Professional Documents
Culture Documents
Amended edition
FOR RESTRICTED
CIRCULATION
No.
INSPECTION
OF
TURBINES AND DIESEL ENGINES
FOR RESTRICTED
CIRCULATION
No.
INSPECTION
OF
TURBINES AND DIESEL ENGINES
Prepared by
COMMITTEE ON INSPECTION
OF ROTATING EQUIPMENT
OISD publications are prepared for use in the oil and gas industry
under Ministry of Petroleum and Natural Gas. These are the
property of Ministry of Petroleum and Natural Gas and shall not
be reproduced or copied and loaned or exhibited to others without
written consent from OISD.
Though every effort has been made to assure the accuracy and
reliability of data contained in these documents, OISD hereby
expressly disclaims any liability or responsibility for loss or
damage resulting from their use.
The Oil Industry in India is 100 years old. Due to various collaboration
agreements, a variety of international codes, standards and practices are in
vogue. Standardisation in design, philosophies and operating and maintenance
practices at a national level was hardly in existence. This coupled with feed back
from some serious accidents that occurred in the recent past in India and
abroad, emphasised the need for the industry to review the existing state of art in
designing, operating and maintaining oil and gas installations.
With this in view, the then Ministry of Petroleum and Natural Gas in 1986
constituted a Safety Council assisted by Oil Industry Safety Directorate (OISD),
staffed from within the industry, in formulating and implementing a series of self
regulatory measures aimed at removing obsolescence, standardising and
upgrading the existing standards to ensure safer operations. Accordingly, OISD
constituted a number of Functional Committees of experts nominated from the
industry to draw up standards and guidelines on various subjects.
List of Members
_______________________________________________________________
In addition to the above several other experts from industry contributed in the
preparation, review and finalisation of this document.
TURBINES AND DIESEL ENGINES
CONTENTS
SECTION
1.0 Introduction
2.0 Scope
7.0 References
TURBINES AND DIESEL ENGINES
ii) The floor shall be mopped clean so vii) Special attention shall be paid to
that there is no oil spillage or bearing temperature, oil temperature
possibility of an accident. All covers of and oil flow through the bearing.
trenches shall be in position. All
instruments and gauges on the 3.4 PROCEDURE FOR COMMISSIONING
turbine and its panel shall be OF NEW TURBINES
checked.
3.4.1 Prestart up checks
iii) Oil leakage from all joints shall be
checked and eliminated specially in Manufacturers of turbines give detailed
places where it may fall on insulation instruction for start up of turbines
or heated parts of steam turbines and supplied by them. Services of their
steam piping. All auxiliaries such as representatives are also available during
condensate pumps, circulation first start up of a new turbine. Therefore,
pumps, oil pumps, etc. shall be tested instructions supplied by them will over
for satisfactory operation. ride the general instructions applicable to
all turbines given here. These
iv) Oil is circulated through the bearing requirements are meant to supplement
governing system and oil level and requirements of the supplier and do not
pressure drop across the filter shall absolve the responsibility of the
be checked. It is necessary that oil is supplier's representative who
circulated through the system so that commission the turbines. During start-up
all dust and foreign particles are in addition to manufacturer's instructions
removed from the system. The quality the following checks shall also be carried
of the oil shall be checked and out.
centrifuged.
i) All pipe connections to the turbine shall
v) Proper Operation of the protection be checked to ensure that they are as
system shall be tested to the extent per drawing and are of proper rating.
possible before starting the turbine or
at the first opportunity while starting ii) All valves and non return valves shall be
the turbine. checked for correctness with reference
to direction of flow in the lines.
vi) Leakages in the steam condensate
system shall be checked and rectified iii) It shall be ensured that blinds are
before starting the turbine. removed and gaskets are provided in all
joints.
vii) While starting the turbine on low
speed, gradual heating shall be iv) It shall be ensured that hydraulic test of
ensured. Constant watch should be all lines are conducted as per
kept on the growth of the casing and specifications and test certificates are
movement recorded. signed by a competent authority.
Vibration reading shall be taken at v) All steam lines to the turbine shall be
operating speed and just below trip blown to remove foreign materials,
speed. Magnitude of vibration shall be electrodes, welding slag and mill scale
within the acceptable range. For from the line and the line shall be
general purpose turbines: certified to be free from foreign material.
