HARGA JUMLAH
No. URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
Rp. Rp.
1 2 3 4 5 6
A PEKERJAAN PENDAHULUAN
I Uitzet 1.00 Ls 500,000.00 500,000.00
Sub Jumlah 500,000.00
II PEKERJAAN K3
1 Biaya K3
Sosialisasi, Promosi dan Pelatihan
a Induksi K3 (Safety Induction) 25.00 Org 5,000.00 125,000.00
b P3K 5.00 Org 500,000.00 2,500,000.00
c Papan Informasi K3 5.00 Bh 100,000.00 500,000.00
Alat Pelindung Kerja (APK) dan Alat Pelindung Diri (APD)
a Topi Pelindung (Safety Helmet) 25.00 Bh 50,000.00 1,250,000.00
b Sarung Tangan (Safety Gloves) 25.00 Psg 15,000.00 375,000.00
c Sepatu Keselamatan Kerja (Safety Shoes) 25.00 Psg 150,000.00 3,750,000.00
d Rompi Keselamatan (Safety Vest) 25.00 Bh 35,000.00 875,000.00
Personil K3 Konstruksi
a Rambu Peringatan 10.00 Bh 100,000.00 1,000,000.00
b Safety Line 1.00 Ls 250,000.00 250,000.00
c Papan Nama Proyek 5.00 Ls 250,000.00 1,250,000.00
Sub Jumlah 11,875,000.00
JUMLAH 12,375,000.00
B RENOVASI BALAI RW 01 WELIRANG PERUMAHAN TENGAH
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pembersihan Awal dan Akhir 1.00 ls 500,000.00 500,000.00
2 Pekerjaan Pembongkaran Atap Lama 1.00 ls 2,000,000.00 2,000,000.00
Sub Jumlah 2,500,000.00
II PEKERJAAN BETON
1 Pekerjaan Ring Balk 10x15cm -
a Pekerjaan Beton K250 0.75 m3 1,142,831.42 861,409.18
b Pekerjaan Pembesian 235.28 kg 17,185.88 4,043,426.13
c Pekerjaan Begesting 10.05 m2 289,143.75 2,905,894.69
Sub Jumlah 7,810,729.99
III PEKERJAAN PASANGAN
1 Pekerjaan Pasangan Bata 1PC : 5 PS 23.20 m2 123,764.55 2,871,337.56
2 Pekerjaan Plesteran 1PC : 5PS 46.40 m2 74,218.41 3,443,734.22
3 Pekerjaan Acian 46.40 m2 45,648.75 2,118,102.00
Sub Jumlah 8,433,173.78
IV PEKERJAAN ATAP
1 Pekerjaan Rangka Atap Galvalum 126.88 m2 293,202.63 37,200,083.68
2 Pekerjaan Pentutup Atap Genteng Karang Pilang 47.20 m2 187,766.25 8,862,567.00
3 Pekerjaan Bubungan Karang Pilang 24.00 m2 170,562.00 4,093,488.00
4 Pekerjaan Kalsiplank 2x30 30.00 m1 64,575.00 1,937,250.00
5 Pekerjaan Pasang Genteng lama 333.43 m2 28,825.00 9,610,975.63
Sub Jumlah 61,704,364.31
JUMLAH 80,448,268.08
C REHAB BALAI RW 05 LINGKUNGAN PERUMAHAN TENGAH
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pembersihan Awal dan Akhir 1.00 ls 500,000.00 500,000.00
2 Pengukuran & Pemasangan Bowplank 1.00 ls 500,000.00 500,000.00
Sub Jumlah 1,000,000.00
II PEKERJAAN TANAH
1 Pekerjaan Galian 11.52 m3 98,437.50 1,134,000.00
2 Pekerjaan Urug Kembali 3.80 m3 32,812.50 124,740.00
3 Pekerjaan Urug Sirtu Leveling 2.52 m3 291,375.00 734,265.00
4 Pekerjaan Urug Pasir Bawah Pondasi 1.15 m3 285,075.00 328,406.40
Sub Jumlah 2,321,411.40
III PEKERJAAN PONDASI
1 Pekerjaan Aanstamping 2.30 m3 534,318.75 1,231,070.40
2 Pekerjaan Pondasi Batu Kali 1PC : 4PS 5.18 m3 931,323.75 4,827,982.32
Sub Jumlah 6,059,052.72
IV PEKERJAAN BETON
1 Pekerjaan Sloof S1 15x20 -
a Pekerjaan Beton K250 0.43 m3 1,142,831.42 493,703.17
b Pekerjaan Pembesian 73.48 kg 17,185.88 1,262,867.15
c Pekerjaan Begesting 5.76 m2 132,772.50 764,769.60
V PEKERJAAN PASANGAN
1 Pekerjaan Pasangan Trasram 1PC : 3PC 4.08 m2 124,801.95 509,191.96
2 Pekerjaan Pasangan Bata 1PC : 5 PS 29.34 m2 123,764.55 3,631,251.90
3 Pekerjaan Plesteran 1PC : 5PS 66.84 m2 74,218.41 4,960,758.52
4 Pekerjaan Acian 66.84 m2 45,648.75 3,051,162.45
Sub Jumlah 12,152,364.83
VI PEKERJAAN ATAP
1 Pekerjaan Rangka Atap Galvalum 9.00 m2 293,202.63 2,638,823.67
2 Pekerjaan Penutup Atap Seng Galvalum 9.00 m2 125,580.00 1,130,220.00
Sub Jumlah 3,769,043.67
VII PEKERJAAN PLAFON
1 Pekerjaan Rangka Plafon Hollow 4x4 Modul 2x4 6.08 m2 309,986.25 1,883,166.47
2 Pekekerjaan Plafon Kalsiboard 6.08 m2 51,863.91 315,073.25
Sub Jumlah 2,198,239.72
VIII PEKERJAAN KERAMIK
1 Pekerjaan Rabat Lantai 5cm 0.30 m3 957,586.25 290,866.82
2 Pekerjaan Keramik 40x40 Polos 6.08 m2 210,960.75 1,281,586.56
Sub Jumlah 1,572,453.38
IX PEKERJAAN PINTU JENDELA
1 Pekerjaan P4 1.00 unit 1,963,676.57 1,963,676.57
2 Pekerjaan J3 2.00 unit 1,163,195.24 2,326,390.48
Sub Jumlah 4,290,067.05
X PEKERJAAN ELEKTRIKAL
1 Pekerjaan Instalasi Titik Lampu dan Stop Kontak 3.00 titik 117,285.00 351,855.00
2 Pekerjaan Lampu SL 20 Watt 2.00 titik 68,932.50 137,865.00
3 Pekerjaan Stop Kontak 1.00 titik 62,212.50 62,212.50
4 Pekerjaan Saklar Tunggal 1.00 titik 62,212.50 62,212.50
Sub Jumlah 614,145.00
JUMLAH 39,629,793.36
E REHAB ATAP KROPOS BALAI RW PANDERMAN BARAT (BELAKANG TAMSIS) ,PANDERMAN 8
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pembersihan Awal dan Akhir 1.00 ls 500,000.00 500,000.00
2 Pekerjaan Pembongkaran Meja Dapur Lama 1.00 ls 150,000.00 150,000.00
3 Pekerjaan Pembongkaran Atap Lama 1.00 ls 1,600,000.00 1,600,000.00
4 Pekerjaan Pembongkaran Aksesoris Kamar Mandi - ls 250,000.00 -
Sub Jumlah 2,250,000.00
II PEKERJAAN BETON
1 Pekerjaan Pembuatan Meja Dapur -
a Pekerjaan Beton 0.18 m3 1,142,831.42 205,709.66
b Pekerjaan Pembesian Ø10 1.85 kg 17,185.88 31,785.28
c Pekerjaan Begesting 3.62 m2 289,143.75 1,046,700.38
۞ 1 m3 Membuat Beton mutu F'c = 19.3 Mpa ( K 225 ), Slump ( 12 ± 2 ) Cm, w/c = 0.58
Bahan An. SNI 2008 6.7
371.000 Kg Semen portland @ Rp. 1,300.00 = Rp 482,300.00
0.499 m3 Pasir beton @ Rp. 250,000.00 = Rp 124,750.00
0.776 m3 Kerikil ( Maksimum 30 mm ) @ Rp. 258,000.00 = Rp 200,208.00
215.000 Liter Air @ Rp. 100.00 = Rp 21,500.00
Total Bahan = Rp 828,758.00
Upah An. SNI 2008 6.7
1.650 Oh Pekerja @ Rp. 120,000.00 = Rp 198,000.00
0.275 Oh Tukang batu @ Rp. 115,000.00 = Rp 31,625.00
0.028 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,500.00
0.083 Oh Mandor @ Rp. 150,000.00 = Rp 12,450.00
= Rp 245,575.00
Total harga = Rp 1,074,333.00
Overhead + Provit 5 % = Rp 53,716.65
Harga satuan pekerjaan = Rp 1,128,049.65
۞ 1 m3 Membuat beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
Bahan ( SNI 7394:2008 ) 6.8
384.000 Kg Semen portland @ Rp. 1,300.00 = Rp 499,200.00
0.494 m3 Pasir beton @ Rp. 250,000.00 = Rp 123,571.43
0.770 m3 Kerikil ( Maksimum 30 mm ) @ Rp. 258,000.00 = Rp 198,564.44
215.000 Liter Air @ Rp. 100.00 = Rp 21,500.00
Total Bahan = Rp 842,835.87
Upah ( SNI 7394:2008 ) 6.8
1.650 Oh Pekerja @ Rp. 120,000.00 = Rp 198,000.00
0.275 Oh Tukang batu @ Rp. 115,000.00 = Rp 31,625.00
0.028 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,500.00
0.083 Oh Mandor @ Rp. 150,000.00 = Rp 12,450.00
= Rp 245,575.00
Total harga = Rp 1,088,410.87
Overhead + Provit 5 % = Rp 54,420.54
Harga satuan pekerjaan = Rp 1,142,831.42
II PEKERJAAN TANAH
1 Pekerjaan Galian 18.00 1.00 1.00 19.00 #REF!
2 Pekerjaan Urug Kembali 0.33 19.00 6.33 #REF!
3 Pekerjaan Urug Sirtu Leveling 3.00 6.00 0.20 3.60 #REF!
4 Pekerjaan Urug Pasir Bawah Pondasi 3.00 6.00 0.10 1.80 #REF!
V PEKERJAAN BETON
1 Pekerjaan Sloof S1 15x20 18.00 0.15 0.20 0.54 #REF!
a. Pekerjaan Beton K250 18.00 0.15 0.20 0.54 m3
b. Pekerjaan Pembesian berat jenis
Tulangan Pokok Ø12 18.00 0.89 4.00 63.92 91.85 kg
Begel Ø8 18.00 0.39 0.59 27.93
c. Pekerjaan Bekisting 18.00 0.20 2.00 7.20 m2
VI PEKERJAAN PASANGAN
1 Pekerjaan Pasangan Trasram 1PC : 3PC 18.00 0.40 7.20 6.84 #REF!
pengurangan kusen 0.90 0.40 0.36
2 Pekerjaan Pasangan Bata 1PC : 5 PS 18.00 2.90 52.20 50.44 #REF!
pengurangan kusen
pintu 0.90 1.60 1.44
boven 0.40 0.40 2.00 0.32
3 Pekerjaan Plesteran 1PC : 5PS 2.00 57.28 114.56 #REF!
X PEKERJAAN ELEKTRIKAL
1 Pekerjaan Instalasi Titik Lampu dan Stop Kontak 3.00 #REF!
2 Pekerjaan Lampu SL 20 Watt 2.00 #REF!
3 Pekerjaan Stop Kontak 1.00 #REF!
4 Pekerjaan Saklar Tunggal 2.00 #REF!
BALAI RW 8 PANDERMAN BARAT
BACK UP VOLUME
NO URAIAN PEKERJAAN Koef/ SATUAN Ket.
Panjang Lebar Tinggi Jumlah Luas Sub Vol Volume
Berat
1 2 3 4 5 6 7 8 9 10 11 12
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pembersihan Awal dan Akhir 1.00 #REF!
2 Pekerjaan Pembongkaran Meja Dapur Lama 1.00 #REF!
3 Pekerjaan Pembongkaran Atap Lama 1.00 #REF!
4 Pekerjaan Pembongkaran Aksesoris Kamar Mandi 1.00 #REF!
II PEKERJAAN BETON
1 Pekerjaan Pembuatan Meja Dapur 5.00 0.60 0.06 0.18 #REF!
a. Pekerjaan Berton K250 5.00 0.60 0.06 0.18
b. Pekerjaan Pembesian
Tulangan Pokok Ø10 5.00 0.60 0.62 1.85 kg
c. Pekerjaan Bekisting 6.20 0.10 0.62 3.62 m2
5.00 0.60 3.00
IV PEKERJAAN ATAP
1 Pekerjaan Rangka Atap Galvalum 13.30 4.18 55.53 79.22 #REF!
km 2.65 1.30 3.45
gudang 4.45 4.55 20.25
2 Pekerjaan Penutup Atap Seng Galvalum 79.22 #REF!
V PEKERJAAN PLAFON
1 Pekerjaan Rangka Plafon Hollow 4x4 Modul 2x4 12.50 3.38 42.19 59.32 #REF!
km 2.65 1.30 3.45
gudang 3.65 3.75 13.69
2 Pekekerjaan Plafon Kalsiboard 59.32 #REF!
VI PEKERJAAN KERAMIK
1 Pekerjaan Keramik 25x25 Polos KM 3.45 #REF!
2 Pekerjaan Keramik Dinding 25x40 10.50 1.60 16.80 15.52 #REF!
pengurangan KM 0.80 1.60 1.28
3 Pekerjaan Keramik Meja Dapur 60x60 5.00 0.80 4.00 #REF!
IX PEKERJAAN SANITAIR
1 Pekerjaan Pipa 3/4' 15.00 #REF!
2 Pekerjaan Pasang Kloset duuk 1.00 #REF!
3 Pekerjaan Pasang Kran 2.00 #REF!
4 Pekerjaan Sink 1.00 #REF!
5 Pekerjaan Pasang Floor Drain 2.00 #REF!
X PEKERJAAN ELEKTRIKAL
1 Pekerjaan Instalasi Titik Lampu dan Stop Kontak 8.00 #REF!
2 Pekerjaan Lampu SL 20 Watt 6.00 #REF!
3 Pekerjaan Stop Kontak 2.00 #REF!
4 Pekerjaan Saklar Tunggal 2.00 #REF!
5 Pekerjaan Saklar Ganda 1.00 #REF!
BALAI RW 1 WELIRANG
BACK UP VOLUME
NO URAIAN PEKERJAAN Koef/ SATUAN Ket.
