40 m
Volume = 104,90 x 0,12 x 0,40 = 5,04 m3
2. V.2 Dinding Kanan Drainase Beton
Panjang = 104,90 m
Tebal = 0,12 m
Tinggi = 0,40 m
Volume = 104,90 x 0,12 x 0,40 = 5,04 m3
PERHITUNGAN PEKERJAAN DRAINASE BETON
DUKUH REMBUL, DESA TUMBREP, KECAMATAN BANDAR
No. ITEM PEKERJAAN PERHITUNGAN VOLUME KETERANGAN
3. V.3 Lantai Drainase Beton
Panjang = 104,90 m
Tebal = 0,10 m
Lebar = 0,54 m
Volume = 104,90 x 0,10 x 0,54 = 5,66 m3