Professional Documents
Culture Documents
SS003 - Drywall Partitions
SS003 - Drywall Partitions
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
SECTION 3
3.1 GENERAL
The partitions shall generally be 150mm thick cavity type drywall partitions and shall
be constructed full height from floor level up soffit of the concrete slab above or to
200mm above suspended ceiling unless otherwise stated. The partitions shall be
installed on 100mm (H) concrete dike depth aligning with proposed partition depths
as included in details particularly to all ground structures and/ or adjacent to internal
space which potentially exposed to water ingress or moisture from floor slabs.
The construction of the partitions shall be made up of galvanised mild steel vertical
and horizontal studs spaces internally at 600mm centres erected on steel floor
tracks with 13mm gypsum plaster boards cladding on both faces of the partition.
The bottom track is made up of a steel floor tract and vinyl coving skirting.
The applied finish on the exposed surfaces of the gypsum plaster board shall be
selected and approved by the Architect and the Architect reserves the right to use
on or combination of the finishes at the rates priced for.
The internal hollow core of the partitions shall be filled up with min. 50mm thick
rockwool for 100mm thick partition or 75mm thick for 150mm thick partition as
described in the drawing.
The Contractor shall also guarantee that the demountable partition system including
doors shall achieve a sound absorption factor of at least 50 decibels.
The partition shall incorporate skirting, trim, fixing clip cover and adjusting pieces
and includes the provision for jointing to the floor, ceiling, column or other walls and
to form door openings complete with solid timber door jambs, etc.
The Contractor must apply the relevant test certificate to substantiate that the
partition is non-combustible or other requirements as specified in this document.
The Contractor must provide ten (10) years of indemnity to the dry wall partitions
against defects, defects in installation and any related components.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/2
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
All drywall partitions (100%), by cost and surface area shall meet the general
emission evaluation or inherently non-emitting source criteria as required for the
LEED Gold rating. Documents must be provided to support the claim.
For at least 90% of the regularly occupied floor area, meet or exceed the thresholds
for area-weighted average surface reflectance i.e. 65% for walls.
3.2 STANDARDS
Unless otherwise agreed by Architect, ensure all of the works comply with the
relevant requirements of the Standards and Codes listed below or referenced in the
body of the Specification. Alternative Standards and Codes may be submitted to the
Architect provided it can be demonstrated that the alternative Standards and Codes
comply with the requirements of the standards specified. All standards and Codes
quoted are the current version, unless specific year references are noted.
Singapore Standards
Other Standards
BS 7364 Galvanised steel studs and channels for stud and sheet
partitions and linings using screw fixed plasterboard
BS 8212 Code of practice for dry lining and partitioning using gypsum
plasterboard
AS/NZS 1866 Aluminium and aluminium alloys - Extruded rod, bar, solid and
hollow shapes
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/3
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
AS/NZS ISO 717.1 Acoustics - Rating of sound insulation in buildings and of building
elements Airborne sound insulation
3.3 DEFINITIONS
High purity synthetic gypsum (HPSG) is fire resistant and moisture resistant
plasterboard consists of gypsum plaster core with vermiculite, fibre glass, silicon and
fly ash additives. Heavy impact board shall be 100% asbestos free, fire reinforced
boards having a density of not less than 925 kg/m3 and approved by Fire Safety
Bureau to be non-combustible/limited combustibility in accordance with the British
Standard 476 Part 22:1987.
The construction of the drywall solid partition shall be tested in accordance with BS
476.
For Conference Rooms & Meeting Rooms: STC shall achieve minimum acoustic
of STC53 on all walls incl. walls adjoining private offices and/ or any other room
space for teleconference/ meeting room use.
For Genset Rooms & enclosure: STC shall achieve minimum acoustic of STC64
on all walls incl. walls adjoining Genset Rooms and/ or any other room space.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/4
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
a) ASTM C1185
b) BS EN 1373
c) ASTM C109
a) General
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/5
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
One (1) layer of 15mm thick fire-rated gypsum fiber panel clad on both sides of
75mm studs system or double 50mm studs system to form an overall wall
thickness of approximately 105-135mm (without wall finishes). Min. acoustic of
STC50 shall be achieved without insulation. Cavity shall be filled with specified
rockwool insulation for enhanced STC for full drywall system.