Panjang Lebar Tinggi Jumlah Luas Sub Vol Volume
Berat
1 2 3 4 5 6 7 8 9 10 11 12
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pembersihan Awal dan Akhir 1.00 #REF!
2 Pekerjaan Pembongkaran Atap Lama 1.00 #REF!
II PEKERJAAN BETON
1 Pekerjaan Ring Balok 15x10 50.25 0.15 0.10 0.75 #REF!
a. Pekerjaan Beton K250
b. Pekerjaan Pembesian 235.28 kg
Tulangan Pokok Ø12 50.25 0.89 4.00 178.44
Begel Ø8 50.25 0.39 0.43 56.84
c. Pekerjaan Bekisting 50.25 0.10 2.00 10.05 m2
IV PEKERJAAN ATAP
1 Pekerjaan Rangka Atap Galvalum 126.88 #REF!
pendopo 10.00 0.50 6.00 4.00 120.00
kantor 10.00 2.75 0.25 6.88
2 Pekerjaan Pentutup Atap Genteng Karang Pilang 47.20 #REF! tambal sulam
pendopo 10.00 0.50 6.00 32% 4.00 38.40
kantor 10.00 2.75 32% 8.80
3 Pekerjaan Bubungan Karang Pilang 6.00 4.00 24.00 #REF!
4 Pekerjaan Kalsiplank 2x30 10.00 3.00 30.00 #REF!
5 Pekerjaan Pasang Genteng lama 10.00 3.00 380.63 #REF!
pendopo 3.00 120.00 360.00 333.43 m2
kantor 3.00 6.88 20.63
BALAI RW 5 KELUD
BACK UP VOLUME
NO URAIAN PEKERJAAN Koef/ SATUAN Ket.
Panjang Lebar Tinggi Jumlah Luas Sub Vol Volume
Berat
1 2 3 4 5 6 7 8 9 10 11 12
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pembersihan Awal dan Akhir 1.00 #REF!
2 Pengukuran & Pemasangan Bowplank 14.40 1.00 #REF!
II PEKERJAAN TANAH
1 Pekerjaan Galian 14.40 0.80 1.00 11.52 #REF!
2 Pekerjaan Urug Kembali 0.33 11.52 3.80 #REF!
3 Pekerjaan Urug Sirtu Leveling 4.20 3.00 0.20 2.52 #REF!
4 Pekerjaan Urug Pasir Bawah Pondasi 14.40 0.80 0.10 1.15 #REF!
V PEKERJAAN BETON
1 Pekerjaan Sloof S1 15x20 14.40 0.15 0.20 0.43 #REF!
a. Pekerjaan Berton K250 14.40 0.15 0.20
b. Pembesian 73.48 kg
tulangan utama Ø12 14.40 0.89 4.00 51.13
begel Ø8 14.40 0.39 0.59 22.35
c. Bekisting 14.40 0.20 2.00 5.76
2 Pekerjaan Kolom K1 15x15 0.15 0.15 4.00 6.00 0.54 #REF!
a. Pekerjaan Berton K250 0.15 0.15 4.00 6.00 0.54
b. Pekerjaan Pembesian 118.68 kg
Tulangan Pokok Ø12 4.00 0.89 24.00 85.22
Begel Ø8 24.00 0.39 0.53 33.46
c. Pekerjaan Bekisting 0.15 4.00 24.00 14.40 m2
5 Pekerjaan Ring Balk 10x12 14.40 0.15 0.10 0.22 0.22 #REF!
a. Pekerjaan Berton K250
b. Pekerjaan Pembesian 67.42 kg
Tulangan Pokok Ø12 14.40 0.89 4.00 51.13
Begel Ø8 14.40 0.39 0.43 16.29
c. Pekerjaan Bekisting 14.40 0.10 2.00 2.88 m2
VI PEKERJAAN PASANGAN
1 Pekerjaan Pasangan Trasram 1PC : 3PC 14.40 0.40 5.76 5.44 #REF!
Pengurangan 0.80 0.40 0.32
Kusen Pintu
2 Pekerjaan Pasangan Bata 1PC : 5 PS 14.40 2.60 37.44 34.88 #REF!
gewel 4.20 2.00 0.50 2.00 8.40
Pengurangan
Kusen Pintu 0.80 1.70 1.36
Kusen Jendela 0.60 1.00 2.00 1.20
3 Pekerjaan Plesteran 1PC : 5PS 2.00 40.32 80.64 #REF!
4 Pekerjaan Acian 80.64 #REF!
IX PEKERJAAN KERAMIK
1 Pekerjaan Rabat Lantai 5cm 4.20 3.00 0.05 0.63 #REF!
2 Pekerjaan Keramik 40x40 Polos 4.20 3.00 12.60 #REF!
X PEKERJAAN PENGECATAN
1 Pekerjaan Pengecatan Dinding 80.64 #REF!
gedung baru 80.64
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pembersihan Awal dan Akhir 1.00 #REF!
2 Pekerjaan Pembongkaran Gedung Lama 1.00 #REF!
3 Pengukuran & Pemasangan Bowplank 8.80 4.70 1.00 #REF!
II PEKERJAAN TANAH
1 Pekerjaan Galian 22.40 #REF!
Gedung A 8.60 0.80 1.00 6.88
Gedung B 19.40 0.80 1.00 15.52
2 Pekerjaan Urug Kembali 0.33 22.40 7.46 #REF!
3 Pekerjaan Urug Sirtu Leveling areacad 6.93 #REF!
Gedung A 3.00 2.80 0.20 1.68
Gedung B 5.00 4.70 0.20 4.70
Teras 0.15 16.39 0.55
4 Pekerjaan Urug Pasir Bawah Pondasi 1.12 #REF!
Gedung A 8.60 0.80 0.05 0.34
Gedung B 19.40 0.80 0.05 0.78
IV PEKERJAAN BETON
1 Pekerjaan Sloof S1 15x20 0.84 #REF!
Gedung A 8.60 0.15 0.20 0.26
a. Pekerjaan Berton K250
b. Pekerjaan Pembesian 142.88 kg
Tulangan Pokok Ø12 8.60 0.89 4.00 30.54
Begel Ø8 8.60 0.39 0.59 13.35
c. Pekerjaan Bekisting 8.60 0.20 2.00 3.44 11.20 m2
Gedung B 19.40 0.15 0.20 0.58
a. Pekerjaan Beton K250
b. Pekerjaan Pembesian
Tulangan Pokok Ø12 19.40 0.89 4.00 68.89
Begel Ø8 19.40 0.39 0.59 30.11
c. Pekerjaan Bekisting 19.40 0.20 2.00 7.76
V PEKERJAAN PASANGAN
1 Pekerjaan Pasangan Bata 1PC : 5 PS 9.84 #REF!
Gedung A 8.60 0.40 3.44
Gedung B 19.40 0.40 7.76
pengurangan kusen
P1 1.30 0.40 2.00 1.04
P2 0.80 0.40 1.00 0.32
2 Pekerjaan Pasangan Bata 1PC : 5 PS 75.04 #REF!
Gedung A 8.60 2.90 24.94
Gedung B 19.40 2.90 56.26
pengurangan kusen
P1 1.30 1.60 2.00 4.16
P2 0.80 1.60 1.00 1.28
J1 0.60 1.20 1.00 0.72
3 Pekerjaan Plesteran 1PC : 5PS 2.00 75.04 150.08 #REF!
4 Pekerjaan Acian 150.08 #REF!
5 Pekerjaan Benangan 3.30 8.00 26.40 #REF!
VI PEKERJAAN ATAP
1 Pekerjaan Rangka Atap Galvalum 8.80 6.50 57.20 #REF!
2 Pekerjaan Penutup Atap Geteng Karang Pilang 57.20 #REF!
3 Pekerjaan Bubungan Karang pilang 8.80 #REF!
4 Pekerjaan Kalsiplank 2/30 8.80 2.00 17.60 #REF!
5 Pekerjaan Talang PVC + Pipa 2'' 12.80 12.80 #REF!
IX PEKERJAAN PENGECATAN
1 Pekerjaan Pengecatan Dinding 150.08 #REF!
2 Pekerjaan Pengecatan Plafon 45.21 #REF!
XI PEKERJAAN ELEKTRIKAL
1 Pekerjaan Instalasi Titik Lampu dan Stop Kontak 8.00 #REF!
2 Pekerjaan Lampu SL 20 Watt 6.00 #REF!
3 Pekerjaan Stop Kontak 2.00 #REF!
4 Pekerjaan Saklar Tunggal 3.00 #REF!
BALAI RW TENGGER RAYA
BACK UP VOLUME
NO URAIAN PEKERJAAN Koef/ SATUAN Ket.
Panjang Lebar Tinggi Jumlah Luas Sub Vol Volume
Berat
1 2 3 4 5 6 7 8 9 10 11 12
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pembersihan Awal dan Akhir 1.00 ls
II PEKERJAAN PASANGAN
1 Pekerjaan Pasangan Bata 1PC : 5 PS 40.95 0.13 5.32 m2
2 Pekerjaan Plesteran 1PC : 5PS 2.00 60.37 120.74 m2
3 Pekerjaan Acian 120.74 m2
4 Pekerjaan Benangan 60.37 2.00 120.74 m1
IV PEKERJAAN ROSTER
1 Pekerjaan Pintu Harmonika 1.00 unit
2 Pekerjaan Pintu Besi Finish Cat 1.00 unit
3 Pekerjaan Roster 46.25 0.20 0.20 40.95 1156.25 1024.00 unit pembulatan
POS KEAMANAN BROMO
BACK UP VOLUME
NO URAIAN PEKERJAAN Koef/ SATUAN Ket.
Panjang Lebar Tinggi Jumlah Luas Sub Vol Volume
Berat
1 2 3 4 5 6 7 8 9 10 11 12
II PEKERJAAN TANAH
1 Pekerjaan Galian 11.00 0.80 1.00 8.80 #REF!
2 Pekerjaan Urug Pasir Bawah Pondasi 11.00 0.80 0.05 0.44 #REF!
IV PEKERJAAN BETON
1 Pekerjaan Sloof S1 15x20 11.00 0.15 0.20 0.33 #REF!
a. Pekerjaan Berton K250
b. Pekerjaan Pembesian 56.13
Tulangan Pokok Ø12 11.00 0.89 4.00 39.06
Begel Ø8 11.00 0.39 0.59 17.07
c. Pekerjaan Bekisting 11.00 0.20 2.00 4.40
VI PEKERJAAN ATAP
1 Pekerjaan Rangka Atap Galvalum 4.50 2.00 9.00 #REF!
2 Pekerjaan Penutup Atap Seng Galvalum 9.00 #REF!
X PEKERJAAN ELEKTRIKAL
1 Pekerjaan Instalasi Titik Lampu dan Stop Kontak 3.00 #REF!
2 Pekerjaan Lampu SL 20 Watt 2.00 #REF!
3 Pekerjaan Stop Kontak 1.00 #REF!
4 Pekerjaan Saklar Tunggal 1.00 #REF!
GEDUNG SERBAGUNA (PENDOPO)
BACK UP VOLUME
NO URAIAN PEKERJAAN Koef/ SATUAN Ket.
Panjang Lebar Tinggi Jumlah Luas Sub Vol Volume
Berat
1 2 3 4 5 6 7 8 9 10 11 12
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pembersihan Awal dan Akhir 1.00 #REF!
2 Pengukuran & Pemasangan Bowplank 8.00 8.00 1.00 #REF!
II PEKERJAAN TANAH
1 Pekerjaan Bor Strouss Diameter 25 cm 3.00 14.00 42.00 #REF!
2 Pekerjaan Galian Pile Cap 0.60 0.60 1.00 14.00 5.04 #REF!
3 Pekerjaan Urug Kembali 3.78 #REF!
4 Pekerjaan Urug Sirtu Leveling 8.00 8.00 0.40 25.60 28.43 #REF!
2.66 2.66 0.40 2.83
IV PEKERJAAN BETON
1 Pekerjaan Sloof S1 15x20 39.72 0.15 0.20 1.19 #REF!
a. Pekerjaan Berton K250
b. Pekerjaan Pembesian 202.69 kg
Tulangan Pokok Ø12 39.72 0.89 4.00 141.05
Begel Ø8 39.72 0.39 0.59 61.64
c. Pekerjaan Bekisting 39.72 0.20 2.00 15.89
1 2 3 4
A PEKERJAAN PENDAHULUAN Rp 5,725,000.00
Terbilang :
Mengetahui :
Mengetahui : Jombang, 2020
Mengetahui / Menyetujui Dibuat Oleh:
LURAH WATES Konsultan Perencana
SELAKU CV. BAGUS BASKARA CONSULTANT
PEJABAT PEMBUAT KOMITMEN
HARGA JUMLAH
No. URAIAN PEKERJAAN VOLUME SAT SATUAN BARU HARGA BARU
Rp. Rp.
