You are on page 1of 12

Available online at www.sciencedirect.

com

ScienceDirect
Underground Space 7 (2022) 786–797
www.keaipublishing.com/undsp

Numerical evaluation of segmental tunnel lining with voids in


outside backfill
Jia-Xuan Zhang a, Ning Zhang b, Annan Zhou c, Shui-Long Shen b,⇑
a
Department of Civil Engineering, School of Naval Architecture, Ocean, and Civil Engineering, Shanghai Jiao Tong University, Shanghai 200240, China
b
MOE Key Laboratory of Intelligent Manufacturing Technology, Department of Civil and Environmental Engineering, College of Engineering,
Shantou University, Shantou, Guangdong 515063, China
c
Discipline of Civil and Infrastructure, School of Engineering, Royal Melbourne Institute of Technology (RMIT), Victoria 3001, Australia

Received 19 June 2021; received in revised form 1 September 2021; accepted 26 December 2021
Available online 29 January 2022

Abstract

This paper presents a numerical investigation of the mechanical behaviour of segmental linings owing to the existence of voids in the
composite lining. The composite lining was formed by mining outside and shield tunnelling inside with backfill in between. Finite element
method was conducted to analyse the axial forces and bending moment for voids of different diameters at different positions. The results
show that the axial forces in the transverse section increase near the crown and then invert and decrease on the left and right sides with an
increase in the void centre angle (b) measured from the vertical axis. The increase in void diameter (d < 300 mm) induces an increase in
the axial force on the left and right sides when b = 45° and 90°, while it decreases near the crown and invert. The occurrence of voids
leads to an increase in the bending moment in the entire segment section with an angle b.

Keywords: Jointly constructed tunnel; Composite lining; Voids; Axial force; Bending moment

1 Introduction grout. Compared to shield tunnelling, mining is a more tra-


ditional method for tunnel excavation through drilling and
Shield tunnelling is widely applied in the construction of blasting (Buffington, 2000), usually used to excavate moun-
metro systems and municipal pipe systems in urban areas tain tunnels for railways and freeways. Mining is suitable
because of its cost-effectiveness, safety, and efficiency for various types of strata, for example, hard rock with
(Mair, 2008; Kavvadas et al., 2017; Liao et al., 2009). good integrity, karst caves, swelling rocks, and upper soft
Because the size of a cutter head is larger than that of lower hard strata. When tunnelling in hard rock stratum,
the shield body and outer diameter of the segment, an mining has a higher efficiency and lower cost than shield
annular interspace is formed between the segment and soil tunnelling (Tan et al., 2021). In addition, mining is feasible
during construction. To prevent the deformation of the for tunnels with irregular sections. For tunnels excavated
segment and soil and avoid groundwater leakage, the annu- using mining, the geological conditions, excavation
lar interspace is filled with grouting material. Therefore, method, and lining type are essential safety considerations;
during the construction and service life of the tunnels exca- in particular, the lining type is a major concern for engi-
vated by the shield machine, the support system is mainly neers. With the application of shotcrete and anchorage sys-
composed of the shield shell, concrete segment, and backfill tems, the composite support structure composed of the
surrounding rock, primary support, and secondary lining
has become the central part of the support structure for
⇑ Corresponding author at: College of Engineering, Shantou University,
these tunnels.
Shantou, Guangdong 515063, China (S.-L. Shen).
E-mail address: shensl@stu.edu.cn (S.-L. Shen).

https://doi.org/10.1016/j.undsp.2021.12.007
2467-9674/Ó 2021 Tongji University. Publishing Services by Elsevier B.V. on behalf of KeAi Communications Co. Ltd.
This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/).
J.-X. Zhang et al. / Underground Space 7 (2022) 786–797 787