Gyproc FireWall® 106mm comprising of single layer Gyproc FireLine® 15mm laid
staggered to opposite layer and screw-fixed at max. 300mm centres to both sides
of framing system formed by GypFrame® C-Stud 74mm (BMT=0.55mm,
Zincalume Steel) spaced at nominal 610mm centres and GypFrame® U-Track
76mm (BMT=0.55mm, Zincalume Steel); all joints are reinforced with Gyproc
Paper Tape and finished with ProTop® All Purpose Ready Mixed Joint Compound
for a seamless surface.
Overall wall system thickness formed of approximately min. 106mm (without wall
finishes).
Min. acoustic of STC50 shall be achieved without insulation. Cavity shall be filled
with specified rockwool insulation for enhanced STC for full drywall system. All
gaps to be back-filled with Gyproc ProTop® Joint Compound, optionally it may be
sealed with fire rated sealant. Boards must be staggered and installed as per
specialist’s recommendation details.
General: Alternative drywall system & built-ups may be submitted to the Architect
provided it can be demonstrated that the alternative proposal complies with the
requirements of the standards specified as well as relevant local authority Fire
Code requirements and FM Global Standards.
Two (2) layers of 12mm thick fire-rated gypsum FireShield on clad both sides of
75mm studs system or double 50mm studs system to form an overall wall
thickness of approximately 123-153mm (without wall finishes). Min. acoustic of
STC50 shall be achieved without insulation. Cavity shall be filled with specified
rockwool insulation for enhanced STC for full drywall system.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/6
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
Gyproc FireWall® 136mm comprising of double layer Gyproc FireLine® 15mm laid
staggered to opposite layer and screw-fixed at max. 300mm centres to both sides
of framing system formed by GypFrame® C-Stud 74mm (BMT=0.55mm,
Zincalume Steel) spaced at nominal 610mm centres and GypFrame® U-Track
76mm (BMT=0.55mm, Zincalume Steel); All joints are reinforced with Gyproc
Paper Tape and finished with ProTop® All Purpose Ready Mixed Joint Compound
for a seamless surface.
Overall wall system thickness formed of approximately min. 136mm (without wall
finishes).
Min. acoustic of STC50 shall be achieved without insulation. Cavity shall be filled
with specified rockwool insulation for enhanced STC for full drywall system. All
gaps to be back-filled with Gyproc ProTop® Joint Compound, optionally it may be
sealed with fire rated sealant. Boards must be staggered and installed as per
specialist’s recommendation details.
General: Alternative drywall system & built-ups may be submitted to the Architect
provided it can be demonstrated that the alternative proposal complies with the
requirements of the standards specified as well as relevant local authority Fire
Code requirements and FM Global Standards.
Gyproc FireWall® 190mm comprising of triple layer Gyproc DuraLine® Plus 19mm
laid staggered to opposite layer and screw-fixed at max. 300mm centres to both
sides of framing system formed by GypFrame® C-Stud 74mm (BMT=0.55mm,
Zincalume Steel) spaced at nominal 610mm centres and GypFrame® U-Track
76mm (BMT=0.55mm, Zincalume Steel); all joints are reinforced with Gyproc
Paper Tape and finished with ProTop® All Purpose Ready Mixed Joint Compound
for a seamless surface.
Min. acoustic of STC55 shall be achieved without insulation. Cavity shall be filled
with specified rockwool insulation for enhanced STC for full drywall system. All
gaps to be back-filled with Gyproc ProTop® Joint Compound, optionally it may be
sealed with fire rated sealant. Boards must be staggered and installed as per
specialist’s recommendation details.
Alternative drywall system & built-ups may be submitted to the Architect provided it
can be demonstrated that the alternative proposal complies with the requirements
of the standards specified as well as relevant local authority Fire Code
requirements and FM Global Standards.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/7
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
Unless otherwise specified, the drywall framing shall be profiled steel studs &
runners. The studs shall have minimum 90mm deep of 22 gauge thick with
proprietary screw of lengths greater than 30 mm. The runners shall also be 90mm
deep of 22 gauge thick. Self-bracket bearing and all necessary accessories,
method of fixing and installation shall be strictly in accordance with manufacturer’s
written instruction.