A PEKERJAAN PENDAHULUAN
I Pekerjaan Uitzet 1.00 Ls 500,000.00 500,000.00
Sub Jumlah 500,000.00
II PEKERJAAN K3
1 Biaya K3
Sosialisasi, Promosi dan Pelatihan
a Induksi K3 (Safety Induction) 15.00 Org 5,000.00 75,000.00
b P3K 1.00 Org 500,000.00 500,000.00
c Papan Informasi K3 1.00 Bh 100,000.00 100,000.00
Alat Pelindung Kerja (APK) dan Alat Pelindung Diri (APD)
a Topi Pelindung (Safety Helmet) 15.00 Bh 50,000.00 750,000.00
b Sarung Tangan (Safety Gloves) 15.00 Psg 15,000.00 225,000.00
c Sepatu Keselamatan Kerja (Safety Shoes) 15.00 Psg 150,000.00 2,250,000.00
d Rompi Keselamatan (Safety Vest) 15.00 Bh 35,000.00 525,000.00
Rambu Rambu Yang Diperlukan
a Rambu Peringatan 3.00 Bh 100,000.00 300,000.00
b Safety Line 1.00 Ls 250,000.00 250,000.00
c Papan Nama Proyek 3.00 Ls 250,000.00 750,000.00
Sub Jumlah 5,725,000.00
JUMLAH 6,225,000.00
B PEKERJAAN RENOVASI BALAI RW TENGGER RAYA WATES
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pembersihan Awal dan Akhir 1.00 ls 500,000.00 500,000.00
Sub Jumlah 500,000.00
II PEKERJAAN PASANGAN
1 Pekerjaan Pasangan Bata 1PC : 5 PS 5.32 m2 123,764.55 658,860.58
2 Pekerjaan Plesteran 1PC : 5PS 120.74 m2 74,218.41 8,960,906.68
3 Pekerjaan Acian 120.74 m2 45,648.75 5,511,492.22
4 Pekerjaan Benangan 120.74 m1 20,574.75 2,484,133.18
Sub Jumlah 17,615,392.66
III PEKERJAAN PENGECATAN
1 Pekerjaan Pengecatan Dinding 548.40 m2 52,749.38 28,927,757.25
Sub Jumlah 28,927,757.25
IV PEKERJAAN ROSTER
1 Pekerjaan Pintu Harmonika 1.00 unit 5,845,000.00 5,845,000.00
2 Pekerjaan Pintu Besi Finish Cat 1.00 unit 4,950,000.00 4,950,000.00
3 Pekerjaan Roster 1,024.00 unit 13,006.36 13,318,512.64
Sub Jumlah 24,113,512.64
JUMLAH 71,156,662.55
C GEDUNG PERTEMUAN BANCANG GG V RT.02 RW.03
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pembersihan Awal dan Akhir 1.00 ls 500,000.00 500,000.00
2 Pekerjaan Pembongkaran Gedung Lama 1.00 ls 500,000.00 500,000.00
3 Pengukuran & Pemasangan Bowplank 1.00 ls 500,000.00 500,000.00
Sub Jumlah 1,500,000.00
II PEKERJAAN TANAH
1 Pekerjaan Galian 22.40 m3 98,437.50 2,205,000.00
2 Pekerjaan Urug Kembali 7.46 m3 32,812.50 244,755.00
3 Pekerjaan Urug Sirtu Leveling 6.93 m3 291,375.00 2,019,228.75
4 Pekerjaan Urug Pasir Bawah Pondasi 1.12 m3 285,075.00 319,284.00
Sub Jumlah 4,788,267.75
III PEKERJAAN PONDASI
1 Pekerjaan Aanstamping 4.48 m3 534,318.75 2,393,748.00
2 Pekerjaan Pondasi Batu Kali 1PC : 4PS 10.08 m3 931,323.75 9,387,743.40
3 Pekerjaan Pasangan Bata Teras 1PC : 5 PS 4.56 m2 123,764.55 564,366.35
Sub Jumlah 12,345,857.75
IV PEKERJAAN BETON
1 Pekerjaan Sloof S1 15x20 -
a Pekerjaan Beton K250 0.84 m3 1,142,831.42 959,978.39
b Pekerjaan Pembesian 142.88 kg 17,185.88 2,455,575.01
c Pekerjaan Begesting 11.20 m2 132,772.50 1,487,052.00
۞ 1 m2 Membuat acian
Bahan ( SNI 2837:2008 ) 6.27
3.250 kg Semen portland @ Rp. 1,300.00 = Rp. 4,225.00
Total bahan = Rp. 4,225.00
A. PEKERJAAN PERSIAPAN
1. Pembersihan Lapangan dan Bongkaran Gedung Existing 1.00 Ls 1.00 Ls
2. Pemasangan Jembatan Sementara ( box culvert 150.150.100) 10.00 bh 10.00 bh
3. Pengukuran & Pemasangan Bowplank 26.66 M 26.66 M
4. Papan Nama Proyek 1.00 Bh 1.00 Bh
B. PEKERJAAN STRUKTUR
I PEKERJAAN TANAH DAN URUGAN
Û Pondasi Setempat P1 = 1.40 x 1.20 x 1.10
= 1.85 x 17 Bh
= 31.42 m3
0.30 + 0.80
VP2 = x 1.30 x 260.50
2.00
= 186.26 m3
Bagian bawah = 260.50 x 1.00 x 0.30
= 78.15 m3
Total VP2 = 264.41 m3
0.30 + 0.65
VP3 = x 0.65 x 118.85
2.00
= 36.69 m3
Bagian bawah = 118.85 x 0.75 x 0.15
= 13.37 m3
Total VP3 = 50.07 m3
Pas . Foot Plat FP1 ( 140 x 120 x 60 ) V1 = 1.40 x 1.20 x 0.60 x 17.00 Bh
= 17.14 m3 17.14 m3
Pas. Kolom 45 x 45 ( K1 )
Û Lantai 1 P = 0.45 x 0.45 x 4.00 x 6 Bh
= 4.86 m3 4.86 m3
Pas. Kolom 40 x 40 ( K2 )
Û Lantai 1 P = 0.40 x 0.40 x 4.00 x 14 Bh
= 8.96 m3 8.96 m3
Pas. Kolom 30 x 30 ( K3 )
Û Lantai 1 P = 0.30 x 0.30 x 4.00 x 33 Bh
= 11.88 m3 11.88 m3
Pas. Kolom 15 x 15 ( K5 )
Û Lantai 1 P = 0.15 x 0.15 x 4.00 x 88 Bh
= 7.92 m3 7.92 m3
Pas . Balok
Lantai 1
Û Balok (B1) 30 x 65 P = 0.30 x 0.65 x 87.5 m1
= 17.06 m3 17.06 m3
Plat Canopi
Û Canopi Lantai 1 t : 5 cm = 1.50 x 0.40 x 0.05 x 9 Bh
= 1.40 x 0.40 x 0.05 x 1 Bh
= 3.15 x 0.40 x 0.05 x 2 Bh
= 2.30 x 0.40 x 0.05 x 1 Bh
= 2.55 x 0.40 x 0.05 x 1 Bh
= 1.90 x 0.40 x 0.05 x 1 Bh
LANTAI - 2
Keterangan Perhitungan Volume
Pas. Kolom 20 x 30 ( K4 )
Û Lantai 2 P = 0.20 x 0.30 x 4.00 x 3.00 Bh
= 0.72 m3 0.72 m3
Lantai 2
Û Balok (B1) 30 x 65 P = 0.30 x 0.65 x 103 m1
= 20.09 m3 20.09 m3
C. PEKERJAAN ARSITEKTUR
1 PEKERJAAN DINDING
LANTAI - 1
Pas. Dinding 1/2 bata 1 Pc : 5 Ps
Û Ruangan Lantai 1
Lantai 1
S Ruangan Lantai 1
= L. dinding - L. Lubang Kusen
= 1690.85 - 237.20 m²
= 1453.64 m2 1453.64 m2
LANTAI - 2
Pas. Dinding 1/2 bata 1 Pc : 5 Ps
Û Ruangan Lantai 2
Lantai 2
L2 = 126.50 - 9.45
= 115.30 x 3.60
= 415.08 m2
Lubang Kusen
Keterangan Perhitungan Volume
S Ruangan Lantai 2
= L. dinding - L. Lubang Kusen
= 640.78 - 203.67 m²
= 437.11 m2 437.11 m2
Lantai 2
Vertikal Kolom P = 10.00 x 4 x 3.7 = 148.00 m'
Sudut P = 15.00 x 4 = 60.00 m'
Canopi P = 15.50 = 15.50 m'
Jendela P = 133.14 = m'
S Pas. Benangan Sudut
= 223.50 m' 223.50 m'
2 PEKERJAAN ATAP
Pas . Rangka Atap WF 200.100.5,5.8
Panjang kuda kuda (B) P = 90.75 m' = 90.75 m'
Panjang kuda kuda (C) P = 86.25 m' = 86.25 m'
Panjang kolom kuda kuda (B) P = 10.25 m' = 10.25 m'
Panjang kolom kuda kuda (C) P = 15.75 m' = 15.75 m'
203.00 m'
5. Pas. Baut 16 x 8 cm
Panjang kuda kuda (B) S = 60.00 bh = 60.00 bh
Panjang kuda kuda (C) S = 60.00 bh = 60.00 bh
Keterangan Perhitungan Volume
120.00 bh 120.00 bh
4 PEKERJAAN LANTAI
LANTAI - 1
1. Pas. Keramik lantai 40 x 40 polos
Lantai 1 R. Peracikan L = 2.40 x 4.50 = 10.80 m²
Gudang obat L = 4.50 x 7.00 = 31.50 m²
R. Tindakan L = 3.90 x 4.40 = 17.16 m²
R. Pemeriksaan L = 3.90 x 2.15 = 8.39 m²
R. Konseling L = 3.90 x 2.15 = 8.39 m²
R. Asi L = 2.65 x 3.40 = 9.01 m²
R. Kes anak dan imunisasi L = 3.65 x 3.40 = 12.41 m²
R. Gigi dan mulut L = 3.40 x 3.40 = 11.56 m²
R. P2 L = 2.90 x 2.90 = 8.41 m²
R. VCT L = 2.90 x 1.90 = 5.51 m²
R. Lab dan speciesmen L = 1.50 x 1.40 = 2.10 m²
L = 5.40 x 3.00 = 16.20 m²
R. Cuci linen L = 2.70 x 4.75 = 12.83 m²
L = 1.20 x 2.90 = 3.48 m²
R. Sterilisasi L = 3.90 x 2.95 = 11.51 m²
Musholla L = 3.00 x 4.00 = 12.00 m²
R. Jaga poned L = 5.40 x 2.90 = 15.66 m²
L = 3.50 x 1.50 = 5.25 m²
Keterangan Perhitungan Volume
LANTAI - 2
R. 1 L = 4.95 x 10.95 = 54.20 m²
R. 2 L = 3.00 x 1.35 = 4.05 m²
R. 3 L = 11.95 x 3.45 = 41.23 m²
R. 4 L = 3.95 x 9.50 = 37.53 m²
R. 5 L = 5.95 x 17.45 = 103.83 m²
R. 6 L = 7.00 x 5.45 = 38.15 m²
R. 7 L = 4.95 x 6.95 = 34.40 m²
R. 8 L = 4.95 x 7.45 = 36.88 m²
R. 9 L = 4.95 x 4.90 = 24.26 m²
R. 10 L = 4.95 x 4.90 = 24.26 m²
R. 11 L = 2.95 x 5.45 = 16.08 m²
R. 12 L = 9.95 x 29.00 = 288.55 m²
R. 13 L = 2.00 x 9.50 = 19.00 m²
R. 14 L = 6.00 x 7.45 = 44.70 m²
R. 15 L = 4.00 x 1.40 = 5.60 m²
R. 16 L = 10.95 x 10.90 = 119.35 m²
892.06 m²
Pengurangan Area Barat = 387.50 m2
6. PEKERJAAN PLAFOND
LANTAI - 1
1. Pas. Plafond gypsum
R. Peracikan L = 2.40 x 4.50 = 10.80 m²
Gudang obat L = 4.50 x 7.00 = 31.50 m²
R. Tindakan L = 3.90 x 4.40 = 17.16 m²
R. Pemeriksaan L = 3.90 x 2.15 = 8.39 m²
R. Konseling L = 3.90 x 2.15 = 8.39 m²
R. Asi L = 2.65 x 3.40 = 9.01 m²
R. Kes anak dan imunisasi L = 3.65 x 3.40 = 12.41 m²
R. Gigi dan mulut L = 3.40 x 3.40 = 11.56 m²
R. P2 L = 2.90 x 2.90 = 8.41 m²
R. VCT L = 2.90 x 1.90 = 5.51 m²
R. Lab dan speciesmen L = 1.50 x 1.40 = 2.10 m²
L = 5.40 x 3.00 = 16.20 m²
R. Cuci linen L = 2.70 x 4.75 = 12.83 m²
L = 1.20 x 2.90 = 3.48 m²
Keterangan Perhitungan Volume
7. PEKERJAAN PENGECATAN
1 Pengecatan Dinding
Lantai 1 L = Plester dinding
= 2907.29 m2
= 2907.29 m2 2907.29 m2
Keterangan Perhitungan Volume
Lantai 2 L = Plafond
= 906.31 m2
= 906.31 m2 906.31 m2
8. PEKERJAAN FASADE
1 Pekerjaan Pasang ACP L1 = 12.25 x 11.85
+ rangka hollow 4x4x1 mm = 145.16 m2
L2 = 21.55 x 4.8
= 103.44 m2
L3 = 2.55 x 1.46
= 3.72 m2
L4 = 3.05 x 2.6
= 7.93 m2
S = 260.26 m2 260.26 m2
Lantai - 2
1. Closet duduk ex = 2.00 Bh 2.00 Bh
2. Pas . Jet Washer ex = 2.00 Bh 2.00 Bh
3. Washtafel ex = - unit 0.00 unit
4. Kran air = 2.00 Bh 2.00 Bh
5. Pas . Krain Air ( Wastafel ) = Bh 0.00 Bh
6. Floor drain = 2.00 Bh 2.00 Bh
7. Pipa PVC 1 1/5 " = 25.00 m' 25.00 m'
8. Pipa PVC 4 " = 55.00 m' 55.00 m'
9. Pipa PVC 8 " ( Pipa Air Hujan ) = 50.00 m' 50.00 m'
2. PEKERJAAN LISTRIK
LANTAI - 1
1. Panel Box = 2.00 bh 2.00 bh
2. Pas. Instalasi titik lampu = 140.00 ttk 140.00 ttk
3. Pas. Instalasi Stop Kontak = 115.00 ttk 115.00 ttk
4. Pas Lampu Downlight LED 12 W = 110.00 bh 110.00 bh
5. Pas Lampu LED 13 W = 15.00 bh 15.00 bh
