ABAP EFFORTS ESTIMATION on 1

OBJECTS

Specific to CR 7000006652 Budget Consumption Report by AC CC Proj view

1 Selection Screen as per the given logic 16 Hrs


2 Radio buttons 8 Hrs
3 Drilldown logic(F4 Search Help) 24 Hrs
Logic Implementation(required Functional
consultant view) includes queries, structures, 30Hrs minimum and increase depends on
4 Internal tables, and validations complexity
Implement ALV Tree Reports including field
5 catalog 40 Hrs
6 user testing and TOC to test on QAS 40 Hrs
7 missilinious 16 Hrs

Detailed Summary :

This report improves users' productivity by


Funds Summary Report(FSR) Which will
help the units in tracking of budget
utilizations.
We analysing MHA and develop the logic for
1 Object Description HTX.
Provide a summary overview and drilldown
of the budget utilization by account, cost
center or project. For projects, for Client,
MIDP projects will be further broken down by
output code. For FGH, all projects will be
2 Scope broken down by output code.
For select overview values, a drilldown
report is enabled. This is to give more details
on the transactions and documents that
comprise the budget utilisation.
The overview as well as the individual
drilldowns will be available for download to
excel for further processing by users, when
required.

3 Technichal Specifications

Type of Development Report

Name of Report Budget Report


ABAP EFFORTS ESTIMATION on 2
OBJECTS

Transaction Name Client: ZSPFITC0035

FGH: ZSPFITCXXXX TBD

Program Name Client: ZSPFITC0035

FGH: ZSPFITCXXXX TBD

Report Output ALV Tree / ALV Grid


include Programs, Tables, Structures, message
Other Chaild Objects classes, Logical Databases etc.,
FMBL, FMIOI, FMIFIT, EKPO, EKKO, EKBE,RBKP,
System Tables RBCO, BSEG, VBSEGK

Input Parameters Fiscal Year-GJAHR

Fund Center FMFCTR-FICTR

Commitment Item FMCI-FIPEX

Projects DP / MIDP

For FGH

Company Code BUKRS

Fiscal Year-GJAHR

Fund Center FMFCTR-FICTR

Commitment Item FMCI-FIPEX

Output Code PRPS-US03

4 Complexity Assesment
1. Create selection screen for User interface for
5 Task Breakdown input.
2.Create Include Programs to subroutines for
easy understanding
3.write queries to fetch data from DDIC tables to
Buffer

4. applying validations for accurate output


5. create ALV Tree output and easy access to
download in speadsheet
6 Hourly Estimation Minimum 93 hrs required for Quality output
ABAP EFFORTS ESTIMATION on 3
OBJECTS

Include Contingency factor Need extra 10 Hrs


7 Contingency Buffer.
8 Total Estimated Hours 103 Hrs.

9 Assumptions
Output totally depends on input provided by
customer, functional consultant and Devloper.
10 Dependencies Regular rapo required of these 3 members
Amendments of process will increase timeline,
So before start the process, conclude the all
11 RISKS proper parameters.
Once Object Starts, Regular track provided based
12 Tracking on priority.

Note :

Remember that SAP ABAP development estimates can vary widely based on the specific project, the
team's expertise, and the complexity of the task. It's essential to document the estimation process
transparently and communicate any changes to stakeholders as the project progresses. Additionally,
using project management tools and methodologies, such as SAP Solution Manager or Agile practices,
can help in managing and tracking development efforts effectively