Install metal stud wall framing in strict accordance with manufacturer’s instructions:
• Attach top tracks and bottom runners to floor structure and structural elements
with suitable fasteners located 50mm from each end and spaced at maximum
300mm centres. Provide continuous sealant joint at the base track.
• Position studs vertically, engaging top tracks and bottom runners, spaced at
maximum 600mm on centre. At splice to bottom runners, place metal stud
section over splice between adjacent vertical studs. Secure splice piece to
each runner with 4 framing screws on each side of runners. Place studs in
direct contact with all doors frame jambs, abutting partitions, partition corners
and existing construction elements.
• Provide horizontal bridging for all stud partitions over 2400mm high at 1200mm
on centre maximum with 38mm rolled channels through studs and screw
attached in place. Lap channels by nesting one inside the other at a depth of at
least 200mm and secure with end angle clips.
• Provide all braced framing of steel stud framing as detailed in shop drawings.
Use only mechanical attachment, or welding as required per AISI Specification.
• Partition above ceiling shall allow for cut out opening service ducts, trunking
and cable trays. The Contractor shall co-ordinate with all sub-contractors for
the exact size and location of the openings. Any gaps around any pipes, ducts,
through the partition shall be properly sealed with proprietary fire and smoke
stop system.
• If full height partition had to be terminated below ventilation duct routed parallel
to the partition, the stud of the partition shall be secured to the support frame of
the duct. In such cases, space between the duct and reinforced concrete soffit
need not be sealed up.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/8
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
• Steel stud framing system shall require to be provided taking into consideration
of load/ weight of proposed door, glazing, mesh panels, glass partition
whichever openings provision deem required & specified in drawings &
schedule.
• Steel stud framing system shall also require to be provided taking into
consideration of load/ weight of media walls, TV/ monitor screens, glassboards,
cabinets, whichever ID components provision & installation deem required &
specified in drawings & schedule.
i) Gyproc WallBoard
- Gyproc FireLine is a plasterboard that contains glass fibre and other additives
for extra fire protection
- Thickness: Min. 12.5mm
- Width: 900-1200mm
- Length: 1800-3000mm
- Weight (per m²): 9.7-11.4kg
- Standards & Certification: BS EN 520 – Type F
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/9
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
- Gyproc CoreBoard is 19mm thick, moitsture and fire resistant board. Used as
main board in ShaftWall system to provide fire protection with temporary
moisture progtection during construction.
- Thickness: 19mm
- Width: 598mm
- Length: 3000mm
- Weight (per m²): 16kg
- Standards & Certification: BS EN 520 – Type D, F, H1
v) Gyproc Habito®
The column & beam encasement shall be in GypLyner ENCASE Steel Encasement
(protection to 4 sides for steel columns, 3 sides for steel beams beam) or
approved equivalent system.
The system comprises Gypframe GL10 GypLyner Steel Framing Clips located on
steel sections at 800mm centres to support Gypframe GL1 Lining Channels.
Gyproc FireLine Lining (or approved equivalent) selection & thickness shall refer to
the Gypsum Section Factor A/V (HP/A) to achieve period of fire resistance
required based on specified BOD Fire rating series and/ or local AHJ requirements
whichever more stringent.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/10
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
The lining material shall be 13 mm thick, high abuse resistance, Gyproc FireLine
or approved equivalent. The characteristic of the fiber-reinforced gypsum panel
shall be follows:
• Apply gypsum fiber board panel perpendicular to stud or framing with all
attachment to firm bearing surfaces over framing members. Install panels
in such a manner that panel joints do not align with edge of opening.
Staggered joints on the opposite side of panel. Tightly butt tapered end
board edge joints.
• Treat cut edges, holes, fastener heads, and joints, including those at angle
intersections with partition paper tapes and All-Purpose Ready-mixed joint
compound.
• Place gypsum fibre board panels over supporting framing members with
panel ends aligning and parallel with framing members.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/11
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
j) Insulation
• All partition shall be filled with termite resistant Acoustical Fire Slab
100kg/m3 density, min. 50mm thick rockwool slab, to give an overall min.
STC50 to the Drywall system.
Frequency Hz
125250500100020004000NRC*
k) Compatibility
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/12
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
• All partition shall be filled with termite resistant Acoustical Fire Slab
100kg/m3 density, min. 50mm thick rockwool slab; to give an overall min.