Considering the characteristics of mining and shield tun- element method was used to investigate the axial force
nelling, engineers sometimes need to employ both methods and bending moment for voids of different sizes at
in different tunnel sections under complex geological condi- different positions in the backfill layer. The results will
tions. Conventionally, a pit is required to lift the shield provide a better understanding of the void effect and
machine after the tunnel is constructed. However, for facilitate the design and construction of composite
mountain tunnels with limited ground space and consider- linings.
able buried depth, digging a new pit is challenging and
expensive. In the absence of a pit, the shield machine must 2 Project background
pass through the mining tunnel. To advance the shield
machine without load, concrete segments are assembled A joint tunnel project combining mining and shield tun-
in the mining tunnel, and the interspace between the seg- nelling was carried out in Shenzhen, China. The tunnel (re-
ments and shotcrete is filled. Therefore, a composite lining ferred to as the Xue-gan tunnel) connects Xuexiang and
composed of a concrete segment, backfill layer, and pri- Gankeng stations of Shenzhen Metro Line 10. Figure 1
mary support is constructed in this section. Voids can shows the plan of the Xue-gan tunnel. As shown in
occur in the backfill layer during grouting. Owing to the Fig. 1, the tunnel was excavated through residential area,
complicated boundary conditions and the various locations industrial park, reservoir, railway, and highway, which
and sizes of voids, it is challenging to evaluate the compos- poses a high risk and demands a low-impact construction
ite lining using empirical or analytical methods (Bock, process. The length of the Xue-gan tunnel is 2.418 km.
2014). Therefore, this study utilised the finite element For the tunnelling process, 1 km of the tunnel was con-
method (FEM) to simulate the effect of voids on the com- structed using shield tunnelling, 1.2 km was constructed
posite lining. using mining, and the rest (0.218 km) was constructed
Finite element method is widely employed for various using a combination of both methods. For the section con-
engineering problems, such as geotechnical engineering structed using a combination of both methods, the second
(Cui et al., 2020; Jin et al., 2018; Yin et al., 2012, lining of the mined tunnel was assembled using a shield and
2018; Zhu et al., 2016), tunnelling (Jiang & Yin, 2014; gap backfill with gravel grout.
Lu et al., 2021; Rashiddel et al., 2020; Shin et al.,
2012), and structural engineering (Zhang et al., 2017). 2.1 Geomorphology
With regard to the support system of tunnels, FEM
was also applied to analyse the effect of voids on tunnel As shown in Fig. 2, the original geomorphology is
linings, where voids were induced by the following fac- dominated by hills with a considerable elevation of
tors: (1) erosion of groundwater (Meguid & Dang, 100–150 m, and several gullies and valleys are distributed
2009; Meguid & Kamel, 2014); (2) dynamic load owing in the construction area along the tunnel alignment. The
to earthquake and train vibration (Jones & Hunt, 2011; left and right line ends of the shield-tunnelled section are
Yasuda et al., 2019); and (3) defect of grouting owing located under a slope and a steep mountain ridge,
to insufficient grouting pressure or inappropriate grout respectively. A ventilation shaft was designed to be
ratio (Li et al., 2019). These studies indicate that the located at the end of the shield-tunnelled section to
presence of voids is closely related to the stress redistri- improve the indoor air quality and ensure that the disas-
bution and failure behaviour of the tunnel lining, and sembled shield machine can be lifted from the tunnel.
the size and location of the voids can directly affect the According to the field investigation, the buried depth
initiation and development of cracks (Fu et al., 2019; of the tunnel at the end of the shield tunnelling area
Min et al., 2020; Wang et al., 2014). The negative influ- was approximately 70 m, which requires a ventilation
ence of the voids behind the tunnel lining can be attrib- shaft excavated to the same depth to connect the ground
uted to the loss of local contact and discontinuity in the surface and tunnel. However, owing to the significant
ground–lining interaction (Lai et al., 2017; Zhang et al., elevation difference, there is not enough ground space
2017), which have also been observed in experimental to transport and employ the construction machinery. In
studies (Leung & Meguid, 2011). However, most studies addition, high-density trees and weeds are covered on
have focused on tunnels with only a single lining, built the slope in this area, which makes it more difficult to
by mining or shield methods. Therefore, the effect of build the ventilation shaft. Therefore, to reduce the cost
voids in the composite lining comprising concrete seg- and difficulty of the ventilation shaft construction, the
ments, backfill layers, and primary supports requires fur- mined section was chosen as the construction site. As
ther investigation. marked in Fig. 2, a gentle slope with an elevation of
This study aims to evaluate the segmental composite 116–107 m was selected to construct the ventilation shaft
tunnel lining with voids by using FEM based on a metro with a depth of 46.65 m. Compared to the planned ven-
tunnel constructed by the combined method (mining and tilation shaft at the end of the shield-tunnelled section,
shield tunnelling). The analysis was conducted to investi- the depth of the shaft constructed on the selected site
gate the formation of voids in the composite lining and was reduced by 23.35 m, and the required excavation
the mechanical behaviour of the concrete segment. Finite area was also reduced remarkably.
788 J.-X. Zhang et al. / Underground Space 7 (2022) 786–797

Fig. 1. Plan view of Xue-gan tunnel.

Fig. 2. Contour map at construction site.