6. Pas. Lampu LED 5 W = 15.00 bh 15.00 bh
7. Pas. Stop kontak "Broco" = 115.00 bh 115.00 bh
8. Pas. Stop kontak AC "Broco" = 24.00 bh 24.00 bh
9. Pas. Saklar Ganda "Broco" = 49.00 bh 49.00 bh
10. Pas. Saklar Tunggal "Broco" = 22.00 bh 22.00 bh
11. Pemindahan Listrik = 1.00 bh 1.00 bh
Keterangan Perhitungan Volume
LANTAI - 2
1. Pas. Instalasi titik lampu = 2.00 ttk 2.00 ttk
2. Pas. Instalasi Stop Kontak = 0.00 ttk 0.00 ttk
3. Pas Lampu Downlight LED 12 W = 0.00 bh 0.00 bh
4. Pas Lampu LED 13 W = 0.00 bh 0.00 bh
5. Pas. Lampu LED 5 W = 2.00 bh 2.00 bh
6. Pas. Stop kontak "Broco" = 0.00 bh 0.00 bh
7. Pas. Stop kontak AC "Broco" = 0.00 bh 0.00 bh
8. Pas. Saklar Ganda "Broco" = 1.00 bh 1.00 bh
9. Pas. Saklar Tunggal "Broco" = 0.00 bh 0.00 bh
AREA PARKIR
1. Pas. Instalasi titik lampu = 13.00 ttk 13.00 ttk
2. Pas Lampu LED 13 W = 13.00 bh 13.00 bh
3. Pas. Stop kontak "Broco" = 1.00 bh 1.00 bh
4. Pas. Saklar Ganda "Broco" = 2.00 bh 2.00 bh
5. Pas. Saklar Tunggal "Broco" = 2.00 bh 2.00 bh
E. PEKERJAAN PENDUKUNG
1. PEKERJAAN PASANG PAVING
Û Urug Pasir bawah Paving 5 cm L = 28.65 x 7.5
Paving Depan = 214.88 x 0.05
= 10.74 m3 10.74 m3
= 4.36 m3 4.36 m3
II PEKERJAAN BETON
Lantai Kerja Pondasi Setempat t : 5 cm V = 1.20 x 0.60 x 0.05
= 0.04 x 22.00 bh
= 0.79 m3 0.79 m3
= 0.36 x 22.00 Bh
= 7.92 m3 7.92 m3
Pas. Kolom 30 x 30 ( K3 )
Û Lantai 1 V = 0.30 x 0.30 x 3.50 x 6.00 Bh
= 1.89 m3
Pas. Balok
Û Balok (B1) 30 x 65 P = 0.30 x 0.65 x 38.73 m1
= 7.55 m3 7.55 m3
Plat Beton
Û Plat drop zone t : 15 cm V1 = 9.40 x 5.9 x 0.15
= 8.32 m3
V2 = 6.62 + 4.48
= 11.10 / 2
= 5.55 x 5.59 x 0.15
= 4.65 m3
V3 = 4.72 x 5.07 x 0.15
= 3.59 m3
V4 = 4.10 + 7.14
= 11.24 / 2
= 5.62 x 9.13 x 0.15
= 7.70 m3
V5 = 12.90 x 5.3 x 0.15
= 10.26 m3
S = 34.51 - 5.50 dikurangi luas balok
= 29.02 m3 29.02 m3
II PEKERJAAN BETON
1. Lantai Kerja Pondasi Setempat t : 5 cm V = 0.80 x 0.8 x 0.05
= 0.03 x 4.00
= 0.13 m3 0.13 m3
= 131.88 kg 131.88 kg
4 PEKERJAAN DRAINASE
I PEKERJAAN TANAH DAN PONDASI
Galian tanah
Saluran drainase V = 103.12 x 0.55 x 0.55
= 31.19 m3 31.19 m3
JUMLAH 8,294,061.86
ANALISA SNI 2008
I PEKERJAAN PERSIAPAN
۞ 1 m3 Urugan Sirtu
Bahan
1.200 m3 Urug Sirtu @ Rp. 175,000.00 = Rp. 210,000.00
= Rp. 210,000.00
Upah
0.250 Oh Pekerja @ Rp. 120,000.00 = Rp. 30,000.00
0.250 Oh Mandor @ Rp. 150,000.00 = Rp. 37,500.00
= Rp. 67,500.00
Total Harga = Rp. 277,500.00
Overhead + Provit 5 % = Rp. 13,875.00
Harga satuan pekerjaan = Rp. 291,375.00
۞ 1 m' Galian Tanah Strous Ø30 cm
Alat
0.200 m3 Sewa bor strous Ø30 @ Rp. 17,000.00 = Rp. 3,400.00
= Rp. 3,400.00
Upah
0.240 Oh Pekerja @ Rp. 120,000.00 = Rp. 28,800.00
0.012 Oh Mandor @ Rp. 150,000.00 = Rp. 1,800.00
= Rp. 30,600.00
Total Harga = Rp. 34,000.00
Overhead + Provit 5 % = Rp. 1,700.00
Harga satuan pekerjaan = Rp. 35,700.00
PEKERJAAN PONDASI
۞ 1 m3 Pasang pondasi batu kosong
Bahan An. SNI 6.14.1
1.200 m3 Batu belah ( 15/20 ) @ Rp. 264,000.00 = Rp 316,800.00
0.300 m3 Pasir pasang @ Rp. 195,000.00 = Rp 58,500.00
Total Bahan = Rp 375,300.00
Upah An. SNI 6.14.1
0.780 Oh Pekerja @ Rp. 100,000.00 = Rp 78,000.00
0.390 Oh Tukang batu @ Rp. 115,000.00 = Rp 44,850.00
0.039 Oh Kepala tukang @ Rp. 125,000.00 = Rp 4,875.00
0.039 Oh Mandor @ Rp. 150,000.00 = Rp 5,850.00
= Rp 133,575.00
Total harga = Rp 508,875.00
Overhead + Provit 5 % = Rp 25,443.75
Harga satuan pekerjaan = Rp 534,318.75
3 STROUS Φ 25
Persegi 3.140 X 0.023 X 1.000 = 0.071 m3
Besi :
Tulangan ø 12 mm ( polos ) 1.000 X 6.000 x 0.893 = 5.357 kg
Begel ø 6 mm ( polos ) 0.785 X 6.667 x 0.223 = 1.168 kg
Jumlah = 6.525 kg
Volume pondasi = 0.071 m3
Jumlah besi tiap 1 m3 beton = 92.355 kg
KOLOM
1 KOLOM praktis 15/15
Beton 0.150 X 0.150 X 1.000 = 0.023 m3
Besi :
Tulangan ø 12 mm ( polos ) 1.000 X 4.000 bh 0.887 = 3.548 kg
Begel ø 8 mm ( polos ) 0.660 X 6.000 x 0.394 = 1.560 kg
Jumlah besi 5.108 kg
Volume beton 0.023 m3
Jumlah besi tiap 1 m3 beton 227.033 kg
BALOK
7 BALOK 15/25
Beton 0.150 X 0.250 X 1.000 = 0.038 m3
Besi :
Tulangan Ø 10 mm ( ulir ) 1.000 X 6.000 bh 0.616 = 3.696 kg
Begel ø 8 mm ( polos ) 0.550 X 6.667 x 0.394 = 1.445 kg
Jumlah besi 5.141 kg
Volume beton 0.038 m3
Jumlah besi tiap 1 m3 beton 137.084 kg
9 Sloof 15/20
Beton 0.150 X 0.200 X 1.000 = 0.030 m3
Besi :
Tulangan Ø 12 mm ( ulir ) 1.000 X 4.000 bh 0.887 = 3.548 kg
Begel ø 8 mm ( polos ) 0.550 X 7.000 x 0.394 = 1.517 kg
Jumlah besi 6.667 5.065 kg
Volume beton 0.030 m3
Jumlah besi tiap 1 m3 beton 168.830 kg
PLAT BETON
1 PLAT BETON T= 12 CM
Volume beton 0.120 X 1.000 X 1.000 = 0.120 m3
2 PLAT BETON T= 15 CM
Volume beton 0.150 X 1.000 X 1.000 = 0.150 m3
6.667
Tulangan ø 8 mm ( polos ) 1.100 X 7.000 X 0.394 X 2.00 = 6.068 kg
Tulangan ø 8 mm ( polos ) 1.100 X 7.000 X 0.394 X 2.00 = 6.068 kg
Jumlah besi 12.135 kg
Volume beton 0.150 m3
Jumlah besi tiap 1 m3 beton 80.901 kg
2 PLAT BETON T= 5 CM
Volume beton 0.050 X 1.000 X 1.000 = 0.050 m3
6.667
Tulangan ø 8 mm ( polos ) 1.100 X 7.000 X 0.397 X 1.00 = 3.055 kg
Tulangan ø 8 mm ( polos ) 1.100 X 7.000 X 0.397 X 1.00 = 3.055 kg
Jumlah besi 6.111 kg
Volume beton 0.050 m3
Jumlah besi tiap 1 m3 beton 122.214 kg
3 PLAT BETON T= 7 CM
Volume beton 0.070 X 1.000 X 1.000 = 0.070 m3
6.667
Tulangan ø 8 mm ( polos ) 2.100 X 7.000 X 0.620 X 1.00 = 9.114 kg
Tulangan ø 8 mm ( polos ) 2.100 X 7.000 X 0.620 X 1.00 = 9.114 kg
Jumlah besi 18.228 kg
Volume beton 0.070 m3
Jumlah besi tiap 1 m3 beton 260.400 kg
4 PLAT BETON T= 10 CM
Volume beton 0.100 X 1.000 X 1.000 = 0.100 m3
6.667
Tulangan ø 8 mm ( polos ) 1.100 X 7.000 X 0.620 X 1.00 = 4.774 kg
Tulangan ø 8 mm ( polos ) 1.100 X 7.000 X 0.620 X 1.00 = 4.774 kg
Jumlah besi 9.548 kg
Volume beton 0.100 m3
Jumlah besi tiap 1 m3 beton 95.480 kg
PEKERJAAN KERAMIK
۞ 1 m2 Pasang Lantai keramaik Ukuran (40 x 40) cm
Bahan ( SNI 7395:2008 ) 6.9
1.000 m2 Keramik 40 x 40 @ Rp. 112,000.00 = Rp 112,000.00
9.800 kg Semen portland @ Rp. 1,300.00 = Rp 12,740.00
0.045 m3 Pasir pasang @ Rp. 195,000.00 = Rp 8,775.00
1.300 kg Semen warna @ Rp. 14,000.00 = Rp 18,200.00
= Rp 151,715.00
Upah ( SNI 7395:2008 ) 6.9
0.250 oh Pekerja @ Rp. 120,000.00 = Rp 30,000.00
0.125 oh Tukang batu @ Rp. 125,000.00 = Rp 15,625.00
0.013 oh Kepala tukang @ Rp. 125,000.00 = Rp 1,625.00
0.013 oh Mandor @ Rp. 150,000.00 = Rp 1,950.00
= Rp 49,200.00
Total harga = Rp 200,915.00
Overhead + Provit 5 % = Rp 10,045.75
Harga satuan pekerjaan = Rp 210,960.75
4 Memasang 1 m2 Kaca t : 5 mm
Bahan :
1.100 m2 Kaca t : 5 mm @ Rp. 80,000.00 = Rp. 88,000.00
Total Bahan = Rp. 88,000.00
۞ Tipe P.1 kusen alumunium 5/10 cm, pintu aluminium + kaca polos + accessories
- Kusen Aluminium 4" tebal 1.2mm (Putih ) 8.660 m1 Rp 151,439 Rp 1,311,461
- Daun Pintu Kaca rangka aluminium 3.075 m 2
Rp 263,865 Rp 811,385
Accessories :
- Engsel pintu 4.000 bh Rp 48,339 Rp 193,358
- Kunci Tanam 1.000 set Rp 152,985 Rp 152,985
- Handle 2.000 Psg Rp 96,731 Rp 193,463
- Door stop 2.000 bh Rp 25,226 Rp 50,453
- Sealent 2.235 tube Rp 40,000 Rp 89,387
- Kaca Bouven 0.584 m2 Rp 80,000 Rp 46,720
Jumlah Total 1.000 unit Rp 2,849,210
۞ Tipe P.4 kusen alumunium 5/10 cm, pintu aluminium + kaca polos + accessories
- Kusen Aluminium 4" tebal 1.2mm (Putih ) 6.860 m1 Rp 151,439 Rp 1,038,871
- Daun Pintu Kaca rangka aluminium 1.640 m2 Rp 263,865 Rp 432,739
Accessories :
- Engsel pintu 3.000 bh Rp 48,339 Rp 145,018
- Kunci Tana 1.000 set Rp 152,985 Rp 152,985
- Handle 1.000 Psg Rp 96,731 Rp 96,731
- Door stop 1.000 bh Rp 25,226 Rp 25,226
- Sealent 1.163 tube Rp 40,000 Rp 46,507
- Kaca Bouven 0.320 m Rp 80,000 Rp 25,600
Jumlah Total 1.000 unit Rp 1,963,677
۞ Tipe J.5 kusen alumunium 4", pintu aluminium + kaca polos + accessories
- Kusen Aluminium 4" tebal 1.2mm 7.160 m1 Rp 151,439 Rp 1,084,302
- Memasang 1 m2 Daun Jendela Kaca Rangka Allumunium 1.155 m 2
Rp 266,057 Rp 307,296
Accessories :
- Kunci tanam kecil 1.000 set Rp 37,853 Rp 37,853
- Handle 1.000 Psg Rp 96,731 Rp 96,731
- Relling Jendela 2.000 Set Rp - Rp -
Boven
- Memasang 1 m2 Kaca mati 0.378 m2 Rp 116,064 Rp 43,826
Jumlah Total 1.000 unit Rp 1,570,008
۞ Tipe J.7 kusen alumunium 4", pintu aluminium + kaca polos + accessories
- Kusen Aluminium 4" tebal 1.2mm (Putih ) 4.380 m1 Rp 151,439 Rp 663,302
- Memasang 1 m2 Daun Jendela Kaca Rangka Allumunium 0.706 m 2
Rp 253,667 Rp 178,987
Accessories :
- Engsel Jendela 2.000 bh Rp 45,203 Rp 90,405
- Grendel 1.000 Psg Rp 42,053 Rp 42,053
- Sponeng 1.411 m' Rp 116,957 Rp 165,050
Boven
- Memasang 1 m2 Kaca mati 0.202 m2 Rp 116,064 Rp 23,399
Jumlah Total 1.000 unit Rp 1,163,195
۞ Tipe BV (Bouvenlist) kusen alumunium 4", jendela aluminium + kaca polos + accessories
- Kusen Aluminium 4" tebal 1.2mm (Putih ) 2.160 m1 Rp 151,439 Rp 327,108