STC50 to the Drywall system.
• Seal all perimeter gaps of the wall frame system with acoustical sealant
prior to installation of gypsum panel, for maximum sound transmission loss.
• Insure that all recessed panels, electrical outlets, light switch boxes, etc are
encased with fire-barrier seal wrap to seal all gaps and maintain continuity in
fire and smoke protection in all fire-rated assemblies.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/13
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
• Place control joints consistent with lines of building spaces, with 12.5mm
between board. Apply Acoustical Sealant at base of space, apply control
joint accessory piece at face. Place joints vertically at jamb head of double
doors. Place vertical joint at jamb head, latch side, of doors set in gypsum
board walls, U.N.O. on the approved shop drawings.
• Reinforced all vertical and horizontal exterior corners with corner beads
fastened with stainless steel stapled at 230mm o.c. on both flanges along
entire length of beads.
o) Joint Treatment
• Reinforce all interior and exterior corners for both ceiling and wall surfaces.
Apply initial coating of joint compound about 76mm wide, pressing tape
firmly into compound, wipe off excess compound. Apply second coat of
compound with tools of sufficient width to extend beyond joint centre
approximately 100mm. Drawn compound down to a smooth even plane.
p) Gypsum Accessories
• Corner Reinforcement
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/14
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
Paper faced metal tape corner bead with internal and external corner
beads in bull nose of various radius, or spray corner.
Material:
• Edge Reinforcement
• Control Joint
Material: Roll-formed zinc control joint with perforated flanges, 1-3/4 inch
wide, with ¼ inch wide center channel.
W-shaped, roll-formed zinc expansion joint trim with integral nailing flange.
Zinc alloy to conform to BS6561:1985 (1991) of minimum 24 gage
(0.70mm). Trim depths to match board thickness.
3.6 CONSTRUCTION
Construction shall be carried out to the approval of the Architect under experiences
factory supervision and control. Only work which cannot be carried out in the
workshop or factory should be prefabricated and assembled quickly on site.
All joints shall be to the best trade practice type of joints. They should be cut and
assembled neatly and accurately and all joints, junctions and intersections shall have
neat hairline.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/15
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
Butt joints shall be constructed between gypsum plaster board panels. Edges of
jointing panels shall be taped and plastered with approved jointing compound and
thereafter apply with sealant to receive wall covering.
Adequate allowance must be made for thermal movements of any aluminium frame
members.
All members shall be of sufficient strength and deflection shall be kept to maximum of
L/50 considering a distributed load of 5 Ibs per sq ft. The weight of the partition shall
not exceed 6 Ibs per sq ft
Accessories to be used to facilitate jointing and fixing may be connected to the edges
of adjacent spaces. He is to allow for in his pricing, methods of finishing above
finished ceiling level, below finished floor level and beyond grid lines against other
wall and windows elements all to the Architect’s satisfaction.
The deviation range to be allowed for on the floor to ceiling height shall be from 0 to
30mm. This includes an allowance of 6mm for variation in the horizontally of the floor
level, 20mm for deflection of ceiling and 6mm for variation sin horizontally of the
ceiling. The partition shall maintain this performance under the most adverse
condition of deviation.
The partition shall not show signs of deterioration which could be objectionable from
points of view of appearance, habitability or application of finishes. The installed
partitions and its component parts shall run straight to line and to be set vertical and
plumb.
3.7 SKIRTING
The partition shall incorporate homogeneous tile/ epoxy/ vinyl/ stainless steel skirting
as detailed in drawings.
Skirting should be provided on both sides of the partitions and shall be capable of
carrying electrical and telephone services and minor plumbing pipes.
The panels on both sides of the cavity type partition generally comprised of approved
quality min. 12.5mm thick plain gypsum plaster board.
The total thickness of the cavity type partition panel shall be 100mm thick and this
overall thickness should be flushed with the aluminium framing.
The partition panel shall be assembled neatly. All panels shall come one piece and
fixed between the aluminium frame members and no joint shall be exposed. No
cutting piece shall be allowed.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/16
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
The sample of partition panel shall be submitted to the Architect for approval.
The panel shall be free from warps and other defects. Any replacement of defective
panels shall be at the expense of the Contractor.