2.2 Engineering geology from Xuexiang station to the joint construction area is
mainly highly weathered granite, and the remaining part
Figure 3 shows the geological profile of the Xue-gan is mainly lightly weathered granite. Considering the risks
tunnel. The lithology of the project mainly consists of plain and costs involved in excavating weathered granite, shield
fill, clay, clay with gravel, fully weathered granite, highly tunnelling was used in the highly weathered granite area,
weathered granite, moderately weathered granite, and whereas mining was used in the lightly weathered granite
lightly weathered granite. As shown in Fig. 3, the portion area.

Fig. 3. Geological profiles of Xue-gan section.


J.-X. Zhang et al. / Underground Space 7 (2022) 786–797 789

2.3 Jointly constructed tunnel shield shell, pea gravel, and primary support provided the
reaction force to improve the quality of the segment
Under the geomorphological and geological conditions assembly.
illustrated in Figs. 2 and 3, it is difficult to construct a large (4) Advance of the shield machine: During the advance-
shaft by deep excavation to accommodate shield tunnelling ment of the shield machine, the advance rate should be
facilities of a length over 120 m. Therefore, this project controlled within a range of 15–40 mm/min. When the con-
used a section constructed using mining to accommodate crete segments were assembled, as shown in Fig. 4, an air
shield tunnelling facilities, and the shield machine had to blower was employed to grout the pea gravel into the top
be driven through a short section of the mined tunnel. This of the tunnel section under a pressure of 0.25–0.3 MPa.
section of the tunnel was constructed using a combination The pea gravel flowed along the back surface of the seg-
of shield tunnelling and mining. Figure 4 shows a sche- ments, filled the interspace, and provided primary support
matic of the joint construction method, the key procedures from the bottom to the crown of the tunnel. Then, the
of which are as follows: cement mortar was grouted at the shield tail, and the pea
(1) Measurement of tunnel transverse section: Consider- gravel and cement mortar were mixed in the interspace
ing the design diameter of the mined section and the outer behind the concrete segments. Table 1 lists the composi-
diameter of the cutter head, the annular space between the tions of the cement mortar grouted at the shield tail. When
shield machine and primary support was only 60 mm. To the mixture of pea gravel and cement mortar was solidified,
avoid the shield machine from getting stuck to the inner the primary support, mixed grout, and the segment formed
wall of the mined section, it was necessary to measure the a composite lining, which could bear the pressure of the
tunnel section accurately and remove the under-excavated surrounding rock and groundwater and resist earthquakes
part. and leakages. The composite lining structure of the jointly
(2) Construction of the orientation platform: To ensure constructed tunnel is shown in Fig. 6. The composite lining
that the shield machine maintains a precise trajectory of the jointly constructed tunnel is composed of a three-
tracking posture, a 15 cm thick arc-shaped orientation plat- layer structure consisting of a primary support layer, back-
form was constructed within 60° of the tunnels inverts by fill layer, and shield segment layer. Every tunnel segmental
mining to provide accurate guidance for the shield lining consists of two rectangular and two trapezoidal seg-
machine. The inner radius of the arc was 3.15 m, and the ments and one wedge-shaped key segment with an inner
centre of the orientation platform coincided with the cen- diameter of approximately 5.4 m. The overall width of
treline of the tunnel. The coordinates and shapes of the ori- one segment is 1.5 m, with a thickness of 0.3 m. The outer
entation platform were re-measured and confirmed when diameter of the excavation profile is 7 m, and the thickness
construction was completed. of the primary support layer and backfill layer is 0.3 and
(3) Preparation of pea gravel: In the excavated tunnel, 0.2 m, respectively.
there was no earth pressure on the front of the shield
machine, and the pressure between the rubber gaskets on 2.4 Field investigation
the segments may not meet the requirements and cause
leakage. Therefore, for backfilling, substantial granite pea 2.4.1 Formation of voids
gravel with a 5–8 mm diameter was heaped in front of There are several reasons for the formation of voids: (1)
the cutter head (see Figs. 4 and 5) to provide additional the thickness of shotcrete and the volume of pea gravel
pressure. Part of the pea gravel was crushed into both sides during backfilling were too small; (2) the grout pressure
of the orientation platform to fill the space at the tunnel was insufficient owing to the pressure loss resulting from
bottom. The other pea gravel was grouted into the interface the friction between the pea gravel and rubber pipe, and
at the top of the segmental lining. The friction between the the potential energy loss for lifting concrete to the crown

Fig. 4. Schematic of the shield machines advancing without load.