- Kaca polos t=5mm 0.240 m2 Rp 120 Rp 29
Jumlah Total 1.000 unit Rp 327,137
۞ Tipe PJ1 kusen alumunium 4", pintu aluminium + kaca polos + accessories
- Kusen Aluminium 4" tebal 1.2mm 8.940 m1 Rp 151,439 Rp 1,353,864
- Memasang 1 m2 Pintu Kaca Rangka Allumunium 1.720 m2 Rp 263,865 Rp 453,848
Accessories :
- Handle 1.000 Psg Rp 96,731 Rp 96,731
- Kunci Tanam 1.000 set Rp 152,985 Rp 152,985
- Handle pintu 0.456 m2 Rp 96,731 Rp 44,080
- Door stop 1.597 m 2
Rp - Rp -
Accessories :
- Relling Jendela 1.000 Set Rp - Rp -
- Handle Tanam Slide 1.000 Psg Rp 96,731 Rp 96,731
- Kunci Selot 1.000 Psg Rp 37,853 Rp 37,853
- Engsel 2.000 bh Rp 45,203 Rp 90,405
Jumlah Total 1.000 unit Rp 2,326,497
۞ Tipe PJ2 kusen alumunium 4", pintu aluminium + kaca polos + accessories
- Kusen Aluminium 4" tebal 1.2mm 7.850 m1 Rp 151,439 Rp 1,188,795
- Memasang 1 m2 Pintu Kaca Rangka Allumunium 1.720 m 2
Rp 263,865 Rp 453,848
Accessories :
- Handle 1.000 Psg Rp 96,731 Rp 96,731
- Kunci Tanam 1.000 set Rp 152,985 Rp 152,985
- Handle pintu 0.456 m2 Rp 96,731 Rp 44,080
- Door stop 1.597 m2 Rp - Rp -
Accessories :
- Relling Jendela 1.000 Set Rp - Rp -
- Handle Tanam Slide 1.000 Psg Rp 96,731 Rp 96,731
- Kunci Selot 1.000 Psg Rp 37,853 Rp 37,853
- Engsel 2.000 bh Rp 45,203 Rp 90,405
Jumlah Total 1.000 unit Rp 2,161,428
۞ Tipe Roster Beton
- Roster 1.000 bh Rp 10,000 Rp 10,000
- Semen 1.800 kg Rp 1,300 Rp 2,340
Jumlah 1.000 unit Rp 12,340
- Profit 5% Rp 666
Jumlah Total 1.000 unit Rp 13,006
PEKERJAAN PENGGANTUNG , PENGUNCI , DAN KACA
B BAHAN LANTAI.
1 Granit tile 60x60 cm Motif (KW 1) m2 Rp. 155,000.00
2 Tegel keramik 30x30 cm Motif ( KW I ) m2 Rp. 50,000.00
3 Dinding GRC m2 Rp. 110,000.00
4 Keramik dinding 30x60 cm ( KW I ) m2 Rp. 90,000.00
5 Buis Beton U 20 bh Rp. 27,500.00
C BAHAN KAYU.
1 Kayu dolken galam btg Rp. 25,000.00
2 Papan begesting (MC) m3 Rp. 4,000,000.00
3 Kayu Papan klas II m3 Rp. 9,000,000.00
4 Kayu Papan Kelas III m3 Rp. 5,200,000.00
5 Kayu balok klas II m3 Rp. 8,300,000.00
6 Kayu balok Kelas III m3 Rp. 5,600,000.00
E. BAHAN ALUMINIUM
1 Profil Aluminium 4 " m' Rp. 110,000.00
2 Skrup fixer bh Rp. 10,000.00
3 sealant Tube Rp. 10,000.00
4 Kaca m2 Rp. 85,000.00
5 Aluminium Strip m2 Rp. 20,000.00
F BAHAN BESI..
1 Besi beton polos. kg Rp. 9,800.00
2 Kawat bendrat kg Rp. 15,000.00
3 Paku reng kg Rp. 14,000.00
4 Paku usuk kg Rp. 13,500.00
5 Paku asbes kg Rp. 20,000.00
6 Paku sekrup bh Rp. 1,300.00
7 Mur Baut bh Rp. 2,500.00
1 2 3 4
DAFTAR
HARGA DASAR SATUAN BAHAN
HARGA
No. KODE SATUAN SATUAN KETERANGAN
( Rp.)
DAFTAR
HARGA SEWA ALAT
HARGA
No. KODE SATUAN SATUAN KETERANGAN
( Rp.)
1 Stamper jam 150,000.00
2 Jack Hammer jam 187,500.00
3 Dump Truck 3,5 ton jam 450,000.00
4 Crane jam 950,000.00
5 Excavator PC 75 jam 175,000.00
6 Forklift jam 150,000.00
7 Gerobak jam 10,000.00
8 Pompa Air jam 13,000.00
9 sewa alat pengelasan jam 150,000.00
10 Sewa Alat Bantu jam 18,000.00
Lampiran I : Keputusan Pengguna Anggaran
: Nomor : 188.4/ 15 / 417.501 / 2020
: Tanggal : 03 April 2020
1 2 3 4
JENIS BAHAN BANGUNAN BAHAN
PENUTUP ATAP & PLAFON
1 Asbes datar tebal 4 mm (60x180) Lbr Rp 50,000.00
2 Asbes datar tebal 5 mm (60x180) Lbr Rp 63,000.00
3 Asbes datar tebal 6 mm (40x180) Lbr Rp 78,000.00
4 Asbes gelombang besar tebal 5 mm (2,50 x 0,92 m) Lbr Rp 125,000.00
5 Asbes gelombang kecil tebal 5 mm (2,25 x 0,92 m) Lbr Rp 85,000.00
6 Asbes gelombang kecil tebal 5 mm (2,00 x 0,92 m) Lbr Rp 78,000.00
7 Asbes wuwung stel gelombang 0,92 mm set Rp 45,000.00
8 Genteng Karang Pilang / wisma bj Rp 6,000.00
9 Genteng wuwung jawa / lokal bj Rp 15,000.00
10 Genteng wuwung karang pilang / wisma bj Rp 20,000.00
11 Genteng bubung kodok bj Rp 5,500.00
12 Genteng Beton bj Rp 4,500.00
13 Genteng kodok bj Rp 4,000.00
14 Nok Genteng Beton bj Rp 7,000.00
15 Seng Gelombang 3" x 6" Lbr Rp 127,000.00
16 Seng Plat 3" x 6" BJLS Lbr Rp 401,000.00
17 Teakwood tebal 4 mm (1,22 x 2,44) Lbr Rp 165,000.00
18 Plywood tebal 4 mm (1,22 x 2,44) Rp 97,500.00
19 Triplek tebal 4 mm (1,20 x 2,40) lbr Rp 70,000.00
20 Triplek tebal 4 mm (0,90 x 2,00) lbr Rp 52,000.00
21 Triplek tebal 4 mm (1,22 x 2,44) lbr Rp 75,000.00
22 Multiplek 120.240.9 mm lbr Rp 167,000.00
23 Gypsum board (120X240X9mm) lbr Rp 83,000.00
24 Profil alluminium "T" m Rp 110,000.00
25 Aluminium strip m Rp 38,500.00
26 Kanal C 0,75 btg Rp 65,550.00
27 Reng Galvalum btg Rp 27,550.00
28 Skrup Kanal C dus Rp 135,550.00
29 Aluminium Foil Rol Rp 250,550.00
30 Roof light fibreglass m2 Rp 159,000.00
31 Tepung Gypsum kg Rp 5,000.00
32 Ramset bh Rp 42,500.00
BAHAN MENGGUNAKAN KAYU
1 Dolken kayu Ø 8-10/400 cm bh Rp 28,000.00
2 Kayu meranti (balok) 8/12, 6/12 m3 Rp 3,500,000.00
3 Kayu meranti (papan)2/20 x 2 m, 3/30 x 3 m m3 Rp 3,250,000.00
4 Kayu meranti (usuk) 5/7, 4/6, 3/5 Lonjor Rp 39,000.00
5 Kayu meranti (begesting) m3 Rp 3,375,000.00
6 List Kayu 1/5 Lonjor Rp 16,900.00
7 List Kayu 2/4 Lonjor Rp 16,900.00
8 Perancah m3 Rp 3,980,000.00
9 Kayu terentang m3 Rp 4,900,000.00
10 Tali ijuk kg Rp 32,000.00
11 Ijuk kg Rp 30,000.00
12 Kaso 5/7 m3 Rp 6,000,000.00
13 Kayu papan tebal 9 mm lbr Rp 112,000.00
14 Bambu Ø6 - 10 / 600 cm btg Rp 25,000.00
15 Tali Rafia roll Rp 22,500.00
BAHAN MENGGUNAKAN BATU/PASIR & SEMEN
1 Batu Bata merah kelas 1 bh Rp 650.00
2 Bata ekspose ex MRH bh Rp 700.00
3 Bata ekspose ex tuban bh Rp 1,650.00
4 Bata Ringan bh Rp 545,000.00
5 Batu kali pecah 15/20 m3 Rp 264,000.00
6 Batu tempel m2 Rp 70,000.00
7 Batu kerikil beton m3 Rp 258,000.00
8 Pasir beton m3 Rp 234,000.00
9 Pasir Pasang m3 Rp 195,000.00
10 Pasir urug m3 Rp 137,800.00
11 Semen berwarna Yiyitan kg Rp 14,000.00
12 Semen PC (Portland Cement)/Semen Gresik ( 40 Kg) zak Rp 52,000.00
13 Semen Tiga Roda (40 Kg) zak Rp 50,000.00
14 Semen Putih kg Rp 3,000.00
15 Kapur Pasang kg Rp 3,400.00
16 Tanah Urug m3 Rp 100,000.00
17 Sirtu m3 Rp 175,000.00
18 Semen nat kg Rp 20,100.00
BAHAN MENGGUNAKAN BESI/LOGAM
1 Besi begel/ baut kg Rp 25,000.00
2 Besi beton polos kg Rp 12,100.00
3 Besi beton (polos/ ulir) kg Rp 12,100.00
4 Besi beton diameter 16 mm, 12 m ljr Rp 189,000.00
5 Besi beton diameter 12 mm, 12 m ljr Rp 110,000.00
6 Besi beton diameter 10 mm, 12 m ljr Rp 70,000.00
7 Besi beton diameter 8 mm, 12 m ljr Rp 48,000.00
8 Besi beton diameter 6 mm, 12 m ljr Rp 35,000.00
11 Besi pipa galvanis medium 1 1/2, 6m ljr Rp 235,000.00
12 Besi pipa galvanis medium 1 1/4, 6m ljr Rp 178,000.00
13 Besi pipa galvanis medium 1 , 6m ljr Rp 148,000.00
14 Besi pipa galvanis medium 1/2, 6m ljr Rp 85,000.00
15 Besi pipa galvanis medium 2 1/2, 6m ljr Rp 320,000.00
16 Besi pipa galvanis medium 2, 6m ljr Rp 198,000.00
17 Besi pipa galvanis medium 3, 6m ljr Rp 457,000.00
18 Besi pipa galvanis medium 4, 6m ljr Rp 589,000.00
19 Besi pipa galvanis medium 5, 6m ljr Rp 657,000.00
20 Besi pipa galvanis medium 6, 6m ljr Rp 752,000.00
21 Besi pipa galvanis medium 3/4, 6m ljr Rp 114,000.00
22 Besi Siku 50.50.5, panjang 6 m ljr Rp 160,000.00
23 Besi Siku 40.40.4, panjang 6 m ljr Rp 90,000.00
24 Besi Siku 30.30.3, panjang 6 m ljr Rp 62,000.00
25 Besi Wire Mesh M5 lmbr Rp 342,000.00
26 Besi Wire Mesh M8 lmbr Rp 775,000.00
27 Besi Wire Mesh M10 lmbr Rp 1,167,500.00
28 Besi hollow 0.05x0.05x0.002,3x600 btg Rp 364,000.00
29 Besi hollow 0.04x0.04x0.002,3x600 btg Rp 284,000.00
30 Kawat ikat beton kg Rp 22,000.00
31 Kawat nyamuk kasa aluminium m2 Rp 40,000.00
32 Kawat harmonika m Rp 27,000.00
33 Kawat las listrik kg Rp 20,000.00
BAHAN UNTUK LANTAI
1 Paving stone persegi abu-abu tebal 6 cm kasar m2 Rp 65,000.00
2 Paving stone persegi abu-abu tebal 8 cm kasar m2 Rp 80,000.00
3 Kanstin uk. 10x20x40 cm bh Rp 13,000.00
4 Stopper / Uskup t = 6 cm bh Rp 4,000.00
5 Tegel keramik 30 x 30 cm bh Rp 87,000.00
6 Tegel keramik 33 x 33 cm bh Rp 97,000.00
7 Tegel keramik 40 x 40 cm bh Rp 112,000.00
8 Tegel keramik dinding (20 x 25) cm bh Rp 85,000.00
BAHAN UNTUK CAT
1 Cat (besi/kayu) Emco kg Rp 75,000.00
2 Cat meni (besi/kayu) cap Pedang kg Rp 38,000.00
3 Meni A kg Rp 28,000.00
4 Meni B kg Rp 14,000.00
5 Cat tembok Vinilek, Aviapaint (sejenis) kg Rp 105,000.00
6 Cat tembok Decolith dan yg setara kg Rp 210,000.00
7 Cat minyak dhoof klg Rp 75,000.00
8 Cat clear dhoof klg Rp 85,000.00
9 Cat Couting Natural klg Rp 85,000.00
10 Minyak pelumas ltr Rp 25,500.00
11 Minyak begisting ltr Rp 30,000.00
12 Plitur jadi kg Rp 75,000.00
13 Kertas gosok/ Ampelas lbr Rp 4,000.00
14 Plamur tembok kg Rp 10,000.00
15 Plamur kayu kg Rp 28,000.00
16 Plamur Besi kg Rp 30,000.00
17 Spiritus liter Rp 20,000.00
18 Lem kayu kg Rp 13,500.00
19 Thinner B / minyak cat liter Rp 27,500.00
20 Soda api kg Rp 30,000.00