Up to 400 rpm speed - 3.0 Mils
xii) Lube oil to the system shall be circulated Only spares obtained from supplier of
after fine mesh strainers are installed in steam turbine shall be used for replacement
the turbine bearings and the quality of oil in governing and protection system of steam
shall be monitored. turbine. However, in the case of obsolete
turbines spares from other sources can be
xiii) The oil shall be replaced after circulation. used but stringent inspection shall be carried
out to ensure that safety is not compromised.
xiv) The operation of bearing gear motor
while circulating the oil through the 4.0 GAS TURBINES
bearing shall be checked.
4.1 DEFINITION OF TERMS
xv) The emergency trip gear shall be
checked for proper functioning, operating
4.1.1 Normal operating point
the knob or level at the trip gear and by
remote operation. The responses of the
emergency stop valve, extraction valve Normal operating point is the point at
and servo valve shall be observed. which usual operation is expected and
optimum efficiency is desired.
xvi) Open or close emergency stop valve by
means of the starting device. The 4.1.2 Trip Speed
response shall be observed.
Trip speed is the speed at which an over
xvii) The operation of the spindles of control speed shall be approximately 105 per cent of
valves shall be checked to ensure easy the maximum continuous speed.
and smooth operation.
4.2 PREDICTIVE MAINTENANCE
xviii) The static characteristic of operation of
SCHEDULE
the valve shall be compared with the test
report.
Since gas turbines are critical equipment
xix) The oil strainers shall be replaced their condition shall be closely monitored as
periodically during circulation of the lube outlined below:
a) Vibration signatures on all bearings machine surveyance system the
shall be taken of a new gas turbine to vibrations shall be taken once a week
obtain baseline data for comparison. and recorded as required by OISD-
After every subsequent overhaul also STD-127 on History Recording.
the signatures shall be obtained to
compare with base line data. If
machine is not provided with built in
4.3 INSPECTION SCHEDULES AND PROCEDURES
v. Relief Valves
Setting
The inspection shall be carried out as ix) Inlet guide vanes shall be inspected
per schedule given in table 4.3 for erosion and cracks.
If any part is found cracked damaged or ii) Combustion liners shall be thoroughly
the amount of wear is more than the inspected for cracks.
manufacturer's recommendations, the part
shall either be replaced or repaired using iii) Carbon deposits in flame failure
correct technique. viewing head and sight windows shall
be removed and cleaned.
Prior to 16000 and 32000 hours
inspection a complete operational test shall iv) The liquid and gas fuel burner shall
be made for reference operating be inspected.
parameters which shall serve as a means of
comparison with identical tests that shall be v) The transition pieces shall be
made immediately after the 16000 and inspected for cracks and wear at the
32000 hours repairs. points of contact.
The operational test shall end with an vi) Wear at the nozzle end of the
over speed trip test to indicate whether transition piece shall be checked as it
attention should be given to the governor or allows excessive vibration of the
tripping mechanism during inspection. transition piece which might lead to
cracking.
4.3.2 Inspection at time of overhaul
vii) Transition pieces shall be replaced if
50 per cent of inner or outer seal is
a) Compressor assembly reduced to half the original thickness.
i) The compressor inspection shall be viii) Ignitor plugs and leads shall be
conducted to determine the checked and replaced if necessary.
mechanical and aerodynamic
condition of the compressor. ix) Fuel valve and actuator settings shall
be checked.
ii) Holding bolts of stacked rotor shall be
inspected for looseness. x) Combustor clearance with respect to
fuel nozzle and igniters and baffles
iii) Both stator and rotor blades shall be shall be measured and compared with
cleaned and checked for cracks with manufacturer recommended figures.
dye penetrant.
xi) Thermocouple weld shall be checked
iv) Blade roots shall be closely inspected for cracks.
for severe pitting as this may lead to
structural failures. c) Turbine Section
v) Rotor blade tip clearance shall be i) Turbine rotor and stator blades for
measured and compared with each stage shall be cleaned and
manufacturer's recommended closely inspected for erosion and
clearances. cracks with non-destructive
examination.
vi) Rotor end float/thrust bearing axial
clearance shall be checked. ii) Rotor/stator blade tip clearances shall
be measured and compared with
vii) Labyrinth seals shall be inspected. manufacturer's recommendation.
iii) Perpendicular distance between the i) Rotor with assembled blades shall be
trailing edges of each vane and the dynamically balanced without the
surface of the next vane shall be coupling, but with half key.
carefully measured to ensure equal
gas distribution of gas flow to the ii) Dynamic balancing shall be done at
rotating blading for elimination of the operating speed range rather than
blade vibration. at low speeds.