790 J.-X. Zhang et al. / Underground Space 7 (2022) 786–797

Fig. 5. Pea gravel preparation in front of the cutter head.

of the tunnel; (3) the mixture of pea gravel and cement tunnel surface, in which the void would possibly occur dur-
mortar shrank during the setting and hardening processes; ing the construction of backfill layer. After the segments
(4) the particle size distribution of pea gravel was unsuit- were assembled using shield tunnelling, ground-
able. In the composite lining of the jointly constructed tun- penetrating radar (GPR) was used to detect the heterogene-
nel, it was found that voids are most prone to occur at the ity of the grouting behind the segments (see Fig. 8). TLS
interface between the primary support and backfill layer. inspection and GPR detection confirmed that voids are
prone to occur in the primary support and backfill layer
of the composite lining. The detailed data for laser scan-
2.4.2 Laser scanning inspection and ground-penetrating ning and ground-penetrating radar can be found in the
radar detection companion data paper by the authors (Zhang et al., 2021).
After the shotcrete was applied in mining, the tunnel
was inspected as a cylindrical high-density point cloud
using terrestrial laser scanning (TLS). The cylindrical
high-density point cloud recorded the measured position
and elevation data of the tunnel. The unrolled map was
then generated from the difference between the measured
data and the designed data, which implied the amount of
over- or under-excavation of the tunnel. Figure 7 presents
the measured over- or under-excavation of the tunnel,
which widely distribute on the tunnel inner wall along the
central axis. The maximum over-excavation is around
0.2 m in the middle areas of the unrolled map, which cor-
responds to the crown of the shield method tunnel. The
areas segmented by the under-excavation and over-
excavation (zoomed in the figure) are the cavities on the

Table 1
Composition of cement mortar.
Material Cement Sand Fly-ash Bentonite Water
3
Quantity (kg/m ) 180 600 320 100 460
Fig. 6. Composite lining structure of jointly constructed tunnel.
J.-X. Zhang et al. / Underground Space 7 (2022) 786–797 791

Fig. 7. Point cloud of mining method tunnel.

3 FEM analysis lining were considered as surface-to-surface contact. The


friction coefficients of the contact surfaces between the soil
3.1 Finite element model and parameters and lining and between each layer of the composite lining
were set to 0.5 and 0.65, respectively. Both the horizontal
A two-dimensional finite element model was built to and vertical displacements at the bottom of the model were
investigate the influence of voids at the interface between restrained. On both sides of the model boundary, only ver-
the primary support and backfill layer. Using this model, tical displacements were allowed. The top boundary was
a segment’s stress state is analysed based on its void posi- set as a free boundary, and the displacements were not
tions and dimensions. As shown in Fig. 9, the model size constrained.
was set to 91 m  53 m. On the basis of geological drilling The physical parameters of the soil layers are listed in
information, the thicknesses of plain fill, clay with gravel, Table 2. These parameters, such as the elastic modulus
fully weathered granite, highly weathered granite, and (E), cohesion (c), internal friction angle (u), coefficient of
slightly weathered granite were set as 2, 3, 6, 13, and earth pressure at rest (K0), and dilation angle (w), are
29 m, respectively. Because the thickness of the soil cover- directly obtained through field and laboratory tests. Pois-
ing varies significantly along the tunnel alignment, the bur- son’s ratio (l) can be calculated using K0/(1 + K0). Table 3
ied depth of the tunnel model was the median buried depth lists the physical parameters of the composite lining in this
(32 m) of the jointly constructed tunnel. The groundwater finite element model, which consists of three layers. The
level was set to 6 m below the ground surface. elastic modulus of the primary support layer in this model
In the FEM model, both the composite lining and soil was set to 28 000 MPa according to the strength of ordi-
layers were considered as homogeneous continua with nary C25 reinforced concrete (China Academy of
Mohr-Coulomb and meshed with the four-node quadrilat- Building Research, 2011). The elastic modulus of the back-
eral element. The element densities of the composite lining fill layer was obtained using a laboratory test. The elastic
and the soil surrounding the lining were adjusted to modulus of the shield-tunnelled segment was determined
improve the accuracy and convergence of the simulation. by the concrete grade (C50) and steel reinforcement,
The soil and lining, along with each layer of the composite regardless of the stiffness reduction caused by the bolt

Fig. 8. Radargram derived from ground-penetrating radar detection.


792 J.-X. Zhang et al. / Underground Space 7 (2022) 786–797

Fig. 9. Finite element mesh generation of simulation model.