The fire resistant material for in in-fill must satisfy the local Building Authority and Fire
Service Bureau and comply with the specifications shown within the fire protection
drawings.
The gypsum plaster board panels for the partitions shall be finished with the wall
covering/ painting as specified.
Thickness of applied finishes to the gypsum plaster board panel shall require to
comply with requirements or standards stipulated by the Building Control Division and
Fire Service Bureau or any equivalent local authority Code and requirements (where
applicable).
The colour of the surface finish shall not appreciable fade or darken due to action of
natural or artificial light during the defects liability period.
Basic in-fill material in partition shall be 75mm rock wool material of not less than 1kg
or 2lbs density or other equivalent materials acceptable to Building Control Authority
or equivalent local authority Building Department. The panels shall be retained with
no fastening of fixing visible. All anchorages shall be concealed. Such sound proof
walls shall go all the way up to the soffit of the concrete floor above.
3.11 GLAZING
All glazed panels to the partitions shall have solid aluminium or stainless steel timber
frame and glazing bars and are glazed in 8mm thick first quality coated or patterned
float glass or otherwise stated or shown on the drawings. All glass shall conform to
BS 952 and shall be free from blemishes, bubbles, air holes, specks, scratches and
other defects and samples shall be submitted for the approval of the Architect.
All glass delivered to site must be in its original packing showing the manufacturer’s
markings, guarantee, type of glass, etc attached to the outside of the container.
All broken, cracked or scratched glass must be removed and replaced with new glass
to satisfaction of the Architect.
All glass must be clean inside and outside after installation. On no account shall be
cleaned by scraping the glass.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/17
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
All glass panels shall be fixed with neoprene or other approved gaskets and
aluminium fixing beads.
Moisture content: Framing shall be installed the following values tested to AS/NZS
1080.1:
- Air conditioned buildings: 8 to 10%.
- Intermittently heated buildings: 10 to 12.5%.
- Unheated buildings: 12 to 15%.
Finished framing: To AS/NZS 2589 clause 4.2.2. Wall frames shall be constructed to
AS 1684.4 Section 6, as appropriate for internal walls. Double faced walls: Provide
gauged timbers in studs, noggings and plates.
Sealant types appropriate for the partition's documented acoustic rating and fire-
resistance levels, and compatible with partition materials and building substrate.
The Nominated Sub-Contractor is deemed to have allowed for in his unit rates for the
filling up of all cavities formed when his partition abuts the existing surfaces of walls,
ceiling and other adjoining structure. The fill used is to be approved by the Architect
and this may be in the manner of felt strips, neoprene strips or wet calcium plaster in
filling.
The Contractor is deemed to have allowed for in his unit rate for the erection of one
full and complete “mock-up” partition (for each type of drywall) for the full storey
height inclusive of necessary security screen and one double leaves door all as
specified. The length of the partition shall consist of min. three panels by 2.4m to 3m
long each (subject to proposed drywall system). Counter-proposed size of mock-up
partition shall obtain Architect’s clearance; Relevant scopes shall be read in
conjunction with Mock-up Scopes under Section SS009_Mock-ups & Tests.
3.15 CO-ORDINATION
The Contractor shall co-ordinate with sub-contractors for all other trades in the
programming of his work, for example trades listed in the following but not limited to:
• Any door/ window/ louvre/ glass walls/ security mesh wall systems;
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/18
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
Notify Architect one week in advance of the date and the time when the Project, or
part of the Project, will be ready for an above-ceiling observation.
Promptly remove any residual joint compound from adjacent surfaces, and where
ever to the clean room standard.
3.18.1 The architectural drawings are diagrammatic and do not purport to identify or solve
the problems of thermal or structural movement, vapour barriers, fixings and
anchorage, flatness and stability of facing, and moisture disposal.
The drawings merely indicated the ‘profile, configurations and finishes required
together with the position relative to the structural frame and interior building
elements. The details contain therein serve merely as suggested directions for
solving some of the major design requirements. The Contractor may use these
details and develop them as he deems fit.
The Specification specifies the minimum requirements without limiting the Fabricator
as to the method of achieving such performance.