21 Kuas 3" bh Rp 10,500.00
22 Kuas 4" bh Rp 25,000.00
23 Kalkarium kg Rp 12,500.00
24 Water Proff kg Rp 50,000.00
BAHAN PENGGANTUNG DAN PENGUNCI
1 Engsel H stl Rp 18,000.00
2 Engsel Kuningan arch asli stl Rp 20,000.00
3 Engsel jendela bh Rp 15,000.00
4 Engsel angin bh Rp 22,500.00
5 Engsel pintu bh Rp 25,000.00
6 Engsel pintu viper dan yg setara bh Rp 45,000.00
7 Espanyolet stl Rp 110,000.00
8 Grendel bj Rp 12,000.00
9 Grendel biasa (besar) bh Rp 15,000.00
10 Grendel biasa (kecil) bh Rp 10,000.00
11 Grendel Tanam bh Rp 55,000.00
12 Kunci tanam antik bj Rp 169,000.00
13 Kunci tanam besar kuda terbang 2 x putar bj Rp 85,000.00
14 Kunci tanam kamar mandi bh Rp 50,000.00
15 Kunci silinder bh Rp 35,000.00
16 Spring knip bh Rp 20,000.00
17 Door closer bh Rp 125,000.00
18 Door stop bh Rp 10,000.00
19 Door holder bh Rp 22,000.00
20 Kunci selot bh Rp 8,000.00
21 Hak angin bj Rp 18,000.00
22 Hak angin 4 mm (lurus) bj Rp 20,000.00
23 Kait angin bh Rp 13,500.00
24 Pegangan pintu pj 20 bh Rp 180,000.00
25 Pintu aluminium m Rp 240,000.00
26 Pintu HPL bh Rp 385,000.00
27 Kusen Aluminium m Rp 118,000.00
28 Kunci tanam biasa bh Rp 95,000.00
BAHAN UNTUK KM/WC/URINOIR
1 Pipa / slang spiral m Rp 35,000.00
2 Closet duduk putih porselin komplit single blok bh Rp 1,250,000.00
3 Closet jongkok porselin warna putih bh Rp 170,000.00
4 Closet jongkok teraso bh Rp 75,000.00
5 Bak teraso bh Rp 1,488,000.00
6 Bak cuci stainless steel bh Rp 150,000.00
7 Seal tape bh Rp 4,000.00
8 Wastafel bh Rp 400,000.00
9 Kran air bh Rp 17,500.00
10 Sumur peresap unit Rp 235,000.00
11 Water drain + Assesories set Rp 28,000.00
12 Urinoir bh Rp 875,000.00
13 Floor drain bh Rp 15,000.00
14 Roof Drain bh Rp 12,750.00
15 Bak fibreglass bh Rp 400,000.00
16 Air ltr Rp 100.00
BAHAN JENIS KACA
1 Kaca polos tb. 3 mm m2 Rp 50,000.00
2 Kaca polos tb. 5 mm m2 Rp 80,000.00
3 Kaca polos tb. 8 mm m2 Rp 200,000.00
4 Kaca rayban tb 5 mm m2 Rp 90,000.00
5 krepyak kaca nako + kerangka lbr Rp 14,000.00
6 Profil kaca m Rp 85,000.00
7 Sealant bh Rp 40,000.00
BAHAN PLASTIK PIPA PVC
1 Keni PVC 1/2" bh Rp 3,000.00
2 Keni PVC 3/4" bh Rp 3,000.00
3 Keni PVC 2" bh Rp 5,000.00
4 Keni PVC 3" bh Rp 8,000.00
5 Keni PVC 4" bh Rp 20,000.00
6 Keni PVC 5" bh Rp 24,000.00
7 Klem PVC bh Rp 2,000.00
8 Pipa PVC 1" tipe D panjang 4.00 mt ljr Rp 36,600.00
9 Pipa PVC 1 1/2" tipe D panjang 4.00 mt ljr Rp 41,600.00
10 Pipa PVC 2" tipe D panjang 4.00 mt ljr Rp 54,300.00
11 Pipa PVC 2 1/2" tipe D panjang 4.00 mt ljr Rp 80,500.00
12 Pipa PVC 3" tipe D panjang 4.00 mt ljr Rp 116,800.00
13 Pipa PVC 4" tipe D panjang 4.00 mt ljr Rp 164,200.00
14 Pipa PVC 5" tipe D panjang 4.00 mt ljr Rp 268,200.00
15 Pipa PVC 3/4" tipe AW panjang 4.00 mt ljr Rp 33,000.00
16 Pipa PVC 1/2" tipe AW panjang 4.00 mt ljr Rp 27,000.00
17 Pipa PVC 1" tipe AW panjang 4.00 mt ljr Rp 48,000.00
18 Pipa PVC 1 1/2" tipe AW panjang 4.00 mt ljr Rp 76,600.00
19 Pipa PVC 2" tipe AW panjang 4.00 mt ljr Rp 113,800.00
20 Pipa PVC 2 1/2" tipe AW panjang 4.00 mt ljr Rp 146,200.00
21 Pipa PVC 3" tipe AW panjang 4.00 mt ljr Rp 172,000.00
22 Pipa PVC 4" tipe AW panjang 4.00 mt ljr Rp 253,700.00
23 Pipa PVC 5" tipe AW panjang 4.00 mt ljr Rp 479,300.00
24 Pipa PVC 3/4" tipe AW panjang 6.00 mt ljr Rp 49,500.00
25 Pipa PVC 1/2" tipe AW panjang 6.00 mt ljr Rp 40,600.00
26 Pipa PVC 1" tipe AW panjang 6.00 mt ljr Rp 72,000.00
27 Pipa PVC 1 1/2" tipe AW panjang 6.00 mt ljr Rp 115,000.00
28 Pipa PVC 2" tipe AW panjang 6.00 mt ljr Rp 170,000.00
29 Pipa PVC 2 1/2" tipe AW panjang 6.00 mt ljr Rp 219,300.00
30 Pipa PVC 3" tipe AW panjang 6.00 mt ljr Rp 258,000.00
31 Pipa PVC 4" tipe AW panjang 6.00 mt ljr Rp 380,550.00
32 Pipa PVC 5" tipe AW panjang 6.00 mt ljr Rp 719,000.00
33 Lem PVC bh Rp 6,250.00
BAHAN JENIS PAKU
1 Paku asbes kg Rp 45,000.00
2 Paku reng kg Rp 20,000.00
3 Paku triplek kg Rp 22,000.00
4 Paku usuk kg Rp 20,000.00
5 Paku sekrup 2" bj Rp 19,500.00
6 Dinaboult BJ Rp 4,000.00
BAHAN PERALATAN LISTRIK
1 Stop kontak (Broco/Setara) bh Rp 15,000.00
2 Skakelar (Broco/Setara) bh Rp 15,000.00
3 Skakelar / hendel bh Rp 16,000.00
4 Zekering lengkap bh Rp 20,000.00
5 Panel box 25cm x 35cm x 12cm bh Rp 263,000.00
6 Panel box 30cm x 40cm x 15cm bh Rp 319,000.00
7 Panel box 40cm x 50cm x 20cm bh Rp 454,000.00
8 Pitingan bh Rp 7,000.00
9 Kabel NYA 1 x 1,5 100m rol Rp 185,000.00
10 Kabel NYA 1 x 2,5 100m rol Rp 300,000.00
11 Kabel NYM 2 x 1,5 50m rol Rp 280,000.00
12 Kabel NYM 2 x 2,5 50m rol Rp 400,000.00
13 Kabel NYM 3 x 1,5 50m rol Rp 360,000.00
14 Kabel NYM 3 x 2,5 50m rol Rp 520,000.00
15 Kabel NYM 4 x 2,5 50m rol Rp 1,400,000.00
16 Kabel NYY 2 x 1,5 mm2 m Rp 25,000.00
17 Kabel NYY 2 x 2,5 mm2 m Rp 29,000.00
18 Kabel NYY 2 x 4 mm2 m Rp 37,000.00
19 Lampu TL 20 W / 220 Komplit Balas, Kaca bh Rp 45,000.00
20 Lampu TL 40 W / 220 Komplit Balas, Kaca bh Rp 54,500.00
21 Lampu LED 20 W bh Rp 28,400.00
22 Lampu LED 25 W / 220 Komplit Balas, Kaca bh Rp 69,000.00
BAHAN PRACETAK
1 U Ditch uk. 30x30x1200 (g = 5 ton) unit Rp 289,000.00
2 U Ditch uk. 30x40x1200 (g = 5 ton) unit Rp 372,000.00
3 U Ditch uk. 30x50x1200 (g = 5 ton) unit Rp 423,000.00
4 U Ditch uk. 40x40x1200 (g = 5 ton) unit Rp 419,000.00
5 U Ditch uk. 40x50x1200 (g = 5 ton) unit Rp 481,000.00
6 U Ditch uk. 40x60x1200 (g = 5 ton) unit Rp 518,000.00
7 U Ditch uk. 40x60x1200 (g = 10 ton) unit Rp 523,000.00
8 U Ditch uk. 50x50x1200 (g = 5 ton) unit Rp 573,000.00
9 U Ditch uk. 50x60x1200 (g = 5 ton) unit Rp 625,000.00
10 U Ditch uk. 50x70x1200 (g = 5 ton) unit Rp 692,000.00
11 U Ditch uk. 60x60x1200 (g = 5 ton) unit Rp 696,000.00
12 U Ditch uk. 60x70x1200 (g = 5 ton) unit Rp 775,000.00
13 U Ditch uk. 60x80x1200 (g = 5 ton) unit Rp 850,000.00
14 U Ditch uk. 80x80x1200 (g = 5 ton) unit Rp 912,000.00
15 U Ditch uk. 80x90x1200 (g = 5 ton) unit Rp 982,000.00
16 U Ditch uk. 80x100x1200 (g = 5 ton) unit Rp 1,067,000.00
17 U Ditch uk. 80x80x1200 (g = 10 ton) unit Rp 1,532,000.00
18 U Ditch uk. 80x100x1200 (g = 10 ton) unit Rp 1,292,000.00
19 U Ditch uk. 100x100x1200 (g = 5 ton) unit Rp 1,738,000.00
20 Cover U Ditch CU 30 (g = 5 ton) unit Rp 140,000.00
21 Cover U Ditch CU 40 (g = 5 ton) unit Rp 169,000.00
22 Cover U Ditch CU 50 (g = 5 ton) unit Rp 213,000.00
23 Cover U Ditch CU 60 (g = 5 ton) unit Rp 266,000.00
24 Cover U Ditch CU 80 (g = 5 ton) unit Rp 472,000.00
25 Cover U Ditch CU 40 (g = 10 ton) unit Rp 225,000.00
26 Cover U Ditch CU 80 (g = 10 ton) unit Rp 510,000.00
27 Buis Beton Diameter 15 cm buah Rp 35,000.00
28 Buis Beton Diameter 20 cm buah Rp 60,000.00
29 Buis Beton Diameter 30 cm buah Rp 80,000.00
30 Buis Beton Diameter 40 cm buah Rp 100,000.00
31 Buis Beton Diameter 50 cm buah Rp 115,000.00
32 Buis Beton U 20 cm buah Rp 35,000.00
33 Buis Beton U 30 cm buah Rp 45,000.00
34 Buis Beton U 40 cm buah Rp 65,000.00
35 Buis Beton U 50 cm buah Rp 75,000.00
BAHAN ASPAL
1 Aspal Curah kg Rp 10,500.00
2 Agr.Base Kelas A m3 Rp 130,000.00
3 Agregat Pecah Kasar m3 Rp 254,387.78
4 Agg. Halus LP A m3 Rp 213,531.24
5 Agregat Lolos # 1 " m3 Rp 280,850.38
6 Lolos screen1 ukuran ( 0 - 5) m3 Rp 213,531.24
7 Lolos screen2 ukuran ( 5 - 9,5) m3 Rp 280,850.38
8 Kerosen / Minyak Tanah ltr Rp 12,500.00
9 Pasir Halus (untuk HRS) m3 Rp 234,000.00
SEWA PERALATAN
1 Asp. Distributor jam Rp 400,000.00
2 Asphalt Finisher jam Rp 400,000.00
3 Asphalt Sprayer jam Rp 350,000.00
4 Buldozzer jam Rp 400,000.00
5 Concrete Vibrator jam Rp 657,000.00
6 Compressor jam Rp 200,000.00
7 excavator jam Rp 350,000.00
8 Jack Hammer jam Rp 187,500.00
9 Wheel Loader jam Rp 340,000.00
10 AMP jam Rp 4,000,000.00
11 Genset jam Rp 400,000.00
12 Dump Truck 3,5 ton jam Rp 300,000.00
13 Asphalt Finisher jam Rp 400,000.00
14 Tandem Roller jam Rp 540,000.00
15 P. Tyre Roller jam Rp 552,000.00
16 Crane jam Rp 950,000.00
17 Stone Crusher jam Rp 3,000,000.00
18 Excavator jam Rp 350,000.00
19 Blending Equipment jam Rp 350,000.00
20 Baby Roller jam Rp 187,000.00
21 P. Tyre Roller jam Rp 552,000.00
22 Vibrator Roller jam Rp 400,000.00
23 Water Tanker jam Rp 300,000.00
24 Motor Grader jam Rp 400,000.00
25 Sewa Alat Bantu jam Rp 18,000.00
26 Sewa Alat Bantu Strouss Pile jam Rp 15,625.00
UPAH TENAGA KERJA
1 Mandor org/hari Rp 150,000.00
2 Kepala Tukang org/hari Rp 125,000.00
3 Tukang org/hari Rp 115,000.00
4 Pekerja org/hari Rp 100,000.00
5 Operator org/hari Rp 125,000.00
6 Pembantu Operator org/hari Rp 100,000.00
7 Sopir / Driver org/hari Rp 125,000.00
8 Pembantu Sopir / Driver org/hari Rp 100,000.00
9 Mekanik org/hari Rp 100,000.00
10 Pembantu Mekanik org/hari Rp 100,000.00
CAMAT MAGERSARI
Selaku
PENGGUNA ANGGARAN
BAMBANG MUJIONO, SH. MH.