Table 2
Soil parameters used for numerical simulation.
Soil layer l (m) c unsat (kN/m3) c sat (kN/m3) Es (MPa) c (kPa) / (°) K0 l
Plain fill 2 18.5 18.5 4.7 12.5 13 0.42 0.30
Clay with gravel 3 18.0 18.0 6.0 24.0 23 0.45 0.31
Fully weathered granite 6 18.1 18.1 8.0 25.5 28 0.40 0.29
Highly weathered granite 13 18.3 18.3 12.0 40.0 35 0.39 0.28
Lightly weathered granite 29 18.6 18.6 20.0 45.0 40 0.37 0.27
Notes: l is the thickness (m), c unsat is the natural unit weight (kN/m3), c sat is the saturated unit weight (kN/m3), Es is the modulus of compression (MPa), c
is the cohesion (kPa), / is the angle of internal friction (°), K0 is the coefficient of earth pressure at rest, and l is the Poisson’s ratio.

connection between the segments (China Academy of the numerical simulation conditions according to the loca-
Building Research, 2011). tion and size of the void. Condition I represents the
absence of voids in the composite lining. Conditions II-
IV were set to investigate the stress states with the size vari-
3.2 Conditions in simulation ation of voids (d = 100, 200, 300, and 400 mm) under a
fixed position (b = 0°, 45°, and 90°). Taking d = 300 mm
Figure 10 shows a schematic of the void location. The as an example, condition V was set to compare the effect
parameter b indicates the centre angle of the void from
the vertical axis of the tunnel profile, and d indicates the
diameter of the void. It is assumed that the shape of the
void is circular in the 2D model, and the circle centre is pre-
cisely located at the interface between the primary support
layer and the backfill layer. In the ideal case, where the pri-
mary support layer is smooth, the maximum value of the
void should be 200 mm. However, considering that the pri-
mary support layer is unsmoothed due to over-excavation
or under-excavation, as shown in Fig. 7, the diameter of
the voids would be larger than 200 mm. Table 4 shows

Table 3
Lining parameters used for numerical simulation.
Lining E (MPa) lr (m) q (kN/m3) l
Primary support 28 000 0.3 18 0.15
Backfill 15 000 0.2 10 0.25
Shield segment 34 500 0.3 27 0.20
Notes: E is the elastic modulus; lr is the radial thickness; q is the unit
weight; l is the Poisson’s ratio. Fig. 10. Schematic of void location and size.
J.-X. Zhang et al. / Underground Space 7 (2022) 786–797 793

Table 4
Cases for FEM simulation.
Simulation cases Position of void, b (°) Diameter of void, d (mm)
I
II II-1 0 100
II-2 0 200
II-3 0 300
II-4 0 400
III III-1 45 100
III-2 45 200
III-3 45 300
III-4 45 400
IV IV-1 90 100
IV-2 90 200
IV-3 90 300
IV-4 90 400
V V-1 0 300
V-2 30 300
V-3 60 300
V-4 90 300

of the same size (d = 300 mm) voids with different positions indicating that the segments are compressed with each
(b = 0°, 30°, 60°, and 90°) on the segment. other. The axial forces on the left and right sides are larger
than those near the crown and invert. Among the axial
forces distributed in the transverse section of the tunnel,
4 Results and discussion the maximum and minimum values are obtained at the ver-
tical and horizontal central axes, respectively. The occur-
4.1 Axial force rence of voids leads to a significant increase in the axial
force near the vertical axis but a decrease in the axial force
Figure 11 shows that the axial force of the segment var- near the horizontal central axis, except in the cases of
ies with different positions of the void of diameter 300 mm. (b = 45°, d = 400 mm) and (b = 90°, d = 200–400 mm).
When the location of the void with the same size Figure 13 shows that the maximum axial force in the
(d = 300 mm) varies from the vertical central axis to the cross-section varies with the ratio of void diameter to seg-
horizontal central axis, the axial force changes slightly (ap- ment thickness at different positions. Evidently, with an
proximately 3%–8%) on the left and right sides, while it increase in the void dimension, the maximum axial force
increases near the crown and invert. Along the vertical cen- on the segment increases. In the ratio range of 0.33–1,
tral axis, the axial force increases by more than 50% (from i.e., d = 100–300 mm, the maximum axial force values of
346.5 to 530.4 N).
Figure 12 shows the axial force distribution under the
condition that the void diameter increases at fixed locations
(b = 0°, 45°, and 90° for Fig. 12 (a), (b), and (c), respec-
tively). When the void is behind the crown (b = 0°), the dis-
tribution curves of the axial force are symmetrical on both
the left and right sides. With an increase in d, the axial force
decreases near the crown and invert, whereas it increases
on both sides. When b = 45°, the axial forces in the seg-
ment sections of 45°–45° and 135°–225° change little,
while the axial forces in the areas of 225°–315° and 45°–
135° increase compared with the common segment. When
b = 90°, the increase in void diameter produces an overall
increase in the entire segment, except near the crown and
invert when d = 100 mm. The figures show that wherever
the void was located, the diameter d = 400 mm had a
remarkable effect on the axial force compared with
d = 100–300 mm. As b increases to 45° and 90°, the axial
forces become much larger when d = 400 mm, while those
of d = 100–300 mm are quite close.
Figures 11 and 12 present a similar distribution in the Fig. 11. Variation of the axial force of the segment with different void
transverse section. The axial force values are all positive, positions (d = 300 mm).
794 J.-X. Zhang et al. / Underground Space 7 (2022) 786–797