However, in case it is not possible, the
iv) Entire turbine rotating blades shall be same should be done as per
replaced if several blades are fatigue manufacturers’ recommendations.
cracked. Note1
vi) It shall be ensured that diaphragm 2.0 mils on rotors with speed below
cooling air supply lines are clean. 4000 rpm
i) Babbited shoe surface 0.5 mils for speeds above 12000 rpm
ii) Pivoting shoe surface and seat in These limits also include shaft run out
retainer ring. (API 616)
ii) Bore and face end plates shall be iii) Oil reservoirs and tanks shall be
inspected for full contact. cleaned and inspected.
iii) Pivoting surfaces of shoe and housing iv) Oil coolers and accumulators shall be
ring shall be checked for scratches, inspected, cleaned and hydrostatically
scoring, or erosion. tested at one and one-half times
design pressure.
iv) For tilting pad bearings, blue shoe the
pivot surface and check for contact v) Oil strainer should be inspected and
area and positions. The contacting cleaned.
surface shall be in center only and at
the bottom portion of the pivot bore in vi) Oil pressure control valves, relief
the retainer. valves and check valves shall be
tested as per testing procedures.
v) Check to ensure that pins do not
bottom out in pads. g) Gear Box
vi) Shaft clearance shall be checked. i) Gear teeth shall be checked for
cracks and wear.
e) Balancing
ii) Backlash shall be measured and
compared with manufacturer's
recommendation.
ii) Tubing connection and hydraulic
iii) Bearings shall be inspected as per hoses shall be checked for wear,
procedure given in 4.3.2(d). leakage and abrasions.
Max. unbalanced force x journal static 2) Fuel valve heaters shall be checked
56,347 weight load for defective element.
(ounce inches) ___________
ii) Fuel oil system shall be inspected
NMC2 as per the following:
ii) Disc couplings shall be checked for iii) Gas control valve and control loop of
cracks by non-destructive test. Fuel Gas System shall be checked
for proper operation, trip action and
iii) Continuous lubricated type coupling calibration.
shall be inspected for corrosive wear
and coupling contamination. l) Inlet System
iv) Cold alignment between shaft shall be i) Air filter shall be ensured cleaned.
checked and ensured that the
readings are within the limits as ii) Inlet compartment, inlet duct and
prescribed by manufacturer. silencers shall be ensured cleaned.
ii) All control systems shall be tested and iii) Hydraulic system piping shall be
calibration of alarm and trip points inspected for corrosion and leakage.
shall be done to control specifications.
n) Cooling and Sealing Air System
j) Starting System
i) Orifice plates and unions of piping
i) Clearance of clutches jaws in shall be inspected.
engaged and disengaged position
shall be checked. ii) Compressor bleed valves shall be
checked for correct open/close
condition.
f) Check Valves provided for lubrication
o) Compressor Cleaning System system shall be checked for correctness
of direction.
i) Flow meter shall be calibrated.
g) It shall be ensured that coupling(s) and
ii) Stop valve shall be checked for proper other naked rotating parts are protected
operation. by the coupling guard or suitable cover.
p) Fire Detection System and Ultraviolet h) All temperature and pressure gauges
Detectors shall be calibrated.
i) Fire detectors shall be inspected for i) All alarm/trip devices shall be calibrated.
damage and proper operation.
j) All controllers, transmitters and control
ii) Ventilation dampers shall be checked valves shall be tested.
for free operation.
4.4.2 Pre-start Operation
iii) High pressure storage cylinders shall
be checked for loss of cylinder weight. a) Before commencing the prestart
operation it shall be ensured that the
q) Water system steps in the preceding section have
been completed.
i) Water pump shall be inspected as per
pump manufacturer's instructions. b) Operation of the cool down and
emergency lube oil pumps, water pumps
ii) System shall be checked for fouling shall be checked.
condition.
c) Lubrication unit should be started and
iii) All valves shall be checked for proper inspected to see that oil is flowing from
operation. the bearing drain. Unless oil flow is
visible at each sight point, the turbine
4.4 COMMISSIONING AND TESTING should not be started.
PROCEDURES
d) Condition of all thermocouples on the
4.4.1 Initial Preparation temperature indicator shall be checked
and ensured that readings are close to
The following checks shall be made prior to ambient temperature.
the first operation or after periodic repair and
long period of non-operation of the gas e) Spark plug shall be checked for proper
turbine: arcing.
a) Assembly of all the piping shall be in f) It shall be ensured that the cooling water
accordance with the Flow diagrams' and system is in operation.