Pembina Tingkat I
NIP. 19660316 198910 1 001
DAFTAR HARGA SATUAN BAHAN & UPAH TENAGA KERJA
Harga
No. Jenis Bahan Satuan
Satuan
1 2 3 4
G Bahan Besi
1 Besi beton Polos / ulir kg 13,500.00
2 Baja konstruksi kg 14,300.00
3 Besi siku L 60,60,6 kg 12,750.00
4 Kawat bendrat kg 22,000.00
5 Paku 2" - 5" kg 20,000.00
6 Profil alluminium m' -
7 Alluminium strip m' -
8 Profil alluminium Hollow m' 15,500.00
9 Metal stat m' 40,000.00
10 Paku Pancing/Paku Sekrup/ramset bh 520.00
11 Paku Sekrup kg 40,000.00
12 Talang plat BJLS 28 m2 45,000.00
13 Kawat Penggantung Kg -
Harga
No. Jenis Bahan Satuan
Satuan
1 2 3 4
14 Kawat las Kg 20,000.00
15 Besi Hollow 5x5x2 m1 44,000.00
16 Besi Hollow 2x4x1.12 m1 22,000.00
17 Polycarbonat m2 100,887.81
18 Besi Wire Mesh M8 Uk. 5,4 x 2,1 m lbr 66,137.57
Harga
No. Jenis Bahan Satuan
Satuan
1 2 3 4
H. Bahan Penutup
1 seng lbr 127,000.00
2 Bubungan bitumen sheet bh 5,000.00
3 Asbes Eternit lbr -
4 Zenk Galvalum t :55 cm lbr 135,000.00
5 Plafon Superrata t = 3 mm ( 100 x 100 ) lbr -
6 List gypsum 15 cm m' 5,000.00
7 Tepung gypsum kg 5,000.00
8 Talang Seng BJLS L : 60 cm m' #REF!
9 Usuk Canal C. 75.0.8 m' 23,000.00
10 Reng Purlin R.36.055 m' 15,000.00
11 Baut bh 10,000.00
I Bahan Cat
1 Plamur tembok kg 10,000.00
2 Plamur kayu " PEDANG " kg 40,000.00
3 Cat kayu / besi EMCO/setara kg 70,000.00
4 Cat tembok "Catylac/Setara" kg 210,000.00
5 Cat meni "PEDANG" kg 38,000.00
6 Dempul kayu kg -
7 Minyak cat / thiner B ltr -
8 Lem kayu Kg 33,000.00
9 Residu / Ter ltr -
10 Minyak Begisting ltr 30,000.00
11 Ampelas / kertas gosok lbr 3,500.00
12 Kuas cat bh 14,000.00
13 Waterproofing Coating ex. Sika Rain Tile ( 3 kali lapis ) Kg 50,000.00
14 Sika top 107 Seal ( Untuk toilet, balkon & area basah ) Kg -
15 Pre treatment/cleaning m² -
16 Curbing sudut m' -
17 Solar ltr 9,800.00
18 Minyak pelumas ltr 25,500.00
1 2 3 4 5
1 Genteng Karang Pilang / wisma bj Rp 6,000.00
2 Genteng wuwung karang pilang / wisma bj Rp 20,000.00
3 Seng Gelombang 3" x 6" Lbr Rp 127,000.00
4 Seng Plat 3" x 6" BJLS Lbr Rp 401,000.00
5 Gypsum board (120X240X9mm) lbr Rp 83,000.00
6 Aluminium strip m Rp 38,500.00
7 Kanal C 80 btg Rp 98,700.00
8 Kanal C 0,76 btg Rp 65,550.00
8 Reng Galvalum btg Rp 27,550.00
9 Skrup Kanal C dus Rp 135,550.00
10 Ramset bh Rp 42,500.00
11 Kayu meranti (papan)2/20 x 2 m, 3/30 x 3 m m3 Rp 3,250,000.00
12 Kayu meranti (begesting) m3 Rp 1,000,000.00
13 Kayu Teretang m12 Rp 3,375,000.00
13 Bambu Ø6 - 10 / 600 cm btg Rp 25,000.00
14 Tali Rafia roll Rp 22,500.00
15 Batu Bata merah kelas 1 bh Rp 650.00
16 Roaster 20x20 bh Rp 10,000.00
17 Batu kali pecah 15/20 m3 Rp 264,000.00
18 Batu kerikil beton m3 Rp 258,000.00
19 Pasir beton m3 Rp 234,000.00
20 Pasir Pasang m3 Rp 195,000.00
21 Pasir urug m3 Rp 137,800.00
22 Semen berwarna Yiyitan kg Rp 14,000.00
53 Semen PC (Portland Cement)/Semen Gresik ( 40 Kg) zak Rp 1,300.00
57 Tanah Urug m3 Rp 100,000.00
58 Sirtu m3 Rp 175,000.00
59 Besi beton (polos/ ulir) kg Rp 12,100.00
60 Besi hollow 0.04x0.04x0.002,3x600 btg Rp 284,000.00
61 Kawat ikat beton kg Rp 22,000.00
64 Kawat las listrik kg Rp 20,000.00
65 Paving stone persegi abu-abu tebal 6 cm kasar m2 Rp 65,000.00
66 Stopper / Uskup t = 6 cm bh Rp 4,000.00
67 Tegel keramik 25 x 25 cm m2 Rp 60,000.00
68 Tegel keramik 25 x 40 cm m2 59,000.00
70 Tegel keramik 30 x 30 cm m2 Rp 87,000.00
71 Tegel keramik 40 x 40 cm m2 Rp 112,000.00
72 Tegel keramik 60 x 60 cm m2 Rp 126,000.00
73 Cat meni (besi/kayu) cap Pedang kg Rp 38,000.00
74 Meni A kg Rp 28,000.00
75 Meni B kg Rp 14,000.00
76 Cat tembok Vinilek, Aviapaint (sejenis) kg Rp 105,000.00
77 Cat tembok Decolith dan yg setara kg Rp 210,000.00
78 Minyak begisting ltr Rp 30,000.00
79 Kertas gosok/ Ampelas lbr Rp 4,000.00
80 Plamur tembok kg Rp 10,000.00
81 Plamur kayu kg Rp 28,000.00
82 Kalsiplank 2/30 m' Rp 19,250.00
83 Lem kayu kg Rp 13,500.00
84 Engsel H stl Rp 18,000.00
85 Engsel jendela bh Rp 15,000.00
86 Engsel pintu bh Rp 25,000.00
87 Grendel bj Rp 12,000.00
88 Grendel Tanam bh Rp 55,000.00
89 Kunci tanam besar kuda terbang 2 x putar bj Rp 85,000.00
90 Door closer bh Rp 125,000.00
91 Door stop bh Rp 10,000.00
92 Door holder bh Rp 22,000.00
93 Kunci selot bh Rp 8,000.00
94 Hak angin bj Rp 18,000.00
95 Pintu aluminium m Rp 240,000.00
96 Pintu HPL bh Rp 385,000.00
97 Kusen Aluminium m Rp 118,000.00
98 Skrup Fixer bh Rp 250.00
99 Closet duduk putih porselin komplit single blok bh Rp 1,250,000.00
100 Bak teraso bh Rp 1,488,000.00
101 Bak cuci stainless steel bh Rp 150,000.00
102 Seal tape bh Rp 4,000.00
103 Kran air bh Rp 17,500.00
104 Floor drain bh Rp 15,000.00
105 Air ltr Rp 100.00
106 Kaca polos tb. 5 mm m2 Rp 80,000.00
107 Sealant bh Rp 40,000.00
108 Klem PVC bh Rp 2,000.00
109 Pipa PVC 3/4" tipe AW panjang 4.00 mt ljr Rp 33,000.00
110 Pipa PVC 2" tipe AW panjang 4.00 mt ljr Rp 113,800.00
111 Lem PVC bh Rp 6,250.00
112 Paku reng kg Rp 20,000.00
113 Paku triplek kg Rp 22,000.00
114 Paku usuk kg Rp 20,000.00
115 Paku sekrup 2" bj Rp 19,500.00
116 Dinaboult BJ Rp 4,000.00
117 Stop kontak (Broco/Setara) bh Rp 15,000.00
118 Skakelar (Broco/Setara) bh Rp 15,000.00
119 Skakelar Ganda(Broco/Setara) bh Rp 15,000.00
120 Isolasi bh Rp 15,000.00
121 Mangkok Listrik bh Rp 7,000.00
122 Pitingan bh Rp 7,000.00
123 Kabel NYM 3 x 2,5 50m rol Rp 520,000.00
124 Lampu LED 20 W bh Rp 28,400.00
125 Asphalt Sprayer jam Rp 350,000.00
126 Buldozzer jam Rp 400,000.00
127 Concrete Vibrator jam Rp 657,000.00
128 excavator jam Rp 350,000.00
129 Jack Hammer jam Rp 187,500.00
130 Genset jam Rp 400,000.00
131 Dump Truck 3,5 ton jam Rp 300,000.00
132 Crane jam Rp 950,000.00
133 Sewa Alat Bantu Strouss Pile jam Rp 15,625.00
UPAH TENAGA KERJA
1 Mandor org/hari Rp 150,000.00
2 Kepala Tukang org/hari Rp 125,000.00
3 Tukang org/hari Rp 115,000.00
4 Pekerja org/hari Rp 100,000.00
5 Operator org/hari Rp 125,000.00
6 Pembantu Operator org/hari Rp 100,000.00
7 Sopir / Driver org/hari Rp 125,000.00
8 Pembantu Sopir / Driver org/hari Rp 100,000.00
9 Mekanik org/hari Rp 100,000.00
10 Pembantu Mekanik org/hari Rp 100,000.00
PEKERJAAN BETON
CATATAN :
Bobot isi pasir = 1400 Kg/m3, Bobot isi kerikil = 1350 Kg/m3, Bukling factor pasir = 20 %
۞ 1 Kg Pembesian dengan besi polos atau ulir
Bahan An. SNI 2008 6.17
1.050 Kg Besi beton ( polos/ulir ) @ Rp. 13,500.00 = Rp 14,175.00
0.015 Kg Kawat beton @ Rp. 22,000.00 = Rp 330.00
Total Bahan = Rp 14,505.00
Upah An. SNI 2008 6.17
0.007 Oh Pekerja @ Rp. 120,000.00 = Rp 840.00
0.007 Oh Tukang besi @ Rp. 125,000.00 = Rp 875.00
0.0007 Oh Kepala tukang @ Rp. 125,000.00 = Rp 87.50
0.0004 Oh Mandor @ Rp. 150,000.00 = Rp 60.00
= Rp 1,862.50
Total harga = Rp 16,367.50
Overhead + Provit 5 % = Rp 818.38
Harga satuan pekerjaan = Rp 17,185.88
۞ 1 m2 Pasang bekisting untuk pondasi
Bahan An. SNI 2008 6.20
0.040 m3 Kayu terentang @ Rp. 3,250,000.00 = Rp 130,000.00
0.300 Kg Paku biasa 2" - 5" @ Rp. 20,000.00 = Rp 6,000.00
0.100 Ltr Minyak bekisting @ Rp. 30,000.00 = Rp 3,000.00
Total Bahan = Rp 139,000.00
Upah An. SNI 2008 6.20
0.520 Oh Pekerja @ Rp. 120,000.00 = Rp 62,400.00
0.260 Oh Tukang kayu @ Rp. 115,000.00 = Rp 29,900.00
0.026 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,250.00
0.026 Oh Mandor @ Rp. 150,000.00 = Rp 3,900.00
= Rp 99,450.00
Total harga = Rp 238,450.00
Bahan pakai 3x = Rp
Bahan pakai 2x = Rp 168,950.00
Overhead + Provit 5 % = Rp 8,447.50
Harga satuan pekerjaan = Rp 177,397.50
۞ 1 m3 Membuat lantai kerja beton mutu F'c = 7,4 Mpa ( K 100 ), Slump ( 12 ± 2 ) Cm, w/c = 0.87
Bahan An. SNI 2008 6.4
230.000 Kg Semen portland @ Rp. 1,300.00 = Rp 299,000.00
0.638 m3 Pasir beton @ Rp. 234,000.00 = Rp 149,258.57
0.762 m3 Kerikil ( Maksimum 30 mm ) @ Rp. 258,000.00 = Rp 196,653.33
215.000 Liter Air @ Rp. 100.00 = Rp 21,500.00
Total Bahan = Rp 666,411.90
Upah An. SNI 2008 6.4
1.650 Oh Pekerja @ Rp. 120,000.00 = Rp 198,000.00
0.275 Oh Tukang batu @ Rp. 115,000.00 = Rp 31,625.00
0.028 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,500.00
0.083 Oh Mandor @ Rp. 150,000.00 = Rp 12,450.00
= Rp 245,575.00
Total harga = Rp 911,986.90
Overhead + Provit 5 % = Rp 45,599.35
Harga satuan pekerjaan = Rp 957,586.25
۞ 1 m3 Membuat beton Strous ∅ 25 K-250
An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.20
92.355 Kg Besi beton @ Rp. 17,185.88 = Rp 1,587,201.30
1.000 m3 Spesi beton K-225 @ Rp. 1,142,831.42 = Rp 1,142,831.42
Total harga = Rp 2,730,032.72
1 m3 Membuat Pondasi Plat beton (60x60x20) K-250
An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.20
162.027 Kg Besi beton @ Rp. 17,185.88 = Rp 2,784,570.04
1.000 m3 Spesi beton K-250 @ Rp. 1,142,831.42 = Rp 1,142,831.42
10.00 m2 Cetakan bekisting @ Rp. 177,397.50 = Rp 1,773,975.00
Total harga = Rp 5,701,376.46
۞ 1 m3 Membuat beton sloof 15/20 K-250
An. SNI 6.7 + An. SNI 6.17 + An. SNI 6.21
142.427 Kg Besi beton @ Rp. 17,185.88 = Rp 2,447,726.89
1.000 m3 Spesi beton K-250 @ Rp. 1,142,831.42 = Rp 1,142,831.42
13.33 m2 Cetakan bekisting @ Rp. 132,772.50 = Rp 1,770,300.00
Total harga = Rp 5,360,858.31
1 2 3 4
A Err:509 Err:509
B Err:509 Err:509
C Err:509 Err:509
Terbilang : Dua Ratus Lima Puluh Dua Juta Lima Puluh Dua Ribu Rupiah
Mengetahui :
Mengetahui : Mojokerto, 28 April 2023
Dibuat Oleh:
Kontraktor Pelaksana
CV. SANDANG PANGAN
HERY KYSWANTO
Direktur
RENCANA ANGGARAN BIAYA
NAMA PEKERJAAN : RENOVASI RUMAH
LOKASI : JL. EMPUNALA
HARGA JUMLAH
No. URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA KETERANGAN
Rp. Rp.