Fig. 13. Relationship between the void size and the maximum axial force
of the segment.

400 mm voids have a significant influence on the maximum


axial force of the segment compared with the 100–300 mm
voids.

4.2 Bending moment

Figure 14 shows the bending moment of the segment


when a void with a diameter of 300 mm is located at differ-
ent positions. As shown in Fig. 14, the existence of voids
leads to an overall increase in bending moment, except at
15°–45° and 120°–135° when b = 0°, and 315°–345° when
b = 90°. As the void location changes from the crown to
the right side of the composite lining, the bending moment
first increases and then decreases. In addition, in contrast
to the result of the axial force, the bending moment
changes are most comparable to the value of the common

Fig. 12. Variation of the axial force of the segment with different void
sizes.

each diameter are quite close, and the values under the con-
ditions of b = 0° and b = 90° are larger than those for
b = 45°. However, when the ratio increases to 1.33, i.e.,
d = 400 mm, the maximum axial force values of the seg- Fig. 14. Variation of the bending moment of the segment with different
ment increase dramatically. This result indicates that the void positions (d = 300 mm).
J.-X. Zhang et al. / Underground Space 7 (2022) 786–797 795

section at the corresponding position where the voids are Figure 15 shows how the distribution of the bending
located. The increments at the positions b = 0°, 30°, 60°, moment varies with the presence of voids of different diam-
and 90° are 72.5, 81.8, 70.6, and 83.1 Nm, respectively. eters at fixed locations behind the segment (b = 0°, 45°, and
90° in Fig. 15 (a), (b), and (c), respectively). The bending
moment increases with an increase in void size (d) for
almost the entire segment. When b = 0°, the positive bend-
ing moment increases near the crown and decreases at the
invert with an increase in void diameter. The increase in d
also causes a slight increase in the negative bending
moment on the left and right sides. The maximum bending
moment was observed in the corresponding location of
b = 0° in the segment section. When b = 45°, the bending
moment is relatively constant for d = 100–300 mm, and
only d = 400 mm causes a noticeable increase in the area
of 0–30° in the segment section. When b = 90°, the positive
bending moment in the segment section 30°–30° and
150°–210°, and the negative bending moment in the seg-
ment section of 240°–300° and 60°–120° increase with the
increase in the void size. The maximum value of the bend-
ing moment was obtained at the position where the void
was located. However, the bending moment in the other
areas remained nearly unchanged. Similar to b = 45°,
d = 400 mm produces a significant increase in the bending
moment in the segment section, especially on the right side.
When comparing Fig. 15 (a), (b), and (c), the difference
between the distribution curves in Fig. 15 (b) is minimal,
except for d = 400 mm. However, when the void is located
at the vertical and horizontal central axes (i.e., b = 0° and
b = 90°), the bending moment changes more noticeably
than that at b = 45°. The results indicate that the size of
the voids located at the top, left, and right sides of the tun-
nel has a greater influence on the bending moment
distribution.
Figures 14 and 15 show that the distribution of the
bending moment exhibits similar characteristics to the dis-
tribution of axial forces. The bending moments near the
crown and invert are negative and positive on the left
and right sides, respectively, because the entire section is
compressed. In particular, the maximum negative and pos-
itive bending moments were obtained at the horizontal and
vertical central axis, respectively.
The change in the maximum bending moment in the
cross-section when voids are present at different positions
of the composite lining is shown in Fig. 16. It can be seen
that the maximum bending moment increases significantly
as the diameter of the void increases, except at b = 45°,
where the maximum bending moment ranges from 281.2
to 285.1 Nm, and only when the ratio of void diameter
to segment thickness reaches 1.33, i.e., d = 400 mm, the
maximum bending moment increases to 302.7 Nm. The
results indicate that the size of the void at b = 0° and
b = 90° has a stronger influence on the maximum bending
moment in the cross-section of the segment than that at
b = 45°. In contrast to the variation of maximum axial
Fig. 15. Variation of the bending moment of the segment with different force, the maximum bending moment does not differ signif-
void sizes. icantly when the void diameter is larger than the segment
796 J.-X. Zhang et al. / Underground Space 7 (2022) 786–797