the Piping assembly drawings.
g) It shall be ensured that oil cooler and oil
b) Tightening of all the nuts and screws filter venting are carried out.
shall be checked with suitable torque
wrenches. h) Before the turbine is coupled to drive
equipment, the following tests shall be
c) All air and fuel piping shall be checked carried out to check the following trip
for cleanliness. system:
d) Air intake duct shall be checked for - Start fail at specified time (Dynamic)
cleanliness. - Low lube oil temperature (Dynamic)
- Flame failure (Dynamic)
e) The lubrication system shall be properly - Emergency stop (Dynamic)
flushed. - Operating temperature (Static)
- High Lube Oil Temperature (Static)
- Governor fail (Static)
- Over speed
- Fuel change over
- High demister level m) Bearing metal temperatures and drain
- Fire and gas detection system failure temperatures shall be within the limits
as specified by manufacturer.
4.4.3 Start - up Operation
5.0 DIESEL ENGINES
Before starting the turbine the following shall
be ensured. 5.1 SCOPE
a) that items listed in the preceeding This section covers the maintenance
section have been completed. systems and procedures to be followed for
maintenance of diesel engines which are
b) that sufficient fuel (gas/oil) pressure is used as prime movers for fire water pumps,
available. instrument air compressors and emergency
generators in oil industry. Generators having
c) that minimum lube oil temperature is a capacity of 500 KVA and above are not
reached. covered in the standard.
d) that hydraulic, pneumatic pressure trip
5.2 INSPECTION SCHEDULES
system is available.
5.2.1 Inspection On-stream
e) that sufficient instrument air supply
pressure is available.
i) The following checks shall be done
f) Check the fuel lines and area around weekly:
the fuel nozzle for leaks after start-up.
1. Fuel, oil, water and exhaust shall be
g) During turbine cranking, the following checked for leaks.
points should be checked:
2. Air cleaner oil level shall be checked.
i) Listen for rubbing noise.
3. Oil level in hydraulic governor shall be
ii) Temperature of the lube oil in bearing checked, if provided.
drain. 4.
Record Oil Pressure. Note1
h) After satisfactory cranking, firing shall be
5.
done and the following checked: Check fuel tank & drain water contents.
Note1
iii) The following checks shall be done after c) Check all valves
1500 hours/ 2years whichever is earlier
Note1 d) Check cam shaft and drive gears
a) Check crank shaft-main bearing The fuel pump shall be inspected and
journals, bearings, big end bearing overhauled.
journals and big end bearings.
vi) Cam Shafts This Standard shall be read in conjunction
with the following standards, codes and
The following shall be checked: publications.
4) In case of tube leakages beyond 10 per vii) OISD 126 Specific Maintenance
cent of the number of tubes, the tube Practices
bundle shall be replaced.
viii) OISD 127 History recording.
viii) Chassis overhaul
ix) API 613 - Special purpose Gear Units
1) The chassis shall be checked for for Refinery Services.
distortion.
x) API 614--Lubrication, Shaft--sealing and
2) All spring hanger brackets shall be control oil system for special purpose
checked for wear. applications.
3) It shall be ensured that spring check xi) API 615--Sound Control of mechanical
cambering are done as recommended equipment
by the manufacturer.
xii) API 616--Combustion Gas Turbine
for General Refinery Services
6.0 DIFFERING SCHEDULES Note1
xiii) API 670--Non contacting vibration and
In case of differences between this standard axial position monitoring system.
and the manufacturers' recommendations,
the instructions given by the manufacturers xiv) API 678--Accelerometer based vibration
shall govern. The maintenance schedules monitoring system.
given in this standard are very broad based
on present experience and practices and xv) ISO 3977--Gas Turbine Procurement
may be modified from time to time. The
schedule indicates the maximum interval of xvi) Gas Turbine Engineering Handbook by
time between two inspections. Dr. M.P.Boyce Gulf Publishing Co.,
Organisations, on the basis of historical Houston, Texas.
records and analysis of failures may alter
the inspection interval accordingly. All xvii) OISD Standard 152 on Instrumentation.
organisations shall maintain records of
history cards and specification sheets, with xviii)Maintenance manual of Cummins
respect to problems on equipment in Diesel Engines
different services. Based on the feed back
so obtained, the committee will attempt to xix) Maintenance manual of international
further sophisticate inspection schedules Harvestor Diesel Engines
and producers.
7.0 REFERENCES Note1 xx) Maintenance manual of Nissam Diesel
Engines.