1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
1 Pembongkaran atap, tembok dan plat lantai 1.00 Ls Rp 5,000,000.00 Rp 5,000,000.00
2 Pembersihan lokasi 1.00 Ls Rp 500,000.00 Rp 500,000.00
Sub Jumlah Rp 5,500,000.00
II PEKERJAAN TANAH DAN PONDASI
1 Galian tanah 3.59 m3 Rp 50,000.00 Rp 179,500.00
2 Pas. Pondasi rollag 2.57 m2 Rp 550,000.00 Rp 1,410,750.00
Sub Jumlah Rp 1,590,250.00
II PEKERJAAN BETON
1 Pile cap 60x60x20 0.14 m3 Rp 3,000,000.00 Rp 432,000.00
2 Sloof 15x20 0.51 m3 Rp 3,500,000.00 Rp 1,795,500.00
3 Kolom 15x15 0.54 m3 Rp 3,500,000.00 Rp 1,890,000.00
4 Balok 10x20 0.34 m3 Rp 4,000,000.00 Rp 1,368,000.00
5 Rabat beton 1.13 m3 Rp 4,000,000.00 Rp 4,504,000.00
Sub Jumlah Rp 9,989,500.00
III PEKERJAAN PASANGAN
1 Pekerjaan bata ringan 68.40 m2 Rp 125,000.00 Rp 8,550,000.00
2 Pekerjaan plesteran 136.80 m2 Rp 60,000.00 Rp 8,208,000.00
3 Pintu PVC 2.00 bh Rp 400,000.00 Rp 800,000.00
Sub Jumlah Rp 17,558,000.00
IV PEKERJAAN LANTAI
1 Pasang keramik 40x40 36.55 m2 Rp 200,000.00 Rp 7,310,000.00
2 Pasang keramik 30x30 8.21 m2 Rp 195,000.00 Rp 1,600,950.00
3 Pasang keramik 25x25 1.80 m2 Rp 180,000.00 Rp 324,000.00
4 Pasang keramik 25x40 8.64 m2 Rp 190,000.00 Rp 1,641,600.00
Sub Jumlah Rp 10,876,550.00
V PEKERJAAN ATAP
1 Pasang plafon (rangka kayu lama) 76.46 m2 Rp 100,000.00 Rp 7,646,000.00
2 Pasang atap spandek rangka galvalume 13.98 m2 Rp 500,000.00 Rp 6,987,500.00
Sub Jumlah Rp 14,633,500.00
VII PEKERJAAN LISTRIK
1 Pasang lampu Downlight 15.00 bh Rp 105,000.00 Rp 1,575,000.00
2 Perbaikan instalasi listrik 1.00 ls Rp 500,000.00 Rp 500,000.00
Sub Jumlah Rp 2,075,000.00
VIII PEKERJAAN PINTU
1 Rolling door 12.00 m2 Rp 650,000.00 Rp 7,800,000.00
Sub Jumlah Rp 7,800,000.00
JUMLAH Rp 70,022,800.00
JUMLAH TOTAL Rp 70,022,800.00
DIBULATKAN Rp 70,022,000.00
HERY KYSWANTO
Direktur
RENCANA ANGGARAN BIAYA ( RAB )
NAMA PEKERJAAN : REHAB RUMAH
HARGA JUMLAH
No. URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
Rp. Rp.
1 2 3 4 5 6
A PEKERJAAN PENDAHULUAN
I Pekerjaan Persiapan & Mobilisasi 1.00 Ls Rp 1,000,000.00 Rp 1,000,000.00
Sub Jumlah Rp 1,000,000.00
II PEKERJAAN PERSIAPAN
1 Pekerjaan Pembersihan Awal dan Akhir 1.00 Ls Rp 500,000.00 Rp 500,000.00
2 Pembongkaran Pagar & Kusen 1.00 Ls Rp 1,000,000.00 Rp 1,000,000.00
Sub Jumlah Rp 1,500,000.00
Jumlah A Rp 2,500,000.00
B PEKERJAAN PASANGAN PAGAR
I PEKERJAAN TANAH
1 Pekerjaan Bor Strouss Diameter 30 cm #NAME? m1 Rp 35,700.00 #NAME?
2 Pekerjaan Galian Pile Cap #NAME? m3 Rp 98,437.50 #NAME?
3 Pekerjaan Galian Pondasi #NAME? m3 Rp 98,437.50 #NAME?
4 Pekerjaan Urug Kembali #NAME? m3 Rp 32,812.50 #NAME?
5 Pekerjaan Urug Pasir Bawah Pondasi #NAME? m3 Rp 285,075.00 #NAME?
II PEKERJAAN BETON
2 Sloof 15x20 43.30 0.15 0.20
3 Kolom 15x15 0.15 0.15 3.50 15.00
4 Balok 10x20 43.30 0.15 0.15
2 Pekerjaan Plesteran
3 Pekerjaan acian
IV PEKERJAAN LANTAI
1 Rabat Lantai 5 cm 9.00 5.80 0.05
7.80 1.20 0.05
VI PEKERJAAN PENGECATAN
1 Pengecatan dinding 6.00 3.80 2.00 2.00
12.00 3.80 2.00 2.00
2.50 3.80 2.00
8.50 3.80 2.00
B PEKERJAAN LANTAI 2
I PEKERJAAN STRUKTUR
1 Kolom beton 15x30 0.15 0.30 3.00
2 Balok WF 200.100.5,5.8 mm 30.00 #REF!
3 Balok beton 15x20 0.15 0.20 1.00
4 Plat Bordes tebal 10 cm 1.00 1.00 0.10
5 Plat Tangga tebal 10 cm 1.00 0.30 0.10
6 Panel lantai 2,5x0,6x0,125 m 12.00 6.00
2 Pekerjaan Plesteran
3 Pekerjaan acian
IV PEKERJAAN LANTAI
1 Rabat lantai 5 cm 6.00 12.00 0.05
2 #REF! 6.00 12.00
3 Pasang lantai vinyl 6.00 12.00
VI PEKERJAAN PENGECATAN
1 Pengecatan dinding 94.00
12.00 2.50 2.00 2.00
6.00 2.50 2.00 2.00
24.00 2.50 2.00
C PEKERJAAN LANTAI 3
I PEKERJAAN LANTAI
1 Rabat lantai 5 cm 6.00 12.00 0.05
2 Pasang rumput sintesis 6.00 12.00
II PEKERJAAN PASANGAN
1 Pekerjaan pasangan bata ringan 6.00 1.00 2.00
12.00 1.00 2.00
IV PEKERJAAN PENGECATAN
1 Pengecatan dinding
2 Pengecatan waterproof
BACK UP VOLUME
SATUAN Ket.
Jumlah Luas Sub Vol Volume
7 8 9 10 11 12
1.00 Ls
21.22 21.22 m3
11.69 11.69 m3
#REF!
1.30 1.30 m3
1.18 1.18 m3
0.97 0.97 m3
151.55
-6.00
-4.80
-8.40
-0.60
131.75 131.75 m2
263.50 m2
263.50 m2
2.61
0.47
3.08 3.08 m3
52.20
9.36
61.56 61.56 m2
1.00 unit
1.00 unit
1.00 ls
91.20
182.40
19.00
64.60
357.20 357.20 m2
52.20 52.20 m2
12.00
24.00
8.50
2.50
47.00 47.00 m2
94.00 m2
94.00 m2
3.60 3.60 m3
72.00 72.00 m2
72.00 72.00 m2
3.00 unit
1.00 unit
4.00 unit
1.00 ls
94.00
120.00
60.00
120.00
394.00 394.00 m2
3.60 3.60 m3
72.00 72.00 m2
12.00
24.00
36.00 36.00 m2
50.00 Bh
72.00 72.00 m2
72.00 m2
36.00 m2
Pekerjaan Acian Lantai
24.04.01.21 m2
(Hardener)
Tenaga:
23.06.01.01.02 Mandor 0.0100 O.H
23.06.01.01.01 Kepala Tukang Batu 0.0100 O.H
23.06.01.01.05 Tukang Batu 0.1200 O.H
23.06.01.01.07 Pekerja/Buruh Tak Terampil 0.1800 O.H
Bahan:
20.01.01.02.01 Harderner 0.2000 ltr
20.01.01.02.02 Semen portland (40 kg) 0.0813 Zak
Nilai HSPK :
200,000 Rp 2,000.00
150,000 Rp 1,500.00
150,000 Rp 18,000.00
105,000 Rp 18,900.00
Jumlah: Rp 40,400.00
168,000 Rp 33,600.00
89,658 Rp 7,284.71
Jumlah: Rp 40,884.71
Nilai HSPK : Rp 81,284.71
Lantai Wiremesh M-8 2 Lapis Tebal
10cm Koef m3
Tenaga:
Mandor 0.2650 O.H 150,000
Kepala Tukang Besi 0.2850 O.H 125,000
Tukang Besi 0.7800 O.H 125,000
Tukang Batu 0.4750 O.H 125,000
Tukang Kayu 0.3300 O.H 125,000
Pekerja / Buruh Tak Terampil 4.1000 O.H 120,000
Jumlah:
Bahan:
Semen portland (40kg) 8.8750 Zak 89,658
Pasir Beton 0.4300 m3 708,900
Batu Pecah Mesin 1/2 cm 0.7100 m3 584,000
Wiremesh M-8 1.0000 Lbr 450,000
Kawat Beton 1.0100 Kg 26,900
Kayu meranti bekisting 0.1010 m3 -
Plywood tebal 9 mm 0.8000lembar -
Paku Usuk 1.2000 Kg -
Minyak Bekisting 0.8000 ltr -
Jumlah:
Nilai HSPK :
795,714.75
304,827.00
414,640.00
450,000.00
27,169.00
-
-
-
-
1,992,350.75
2,757,860.00
Rp 2,000.00
Rp 1,250.00
Rp 15,000.00
Rp 21,600.00
Rp 39,850.00
Rp 33,600.00
Rp 7,284.71
Rp 40,884.71
Rp 80,734.71