(1) The position of the void has a significant effect on the


internal forces, for example, bending moment and axial
forces. When a void of the same size (d = 300 mm) occurs
in different positions from the crown to the right side of the
composite lining, the axial force increases on both sides
and decreases near the crown and invert area of the
segment.
(2) The increase in the void size at a fixed position
induces an increase in the bending moment in the entire
segment. The axial force varies in different areas of the sec-
tion. With an increase in d from 100 to 300 mm, the axial
force increases on both sides. The variation trend of the
axial force near the crown and invert changes from decreas-
ing to increasing.
(3) The maximum values of the axial force and the
bending moment in the cross-section increase as the void
Fig. 16. Relationship between the void size and the maximum bending
diameter d increases. There exists a threshold value of
moment. void size (d = 300 mm), over which there is a significant
increase in both the bending moment and axial force.
Therefore, large voids should be avoided during
construction.
thickness (d = 400 mm) compared to when the diameter (4) The voids in the outside backfill cause groundwater
ranges from 100 to 300 mm. leakage in the service life of the segment and may result
in the occurrence and propagation of cracks at the segment
4.3 Suggestions for construction joint. In particular, voids occurring at the top of the tunnel
and large voids should be of concern because of their sig-
The results of the numerical simulation show that the nificant influence on the segment. Therefore, compensation
void induces a noticeable change in the stress distribution grouting is necessary for the construction of a backfill layer
of the segment. Compared with the axial forces of the seg- to reduce the occurrence of voids.
ments without voids, the axial force of the segments with
voids increases significantly on the left and right sides at Declaration of Competing Interest
the transverse section, while it varies slightly at the crown
and invert. The decrease in the axial force leads to a The authors declare that they have no known competing
decrease in the compressive pressure between the rubber financial interests or personal relationships that could have
gaskets at the crown and invert, which may cause ground- appeared to influence the work reported in this paper.
water leakage during the service life of the segment. In
addition, the void increases the bending moment in the
Acknowledgements
entire cross-section of the segment. The increase in the
bending moment may result in the occurrence and propa-
The research work described herein was funded by the
gation of cracks at the segment joint in the circumferential
Pearl River Talent Recruitment Program (Grant No.
direction. Furthermore, the maximum values of the axial
2019CX01G338), Guangdong Province and the Research
force and the bending moment of the segment increase sig-
Funding of Shantou University for New Faculty Member
nificantly when a large void occurs behind the segment.
(Grant No. NTF19024-2019).
The results indicate that the voids at the top of the tunnel
and the large size voids significantly impact the safety of
References
the segment, thus requiring treatment. In addition, it is nec-
essary to conduct compensation grouting to avoid voids Bock, S. (2014). Numerical modelling of a void behind shaft lining using
when the grout solidifies and shrinks. FDM with a concrete spalling algorithm. Journal of Sustainable
Mining, 13(2), 14–21.
Buffington, G. L. (2000). The art of blasting on construction and surface
5 Conclusions mining sites. ASSE Professional Development Conference and Exposi-
tion. American Society of Safety Engineers.
This paper presents a novel joint construction method China Academy of Building Research (CABR) (2011). Code for design of
concrete structures. GB 50010—2010. Ministry of Housing and Urban-
combining shield tunnelling with mining. To investigate Rural Development of the People’s Republic of China (MOHURD),
the influence of the voids in the backfill layer and the voids Beijing (in Cinese).
between the primary support and backfill layer on the Cui, S., Tan, Y., & Lu, Y. (2020). Algorithm for generation of 3D
polyhedrons for simulation of rock particles by DEM and its
stress state of the segment, FEM was conducted, based application to tunneling in boulder-soil matrix. Tunnelling and Under-
on which the following conclusions can be drawn: ground Space Technology, 106, 103588.
J.-X. Zhang et al. / Underground Space 7 (2022) 786–797 797