The Contractor shall be deemed to have visited the site before submitting his Tender
and shall be wholly responsible for acquainting himself with the nature, position,
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/19
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
constraints of the site and the full extent and character of the works and all other
information relevant to the execution of the works.
The Contractor shall not be entitled to claim extra payment on the grounds of
insufficient or inaccurate tender information relating to propose or existing
structures.
Preliminary design proposals must be submitted with the tender. Notwithstanding the
acceptance of the Contractor’s design recommendation/ proposals by the Architect,
Contractor shall be solely responsible for the adequacy of the works including design
and shall make good any damage or defects arising from inadequate design.
The Contractor shall submit for the consideration of the Architect preliminary design
drawings showing typical details fully dimensioned, showing finish, thickness,
profiles, jointing, welds, intersections and assembly; details of construction,
weatherproofing hardware and hardware schedules; reinforcement, anchorage and
structural supports; and such drawings and details (whichever applicable) as
required to fully illustrate all details of the work. The scale and detail of the drawings
are subject to Architect’s approval.
The Contractor shall outline details of his intended temporary works to the Architect
and incorporate his comments into the design. He shall then submit for the
Architect’s approval before the commencement of any on site construction, shop
drawings and calculations showing all details, manner and magnitude of the loading
on the structure. The Contractor shall be responsible for ensuring that the structural
elements to which the elements are to be fixed is adequate to support the load.
3.22 MEASUREMENTS
All true measurements of the building are to be in the metric system. The Contractor
shall be responsible for verifying all the dimensions and actual conditions on site.
These dimensions should be incorporated in the shop drawings prior to final
approval.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/20
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
The Tenderer shall also submit a preliminary programme of the works showing the
various stages of design sampling, testing, fabrication, delivery and installation of
the works.
The Contractor shall submit with his Tender details of builder’s work and special
attendance required other than those already described in this Specification. Any
other items of work or facilities not so stated shall be deemed to be provided by the
Contractor when required.
Within one month of award of the Contract, the Contractor shall submit updated
information as follows:-
i. Organization Chart.
ii. Detailed programme of the Works.
iii. Shop Drawings:-
Complete scaled construction detail drawings drawn to full scale. The
drawings shall fulfil all requirements made by the Architect during the
technical negotiation with the Contractor.
(b) Upon Architect’s approval of the shop drawings, four copies and one
reproducible print for each of the final approved drawings, plus four sets of the
above reduce to one-quarter of the original size shall be submitted for the
Architect’s and Employer’s use.
(c) After the shop drawings and the structural calculation, etc. are approved, the
Contractor shall submit the following for the Architect’s approval before
fabrication of the bulk.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/21
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
(e) Before the components are installed, the Contractor shall submit the following
for the Architect’s approval.
v. Plan of Protection –
Preliminary plan of the method of protecting the works with description as to
when the protection can be removed. The plan to consider effect on other
trades.
(f) Before the date of completion of the works, the contractor shall prepare and
supply to the Architect, record drawings and record photographs of the whole
of the works as installed and as requested by the Architect. These drawings
and photographs shall be specially prepared for record purpose
(g) The Contractor shall submit a maintenance manual for all systems.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/22
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
• 100% water-resistant
• Dimensional stability
• Robust and reliable with high impact resistance and sound insulation
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.
PROJECT IGNITE SS3/23
FEB 2023 ISSUED FOR 100% DELIVERABLES SECTION 3 - SUPPLY AND INSTALLATION OF DRYWALL PARTITIONS
3.27 GUARANTEE
(a) Submit written guarantee agreeing to repair or replace defective materials and
workmanship during the guarantee period. The Contractor shall be responsible
for damages to building and furnishings caused by defective materials and
workmanship including water leakage during the guarantee period.
(b) The general guarantee shall cover a period of ten (10) years from the date of
issue of the Completion Certification of the Main contract by the Architect.
(d) The guarantee shall cover structural failure and latent defects of the system in
compliance with the current and latest regulations and requirements stipulated
by the relevant local authorities.
COPYRIGHT BY M/S AWP PTE LTD. THIS SPECIFICATION IS THE PROPERTY OF M/S AWP PTE LTD AND CANNOT BE COPIED, REPRODUCED PARTLY OR
WHOLLY WITHOUT THE WRITTEN PERMISSION OF M/S AWP PTE LTD.