Fu, J., Xie, J., Wang, S., Yang, J., Yang, F., & Pu, H. (2019). Cracking Meguid, M. A., & Kamel, S. (2014). A three-dimensional analysis of the
performance of an operational tunnel lining due to local construction effects of erosion voids on rigid pipes. Tunnelling and Underground
defects. International Journal of Geomechanics, 19(4), 04019019. Space Technology, 43, 276–289.
Jiang, M., & Yin, Z. Y. (2014). Influence of soil conditioning on ground Min, B., Zhang, C., Zhang, X., Wang, H., Li, P., & Zhang, D. (2020).
deformation during longitudinal tunneling. Comptes Rendus Mecani- Cracking performance of asymmetric double-arch tunnels due to the
que, 342(3), 189–197. voids behind linings. Thin-Walled Structures, 154, 106856.
Jin, Y. F., Yin, Z. Y., Wu, Z. X., & Daouadji, A. (2018). Numerical Rashiddel, A., Kharghani, M., Dias, D., & Hajihassani, M. (2020).
modeling of pile penetration in silica sands considering the effect of Numerical study of the segmental tunnel lining behavior under a
grain breakage. Finite Element in Analysis and Design, 144, 15–29. surface explosion – Impact of the longitudinal joints shape. Computers
Jones, S., & Hunt, H. (2011). Voids at the tunnel–soil interface for and Geotechnics, 128, 103822.
calculation of ground vibration from underground railways. Journal of Shin, J. H., Kim, S. H., & Shin, Y. S. (2012). Long-term mechanical and
Sound and Vibration, 330(2), 245–270. hydraulic interaction and leakage evaluation of segmented tunnels.
Kavvadas, M., Litsas, D., Vazaios, I., & Fortsakis, P. (2017). Develop- Soils and Foundations, 52(1), 38–48.
ment of a 3D finite element model for shield EPB tunnelling. Tan, Y., Lu, Y., & Wang, D. (2021). Catastrophic failure of Shanghai
Tunnelling and Underground Space Technology, 65, 22–34. Metro Line 4 in July, 2003: Occurrence, emergency response, and
Lai, J., Qiu, J., Fan, H., Chen, J., Hu, Z., Zhang, Q., & Wang, J. (2017). disaster relief. Journal of Performance of Constructed Facilities, 35(1),
Structural safety assessment of existing multiarch tunnel: A case study. 04020125.
Advances in Materials Science and Engineering, 2017, 1697041. Wang, J., Huang, H., Xie, X., & Bobet, A. (2014). Void-induced liner
Leung, C., & Meguid, M. A. (2011). An experimental study of the effect of deformation and stress redistribution. Tunnelling and Underground
local contact loss on the earth pressure distribution on existing Space Technology, 40, 263–276.
tunnel linings. Tunnelling and Underground Space Technology, 26(1), Yasuda, N., Tsukada, K., & Asakura, T. (2019). Three-dimensional
139–145. seismic response of a cylindrical tunnel with voids behind the lining.
Liao, S. M., Liu, J. H., Wang, R. L., & Li, Z. M. (2009). Shield tunneling Tunnelling and Underground Space Technology, 84, 399–412.
and environment protection in Shanghai soft ground. Tunnelling and Yin, Z. Y., & Wang, J. H. (2012). A one-dimensional strain-rate based
Underground Space Technology, 24(4), 454–465. model for soft structured clays. Science China Technological Sciences,
Li, Z. C., Wang, R. L., & Chen, Y. Z. (2019). Theoretical and numerical 55(1), 90–100.
analyses of the structural stability of the pipe-grout-liner system with a Yin, Z. Y., Wu, Z. X., & Hicher, P. Y. (2018). Modeling monotonic and
crown void subjected to external pressure. Composites Part B: cyclic behavior of granular materials by exponential constitutive
Engineering, 173, 106944. function. Journal of Engineering Mechanics, 144(4), 04018014.
Lu, Y., Tan, Y., Yang, B., & Chen, W. L. (2021). Ground subsidence Zhang, J. X., Zhang, N. & Xu, Y. S. (2021). Data on point cloud scanning
hazards due to crushing and removing large isolated boulder by and ground radar of composite lining in jointly constructed tunnel,
tunneling. Journal of Performance of Constructed Facilities, 35(2), Data in Brief, Under Review.
04020149. Zhang, Y., Shi, Y., Zhao, Y., & Yang, J. (2017). Damage in Concrete
Mair, R. (2008). Tunnelling and geotechnics: new horizons. Géotechnique, Lining of an Operational Tunnel. Journal of Performance of Con-
58(9), 695–736. structed Facilities, 31(4), 06017002.
Meguid, M. A., & Dang, H. (2009). The effect of erosion voids on existing Zhu, Q. Y., Yin, Z. Y., Hicher, P. Y., & Shen, S. L. (2016). Nonlinearity of
tunnel linings. Tunnelling and Underground Space Technology, 24(3), one-dimensional creep characteristics of soft clays. Acta Geotechnica,
278–286. 11(4), 887–900.

You might also like